Home / Westpac / Determination 659561

Determination 659561

Delay approving bank guarantee and services drawdown during construction loan

FirmWestpac
Decided2020-06-29
ProductCredit · Home loan
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant said the bank unreasonably delayed approving a bank guarantee and services drawdown after his builder went into liquidation, and that he was charged interest on frozen funds. AFCA found the bank acted within its contractual rights and ordered nothing.

The loan terms entitled the bank to require a new building contract, council approvals and insurance before releasing funds, so the delay was not unreasonable.

Issues

Subjects and remedies

no remedy

Related

All Westpac determinations · Find similar determinations

Text of the determination

Determination Case number 659561 Financial firm Westpac Banking Corporation Determination | Case number: 659561 Page 2 of 8 Case number: 659561 29 June 2020 1 Determination overview 1.1 Complaint In May 2018 the complainant took out a $728,000 investment home loan ( loan ) with the financial firm ( bank ) to construct two dwellings on the complainant‟s land ( dwellings ). The complainant had a building contract with a builder ( original builder ) for the construction of the dwellings at a fixed cost of $683,777 ( original contract ). The estimated surplus after loan-related fees and construction of the dwellings was $43,603. On 18 May 2018 the complainant drew down on the loan to pay an $8,000 deposit to the original builder. This was the only progress payment made to the original builder. On 30 May 2019, more than a year later, the complainant advised the bank that the original builder had gone into liquidation and that he was in the process of obtaining a new builder. The complainant says that thereafter the bank unreasonably delayed in approving a bank guarantee for the purposes of a bonding agreement with the council ($20,570) ( bank guarantee ) and a draw down on the loan to fund the running of water and sewerage services to the land ($62,974.27) ( services draw down ). He says he needed to access his superannuation to pay for these items and wants the bank to compensate him for its unreasonable delays. 1.2 Issues and key findings Did the bank unreasonably delay in approving the bank guarantee and the services draw down? Based on all the available information, for the reasons set out in Section 2.1 below, I find the bank did not unreasonably delay in providing the bank guarantee and the services draw down. Under the loan contract the bank was entitled to request additional information after the original builder went into liquidation. I do not consider the bank acted unreasonably or unfairly in exercising its contractual rights as it did. 1.3 Determination This determination is in favour of the bank. The bank is not required to compensate the complainant or take any action. Determination | Case number: 659561 Page 3 of 8 2 Reasons for determination 2.1 Did the bank unreasonably delay in approving the bank guarantee and the services draw down? The complainant says the bank should not have required additional information The complainant says that the bank unreasonably delayed in approving the bank guarantee and the services draw down by insisting on obtaining additional information, including new valuations, in circumstances where:  the estimated surplus available after construction of the dwellings was more than adequate to cover the bank guarantee  it was always envisaged that the surplus was going to cover the bank guarantee  more than $70,000 was allocated in the specifications and costings of the original contract for demolition and running of services, so there were ample loan funds available to pay both the bank guarantee and the services draw down  he was going to build the dwellings to exactly the same plans – just with a new builder – so there was no need for updated valuations, especially since the previous buildings had already been demolished  the original builder‟s insurer was going to cover any shortfall between the cost of the original contract and the new building contract, so t he bank‟s security position was protected  in the end, the new building contract was priced at $638,032 – close to $90,000 cheaper than the original contract, which meant there would be an even greater surplus to cover the bank guarantee and the services draw down, and  he was paying interest on the loan so his funds should not have been „frozen‟. Under the loan contract the bank could require additional information Prior to approving the bank guarantee and the services draw down, the bank required the following additional information:  a copy of new building contract  a copy of council approved plans  a copy of new builder‟s risk insurance policy, and  updated valuations. Based on my review of the terms and conditions applying to the loan, the bank was entitled to require that information before approving the bank guarantee and the services draw down. Clause 1(a) of the term and conditions states that before drawing down any part of the loan, the complainant must do everything the bank reasonably requests to ensure Determination | Case number: 659561 Page 4 of 8 that the security provided by the complainant is acceptable to the bank. I consider this would fairly include:  providing, or allowing the bank to undertake, updated valuations, and  providing the information required under clause 4(a) in respect of a new builder appointed to complete the construction. Clause 1(a) also states that where a loan is a construction loan with progressive draw downs (as was this loan) the requirements under clause 4 of the terms and conditions “Loans for Construction or Renovation” must be met before the first draw down and when draw downs for progress payments are made. Clause 4(a) states that the complainant, who was using a licensed builder to undertake the construction works, must send the bank:  a copy of the signed bu ilding contract containing the builder‟s licence number and a schedule of required payments  a copy of the schedule of proposed finishes and specifications  a copy of the council approved plans  a copy of council approval for the work in the form of a letter or stamped plans, and  a copy of the builder‟s risk insurance policy covering the property until the construction is finished. An extract of the relevant terms and conditions is set out in Section 3.2 below. The bank did not act unfairly or unreasonably in exercising its rights It is understandable that the complainant is concerned that, through no fault of hi s own, due to the original builder going into liquidation, he was required to supply additional information to the bank before being able to access funds on an already approved loan. I acknowledge that, from his perspective, he was only seeking access to funds (to the value of the bank guarantee and the service draw down) that had already been factored into an approved loan amount – he was not asking for additional funds. While I acknowledge the complainant‟s frustration with the situation in which he found himself, I am unable to find that the bank acted unreasonably or unfairly in exercising its contractual rights to seek additional information before releasing the funds. I have reached this view for reasons including the following :  On 30 May 2019, the complainant advised the bank that the original builder had gone into liquidation and he was in the process of sourcing a new builder.  On 11 June 2019, the complainant asked the bank for the bank guarantee and on 13 June 2019, the bank advised that it needed the new building contract before it could release any funds. This was an entirely reasonable requirement because it Determination | Case number: 659561 Page 5 of 8 was not clear that the complainant could source a new building contract on the same terms (for the same fixed cost) as the original contract – meaning it was unclear there would be sufficient surplus to support the bank guarantee.  Instead of providing a copy of the new building contract, the complainant replied that the insurers of the original builder would cover any s hortfall under the new contract – and implied that he therefore did not need to provide the new contract before the bank approved the bank guarantee. In support, he provided a copy of an email from the original builder‟s insurer.  Reasonably, the bank did not accept this arrangement because it was not clear that the insurer would cover any shortfall in circumstances where the new contract had not yet been signed and the shortfall had not yet been determined – the bank advised the complainant of this in an email on 25 June 2019.  On 1 August 2019 the complainant supplied the new building contract (dated 31 July 2019) and the bank sought clarification around the specifications and the finishes before sending it to the valuer to undertake new valuations of the proposed dwellings.  It was entirely reasonable for the bank to insist on new valuations in these circumstances because the loan had not been fully drawn down within 12 months as was required under the loan offer, and the last valuations supporting the loan were more than a year old. The fact that the existing buildings had been demolished in the interim was irrelevant as the valuer was providing an estimated value of the properties once the dwellings were completed by the new builder. Consequently, the new building contract (including specifications) was required before the valuations could proceed.  On 13 August 2019, the bank advised the complainant that the valuations had been received and requested stamped council approved plans and a copy of the builder‟s risk insurance (the then current policy expired at the end of the month). This request was reasonable as it was central to protecting the bank‟s security position – namely that the proposed construction was in fact council approved and the builder was appropriately insured. In reply, the complainant advised that the builder was renegotiating his insurance, that the builder‟s insurance certificate would be provided shortly and that he had already provided the plans in July 2018. The bank replied on 15 August 2019 clarifying that the plans previously provided were for the development approval and that what the bank required was the separate council approval to build the dwellings, the building permit and the set of approved plans.  On around 17 August 2019, the complainant submitted a request to the bank for reimbursement of the services draw down. However, the bank did not approve the request due to the outstanding documentation.  On 20 August 2019, although the complainant had not yet supplied the outstanding documentation, after a discussion with the complainant, the bank approved the bank guarantee. However, the bank made it clear to the complainant that no other payments would be released until the permit to build (council approval), council approved plans and updated builders risk insurance certificate was supplied. Determination | Case number: 659561 Page 6 of 8  On 30 August 2019, the complainant forwarded to the bank the new builder‟s risk insurance certificate.  On 11 September 2019, the complainant enquired about the reimbursement of the services draw down. However, by this stage he had still not produced the stamped council approved plans and the bank once again requested them. This may have been a misunderstanding on the complainant‟s part as he had previously submitted stamped development plans, however he was able to provide the required documents the following day. Although it is unfortunate that the complainant may have misunderstood the requirement for the plans, this is not something for which the bank is responsible – particularly when it explained the distinction in the types of plans in its email of 15 August 2019.  On 12 September 2019, as soon as the complainant submitted the outstanding documentation (being the necessary council approvals), the bank released the amount of $60,778 to reimburse the complainant. Notably, this was less than the $62,974.27 sought, due to there being less of a surplus available under the new contract. This reality demonstrates the reasons for the bank‟s prudence in releasing any of the loan funds in the absence of the additional information it required. The bank did not charge interest on loan funds that were not yet drawn down The complainant says that the loan funds should not have been „frozen‟ while he was being charged interest. The complainant‟s loan was a construction loan which was to be accessed by progressive draw downs. Under such a loan arrangement the bank only charges interest on the amounts that have been drawn down on the loan at any point in time. Up until the bank guarantee was approved on 20 August 2019, the complainant was only being charged interest on the $8,000 deposit paid to the original builder and the $620 loan-related fee paid on draw down of the loan. Up until the services draw down was approved on 12 September 2019, the complainant was only being charged interest on the $8,000 deposit paid to the original builder, the $620 loan-related fee paid on draw down of the loan and the bank guarantee. Accordingly, the complainant was not being charged interest on „frozen‟ loan funds while the bank was seeking additional information to approve the bank guarantee and the services draw down. Determination | Case number: 659561 Page 7 of 8 3 Supporting information 3.1 Decision basis and process This complaint was the subject of a recommendation in favour of the bank which the complainant rejected. Accordingly, the matter proceeded to determination. I have decided this complaint based on what is fair in all the circumstances having regard to the relevant law, good industry practice, codes or guidance as to practice and previous AFCA decisions. I have considered all relevant material submitted by the parties. I am satisfied that the material I relied upon in reaching my findings has been exchanged between the parties or is otherwise in their possession. While the parties have raised numerous issues in their submissions, commentary in this determination is restricted to those matters directly relevant to the outcome. 3.2 Key clauses in the loan contract terms and conditions 1. BEFORE YOU CAN DRAW YOUR LOAN Before you can draw your loan, there are several things that you need to do, and some things that we may need to do. These are set out below, and each must meet our requirements. (a) What You Need To Do … Satisfy the following requirements Our security requirements: we need to be satisfied that before or when you draw any part of your loan, you (and any guarantor giving security) own the security property, the security is acceptable to us, we have a valid security interest in the security property or other form of security interest over any security property and no one else has any interest in or claim on the property which is unacceptable to us. You will need to do everything we reasonably ask to ensure that this is the case. We may also undertake a final inspection of the security property. … Construction or renovation (Progressive Draw loans) If you intend to use the loan to finance construction or renovation, you also need to satisfy the requirements set out under Loans for Construction or Renovation before you first draw your loan and when you draw for progress payments. Determination | Case number: 659561 Page 8 of 8 4. LOANS FOR CONSTRUCTION OR RENOVATION If you have chosen the Progressive Draw option, we will issue progress payments for the construction or renovation based on the requirements set out below. … (a) Before You Can Draw Your Loan As well as the other things you need to do before drawing your loan, you need to send the following additional documents to us: • If you are using a licensed builder or home improvements firm: i) a copy of the Contract signed by all borrowers and your builder I firm (it must contain their licence number(s) and a schedule of required payments); ii) a copy of the schedule of proposed finishes and specifications; iii) a copy of Council approved plans with dimensions and measurements, including site plan, floor plans and elevations (or Privately Certified plans in WA); iv) a copy of Council approval for your work (in the form of a letter or stamp on the plans); v) a copy of the Builder's Risk Insurance policy (or a certificate of currency for that insurance), covering the property until the construction I renovation is finished; and vi) a copy of a report from a Quantity Surveyor who is a member of the Australian Institute of Quantity Surveyors (only required if we tell you so).

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.