Home / Suncorp Group / Determination 659743

Determination 659743

Refusal to pay for deteriorated stumps; inadequate settlement offer; premature repairs after water inundation

FirmSuncorp Group
Decided2020-07-24
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$213,400
Non-financial loss$5,000
Amount claimed—
SourceAFCA PDF

Summary

The insurer refused to pay for decayed stumps after a sewer overflow and offered $89,474.83 on an incomplete repair quote, after it had started repairs too early. AFCA ordered payment of the $213,400 sum insured with interest, $5,000 non-financial loss, and further policy benefits and utility costs.

The insurer bears the onus to prove an exclusion applies and did not establish that long-term decay was the proximate cause; a settlement must be fair and based on a reliable quote.

Issues

Subjects and remedies

home or building damagepay claimpay compensationpay interestpay non financial loss

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 659743 Financial firm AAI Limited Determination | Case number: 659743 Page 2 of 20 Case number: 659743 21 July 2020 1 Determination overview 1.1 Complaint The complainant held a home building insurance policy with the financial firm (insurer). In September 2016, a council pipe broke and the property was inundated for several days with stormwater and sewage waste, resulting in movement related damage to the home. The insurer accepted the claim. The insurer commenced repairs before allowing sufficient time for soil drying, resulting in the requirement for significant rectification work. The insurer says it will cover related damage, yet it is not liable for stumps which it says were deteriorated before the loss. It offers settlement for outstanding damage on this basis. The complainant says the condition of stumps is a result of the water inundation and subsequent actions of the insurer. She says finished repairs are of a poor standard and damage is ongoing. She also says the claim experience has taken an emotional and financial toll. 1.2 Issues and key findings Is the insurer liable for the deteriorated stumps? The insurer says the proximate cause of damaged stumps is long term deterioration which is excluded under the policy. The panel is not satisfied this is the case. As the insurer has not established an exclusion applies, it is liable for the stumps. Is the insurer’s settlement otherwise offer fair and reasonable? The insure r‟s settlement offer is not fair as it is based on an incomplete quote. The insurer is liable for the lesser cost of rebuilding the home or the policy sum insured plus applicable additional benefits. Is the complainant entitled to any compensation? The cla im has not been managed in line with the complainant‟s reasonable expectations, resulting in an unusual degree of stress and inconvenience. The complainant is entitled to $5,000 compensation for non-financial loss and subject to proof is also entitled to the indirect financial costs of increased heating and cooling. Determination | Case number: 659743 Page 3 of 20 1.3 Determination This determination is substantially in favour of the complainant. Should be complainant accept this determination then within seven days of notification of acceptance, the insurer is to pay to the complainant the sum insured of $213,400 and $5,000 non-financial loss compensation. The insurer is also to pay interest on $213,400 pursuant to section 57 of the Insurance Contracts Act (the Act) from 5 March 2020 (the date of the insur er‟s offer) until settlement. Taking into account the policy limits and policy terms and conditions and past conduct, the insurer is to indemnify the complainant for the fair costs of demolition and removal of debris and benefits payable under temporary accommodation and the cost of removing and storing the contents of the home. Subject to the AFCA Rules limit of $5,000 for indirect financial loss and requisite proof, the insurer to compensate the complainant for any increased costs in utilities bills from July 2018 (the date it was advised repairs were failing). Interest pursuant to section 57 of the Act is to be paid on the agreed sum from the date of payment of the utility bills by the complainant until settlement. Determination | Case number: 659743 Page 4 of 20 2 Reasons for determination 2.1 Is the insurer liable for the deteriorated stumps? Insurer must establish exclusions apply The complainant must establish, on the balance of probabilities, she has suffered loss or damage which is covered by the terms and conditions of the policy. This is known as a prima facie or valid claim. Once the complainant establishes this, the onus shifts to the insurer to demonstrate a policy exclusion applies, or cover is otherwise limited. It is not in dispute the complainant‟s policy covers damage resulting from an esca pe of liquid, and this event caused damage at the home. The insurer says some subfloor stumps were deteriorated and damaged before the loss because of gradual deterioration. It says damage because of gradual deterioration is excluded from cover and it is therefore entitled to decline cover for these stumps. The panel accepts there was damage to the home because of an insured event, and views this as prima facie evidence of an insured event to account for the claimed loss, including the deteriorated stumps. On this basis, the panel considers the onus shifts to the insurer to show, on the balance of probabilities, it is entitled to rely on policy exclusion(s) to limit its liability under the claim. Insurer engaged forensic engineer to review evidence Throughout the life of the claim, the insurer obtained engineer and assessment reports on the condition of the property. Early reports noted relevelling the floor was required due to movement, yet these reports identified no damage to the subfloor stumps. The complainant disputes the accuracy of reports. She said stumps had almost completely decayed because of the loss, therefore the insurer is liable for this damage. In support, the complainant supplied photographs and video footage showing subfloor stumps in a decayed state. Late last year, the insurer agreed to engage a forensic engineer (FM) to review early reports and comment on current condition of the home. FM found:  stumps, primarily located beside the unpaved rear side and side of the home, are in an advanced state of decay and resulted in a failed footing system  the advanced state of decay has been exacerbated by poor site drainage, including a lack of pavement, and further exacerbated by the claimed overflow event. Determination | Case number: 659743 Page 5 of 20  stumps located closest to the unpaved side of the home were in relatively worse condition than other stumps  footing movement, resulting from on-going changes in soil moisture content, contributed to damage  the lifespan of the stumps is between 15 and 30 years, and full-service life has expired  decay would have been obvious when the floorboards were removed and replaced  there is no evidence that any party had previously investigated the condition of stumps. The panel notes the age of the building is not definitively established. FM esti mates the building was constructed over 30 years ago. FM says decay was exacerbated by the overflow event, yet it does not describe the extent. The panel considers such discussion important, particularly in circumstances where soil moisture was so greatly increased as to require mould removal, and therefore considers FM‟s report as lacking in relevant detail in this regard. Additionally, the complainant reported a downpipe was left off after the insurer conducted initial repairs, causing water to disperse around the house‟s rear during rainfall events. FM make no comment as to any potential impact this may have had. The report confirmed the complainant‟s view that stumps are damaged and require replacement. Findings of insurer’s other engineers Soon after the claim was lodged the insurer arranged for an engineer (IE) to attend the property and report on the cause of damage. The property was inspected on 16 March 2017 and IE concluded the overflow and subsequent inundation had caused the reactive clay soil to swell, causing movement damage to the home. IE recommended re- levelling the house by „jacking and packing‟ between existing stumps and bearers. IE specifies „existing stumps‟ when discussing repair methods, and in the same report says there i s no sign of failed footings. In the panel‟s view, this statement suggests IE probably considered the condition of stumps. IE recommended monitoring soil moisture for two years prior to conducting repairs, however the insurer arranged repairs before this period had expired. As a result, repairs failed, and rectification work was required. The panel acknowledges mould damage required the early intervention, but the panel also notes FM‟s strong recommendation that the complainant should have been made aware of the condition of the stumps and should have been warned that it was premature to commence repairs. Determination | Case number: 659743 Page 6 of 20 A second inspection occurred on 4 September 2018 after repairs had failed. IE was directed to matters of concern by the complainant, including issues relating to stumps. IE make no mention of the condition of the stumps in this report. IE later prepared a scope of works in August 2019 which, again, makes no mention of deteriorated stumps. Throughout the claim, subfloor work has been ongoing and involved multiple parties. Work involved stripping the existing tongue and groove flooring, replacing it with new materials, and installing new stumps. Rectification work was later required relating to the new stumps. Tellingly, a scope of works prepared by builder PB in April 2017 describes what actions to take if significant damage is found underneath the floor, implying the potential for stump damage was recognised. In short, the floor and subfloor has been a significant part of the claim, increasing the likelihood t hat the pre- existing deterioration of stumps (if it existed) would be identified. In circumstances where subfloor work was central to repairs, the panel consider FM‟s view that the advanced state of decay should be obvious is particularly significant. None of the various parties involved in repair and assessment, including an engineer and assessor engaged soon after the loss occurred, identified any pre-existing decay or gave proper advice to the complainant before commencing remedial repairs. The panel also notes multiple drainage issues at the property were raised by the assessor in early 2018. While IM say these issues did not contribute to damage, the panel is further persuaded the insurer and its agents were aware of factors which could cause or exacerbate stump decay. Despite this, no such decay was observed or taken into account. Deteriorated stumps not observed immediately after the loss The insurer relies on FM‟s report and says the proximate cause of damage to stumps on the unpaved side of the home is gradual deterioration. It says this damage is excluded under the policy therefore it is not liable for the impacted stumps. While FM provides a strong opinion as to the cause of damage, the onus is on the insurer to establish an entitlement to rely on exclusions on the balance of probabilities. The panel is not satisfied FM‟s views can be relied upon to the exclusion of all others. FM attended the premises over three years after the insured event. Comparatively, other agents of the insurer were onsite soon after the overflow and regularly over the following years. IE attended the property less than six months after the loss and, while methods of investigation are not described, says no sign of failed footings was observed. Similarly, assessors and tradespersons who replaced flooring and stumps did not observe any decay or rot, evidence of which FM says would be obvious to any repairer. The property was described as in a fair condition with no maintenance required. Determination | Case number: 659743 Page 7 of 20 Insurer is liable for deteriorated stumps FM accepted the insured event contributed to the decayed condition of the stumps. This is significant as it affirms the panel‟s view the stumps should be covered, particularly as FM‟s report was so long after the event and the other more contemporaneous reports cite no apparent issues. The available evidence does not support the view the prior inspections were insufficiently thorough (compared to FM) or did not pay attention to the stumps. This leaves the evidence from FM as an outlier, which might be explained by the passage of time since the event, and the likelihood of ongoing deterioration and damage because of it. On review of available evidence, the panel is not satisfied the insurer has shown the proximate cause of damage is long term decay. Therefore, the panel is of the view the insurer is liable for the deteriorated stumps. This is so not only because of the above analysis but because FM was unable to provide an opinion about the extent of damage caused by the inundation event because of the time which had elapsed between the event, the repairs and FM‟s inspection of the property. In the circumstances, the panel is not satisfied the insurer has reasonably met the onus to establish the policy exclusion relied on. 2.2 Is the insurer’s settlement offer o therwise fair and reasonable? Complainant says property is poor condition and cannot be repaired The complainant says the tongue and groove flooring was damaged when the insurer raised the home. In support she supplied photographs and video footage showing sunlight visible through gaps. The material supplied by the complainant clearly depicts sunlight visible through gaps in floorboards. Additionally, the complainant says other work is either outstanding or inadequate, or the insurer has not assessed certain damage, including:  roof and gutters have twisted as a result of movement  bathroom toilet has lifted from the floor  bath drain is partially blocked and draining slowly  property displays cracks in wall and ceiling  there is a large gap under front door  kitchen cupboards are unsecure. The insurer has offered to pay the complainant $89,474.83 to settle the loss. It bases this amount on the cost to restump the building in situ, the cost of drainage repairs and internal cracking. It includes cost of installing new tongue and groove flooring in the quote for restumping. Determination | Case number: 659743 Page 8 of 20 The complainant rejects this offer on the basis it will not allow her to complete repairs to her home. FM unable to provide scope of works due to foreseen and unforeseen blowouts The insurer requested FM to provide a scope of works for restumping the home, and repairs and rectification work. FM responded advising repairs should not proceed until the inadequate and failed footing system had been replaced which would require moving the building off site. FM later clarified that whatever repair method was adopted, foreseen and unforeseen complications would cause budget blowouts and time delays. FM suggested the insurer consider construction of a new home, or a cash settlement. Insurer bases settlement offer on incomplete information After FM indicated it would be unable to provide a scope of works, the insurer sought quotes from builders (JG). JG provided separate scopes for rebuilding the home, restumping with the building moved off site, and restumping without moving the building. The insurer‟s offer of settlement is based on the quote to restump without moving the building. The quote for restumping, prepared by builder JG, allows for installation of new footings, tongue and groove flooring and subsequent painting. It lists standard exclusions to its scope and various other fees and costs which may be incurred. The panel notes with concern the broad exclusion for „any item not detailed in the scope of work‟. JG proposes to install a pile system bas ed on a yet to be determined engineer‟s scope of proposed works. An allowance for engineer‟s costs is not included. It is clear the quote will increase, most likely substantially, should it ever be actioned. Of particular concern, JG notes all care will be taken yet it will not guarantee further damage will not occur, given the nature of works to be carried out. It says, should work proceed, further details of all risk and costings can be provided. The panel is concerned the insurer bases its offer on a quote which is clearly incomplete and explicitly states work cannot be guaranteed. This concern is compounded when the panel considers FM‟s advice which states any scope will increase due to foreseen and unforeseen cost blowouts and delays. Additionally, the insurer does not include costs such as alternative accommodation arrangements or moving and storing contents while any proposed repairs occur. Determination | Case number: 659743 Page 9 of 20 The panel does not consider the settlement offer made by the insurer is fair or reasonable. This is not only because of the analysis set out above but also because the insurer‟s actions in repairing the home prematurely without adequate warning, have resulted in repairs and rectification required to the home which the insurer‟s own expert is reluctant to cost but says a fair resolution is the rebuild of the home or provide a cash settlement. Insurer to pay what it would cost to repair the damage or pay the sum insured The policy describes how the insurer may settle the claim. If it agrees to pay a claim it will decide whether it will repair the damage or pay what it would cost to repair the damage or pay the building sum insured shown on the certificate of insurance. The policy stipulates where the insurer rebuilds, repairs or pays the policy holder the equivalent costs, it will do so on a new for old basis. The policy definition of new for old states the insurer will repair to the same type, standard and specification as when new. The policy also includes a lifetime guarantee on building repairs. Any offer to pay the complainant the cost of repairs should reflect these policy provisions and should be fair. A fair cash offer must take into account variations and contingencies which may occur during repairs. Further, a fair cash offer should reflect the transfer of risk to the insured who loses the lifetime guarantee on building repairs. The panel is not satisfied the insurer has supplied a fair or reasonable quote for repairs on which a negotiated settlement can be based. The panel considers the insurer has had ample time to obtain such a quote. It first engaged FM to report on the condition of the home, and what was required to repair it, in September 2019. Its settlement offer was not made until March 2020, partially due to the reluctance of FM to provide a scope. In December 2016, the property was described as in fair condition with no maintenance required. The insurer reviewed the condition of the home on 21 June 2018 and elected to continue insuring the property as it had not found any indication the home was in poor condition. The property now requires substantial restumping and rectification work. Determination | Case number: 659743 Page 10 of 20 The insurer accepts damage has occurred as a result of an insured event. It accepts liability for rectification as a result of repairs which commenced prior to soil sufficiently drying. The panel considers the insurer is liable for deteriorated stumps. This liability extends to costs resulting from the repair or replacement of these stumps. The panel notes if the most appropriate repair method is restumping the entire building, the insurer is liable for the entire cost. The panel considers this a fair outcome in circumstances where the insurer‟s own expert engineer is reluctant to provide a scope of works a nd says a more appropriate resolution is the construction of a new house or a cash settlement. Considering the insurer cannot provide a quote which guarantees work will not fail or cause further damage, the panel is not satisfied it is fair or reasonable for settlement to be based on the quote relied on. The panel notes the insurer has acknowledged it could have better addressed the requirement to have the stumps replaced before proceeding with repairs. The panel also notes the insurer‟s submission about b etterment. However, in circumstances where the insurer is unable to establish to the panel‟s satisfaction the extent of exacerbation caused by the inundation event, and FM‟s reluctance to cost an outcome where the insurer is only liable to repair some of the stumps, the panel is satisfied the outcome proposed in this determination is the fairest outcome. The panel considers it is fair the insurer rebuilds the home or settles the complainant for the sum insured. The only available evidence establishes it is likely the cost of rebuilding the home ($315,308.79) exceeds the sum insured ($213,400) at the date of loss. Therefore, the panel is satisfied a fair outcome is that the insurer pays to the complainant the sum insured of $213,400. The insurer is also to pay interest on $213,400 pursuant to section 57 of the Insurance Contracts Act (the Act). The section provides interest is payable from the day on which it was unreasonable for the insurer to have withheld payment. In view of the material from FM in January 2020 and the costing from JG in February 2020, and allowing necessary time to consider this material, the panel considers it is fair interest is paid from 5 March 2020 being the date of the insurer‟s offer until the date of settlement. The policy provides additional features in addition to the cover provided under building insurance. This includes the reasonable and necessary cost of demolishing and removing the damaged parts of the building from the insured address and temporary accommodation (both of which are limited to 10% of the building sum insured and are subject to policy terms and conditions). Taking into account the policy limits and policy terms and conditions, the insurer is also to indemnify the complainant for the fair costs of demolition and removal of debris and benefits payable under temporary accommodation. Determination | Case number: 659743 Page 11 of 20 The complainant also seeks the cost of removing and storing the contents of the home. This benefit is not covered by the policy. The panel is satisfied it is fair the insurer includes this item in the settlement in circumstances where the complainant was not sufficiently advised of the ramifications of early repairs which resulted in delays and ongoing rectification and an outcome which would otherwise not have occurred. On the available information, the panel is unable to quantify these additional benefits. The parties are encouraged to work together to formulate a fair settlement. However, if this aspect of the complaint cannot be agreed, the parties can return to AFCA for a further determination on the quantum of these additional benefits. 2.3 Is the complainant entitled to any compensation? AFCA may award compensation in certain circumstances Under paragraph D.3 of the AFCA Rules, we may award compensation for non- financial loss (capped at $5,000) where there has been an unusual amount of:  physical inconvenience  time taken to resolve the situation  interference with the complainant‟s expectat ion of enjoyment or peace of mind. We take a conservative approach to compensation and expect a complainant to bear a normal degree of inconvenience during a claim. We can also award compensation for financial loss (out of pocket expenses or other liabilities, which are caused because of the insurer‟s conduct). This is capped at $5,000 per claim. Complainant entitled to costs and compensation for non-financial loss The complainant is dissatisfied with the insurer‟s management of the claim. She says delays and inadequate repairs caused significant stress and she was required to be heavily involved in the process. The insurer arranged repairs without allowing sufficient time for soil to dry, against its engineer‟s advice. The panel acknowledges the repairs we re commenced because of mould issues. However, the panel is satisfied the complainant was not sufficiently advised of the ramifications of these early repairs. This decision resulted in lengthy delays and a requirement for ongoing rectification, which would otherwise not have occurred, and which caused significant disruption for the complainant. Determination | Case number: 659743 Page 12 of 20 The panel does not consider that the claim has been managed in line with the complainant‟s reasonable expectations. The complainant was involved in the claim to an unusual degree and has suffered significant interruption, frustration and distress as a result. Taking all matters into account, the panel is satisfied it is fair the insurer pays $5,000 in compensation for non-financial loss. Additionally, the complainant says utilities costs increased as gaps in flooring and throughout the home resulted in the uneconomical use of heating and cooling. She supplied a utilities bill showing usage equivalent to a home of over four occupants yet says she lives alone. She also supplied photographs of the gaps in the flooring. Subject to the AFCA Rules limit of $5,000 for indirect financial loss, the panel considers it reasonable for the insurer to compensate the complainant for any increased costs from July 2018, that being the date it was advised repairs were failing. This is provisional on the complainant supplying utility bills showing current usage against pre-loss usage, preferably spanning 12-months of each period. The insurer should use these bills to establish an average differential rate and apply this from July 2018 until the date the claim is resolved. Interest pursuant to section 57 of the Act should be paid on the agreed sum from the date of payment of the utility bills by the complainant until the date of settlement. Determination | Case number: 659743 Page 13 of 20 3 Supporting information 3.1 Our Approach This complaint has not been the subject of a recommendation. Due to the nature of the complaint, it has been referred directly to a panel for determination, in line with the Operational Guidelines to the AFCA Rules. The panel consists of an ombudsman and two representatives with consumer and insurance experience. The panel has decided this complaint based on what is fair in all the circumstances, having regard to legal principles, applicable industry codes or guidance, good industry practice and previous relevant determinations of AFCA or predecessor schemes (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. The panel has reviewed and considered all the material provided by the parties. While the parties have raised numerous issues in their submissions, for the purposes of this determination the panel has restricted its commentary to those issues that it considers directly relevant to the outcome only. It is an accepted principle of general insurance law that the insured bears the onus to establish on the balance of probabilities that they have suffered a loss caused by an event to which the policy responds. This is known as a prima facie claim. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss. For some part of the complaint, the complainant was represented. Where relevant, references to the complainant include references to the complainant‟s representative. 3.2 Relevant policy terms The relevant policy terms are referred to in correspondence between the parties and in the additional notice of response. The notice and the policy document have been exchanged with the complainant. What you are covered for – insured events Escape of liquid We cover Loss or damage to the building caused by liquid leaking, overflowing or bursting from any of the following:  refrigerators, freezers, dishwashers and washing machines; Determination | Case number: 659743 Page 14 of 20  any drain, fixed pipes, roof gutters or guttering and rainwater downpipes, drainage and sewage systems;  fixed tanks;  swimming pools or spas;  waterbeds;  baths, sinks, toilets and basins;  fixed heating or cooling system;  water main, fire hydrant or water supply pipe;  an aquarium. We do not cover …  wear and tear, or loss or damage by the escape of liquid occurring as a result of a gradual process of leaking, splashing, dripping or overflowing over a period of time when you could reasonably be expected to be aware of this condition; …  loss or damage caused by wear, tear, rust, fading, rising damp, mould, mildew, corrosion, rot. What we do not cover – general exclusions You are not covered under any section of your policy for damage, loss, cost or legal liability that is caused by, arises from or involves: Wear, tear and gradual deterioration wear, tear, rust, fading, rising damp, mould, mildew, corrosion, rot, action of light, atmospheric or climatic conditions or gradual deterioration such as, but not limited to:  tiles and their adhesive or grouting breaking down;  weathering of roof tiles or roof ridge capping;  gradual weathering and breakdown of bricks, mortar or concrete. Ground movement erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage or any other earth movement, but we will cover landslide or subsidence that is specifically covered under the following insured events:  „Storm‟;  „Flood‟ (but only if you have cover for insured event „Flood‟);  „Earthquake and Tsunami‟; Determination | Case number: 659743 Page 15 of 20  „Explosion‟. We will not:  pay more than the relevant sum insured (unless you have the Complete Replacement Cover® option) or policy limit;  pay extra to repair or rebuild the building to a better standard, specification or quality than it was before the loss or damage occurred except as stated in the meaning of „new for old‟;  fix a fault that existed before the loss or damage occurred. … Repairing or rebuilding damaged parts We will only repair or rebuild the parts that are damaged in the incident covered by your policy.” 3.3 Relevant extracts from material provided by parties Date Action Insurer report (IE) 3 April 2017  Inspected and photographed 16 March 2017 to determine the cause of damage due to the subfloor inundation as a result of sewer overflow.  Floor comprises timber floorboards, joists and bearers supported above ground on timber stumps.  Since the inundation and storm event house experienced movement and damage.  Some internal cracking shows signs of age. Majority of cracking not rec ent.  Floor uneven and settles to the window next to the kitchen and the bathroom window is out of alignment.  Bore logs show foundation soil has an upper layer of silty soil underlaid by reactive clay soil. Possible moisture lev els in the deeper soils have increased because of the moisture concentrations that led to the collapse of the upper soil.  Level survey conducted and levels vary from a maximum of +4omm to - 144mm.  Spot level shows house generally settled towards the front with a significant settlement next to the kitchen.  Hous e moving cracking throughout its life bec ause of the moisture changes in the soil.  Recent subfloor inundation has contributed to hous e movement. Made some of the existing cracking and movement wors e. H ous e will continue to move a soil dries out. Repairs should be wit hheld until soil is dry out and hous e stabilises.  Recommend we reinspect in September 2017 and Determination | Case number: 659743 Page 16 of 20 Date Action provide a scope of works once house settled.  Without prejudice, the repairs to the inundation - induced damage would including: > • Re - levelling the house by jacking and packing between the existing stumps and bearers; > • Re - adjust all doors and windows to ensure full working operation; > •Cosmetic repair wall, ceiling and cornice cracks throughout. > • Replace cracked tile adjac ent bathroom window and re - grout bathroom, where required; > • Paint repaired surfaces to match existing. Insurer report (IE) 12 September 2018  Reins pected 4 September 2018 to determine the cause of cracking damage seen after repairs.  Recorded cracking in the cornices and wall in the bathroom and living room.  Gaps scene between floorboards in the living room.  Downpipe next to the toilet was left off by the builder causing water to disperse around the house‟s rear during rain.  Pattern of movement not consistent with disconnected stormwat er pipe or tank overflow. Repairs were undertaken (too) early because of reported mould damage.  Recent cracking around the internal walls has been caused by settlement of the foundation soil bene ath the house‟s centre as the inundated affected soil has continued to dry out. Based on the available evidence, there may still be some furt her movement in the house as the inundated affected soil continues to dry out.  Recommend monitoring the house over the coming summer period, by reins pecting in May 2019. This should allow us to determine the appropriat e time for final repairs, which would include cosmetic repainting and redecorating only. Insurer report (IE) 3 October 2018  Cracking in the bathroom has not created a potential for a fire risk in the electrical work in the walls, or the potential for additional damage due to the humid bathroom environment.  Based on the recent cracking, it appears the repairs to the house were undertaken prior to the influence of the inundation fully dissipating. ….these repairs were required to be undertaken to remediate the mould issues, and so the recurrence of some damage was unavoidable in the circumstanc es.  All movement and damage relatin g to the original event in September 2016 will fully dissipate over time. In light of the recent movement, there may still be Determination | Case number: 659743 Page 17 of 20 Date Action some minor movement in the near future and recommend reinspecting after the coming summer period, in around March 2019, to determi ne the extent of remaining damage from the event that requires repairs. These final repairs will consist of cosmetic crack repairs and repainting only. Insurer report (IE) 3 July 2019  Reins pected 18 June 2019 to determine damage since repairs.  Continued movement with new cracking. Toilet lifted from the floor. Front and rear doors out of alignment.  Adequate time provided for any soil affected by the inundation in 2016 to dry out and return to the condition it held prior to the inundation. Therefore, fina l repairs to the house as a result of the inundation could be considered.  Influence of the 2016 inundation has dissipated.  Minor cracking and movement can be repaired. Install a flexible joint in the pipe under the toilet. Scope can be provided.  Movement in the toilet pipework suggests the possibility of a further pipe leak. Recommend testing the house‟s plumbing to det ermine if there are any additional leaks.  Hous e will continue to move and crack in the future due to seasonal and environmental factors un related to the inundation event in 2016. Therefore, any repairs to the house cannot be guaranteed. IE Scope of works 19 August 2019  Possible that other work may be required to ac hieve total reinstatement.  Other building repairs not specified in this Scope of Works may become necessary if work at the site exposes additional damage or circumstances not previously considered. Engineer’s report (FM) 27 November 2019  Senior forensic engineer inspected and photographed property with the complainant on 23 O ctober 2019.  Reviewed several reports provided to him.  Estimates house constructed 30 years ago. Floor is a timber framed construction support ed by stock footings. Footings are mainly timber stumps buried in the ground and (recently installed) bearing on concrete blocks.  Undertook level survey. Total variance in levels across house 78mm. General pattern of settlement towards the north west. Assumes house faces West.  Soil tests show soils are extremely reactive.  Describes internal damage as very slight.  In ternal damage caused by failed footing system as a Determination | Case number: 659743 Page 18 of 20 Date Action result of the severe (long - term) decay of the timber stumps located mainly along the (unpaved) elevations of the house to the nort h and east ( by far the predominant cont ributing factor to the observed dam age) and differential footing movement resulting from on - going, differential changes in the moisture content of the extremely reactive foundation soils due to seasonal changes in soil moisture and inadequate site drainage particularly along the east (rear) .  Typical lifespan of hardwood timber stumps supporting the house lies somewhere between 15 to 30 years.  Timber stumps supporting the hous e have gradually decayed over time as a res ult of being in contact with the ground for their full - service life thus fa r.  Observed severe to total decay of the timber stumps, mainly along the (unpaved) perimet er of the house to the north and east, has been exacerbat ed by the prevailing poor drainage conditions as a result of the lack of any protective impervious pavement in t his area.  Decay has been further exacerbated by the sewer overflow event of 2016.  This is in contrast to the naturally weathered and aged (but not decayed) timber stumps along the (paved) western perimeter.  On - going dec ay of the hardwood stumps combined with seasonal footing movements resulting from differential variations in the moisture content of the extremely reactive foundation has continued to cause misalignment of the timber floor, in particular the continuing floor movement around the toilet pan/ waste pipe and the very slight to slight cracking in the house.  Successive works thus far completed should not have been proceeded with considering the presence of the existing decayed timber stumps. Any rating of the completed work is now irrelevant as th e provided scopes have bot h dealt with the repair of resultant damage symptoms without due consideration being given to the advanced state of decay of the timber stumps, mainly along the (unpaved) perimeter of the house to the nort h and east elevations.  H ous e is still considered safe to occupy from a structural adequacy point of view. But concerned about the advanced deterioration of the timber stumps which are locat ed mainly along the rear perimeter.  Serviceability of the house will continue to regress by way of on - going movement of the house, predominantly as a result of the continuing deterioration of the hardwood timber stumps.  Could not find any phot ographic evidence, or Determination | Case number: 659743 Page 19 of 20 Date Action otherwise, that the timber stumps had been investigated and/or considered by any p arty prior to this site attendance.  Would have expected that the advanced decayed condition of the timber stumps would have been obvious to a repair builder at least at the stage when the floorboards were removed and replaced with new.  Initial repairs and subsequent repair works have not adequately performed not as a result of any sub - standard works but because of premature execution of remedial works prior to addressing the seriously decayed timber stump footing system mainly along the (unpaved) perimeter of the house to the north and east.  Any future repairs to address on - going soil movement and related cracking to the house should not proceed until the inadequate and failed timber footing stumps have been replaced. Emails between FM and Insurer 4 Decemb er 2019  When the floor was up during repairs, and prior to repairs, FM would have highlighted (to the owner) the deteriorated condition of the timber stumps and recommended that the crack repairs should not be performed prior to addressing the repair/repla c ement of the timber stumps.  FM would have raised concerns regarding the suitability and the adequacy of the existing footing system with respect to the actual site classification which is extremely reactive. A very explicit and emphatic warning would have also been made that the (flexible) timber stump footing system, founded upon a reactive clay soil will continue to experience the effects of seasonal soil movement and long - term clay soil settlement and that there may be future cracking in this dwelling n ot as a consequence of leaking pipe events, flooding or the like, or for that matter the occurrence of any other policy defined events, but as a result of natural soil - footing interaction movement in response to changes in climate that bring about concomit ant changes in soil moisture content.  Re the need to reloc ate the house, or ot herwise, for the purpose of “restumping”, FM may consider and propose the following option or an alternative option (whic h will not require the reloc ation of the house, if possib le): a) A screw piles system installed from inside the house – will require lifting the floorboards and the use of a very small (1 tonne) machine and a lot of physical labour to install the screw piles .  As for the extent of the event impact on the stumps, FM cannot answer that question because of the time Determination | Case number: 659743 Page 20 of 20 Date Action which has elapsed bet ween the event and the repairs and its inspection.  Observed severe to total decay of the timber stumps, mainly along the (unpaved) perimet er of the house to the north and east, has been exacerbat ed by the prevailing poor drainage conditions as a result of the lack of any protective impervious pavement in t his area.  Decay has been further exacerbated by the sewer overflow event of 2016. This is in contrast to the naturally weathered and aged (but not decayed) timber stumps along the (paved) western perimet er. Emails between FM and Insurer 20 January 2020  Q: Would it be correct to say that you do not consider the option of temporary removal of the home and restumping a viable method for the stump replacement and therefore should not be considered as an option at all for this customer?  A: After careful considerations and the concerns raised (lack of lateral bracing, ACM), FM is of the opinion that what ever repair method is adopted, foreseen and unforeseen complications during the repair stage will ultimately cause budget blowouts and extended time delays and therefore no scope of works can sufficiently address all the above concerns and preferably the construction of a new house should be considered or a cash settlement (under the insured‟s policy) is the more appropriat e resolution in this case. 3.4 Other relevant material considered and relied on  Parties‟ submissions/emails and all attachments to all submissions/emails.  Parties‟ expert reports.  Photographs and videos.  Correspondence between the parties.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.