Quality of restumping repairs disputed; ongoing movement damage and cash settlement offer disputed
Text of the determination
Determination
Case number 660650
Financial firm AAI Limited
Determination | Case number: 660650 Page 2 of 14
Case number: 660650 15 September 2020
1 Determination overview
1.1 Complaint
The complainant held a home insurance policy with the financial firm (insurer) and
lodged a claim for storm damage in early 2011.
The claim is subject to two previous determinations. The first issued on 17 April 2014
required the insurer to restump the property and pay for 85% of the repairs to the
property (No. 323420). The second, on 30 June 2016, required the insurer to appoint
an independent building surveyor to ensure the restumping was compliant. The
insurer was also to arrange the repairs unless the complainant wanted a cash
settlement (No. 421071).
The insurer inspected the restumping and says the work is structurally sound and of a
high standard. The insurer has also offered a cash settlement for the remainder of the
works.
The complainant says the insurer‟s restumping is defective and requires fu rther
rectification. She also says the insurer‟s settlement offer is unreasonable.
1.2 Issues and key findings
Is the footing system structurally sound?
Yes. The restumping works were done adequately in accordance with the building
permit issued.
Is the insurer liable for ongoing damage or rectification?
The insurer is not liable for ongoing damage as this is due to general movement.
However, the insurer must obtain footing plans by a qualified engineer and ensure
restumping is completed in accordance with this design.
How should the claim be settled?
The claim should be settled as set out in section 2.3.
1.3 Determination
This determination is partially in favour of the complainant.
The insurer should obtain footing plans and ensure the restumping has been
completed in accordance with this design. If it is not, then it is required to pay for the
additional work to ensure they are compliant as set out in section 2.2.
The insurer should settle the claim as set out in section 2.3.
Determination | Case number: 660650 Page 3 of 14
2 Reasons for determination
2.1 Is the footing system structurally sound?
Complainant has numerous concerns with restumping
The complainant is concerned the restumping has not been completed satisfactorily
and will lead to ongoing damage. Her primary concerns are as follows:
no stump checked was below 250mm – they should have been a minimum of
500mm below ground level and a minimum of 600mm on load bearing walls
stumps were cut in half during installation
there is soil between the stump and the foot pad – in some instances, the stump is
not centred on the foot pad
stump pads are only a few millimetres deep
stumps are not attached to bearers
ant caps have not been installed.
The complainant says she is reluctant to allow the insurer to proceed with repairs to
the property when these issues will lead to further damage. She says the damage to
her property is ongoing.
Insurer’s experts have examined restumping works
The previous determination of 30 June 2016 required the insurer to inspect the
restumping for compliance and, if necessary, complete any additional restumping
work required.
The insurer subsequently engaged an engineer (MP) to carry out a restumping
compliance inspection. MP inspected the works and recommended a builder remove
the soil between stumps and pad footings to ensure they were property installed. MP
said whether the work was compliant was dependent on stump manufacturer
specifications, and pad depth.
The insurer then engaged an independent and experienced structural engineer and
building surveyor (GC). GC provided two detailed and persuasive reports. The first
report compared restumping against the relevant building permit and Australian
Standards. The second addressed the complainant‟s specific concerns and potential
warranty issues.
In summary, GC found restumping was carried out to a high standard. GC noted
existing stumps lacked ant caps, and the area was not a declared termite protection
area. Loose stumps were not found, unsupported bearers and old stumps were
unrelated to restumping and thus irrelevant, and a stump near the edge of a stump
pad was not poorly installed.
Determination | Case number: 660650 Page 4 of 14
GC noted the building permit required a concrete pad depth of 450mm below the
ground, and his inspection of several pads found this was the case. GC found no
significant defects on any of the restumping work, and no additional work is required
from a structural viewpoint. However, the work did not comply with building regulation
requirements as floors did not finish level, there was insufficient information in the
building permit and the footing pads required design by a qualified engineer.
GC noted floors should only be returned to the pre-work levels, else the building
would sustain damage.
The insurer subsequently engaged an engineer (FM) to report on stump pad
compliance with building regulations. FM obtained confirmation from the original
restumping contractor that stump footings were founded at 700mm below natural
ground level. It noted this was sufficient for the site conditions, being a class-P with
compacted fill present in soil.
FM found the work was adequate, yet a building surveyor should comment on
compliance with relevant regulations.
Complainant’s expert says stump depth is inadequate
The complainant engaged an independent engineer (MA) to assess the structural
integrity of foundations.
MA says photographs taken by the complainant indicate the stump pads were
founded at around 300 mm below the existing ground level. MA also says the
photographs show some stumps were not adequately attached to bearers.
MA noted that a geotechnical report prepared by SS when renovations were done at
the property in 1997 deemed the site class-P. MA says the site requires that stumps
are located 1200 mm below existing ground level.
MA concludes that as stumps are not located at this depth, the restumping work that
was carried out in 2016 was less than an acceptable standard. MA recommends
extensive works to rectify this problem.
Experts disagree on required restumping depth
The site classification and soil conditions at the site are crucial to determining whether
the restumping work is adequate. This is because the design of the system is based
on the depth of reliable founding material.
The design is based on a soil classification and footing recommendation report
prepared by engineer FM in 2013. It says fill was observed between 450mm and
500mm, with A Horizon Silty Sand below. Given this, it prescribed footings must be:
founded a minimum of 475mm below surface level,
have a minimum depth of 400mm; and
be founded a minimum of 150mm into A Horizon Silty Sand.
Determination | Case number: 660650 Page 5 of 14
The insurer‟s building co - ordinator (CM) reviewed SS‟s report and FM‟s soil report.
CM noted SS took samples towards the rear extension of the property whereas FM‟s
sample was nearer to the property affected by the claim. Therefore, CM said FM‟s
report should be preferred.
The panel agrees with this. FM‟s investigation was more recent and took samples
closer to the area in question.
The panel is satisfied the required stumping depth should be set out as described in
the FM report.
Footing system is structurally sound and does not contain defects
The building permit requires a concrete pad depth of 450mm below the ground , and
depth of the actual pad of 150mm.
The complainant has supplied photographs of stumps and stump pads. She
excavated down to the surface of a stump pad and measured the distance to ground
level. She estimates stumps are only 200mm below ground level.
MA says the stumps pads are not 450mm below ground level. However, this was
based on the compla inant‟s photos. MA noted he did not expose any of the pads.
Further, MA‟s opinion about the non - compliance of the pads were based on SS‟s soil
report. The panel does not accept this is preferred regarding the depth of the pads.
Further, GC says the base of stump pads are at least 450mm below the ground
surface. This is consistent with the building permit. Other reports prepared by the
insurer‟s experts concur with this view.
While the photographs are helpful, the panel is unable to ascertain whether the
com plainant‟s measurements are accurate. It is also unclear whether her
measurements are against the surface level of the subfloor area, which is lower than
ground level.
Regarding the complainant‟s concern that the contractor cut through the stumps,
none of the reports confirm this.
For the ant caps, the panel does not accept there is any evidence to show:
they were previously installed, or
are required to be installed pursuant to any regulation or guidelines – the experts
say it is not required.
As such, based on available information, the panel is satisfied the work has been
done adequately based on the building permit issued
Determination | Case number: 660650 Page 6 of 14
2.2 Is the insurer liable for ongoing damage or rectification?
Repairs must comply with local government or other statutory requirements
The policy sets out the way the insurer will settle a claim for damage. It says the
insurer will pay the extra costs necessary to satisfy the current requirements of any
local council or government authority.
The insurer engaged MC to review the GC report. This found works and building
permit documentation did not comply with building regulation requirements. The issue
is discussed extensively, and for the sake of brevity will not be restated.
In summary, GC found that in the absence of an approved engineering design for
restumping, the restumping works do not meet the current building regulation
requirements. This should have been included when a building permit was issued.
The insurer‟s submissions suggest that FM was engaged to provide a footing stump
design. However, FM has not produced such a design document. This is problematic
as, while the available information suggests the work has been performed adequately,
it was based on a building permit that did not comply with the building regulations.
Design by qualified engineer is required to ensure compliance with regulations
MC recommends restumping of the home be completed in accordance with an
approved engineering footing design and building permit conditions. It does not
specify if this requires restumping the building anew.
GC also says a footing design by a qualified engineer is required to ensure
compliance with the building regulations. If the engineer‟s design is different to the
requirements of the building permit, then additional or altered work would be required.
A footing recommendation report prepared by FM notes that a final design and
construction details can only be provided by FM on submission of architectural plans
and a proposed site drainage plan. The insurer has been unable to produce t his
footing design.
In the event the insurer cannot supply original footing designs by a qualified engineer,
it should instruct an engineer to design footings based on information available in
2013. If additional or altered work is required, the insurer is liable for the cost of these
works.
The complainant says she has lost faith in the insurer and its chosen repairers. This is
understandable given the circumstances. If additional or altered work is required, the
insurer should cash settle the value of restumping repairs. In doing so, the insurer
should:
ensure it is based on an actionable quote, and
provide a contingency of 15% to account for any variances and the fact the risk of
the works is passing to the complainant
Determination | Case number: 660650 Page 7 of 14
Movement damage is unrelated to insured event or repairs
The complainant reported ongoing movement across the building to the insurer. The
insurer engaged specialist engineer MC to prepare a causation report.
MC concluded the damage is a result of long term movement exacerbated by poor
maintenance, poor ventilation, poor site drainage and trees. MC did not accept the
damage was due to the insured event or subsequent repairs.
The insurer and the complainant have both carried out some works to rectify the roof
drainage and other issues. However, experts recommend site drainage works and
other improvements are necessary to minimise further damage. Previous
determinations did not require the insurer to carry out such improvements at the
property.
The complainant‟s engineer, MA, noted almost no cracks were in evidence internally
or externally, and assumed previous damage had been repaired. The submissions do
not suggest recent repairs have occurred.
The complainant says the insurer was responsible for replacing missing downpipes
and spouting. She also believes there is sufficient ventilation. Further, she notes the
slope of the land has not changed.
Most of the experts consistently note issues with the property‟s site drainage. In
particular, several times they have referred to the perimeter ground levels not being
graded away from the foundation. Further, there was reference to the subfloor level
being lower than the external ground. In addition, it appears there are aspects of the
subfloor that are not easily accessible.
This shows there are several issues with the site drainage which would affect the
foundations. These would have not been caused by the clamed event in 2011 or the
claim related repairs. Further, it is likely these issues would cause ongoing movement
to the property.
Therefore, the panel is not persuaded the available information show any ongoing
movement at the property is a result of either the initial insured event, or the
subsequent repairs. Therefore, the insurer is not liable for any ongoing movement
damage at the property.
2.3 How should the claim be settled?
Insurer’s settlement offer is fair if there is no restumping work required
The previous determination noted that once restumping was complete, the insurer is
to attend to repairs unless the parties agree to a cash settlement.
Determination | Case number: 660650 Page 8 of 14
The insurer has made an offer to pay $188,272.79 for cash settlement purposes. This
was set out in an email to the complainant dated 28 December 2018 and appeared to
comprise of the following:
repair quotation from PP dated 20 September 2017 totalling $87,847.99
temporary accommodation for 130 nights totalling $45,000
furniture packing/removal/reinstatement based on S‟s quotation dated 2 October
2017 totalling $37,400
an ex-gratia payment of $1,000
a further 10% to a new quotation for contingency/unforeseen repairs (no amount
quoted)
The panel notes these figures, excluding the 10%, total $173,247.99. This leaves a
gap of $15,024.80. Whilst there is an allowance of a 10% contingency to the repair
quote, this does not appear to account for the difference. Nevertheless, it is an offer
the insurer has provided and maintained.
The complainant has not provided evidence to show this is unfair. The panel also
notes the following:
PP‟s quote included „Furniture Removalist‟ for $18,040 even though this is
separately allowed in S‟s quotation
RP‟s more recent quote dated 30 January 2019 ($67,146.23) for the repairs is les s
than PP‟s quote
no evidence to show the accommodation allowance or rate is unreasonable – the
timeframe is also consistent with PP‟s quote
a more recent quotation from S for furniture packing/removal/reinstatement totalled
$33,000 – this is less than the insurer‟s allowance of $37,400
the panel is not satisfied that further movement damage identified by the
complainant was caused by the claimed event or repairs
The panel notes that the repair quote and the furniture are outdated. However, the
panel also notes that the more recent quotes show the older ones were generous.
Particularly PP‟s quote which included furniture removal.
Further, the insurer added $15,024.80 to its overall liability. This provides an
allowance for contingencies and variances to the works.
Given this, the panel considers the insurer‟s offer is fair subject to the restumping not
requiring further works.
The complainant also says her heating costs increased as the insurer did not correctly
install a heating unit. The insurer has accepted liability for this issue. On provision of
utilities bills showing an increase in costs, the insurer should reimburse the
complainant.
Determination | Case number: 660650 Page 9 of 14
Insurer should add 30% if further restumping is required
The panel recognises that if additional restumping works is required, further damage
to the property is likely to occur.
This claim has been protracted. The claimed event occurred almost 10 years ago.
This is the third dispute lodged between the parties. Given this, the panel considers it
is fair in all the circumstances that, where possible, finality be achieved to this dispute.
Therefore, the panel considers that if further restumping work is required, the insurer
should pay an additional 30% to the settlement figure. This is due to the following:
if further scopes and quotes had to be obtained following the restumping works,
this will protract the dispute further and possibly lead to further disputes – this is
undesirable for all parties
the insurer has had sufficient opportunities to check and ensure the restumping
was done properly yet, to date, the information still has not established if this is the
case (i.e. that the restumping was properly designed)
it is likely further damage will occur if further restumping work is required
this allowance should be sufficient to account for the further damage
The panel acknowledges the last decision said the insurer should attempt to complete
the works. However, it is not clear how practical this is when there appears to be site
drainage issues, tree influence and other maintenance issues that need to be
addressed.
Instead, the panel considers it is fair in all the circumstances that the repairs be cash
settled to provide finality to this dispute.
Determination | Case number: 660650 Page 10 of 14
3 Supporting information
3.1 Relevant policy provisions
Repairing or rebuilding your building – other costs
We will also pay for the following where applicable.
Compliance costs
In repairing or rebuilding your building, we will pay the extra costs necessary to
satisfy the current requirements of any local council or government authority.
3.2 Reports
All information has been considered in providing this determination. A summary of
referenced reports is below:
Record Key points
Insurer’s engineer (FM)
Soil classification and footing
recommendation report
23 January 2013
Fill was observed in the borelogs undertaken and observed at
between 450mm and 500mm
The site is classified as „P‟ to account for… the presence of
significant fill found on site…
The site is classified as „P‟ (due to significant fill one site). The
footing des ign can be selected for an ‟S‟ site classification based
upon the reactivity of the soil as set out in AS2870.
Perimeter and internal strip footings shall be founded a minimum
of 475mm below surface level, having a minimum depth of
400mm, and be founded a minimum of 150mm into A Horizon Silty
Sand.
Stumps placed internally should be founded 400mm minimum
below surface level and at least 150mm int o A Horizon Silty Sand.
Insurer’s engineer (MP )
Restumping compliance
inspection
22 August 2016
The Insured indicated that the previous timber stumps were
replaced with concrete stumps by a builder appointed by the
Insurer. However, the Insured was not sure whether the original
pad footings were replaced or not.
The Insured is of the opinion that th e subfloor stumps are
undersized and are not deep enough as not ed by her builder.
We reviewed the soil investigation report by FM , dated 23 January
2013. This soil investigation report indicates that the subject site
can be classified as „P‟ due to significant fill on the site. The
borehole information shows that this filling material depth is
approximately 450mm to 500mm in the sub ject site. The soil below
this filling material was found to be A Horizon Silty Sand. The soil
investigation report recommends that the footing design for the
subject site shall be carried out for a “S” site classification. It
further states that the stump s placed in the subfloor area shall be
founded 400mm minimum depth below the surfac e level and at
Determination | Case number: 660650 Page 11 of 14
Record Key points
least 150mm int o A Horizon Silty sand.
We were unable to determine the dept h of the pad footings, as we
did not excavate to that extent due to limited access. However, we
observed filling material on top of most of the pad footings.
Therefore, the depth of the pad footing should be at least 150mm
thick, assuming A Horizon silty sand starts form the top of the pad
footing.
We noted that the soil investigation re port indicated that subject
site has filling material up to 450 to 500mm depth. We observed
that top of the pad footing was located approximat ely 100mm to
150mm below the surface ground level of the subfloor area.
Therefore, it is possible that some of the pad footings have been
placed just on the filling material and they have not been founded
150mm below the A Horizon Silty Sand, as recommended by the
soil investigation report. It is also possible that the builder has
used deeper pad footings to fulfil th is requirement.
Notwithstanding this, we rec ommend the builder appointed by the
Insurer provides certification/assurance that they have carried out
works as per the rec ommendation given in the soil investigation
report. Alternatively, we are able to re - att end the site and excavate
some of the pad footings to det ermine whether the builder has
carried out works as per the given recommendations, if you
consider it warranted.
Insurer’s building inspector
( GC )
Stump footing audit report
11 April 2017
T he buildi ng permit required a conc rete pad depth of 450mm
below the ground. My inspection of several pads on 20 January
2017 revealed that the base of the pads was at least 450mm
below the ground surface.
The building permit documentation for the reblocking work do es
not comply with the requirements of the building regulations.
The reblocking work did not comply wit h all the requirements of
the building permit, but is still adequat e from a structural viewpoint .
The completed work does not comply with the building permit as
the stump pads are round: not square as specified on the building
permit.
The building permit required a concrete pad depth of 450mm
below the ground. My inspection of several pads on 20 January
2017 revealed that the base of the pads was at lea st 450mm
below the ground surface.
A design by a qualified engineer was required for the stump pads
in Class P soil classification. The building permit was issued
without an engineer‟s design and the work was performed wit hout
the required engineer‟s desig n.
Whether or not the reblocking work is required to comply with the
building permit documents, or alternatively the requirements of the
building regulations and its relevant referenced building codes is a
legal matter and could be dependent on the buildin g contract.
There is no structural requirement to repair any of the reblocking
work and the work does not contain any significant defects.
The work carried out by EA primarily complies with the building
Determination | Case number: 660650 Page 12 of 14
Record Key points
permit documentation, except that the conc rete pad footings are
300mm in diameter rather than 300mm x 300mm square. Whilst
the 300mm diameter pads are approximately 20% less in area
than the 300mm square pads specified, the 300mm diameter pads
are only working at 73% capacity; and are therefore structurally
adequate.
Increasing the area of the pads to 300mm x 300mm would not
result in any quantifiable increased performance of the work
executed by EA, and would be both a redundant and wasteful
exercise in my opinion.
… there is evidence that EA provided an exemplary standard of
work. Prime examples of the high standard of EA‟s work include
minimal sized and incompressible packers, as well as steel plate
connecto rs at bearer joints.
… the stump pad sizes are lesser in area than their specified area
on the building permit endorsed plan, they are still adequate in
area to perform satisfactorily.
FOS‟s Determination cited unsupported bearers, poorly installed
stumps, loose stumps, remaining old stumps, no ant caps on
stumps, and crushed heating ducts. None of this work applied to
the work conducted by EA in my view.
Insurer’s engineer (FM )
Report on stump pads for
building regulation compliance
25 August 2017
EA Restumping provided FMG with the following information in
relation to the restumping works that have been carried out at the
subject house:
> Stump footings (including soleplates) founded at 700mm below
natural ground level.
The FM Report classified the si te as Class P due to the pres ence
of fill found on - site.
The FM Report calculated the maximum y s (characteristic surface
movement (mm)) value at this site to be 0mm.
The subject stump footings are understood to have been founded
a minimum of 700mm below natural ground level, which meets the
requirements of the founding depth for stump footings provided in
the FM Report.
In FM‟s opinion, the subject stumps have been installed
adequately through the fill layer present at the subject site (based
on the FM Report and EA Restumping information) and these
stumps are not expected to be adversely impacted by the fill. In
the absence of fill, FM considers the subject site to be a Class A
site (i.e. non - reactive) and a stump footing system may be
designed accordin gly.
FM observed the following items considered to be consistent with
poor building maintenance:
> Debris and/or vegetation loc ated within eaves gutters, including
those understood to have been installed by the insurer since the
Event.
Insurer’s engineer (MC)
Ongoing movement causation
The home generally presents in a poorly maintained condition wit h
significant defects and deficiencies to the property that has
Determination | Case number: 660650 Page 13 of 14
Record Key points
report
15 November 2018
resulted in long term building movement, with the further and
ongoing development of movement.
Proximate Cause
The purported on - going building movement and damage is due to
the pre - existing site conditions and general absence of adequate
maintenance not limited to the defects outlined wit hin this report
and further reiterated below:
‒ Absence of a surface storm water drainage system.
‒ Ground surface levels graded toward s the home.
‒ Absence of eave guttering.
‒ Corroded eave guttering
‒ Absence of subfloor ventilation.
‒ Subfloor ground surface levels lower than external ground
surface levels.
‒ Proximity of maturing trees.
The ongoing building movement is not relat ed to the purported
flooding event of January 2011, and is consistent with the defects
and deficiencies to the property.
Complainant’s engineer
(MA)
Assessment of structural
integrity of foundations
26 March 2020
Photographs taken by the home owner at the time this work was
carried out indicate that these pads were founded at no more than
300 mm below the existing ground level. Some of the stumps have
not been adequately fixed to the original bearers.
A geotechnic al report, No. 97A22, prepared by SS in 1997, pri or to
the construction of the two storey addition, gave the site a Class P
rating in accordance wit h AS 2870 - 2011, i.e. it is a “Problem”
site. This classification reflects the large depth of filling (up to 1400
mm) discovered above the natural sand in t he exploratory
boreholes.
In our opinion , the reblocking/restumping work that was carried out
in 2016 was less than an acceptable standard. This conclusion is
based on the founding depth for the replacement stumps, being
300 mm approximately when the recom mended founding depth for
this site is 1400 mm. The Geotechnical report provided in 1997
was available to the cont ractors who carried out the work, however
it is understood that anot her report was provided to the contractor
which was not made available to the home owner.
At the time of our inspections, almost no cracks were in evidence
internally, and similarly for the external brickwork veneer cladding.
It is assumed that these have all undergone some form of repair.
Insurer’s building consultant
(MC)
Rep ort: Damage to property
17 April 2020
The restumping works to the premises generally appears to have
been undertaken and completed in the absence of an approved
engineering design.
The absence of the engineering design within the building permit
leads to suggest that the restumping works were not completed in
accordance with an approved engineering design.
The restumping works are required to have been complet ed in
accordance with an approved engineering design.
In the absenc e of an approved engineering de sign, the restumping
Determination | Case number: 660650 Page 14 of 14
Record Key points
works is considered to have not been completed to an acceptable
standard .
The property has several pre - existing issues as previously d etailed
within the MCS Reports, that will result in further and o ngoing
movement to the premis es.
T he restumping of the home is recommended to be completed in
accordance with an approved engineering design and building
permit conditions.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.