Home / Westpac / Determination 659561
Determination 659561
Delay approving bank guarantee and services drawdown during construction loan
Summary
The complainant said the bank unreasonably delayed approving a bank guarantee and services drawdown after his builder went into liquidation, and that he was charged interest on frozen funds. AFCA found the bank acted within its contractual rights and ordered nothing.
The loan terms entitled the bank to require a new building contract, council approvals and insurance before releasing funds, so the delay was not unreasonable.
Issues
- Delay primary · not upheld“I do not consider the bank acted unreasonably or unfairly in exercising its contractual rights as it did.”
- Incorrect fees or charges secondary · not upheld“the complainant was not being charged interest on 'frozen' loan funds while the bank was seeking additional information.”
Subjects and remedies
no remedy
Related
Text of the determination
Determination
Case number 659561
Financial firm Westpac Banking Corporation
Determination | Case number: 659561 Page 2 of 8
Case number: 659561 29 June 2020
1 Determination overview
1.1 Complaint
In May 2018 the complainant took out a $728,000 investment home loan ( loan ) with
the financial firm ( bank ) to construct two dwellings on the complainant‟s land
( dwellings ). The complainant had a building contract with a builder ( original builder )
for the construction of the dwellings at a fixed cost of $683,777 ( original contract ).
The estimated surplus after loan-related fees and construction of the dwellings was
$43,603.
On 18 May 2018 the complainant drew down on the loan to pay an $8,000 deposit to
the original builder. This was the only progress payment made to the original builder.
On 30 May 2019, more than a year later, the complainant advised the bank that the
original builder had gone into liquidation and that he was in the process of obtaining a
new builder.
The complainant says that thereafter the bank unreasonably delayed in approving a
bank guarantee for the purposes of a bonding agreement with the council ($20,570)
( bank guarantee ) and a draw down on the loan to fund the running of water and
sewerage services to the land ($62,974.27) ( services draw down ). He says he
needed to access his superannuation to pay for these items and wants the bank to
compensate him for its unreasonable delays.
1.2 Issues and key findings
Did the bank unreasonably delay in approving the bank guarantee and the
services draw down?
Based on all the available information, for the reasons set out in Section 2.1 below, I
find the bank did not unreasonably delay in providing the bank guarantee and the
services draw down.
Under the loan contract the bank was entitled to request additional information after
the original builder went into liquidation. I do not consider the bank acted
unreasonably or unfairly in exercising its contractual rights as it did.
1.3 Determination
This determination is in favour of the bank.
The bank is not required to compensate the complainant or take any action.
Determination | Case number: 659561 Page 3 of 8
2 Reasons for determination
2.1 Did the bank unreasonably delay in approving the bank guarantee and
the services draw down?
The complainant says the bank should not have required additional information
The complainant says that the bank unreasonably delayed in approving the bank
guarantee and the services draw down by insisting on obtaining additional
information, including new valuations, in circumstances where:
the estimated surplus available after construction of the dwellings was more than
adequate to cover the bank guarantee
it was always envisaged that the surplus was going to cover the bank guarantee
more than $70,000 was allocated in the specifications and costings of the original
contract for demolition and running of services, so there were ample loan funds
available to pay both the bank guarantee and the services draw down
he was going to build the dwellings to exactly the same plans – just with a new
builder – so there was no need for updated valuations, especially since the
previous buildings had already been demolished
the original builder‟s insurer was going to cover any shortfall between the cost of
the original contract and the new building contract, so t he bank‟s security position
was protected
in the end, the new building contract was priced at $638,032 – close to $90,000
cheaper than the original contract, which meant there would be an even greater
surplus to cover the bank guarantee and the services draw down, and
he was paying interest on the loan so his funds should not have been „frozen‟.
Under the loan contract the bank could require additional information
Prior to approving the bank guarantee and the services draw down, the bank required
the following additional information:
a copy of new building contract
a copy of council approved plans
a copy of new builder‟s risk insurance policy, and
updated valuations.
Based on my review of the terms and conditions applying to the loan, the bank was
entitled to require that information before approving the bank guarantee and the
services draw down.
Clause 1(a) of the term and conditions states that before drawing down any part of
the loan, the complainant must do everything the bank reasonably requests to ensure
Determination | Case number: 659561 Page 4 of 8
that the security provided by the complainant is acceptable to the bank. I consider
this would fairly include:
providing, or allowing the bank to undertake, updated valuations, and
providing the information required under clause 4(a) in respect of a new builder
appointed to complete the construction.
Clause 1(a) also states that where a loan is a construction loan with progressive draw
downs (as was this loan) the requirements under clause 4 of the terms and conditions
“Loans for Construction or Renovation” must be met before the first draw down and
when draw downs for progress payments are made.
Clause 4(a) states that the complainant, who was using a licensed builder to
undertake the construction works, must send the bank:
a copy of the signed bu ilding contract containing the builder‟s licence number and
a schedule of required payments
a copy of the schedule of proposed finishes and specifications
a copy of the council approved plans
a copy of council approval for the work in the form of a letter or stamped plans, and
a copy of the builder‟s risk insurance policy covering the property until the
construction is finished.
An extract of the relevant terms and conditions is set out in Section 3.2 below.
The bank did not act unfairly or unreasonably in exercising its rights
It is understandable that the complainant is concerned that, through no fault of hi s
own, due to the original builder going into liquidation, he was required to supply
additional information to the bank before being able to access funds on an already
approved loan. I acknowledge that, from his perspective, he was only seeking access
to funds (to the value of the bank guarantee and the service draw down) that had
already been factored into an approved loan amount – he was not asking for
additional funds.
While I acknowledge the complainant‟s frustration with the situation in which he found
himself, I am unable to find that the bank acted unreasonably or unfairly in exercising
its contractual rights to seek additional information before releasing the funds. I have
reached this view for reasons including the following :
On 30 May 2019, the complainant advised the bank that the original builder had
gone into liquidation and he was in the process of sourcing a new builder.
On 11 June 2019, the complainant asked the bank for the bank guarantee and on
13 June 2019, the bank advised that it needed the new building contract before it
could release any funds. This was an entirely reasonable requirement because it
Determination | Case number: 659561 Page 5 of 8
was not clear that the complainant could source a new building contract on the
same terms (for the same fixed cost) as the original contract – meaning it was
unclear there would be sufficient surplus to support the bank guarantee.
Instead of providing a copy of the new building contract, the complainant replied
that the insurers of the original builder would cover any s hortfall under the new
contract – and implied that he therefore did not need to provide the new contract
before the bank approved the bank guarantee. In support, he provided a copy of
an email from the original builder‟s insurer.
Reasonably, the bank did not accept this arrangement because it was not clear
that the insurer would cover any shortfall in circumstances where the new contract
had not yet been signed and the shortfall had not yet been determined – the bank
advised the complainant of this in an email on 25 June 2019.
On 1 August 2019 the complainant supplied the new building contract (dated 31
July 2019) and the bank sought clarification around the specifications and the
finishes before sending it to the valuer to undertake new valuations of the proposed
dwellings.
It was entirely reasonable for the bank to insist on new valuations in these
circumstances because the loan had not been fully drawn down within 12 months
as was required under the loan offer, and the last valuations supporting the loan
were more than a year old. The fact that the existing buildings had been
demolished in the interim was irrelevant as the valuer was providing an estimated
value of the properties once the dwellings were completed by the new builder.
Consequently, the new building contract (including specifications) was required
before the valuations could proceed.
On 13 August 2019, the bank advised the complainant that the valuations had
been received and requested stamped council approved plans and a copy of the
builder‟s risk insurance (the then current policy expired at the end of the month).
This request was reasonable as it was central to protecting the bank‟s security
position – namely that the proposed construction was in fact council approved and
the builder was appropriately insured. In reply, the complainant advised that the
builder was renegotiating his insurance, that the builder‟s insurance certificate
would be provided shortly and that he had already provided the plans in July 2018.
The bank replied on 15 August 2019 clarifying that the plans previously provided
were for the development approval and that what the bank required was the
separate council approval to build the dwellings, the building permit and the set of
approved plans.
On around 17 August 2019, the complainant submitted a request to the bank for
reimbursement of the services draw down. However, the bank did not approve the
request due to the outstanding documentation.
On 20 August 2019, although the complainant had not yet supplied the outstanding
documentation, after a discussion with the complainant, the bank approved the
bank guarantee. However, the bank made it clear to the complainant that no other
payments would be released until the permit to build (council approval), council
approved plans and updated builders risk insurance certificate was supplied.
Determination | Case number: 659561 Page 6 of 8
On 30 August 2019, the complainant forwarded to the bank the new builder‟s risk
insurance certificate.
On 11 September 2019, the complainant enquired about the reimbursement of the
services draw down. However, by this stage he had still not produced the stamped
council approved plans and the bank once again requested them. This may have
been a misunderstanding on the complainant‟s part as he had previously submitted
stamped development plans, however he was able to provide the required
documents the following day. Although it is unfortunate that the complainant may
have misunderstood the requirement for the plans, this is not something for which
the bank is responsible – particularly when it explained the distinction in the types
of plans in its email of 15 August 2019.
On 12 September 2019, as soon as the complainant submitted the outstanding
documentation (being the necessary council approvals), the bank released the
amount of $60,778 to reimburse the complainant. Notably, this was less than the
$62,974.27 sought, due to there being less of a surplus available under the new
contract. This reality demonstrates the reasons for the bank‟s prudence in
releasing any of the loan funds in the absence of the additional information it
required.
The bank did not charge interest on loan funds that were not yet drawn down
The complainant says that the loan funds should not have been „frozen‟ while he was
being charged interest.
The complainant‟s loan was a construction loan which was to be accessed by
progressive draw downs. Under such a loan arrangement the bank only charges
interest on the amounts that have been drawn down on the loan at any point in time.
Up until the bank guarantee was approved on 20 August 2019, the complainant was
only being charged interest on the $8,000 deposit paid to the original builder and the
$620 loan-related fee paid on draw down of the loan. Up until the services draw down
was approved on 12 September 2019, the complainant was only being charged
interest on the $8,000 deposit paid to the original builder, the $620 loan-related fee
paid on draw down of the loan and the bank guarantee.
Accordingly, the complainant was not being charged interest on „frozen‟ loan funds
while the bank was seeking additional information to approve the bank guarantee and
the services draw down.
Determination | Case number: 659561 Page 7 of 8
3 Supporting information
3.1 Decision basis and process
This complaint was the subject of a recommendation in favour of the bank which the
complainant rejected. Accordingly, the matter proceeded to determination.
I have decided this complaint based on what is fair in all the circumstances having
regard to the relevant law, good industry practice, codes or guidance as to practice
and previous AFCA decisions. I have considered all relevant material submitted by
the parties. I am satisfied that the material I relied upon in reaching my findings has
been exchanged between the parties or is otherwise in their possession.
While the parties have raised numerous issues in their submissions, commentary in
this determination is restricted to those matters directly relevant to the outcome.
3.2 Key clauses in the loan contract terms and conditions
1. BEFORE YOU CAN DRAW YOUR LOAN
Before you can draw your loan, there are several things that you need to do, and
some things that we may need to do. These are set out below, and each must meet
our requirements.
(a) What You Need To Do
…
Satisfy the following requirements
Our security requirements: we need to be satisfied that before or when you draw
any part of your loan, you (and any guarantor giving security) own the security
property, the security is acceptable to us, we have a valid security interest in the
security property or other form of security interest over any security property and no
one else has any interest in or claim on the property which is unacceptable to us. You
will need to do everything we reasonably ask to ensure that this is the case. We may
also undertake a final inspection of the security property.
…
Construction or renovation (Progressive Draw loans)
If you intend to use the loan to finance construction or renovation, you also need to
satisfy the requirements set out under Loans for Construction or Renovation before
you first draw your loan and when you draw for progress payments.
Determination | Case number: 659561 Page 8 of 8
4. LOANS FOR CONSTRUCTION OR RENOVATION
If you have chosen the Progressive Draw option, we will issue progress
payments for the construction or renovation based on the requirements set out
below.
…
(a) Before You Can Draw Your Loan
As well as the other things you need to do before drawing your loan, you need to
send the following additional documents to us:
• If you are using a licensed builder or home improvements firm:
i) a copy of the Contract signed by all borrowers and your builder I firm (it must
contain their licence number(s) and a schedule of required payments);
ii) a copy of the schedule of proposed finishes and specifications;
iii) a copy of Council approved plans with dimensions and measurements,
including site plan, floor plans and elevations (or Privately Certified plans in
WA);
iv) a copy of Council approval for your work (in the form of a letter or stamp on the
plans);
v) a copy of the Builder's Risk Insurance policy (or a certificate of currency for
that insurance), covering the property until the construction I renovation is
finished; and
vi) a copy of a report from a Quantity Surveyor who is a member of the Australian
Institute of Quantity Surveyors (only required if we tell you so).