Determination 660650

Quality of restumping repairs disputed; ongoing movement damage and cash settlement offer disputed

FirmSuncorp Group
Decided2020-09-28
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$188,273
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A third dispute over storm-related restumping and ongoing movement damage at a home. AFCA found the restumping structurally sound but required footing design compliance, rejected liability for ongoing movement, and ordered settlement based on the insurer's offer of $188,272.79.

Repairs must meet current building regulation requirements, so a qualified engineer's footing design is required, while movement damage from pre-existing site and maintenance issues is not covered.

Issues

Subjects and remedies

home or building damagepay claimrepair or rectify

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 660650 Financial firm AAI Limited Determination | Case number: 660650 Page 2 of 14 Case number: 660650 15 September 2020 1 Determination overview 1.1 Complaint The complainant held a home insurance policy with the financial firm (insurer) and lodged a claim for storm damage in early 2011. The claim is subject to two previous determinations. The first issued on 17 April 2014 required the insurer to restump the property and pay for 85% of the repairs to the property (No. 323420). The second, on 30 June 2016, required the insurer to appoint an independent building surveyor to ensure the restumping was compliant. The insurer was also to arrange the repairs unless the complainant wanted a cash settlement (No. 421071). The insurer inspected the restumping and says the work is structurally sound and of a high standard. The insurer has also offered a cash settlement for the remainder of the works. The complainant says the insurer‟s restumping is defective and requires fu rther rectification. She also says the insurer‟s settlement offer is unreasonable. 1.2 Issues and key findings Is the footing system structurally sound? Yes. The restumping works were done adequately in accordance with the building permit issued. Is the insurer liable for ongoing damage or rectification? The insurer is not liable for ongoing damage as this is due to general movement. However, the insurer must obtain footing plans by a qualified engineer and ensure restumping is completed in accordance with this design. How should the claim be settled? The claim should be settled as set out in section 2.3. 1.3 Determination This determination is partially in favour of the complainant. The insurer should obtain footing plans and ensure the restumping has been completed in accordance with this design. If it is not, then it is required to pay for the additional work to ensure they are compliant as set out in section 2.2. The insurer should settle the claim as set out in section 2.3. Determination | Case number: 660650 Page 3 of 14 2 Reasons for determination 2.1 Is the footing system structurally sound? Complainant has numerous concerns with restumping The complainant is concerned the restumping has not been completed satisfactorily and will lead to ongoing damage. Her primary concerns are as follows:  no stump checked was below 250mm – they should have been a minimum of 500mm below ground level and a minimum of 600mm on load bearing walls  stumps were cut in half during installation  there is soil between the stump and the foot pad – in some instances, the stump is not centred on the foot pad  stump pads are only a few millimetres deep  stumps are not attached to bearers  ant caps have not been installed. The complainant says she is reluctant to allow the insurer to proceed with repairs to the property when these issues will lead to further damage. She says the damage to her property is ongoing. Insurer’s experts have examined restumping works The previous determination of 30 June 2016 required the insurer to inspect the restumping for compliance and, if necessary, complete any additional restumping work required. The insurer subsequently engaged an engineer (MP) to carry out a restumping compliance inspection. MP inspected the works and recommended a builder remove the soil between stumps and pad footings to ensure they were property installed. MP said whether the work was compliant was dependent on stump manufacturer specifications, and pad depth. The insurer then engaged an independent and experienced structural engineer and building surveyor (GC). GC provided two detailed and persuasive reports. The first report compared restumping against the relevant building permit and Australian Standards. The second addressed the complainant‟s specific concerns and potential warranty issues. In summary, GC found restumping was carried out to a high standard. GC noted existing stumps lacked ant caps, and the area was not a declared termite protection area. Loose stumps were not found, unsupported bearers and old stumps were unrelated to restumping and thus irrelevant, and a stump near the edge of a stump pad was not poorly installed. Determination | Case number: 660650 Page 4 of 14 GC noted the building permit required a concrete pad depth of 450mm below the ground, and his inspection of several pads found this was the case. GC found no significant defects on any of the restumping work, and no additional work is required from a structural viewpoint. However, the work did not comply with building regulation requirements as floors did not finish level, there was insufficient information in the building permit and the footing pads required design by a qualified engineer. GC noted floors should only be returned to the pre-work levels, else the building would sustain damage. The insurer subsequently engaged an engineer (FM) to report on stump pad compliance with building regulations. FM obtained confirmation from the original restumping contractor that stump footings were founded at 700mm below natural ground level. It noted this was sufficient for the site conditions, being a class-P with compacted fill present in soil. FM found the work was adequate, yet a building surveyor should comment on compliance with relevant regulations. Complainant’s expert says stump depth is inadequate The complainant engaged an independent engineer (MA) to assess the structural integrity of foundations. MA says photographs taken by the complainant indicate the stump pads were founded at around 300 mm below the existing ground level. MA also says the photographs show some stumps were not adequately attached to bearers. MA noted that a geotechnical report prepared by SS when renovations were done at the property in 1997 deemed the site class-P. MA says the site requires that stumps are located 1200 mm below existing ground level. MA concludes that as stumps are not located at this depth, the restumping work that was carried out in 2016 was less than an acceptable standard. MA recommends extensive works to rectify this problem. Experts disagree on required restumping depth The site classification and soil conditions at the site are crucial to determining whether the restumping work is adequate. This is because the design of the system is based on the depth of reliable founding material. The design is based on a soil classification and footing recommendation report prepared by engineer FM in 2013. It says fill was observed between 450mm and 500mm, with A Horizon Silty Sand below. Given this, it prescribed footings must be:  founded a minimum of 475mm below surface level,  have a minimum depth of 400mm; and  be founded a minimum of 150mm into A Horizon Silty Sand. Determination | Case number: 660650 Page 5 of 14 The insurer‟s building co - ordinator (CM) reviewed SS‟s report and FM‟s soil report. CM noted SS took samples towards the rear extension of the property whereas FM‟s sample was nearer to the property affected by the claim. Therefore, CM said FM‟s report should be preferred. The panel agrees with this. FM‟s investigation was more recent and took samples closer to the area in question. The panel is satisfied the required stumping depth should be set out as described in the FM report. Footing system is structurally sound and does not contain defects The building permit requires a concrete pad depth of 450mm below the ground , and depth of the actual pad of 150mm. The complainant has supplied photographs of stumps and stump pads. She excavated down to the surface of a stump pad and measured the distance to ground level. She estimates stumps are only 200mm below ground level. MA says the stumps pads are not 450mm below ground level. However, this was based on the compla inant‟s photos. MA noted he did not expose any of the pads. Further, MA‟s opinion about the non - compliance of the pads were based on SS‟s soil report. The panel does not accept this is preferred regarding the depth of the pads. Further, GC says the base of stump pads are at least 450mm below the ground surface. This is consistent with the building permit. Other reports prepared by the insurer‟s experts concur with this view. While the photographs are helpful, the panel is unable to ascertain whether the com plainant‟s measurements are accurate. It is also unclear whether her measurements are against the surface level of the subfloor area, which is lower than ground level. Regarding the complainant‟s concern that the contractor cut through the stumps, none of the reports confirm this. For the ant caps, the panel does not accept there is any evidence to show:  they were previously installed, or  are required to be installed pursuant to any regulation or guidelines – the experts say it is not required. As such, based on available information, the panel is satisfied the work has been done adequately based on the building permit issued Determination | Case number: 660650 Page 6 of 14 2.2 Is the insurer liable for ongoing damage or rectification? Repairs must comply with local government or other statutory requirements The policy sets out the way the insurer will settle a claim for damage. It says the insurer will pay the extra costs necessary to satisfy the current requirements of any local council or government authority. The insurer engaged MC to review the GC report. This found works and building permit documentation did not comply with building regulation requirements. The issue is discussed extensively, and for the sake of brevity will not be restated. In summary, GC found that in the absence of an approved engineering design for restumping, the restumping works do not meet the current building regulation requirements. This should have been included when a building permit was issued. The insurer‟s submissions suggest that FM was engaged to provide a footing stump design. However, FM has not produced such a design document. This is problematic as, while the available information suggests the work has been performed adequately, it was based on a building permit that did not comply with the building regulations. Design by qualified engineer is required to ensure compliance with regulations MC recommends restumping of the home be completed in accordance with an approved engineering footing design and building permit conditions. It does not specify if this requires restumping the building anew. GC also says a footing design by a qualified engineer is required to ensure compliance with the building regulations. If the engineer‟s design is different to the requirements of the building permit, then additional or altered work would be required. A footing recommendation report prepared by FM notes that a final design and construction details can only be provided by FM on submission of architectural plans and a proposed site drainage plan. The insurer has been unable to produce t his footing design. In the event the insurer cannot supply original footing designs by a qualified engineer, it should instruct an engineer to design footings based on information available in 2013. If additional or altered work is required, the insurer is liable for the cost of these works. The complainant says she has lost faith in the insurer and its chosen repairers. This is understandable given the circumstances. If additional or altered work is required, the insurer should cash settle the value of restumping repairs. In doing so, the insurer should:  ensure it is based on an actionable quote, and  provide a contingency of 15% to account for any variances and the fact the risk of the works is passing to the complainant Determination | Case number: 660650 Page 7 of 14 Movement damage is unrelated to insured event or repairs The complainant reported ongoing movement across the building to the insurer. The insurer engaged specialist engineer MC to prepare a causation report. MC concluded the damage is a result of long term movement exacerbated by poor maintenance, poor ventilation, poor site drainage and trees. MC did not accept the damage was due to the insured event or subsequent repairs. The insurer and the complainant have both carried out some works to rectify the roof drainage and other issues. However, experts recommend site drainage works and other improvements are necessary to minimise further damage. Previous determinations did not require the insurer to carry out such improvements at the property. The complainant‟s engineer, MA, noted almost no cracks were in evidence internally or externally, and assumed previous damage had been repaired. The submissions do not suggest recent repairs have occurred. The complainant says the insurer was responsible for replacing missing downpipes and spouting. She also believes there is sufficient ventilation. Further, she notes the slope of the land has not changed. Most of the experts consistently note issues with the property‟s site drainage. In particular, several times they have referred to the perimeter ground levels not being graded away from the foundation. Further, there was reference to the subfloor level being lower than the external ground. In addition, it appears there are aspects of the subfloor that are not easily accessible. This shows there are several issues with the site drainage which would affect the foundations. These would have not been caused by the clamed event in 2011 or the claim related repairs. Further, it is likely these issues would cause ongoing movement to the property. Therefore, the panel is not persuaded the available information show any ongoing movement at the property is a result of either the initial insured event, or the subsequent repairs. Therefore, the insurer is not liable for any ongoing movement damage at the property. 2.3 How should the claim be settled? Insurer’s settlement offer is fair if there is no restumping work required The previous determination noted that once restumping was complete, the insurer is to attend to repairs unless the parties agree to a cash settlement. Determination | Case number: 660650 Page 8 of 14 The insurer has made an offer to pay $188,272.79 for cash settlement purposes. This was set out in an email to the complainant dated 28 December 2018 and appeared to comprise of the following:  repair quotation from PP dated 20 September 2017 totalling $87,847.99  temporary accommodation for 130 nights totalling $45,000  furniture packing/removal/reinstatement based on S‟s quotation dated 2 October 2017 totalling $37,400  an ex-gratia payment of $1,000  a further 10% to a new quotation for contingency/unforeseen repairs (no amount quoted) The panel notes these figures, excluding the 10%, total $173,247.99. This leaves a gap of $15,024.80. Whilst there is an allowance of a 10% contingency to the repair quote, this does not appear to account for the difference. Nevertheless, it is an offer the insurer has provided and maintained. The complainant has not provided evidence to show this is unfair. The panel also notes the following:  PP‟s quote included „Furniture Removalist‟ for $18,040 even though this is separately allowed in S‟s quotation  RP‟s more recent quote dated 30 January 2019 ($67,146.23) for the repairs is les s than PP‟s quote  no evidence to show the accommodation allowance or rate is unreasonable – the timeframe is also consistent with PP‟s quote  a more recent quotation from S for furniture packing/removal/reinstatement totalled $33,000 – this is less than the insurer‟s allowance of $37,400  the panel is not satisfied that further movement damage identified by the complainant was caused by the claimed event or repairs The panel notes that the repair quote and the furniture are outdated. However, the panel also notes that the more recent quotes show the older ones were generous. Particularly PP‟s quote which included furniture removal. Further, the insurer added $15,024.80 to its overall liability. This provides an allowance for contingencies and variances to the works. Given this, the panel considers the insurer‟s offer is fair subject to the restumping not requiring further works. The complainant also says her heating costs increased as the insurer did not correctly install a heating unit. The insurer has accepted liability for this issue. On provision of utilities bills showing an increase in costs, the insurer should reimburse the complainant. Determination | Case number: 660650 Page 9 of 14 Insurer should add 30% if further restumping is required The panel recognises that if additional restumping works is required, further damage to the property is likely to occur. This claim has been protracted. The claimed event occurred almost 10 years ago. This is the third dispute lodged between the parties. Given this, the panel considers it is fair in all the circumstances that, where possible, finality be achieved to this dispute. Therefore, the panel considers that if further restumping work is required, the insurer should pay an additional 30% to the settlement figure. This is due to the following:  if further scopes and quotes had to be obtained following the restumping works, this will protract the dispute further and possibly lead to further disputes – this is undesirable for all parties  the insurer has had sufficient opportunities to check and ensure the restumping was done properly yet, to date, the information still has not established if this is the case (i.e. that the restumping was properly designed)  it is likely further damage will occur if further restumping work is required  this allowance should be sufficient to account for the further damage The panel acknowledges the last decision said the insurer should attempt to complete the works. However, it is not clear how practical this is when there appears to be site drainage issues, tree influence and other maintenance issues that need to be addressed. Instead, the panel considers it is fair in all the circumstances that the repairs be cash settled to provide finality to this dispute. Determination | Case number: 660650 Page 10 of 14 3 Supporting information 3.1 Relevant policy provisions Repairing or rebuilding your building – other costs We will also pay for the following where applicable. Compliance costs In repairing or rebuilding your building, we will pay the extra costs necessary to satisfy the current requirements of any local council or government authority. 3.2 Reports All information has been considered in providing this determination. A summary of referenced reports is below: Record Key points Insurer’s engineer (FM) Soil classification and footing recommendation report 23 January 2013  Fill was observed in the borelogs undertaken and observed at between 450mm and 500mm  The site is classified as „P‟ to account for… the presence of significant fill found on site…  The site is classified as „P‟ (due to significant fill one site). The footing des ign can be selected for an ‟S‟ site classification based upon the reactivity of the soil as set out in AS2870.  Perimeter and internal strip footings shall be founded a minimum of 475mm below surface level, having a minimum depth of 400mm, and be founded a minimum of 150mm into A Horizon Silty Sand.  Stumps placed internally should be founded 400mm minimum below surface level and at least 150mm int o A Horizon Silty Sand. Insurer’s engineer (MP ) Restumping compliance inspection 22 August 2016  The Insured indicated that the previous timber stumps were replaced with concrete stumps by a builder appointed by the Insurer. However, the Insured was not sure whether the original pad footings were replaced or not.  The Insured is of the opinion that th e subfloor stumps are undersized and are not deep enough as not ed by her builder.  We reviewed the soil investigation report by FM , dated 23 January 2013. This soil investigation report indicates that the subject site can be classified as „P‟ due to significant fill on the site. The borehole information shows that this filling material depth is approximately 450mm to 500mm in the sub ject site. The soil below this filling material was found to be A Horizon Silty Sand. The soil investigation report recommends that the footing design for the subject site shall be carried out for a “S” site classification. It further states that the stump s placed in the subfloor area shall be founded 400mm minimum depth below the surfac e level and at Determination | Case number: 660650 Page 11 of 14 Record Key points least 150mm int o A Horizon Silty sand.  We were unable to determine the dept h of the pad footings, as we did not excavate to that extent due to limited access. However, we observed filling material on top of most of the pad footings. Therefore, the depth of the pad footing should be at least 150mm thick, assuming A Horizon silty sand starts form the top of the pad footing.  We noted that the soil investigation re port indicated that subject site has filling material up to 450 to 500mm depth. We observed that top of the pad footing was located approximat ely 100mm to 150mm below the surface ground level of the subfloor area. Therefore, it is possible that some of the pad footings have been placed just on the filling material and they have not been founded 150mm below the A Horizon Silty Sand, as recommended by the soil investigation report. It is also possible that the builder has used deeper pad footings to fulfil th is requirement.  Notwithstanding this, we rec ommend the builder appointed by the Insurer provides certification/assurance that they have carried out works as per the rec ommendation given in the soil investigation report. Alternatively, we are able to re - att end the site and excavate some of the pad footings to det ermine whether the builder has carried out works as per the given recommendations, if you consider it warranted. Insurer’s building inspector ( GC ) Stump footing audit report 11 April 2017  T he buildi ng permit required a conc rete pad depth of 450mm below the ground. My inspection of several pads on 20 January 2017 revealed that the base of the pads was at least 450mm below the ground surface.  The building permit documentation for the reblocking work do es not comply with the requirements of the building regulations.  The reblocking work did not comply wit h all the requirements of the building permit, but is still adequat e from a structural viewpoint .  The completed work does not comply with the building permit as the stump pads are round: not square as specified on the building permit.  The building permit required a concrete pad depth of 450mm below the ground. My inspection of several pads on 20 January 2017 revealed that the base of the pads was at lea st 450mm below the ground surface.  A design by a qualified engineer was required for the stump pads in Class P soil classification. The building permit was issued without an engineer‟s design and the work was performed wit hout the required engineer‟s desig n.  Whether or not the reblocking work is required to comply with the building permit documents, or alternatively the requirements of the building regulations and its relevant referenced building codes is a legal matter and could be dependent on the buildin g contract.  There is no structural requirement to repair any of the reblocking work and the work does not contain any significant defects.  The work carried out by EA primarily complies with the building Determination | Case number: 660650 Page 12 of 14 Record Key points permit documentation, except that the conc rete pad footings are 300mm in diameter rather than 300mm x 300mm square. Whilst the 300mm diameter pads are approximately 20% less in area than the 300mm square pads specified, the 300mm diameter pads are only working at 73% capacity; and are therefore structurally adequate.  Increasing the area of the pads to 300mm x 300mm would not result in any quantifiable increased performance of the work executed by EA, and would be both a redundant and wasteful exercise in my opinion.  … there is evidence that EA provided an exemplary standard of work. Prime examples of the high standard of EA‟s work include minimal sized and incompressible packers, as well as steel plate connecto rs at bearer joints.  … the stump pad sizes are lesser in area than their specified area on the building permit endorsed plan, they are still adequate in area to perform satisfactorily.  FOS‟s Determination cited unsupported bearers, poorly installed stumps, loose stumps, remaining old stumps, no ant caps on stumps, and crushed heating ducts. None of this work applied to the work conducted by EA in my view. Insurer’s engineer (FM ) Report on stump pads for building regulation compliance 25 August 2017  EA Restumping provided FMG with the following information in relation to the restumping works that have been carried out at the subject house: > Stump footings (including soleplates) founded at 700mm below natural ground level.  The FM Report classified the si te as Class P due to the pres ence of fill found on - site.  The FM Report calculated the maximum y s (characteristic surface movement (mm)) value at this site to be 0mm.  The subject stump footings are understood to have been founded a minimum of 700mm below natural ground level, which meets the requirements of the founding depth for stump footings provided in the FM Report.  In FM‟s opinion, the subject stumps have been installed adequately through the fill layer present at the subject site (based on the FM Report and EA Restumping information) and these stumps are not expected to be adversely impacted by the fill. In the absence of fill, FM considers the subject site to be a Class A site (i.e. non - reactive) and a stump footing system may be designed accordin gly.  FM observed the following items considered to be consistent with poor building maintenance: > Debris and/or vegetation loc ated within eaves gutters, including those understood to have been installed by the insurer since the Event. Insurer’s engineer (MC) Ongoing movement causation  The home generally presents in a poorly maintained condition wit h significant defects and deficiencies to the property that has Determination | Case number: 660650 Page 13 of 14 Record Key points report 15 November 2018 resulted in long term building movement, with the further and ongoing development of movement. Proximate Cause The purported on - going building movement and damage is due to the pre - existing site conditions and general absence of adequate maintenance not limited to the defects outlined wit hin this report and further reiterated below: ‒ Absence of a surface storm water drainage system. ‒ Ground surface levels graded toward s the home. ‒ Absence of eave guttering. ‒ Corroded eave guttering ‒ Absence of subfloor ventilation. ‒ Subfloor ground surface levels lower than external ground surface levels. ‒ Proximity of maturing trees. The ongoing building movement is not relat ed to the purported flooding event of January 2011, and is consistent with the defects and deficiencies to the property. Complainant’s engineer (MA) Assessment of structural integrity of foundations 26 March 2020  Photographs taken by the home owner at the time this work was carried out indicate that these pads were founded at no more than 300 mm below the existing ground level. Some of the stumps have not been adequately fixed to the original bearers.  A geotechnic al report, No. 97A22, prepared by SS in 1997, pri or to the construction of the two storey addition, gave the site a Class P rating in accordance wit h AS 2870 - 2011, i.e. it is a “Problem” site. This classification reflects the large depth of filling (up to 1400 mm) discovered above the natural sand in t he exploratory boreholes.  In our opinion , the reblocking/restumping work that was carried out in 2016 was less than an acceptable standard. This conclusion is based on the founding depth for the replacement stumps, being 300 mm approximately when the recom mended founding depth for this site is 1400 mm. The Geotechnical report provided in 1997 was available to the cont ractors who carried out the work, however it is understood that anot her report was provided to the contractor which was not made available to the home owner.  At the time of our inspections, almost no cracks were in evidence internally, and similarly for the external brickwork veneer cladding. It is assumed that these have all undergone some form of repair. Insurer’s building consultant (MC) Rep ort: Damage to property 17 April 2020  The restumping works to the premises generally appears to have been undertaken and completed in the absence of an approved engineering design.  The absence of the engineering design within the building permit leads to suggest that the restumping works were not completed in accordance with an approved engineering design.  The restumping works are required to have been complet ed in accordance with an approved engineering design.  In the absenc e of an approved engineering de sign, the restumping Determination | Case number: 660650 Page 14 of 14 Record Key points works is considered to have not been completed to an acceptable standard .  The property has several pre - existing issues as previously d etailed within the MCS Reports, that will result in further and o ngoing movement to the premis es.  T he restumping of the home is recommended to be completed in accordance with an approved engineering design and building permit conditions.