Home / Suncorp Group / Determination 659549
Determination 659549
Cash settlement of water damage building claim
Summary
The complainants disputed the insurer's cash settlement of their water damage building claim and sought further payment for building, mould, storage and accommodation costs. AFCA ordered the insurer to pay a further $77,229 for contingencies and mould remediation but rejected the other claimed amounts and compensation.
The insurer may cash settle under the policy discretion if exercised fairly, and a cash settlement should include an allowance for contingencies.
Issues
- Claim amount dispute primary · upheld“The insurer must therefore pay the complainants a further $77,229.00 to settle the claim for the building damage.”
- Poor claim handling secondary · not upheld“The Panel is satisfied that the insurer handled the claim reasonably in the circumstances.”
Subjects and remedies
home or building damagepay claim
Related
All Suncorp Group determinations · Find similar determinations
Text of the determination
Determination
Case number 659549
Financial firm AAI Limited
Determination | Case number: 659549 Page 2 of 14
Case number: 659549 30 November 2020
1 Determination overview
1.1 Complaint
The complainants lodged a claim under their home insurance policy with the financial
firm (insurer) for water damage that occurred after their refrigerator hose burst in
December 2015.
The complainants are dissatisfied with the insurer‟s handling and settlemen t of the
claim. They say the scope of work (SOW) on which the insurer based its cash
settlement ($295,149) did not cover the actual cost of repairing the claimed damage.
They are seeking additional payment of $348,701 for building works, mould
remediation, storage, temporary accommodation and utilities at the temporary
accommodation.
The insurer offered/paid an additional $40,128 for building and mould remediation
work and covered two additional weeks of temporary accommodation. To resolve this
complaint, the insurer has offered a further $64,951 for contingencies. The
complainants reject the offer and seek a review of the insurer‟s decision.
1.2 Issues and key findings
Is the insurer required to increase its settlement for building repairs?
The Panel accepts the insurer is entitled to rely on the quotations from its builder R
and roofer HWF to settle the claim. However, the Panel determines the insurer should
pay an additional $77,229 being $64,951 as a contingency as offered and $12,278 for
the balance of the mould remediation costs.
Is the insurer required to cover additional temporary accommodation?
For the reasons set out under section 2.2 the insurer is not required to cover any
further temporary accommodation costs.
Is the insurer required to cover storage and utilities costs claimed?
Based on the available information the Panel is satisfied the insurer has met its
liability for any storage or utilities costs concerning this claim. In the absence of any
information to the contrary, the insurer is not required to pay any additional utilities
connection costs.
Is the insurer required to compensate the complainants?
The insurer is not required to compensate the complainants. While the duration from
claim lodgement to settlement was approximately 11 months, there is no evidence of
extended period of inaction by the insurer. The Panel is satisfied that the insurer
handled the claim reasonably in the circumstances.
Determination | Case number: 659549 Page 3 of 14
1.3 Determination
This determination is partly in favour of the complainants.
The insurer is to pay the complainants a further $77,229.00 to cover contingencies
and the balance of the mould remediation in finalisation of the claim. The insurer has
otherwise met its liability in accordance with the terms and condition of the policy.
Determination | Case number: 659549 Page 4 of 14
.
2 Reasons for determination
There has been a full exchange of material between the parties and each party has
had the opportunity of addressing the issues in dispute.
Due to the circumstances involved, this dispute has been referred to a Panel for
determination. The Panel comprises the Lead Ombudsman, a member with significant
industry experience and a member with extensive experience as a consumer
representative.
The determination follows consideration of all the available information. It is based on
what is fair in all the circumstances having regard to the relevant legal principles,
terms of the policy, good industry practice including codes of practice and prior
determinations where applicable.
2.1 Is the insurer required to increase its settlement for building repairs?
Policy covers loss or damage caused by escape of liquid
There is no dispute the complainants had a valid claim for damage caused by the
escape of liquid. The complainant ‟ s home and contents policy provides cover for a
series of insured events including the escape of liquid subject to several limitations
and exclusions.
The complainants lodged the claim with the insurer on 21 December 2015 for damage
caused by a leaking water machine on a refrigerator. During investigation of the claim
the insurer identified two other events, namely damage from a bathtub leak or
overflow and damage from a leaking air conditioner. Both claims have been settled
and are not part of this complaint.
Claim cash settled based on SOW
A brief timeline of events leading to the cash settlement is provided in section 3.2 of
this determination. The timeline is mainly drawn from file notes/record provided by the
insurer, the parties submissions and copies of email correspondence provided.
The insurer appointed an assessor on 22 December 2015 and a builder M to assess
the damage in January 2016. M identified maintenance issues with the property that
would make it hard to warrant the repairs . Mould related issues arose, and
remediation was attempted in July 2016.
Ultimately the insurers builder R provided a SOW for the damage determined to have
been caused by the refrigerator pipe leak. R indicated it could not warrant building
works due to ongoing/incomplete repairs in one of the bathrooms. In the insurer‟s
claim outcome letter, it also suggests a break-down in relationship between parties.
Determination | Case number: 659549 Page 5 of 14
Policy allows insurer to decide how to settle claim
The insurer cash settled the contents claim for the sum insured and the building claim
for $295,149.72 based on quotes from R and HWL, a flooring specialist.
The complainants consider the insurer should have repaired rather than cash-settled
them for building repairs. They expressed preference for the insurer to complete the
building repairs, however the insurer went ahead with cash settlement citing R‟s
inability to warrant repairs. They do not accept available information shows the work
could not be completed and warranted by R.
Under the terms of the policy, if the insurer agrees to pay a claim, it will decide
whether to repair/rebuild or pay the complainants what it would cost it (insurer) to
repair/rebuild the home. The Panel accepts the insurer is entitled to exercise this
discretion under the policy terms however, it is required to exercise such discretion
fairly, reasonably and consistent with utmost good faith.
Having carefully considered the available information, the Panel is satisfied the
application of the insurer‟s discretion to cash settle was reasonable , given:
R clearly expressed unwillingness to warrant the repairs due to ongoing repairs
and condition of the property unrelated to the claimed event
there is an extensive history of complaints made by the complainants through the
claim process. The complaints include contents/contents remediation, claim
handling and conduct of the insurer‟s contr actors. This is evidence of breakdown in
relations/communication.
The quote from the HWF for supply and replacement of all timber flooring
Complainants say settlement amount is insufficient
After the claim was settled, the complainants contacted the insurer and advised their
builder (D) would be unable to complete works relating to structural flooring in the
manner provided for in the insurer‟s SOW and requested a meeting.
Following a site meeting on 9 February 2017, the insurer wrote to the complainants in
March 2017 maintaining the SOW and cash settlement amount was sufficient to cover
the reasonable cost of repairs and discharges its obligation.
The complainants sent a request for additional costs incurred to the insurer in June
2017. A list of items that make up additional costs claimed is provided in section 3.2
below.
After reviewing this information, the insurer paid the complainants $40,129.15 being
$29,605.30 for additional building and $10,523.85 for 50% of the mould remediation
cost.
Determination | Case number: 659549 Page 6 of 14
The complainants say the total cash settlement is not sufficient to cover the cost
incurred to repair the insured damage and provided the following information as
evidence of additional loss they say they have incurred:
construction proposal/ revised SOW by their builder „D‟ totalling $861,910.78
statement by D outlining why structural flooring cannot be accessed in manner
provided for in R‟s S OW
mould testing reports dated 6 March 2017, 18 & 25 January 2018
mould testing invoices
plasterer‟s invoice
timber/hardware invoices from two suppliers
cabinetry invoices covering kitchen cabinetry, 6 vanities, 4 robes and stone
electrical invoices which include variation due to wall removal as well as remove
The complainants say D‟s statement shows that structural flooring could not be
accessed, and flooring repl aced as provided for in R‟s S OW.
According to D‟s statement several methods were attempted to complete work as
provided for and failed. The complainants say D‟s statement supports conclusion that
R‟s S OW was unachievable and the cash settlement amount, insufficient.
The complainants say the only method that worked resulted in damage to battens,
wall frames, ceiling (battens and sheets), cornices, electrical wiring and cabinetry in
the pantry, laundry and wardrobes. They also say further mould remediation was
required after removal of these building materials as their hygienist found mould
contamination due to water leak at the premises.
Information does not establish entitlement to further amount claimed
The Panel has reviewed information provided by the parties.
The Panel is satisfied that the assessed scope of works provided by R is reasonable.
It is detailed and itemised. The quote from HWF is clear and covers replacement of all
timber floors.
The Panel has reviewed the complainants‟ submissions, including D‟s S OW, email
statement and individual supplier invoices to D. The SOW does not contain a detailed
break-down of costs on a room by room basis showing what material/labour falls
within each section.
Further, the email statement from D does not provide any detail in relation to specific
increases in cost of material, labour etc. The statement is not supported by any
detailed report, documents, photographs or the like and it does not provide an
analysis of evidence supporting the conclusion that the repair method provided for by
R was not standard in the industry or would result in the repairs being non-compliant.
Determination | Case number: 659549 Page 7 of 14
While the supplier invoices provided show D was billed for certain material and
contractors‟ work (cabinetry, electrician etc) , these documents do not show the costs
were incurred solely due to claim related damage.
The Panel also notes information from D is not provided in a manner that would allow
for a proper like for like comp arison between what was provided for in R‟s SOW and
what was in D‟s SOW.
AFCA drew the complainants‟ attention to the need for detailed scope of
works/actionable quotes to support their position throughout the complaint process.
However, the complainants have not provided information other than what is
mentioned in this determination. The complainants say what they provided sufficiently
shows they are entitled to the full additional amount claimed.
The complainants say the quotation which the insurer based its cash settlement on is
not achievable in the market. They have not provided any evidence (such as
comparison quotes they obtained at the time) to support this position.
The Panel is satisfied the insurer was entitled to rely on the quotations obtained to
settle the claim. The repairs included in the scope of works are consistent with the
claim-related damage identified in the reports provided (including photographs) by the
insurer‟s contractors following their assessment of the claimed damage.
Fair in the circumstances that insurer increase the cash settlement
While the insurer has cash settled the claim, by cash settling the claim it has
transferred to risk of the repair process to the comp lainants. Where an insurer
chooses to cash settle a claim then it should make an allowance for the contingencies
that may occur in the repair process.
The insurer has offered to the pay a further $64,951 being a 20% contingency
payment to cover the transfer of risk. The Panel considers this is a reasonable
amount for the building works.
The Panel notes the complainants claimed $24,556.27 for further mould remediation.
The complainants say this was required after mould testing following demolition
showed airborne mould particles and surface mould contamination. The complainants
say this was a direct result of the water damage .
The Panel has reviewed the extensive history relating to mould remediation at the
premises following the claimed event. It is not clear on the available information that
mould issues at the premises had been completely resolved as there is no report to
that effect.
The insurer allowed for 50% of the costs of further mould remediation. There is no
information to support the conclusion that this is a reasonable contribution to those
costs. The Panel accepts that it is likely that any mould issue would have been
contributed to by the claimed event.
Determination | Case number: 659549 Page 8 of 14
To achieve finalisation of this aspect of the claim, the Panel considers it fair in the
circumstances that the insurer pays an additional $12,278.00 to cover the full amount
claimed for additional mould remediation at the property.
The insurer must therefore pay the complainants a further $77,229.00 to settle the
claim for the building damage.
2.2 Is the insurer required to cover additional temporary accommodation?
The complainants‟ policy provides benefits including temporary accommodation up to
12 months to a limit of 10% of the sum insured. Relevant policy wording is provided in
section 3 of this determination.
The insurer is not required to pay temporary accommodation benefits for the entire
repair period, but only for such time as the complainants ‟ property is unliveable.
Available information shows the insurer covered the emergency and temporary
accommodation to 12 May 2017, and a further two-weeks cost was reimbursed to the
complainants in or around August 2017.
While the complainants suggest they are entitled to further temporary accommodation
payment due to delays in construction, they have not provided evidence that the
duration of claim related repairs exceeds what the insurer has provided, that the
home was unliveable throughout the period of repairs, or that any additional time
taken was a result of the insurer ( rather than their builder‟s ) actions. Further they have
not provided evidence of the additional loss claimed.
On the available information, the insurer is not required to cover any further temporary
accommodation costs.
2.3 Is the insurer required to cover utilities and storage costs claimed?
The policy benefit for utility at temporary accommodation extends to connection costs
reasonably and necessarily incurred , not usage costs.
The insurer says it has made payment for connection costs; the complainants have
not provided any evidence to the contrary. As such there is no basis to determine any
additional cost is payable to the complainants in this regard.
In relation to storage costs, the available information shows the complainants were
settled the full sum insured for contents that were deemed total loss; therefore, they
are not entitled to further payment for storage of “undamaged” contents provided for
under the policy.
Determination | Case number: 659549 Page 9 of 14
2.4 Is the insurer required to compensate the complainants?
We can award compensation in certain circumstances
Under AFCA‟s Rules, we may award an amount of compensation (capped at $5,000)
for non-financial loss where a complainant has suffered:
an unusual degree or extent of physical inconvenience
time taken to resolve the situation
interference with their expectation of enjoyment or peace of mind.
However, we expect a complainant to be moderately robust and bear the usual stress
and inconvenience associated with an insurance claim.
The complainants say the insurer did not take steps to prevent mould growth and its
actions in conducting several assessment and inspections resulted in growth of mould
and damage which could have been avoided. They say the mould negatively
impacted the female complainant and their child‟s health .
No award of compensation is warranted in the circumstances
The Panel has carefully reviewed the available information, including the insurer‟s
claim records and considers the insurer did not unreasonably delay or mishandle the
claim overall.
There is no record of extended periods of inaction by the insurer. While there was a
lot of communications, assessment, appointment of different experts to determine the
extend of loss/damage to building and contents, the Panel does not consider this
unreasonable given the complexity of the claim (including the discovery of two other
leaks), issues that arose about the installation and repairs to the timber flooring and
remediation at the premises.
In the circumstances, the Panel does not consider that an award of compensation for
non-financial loss is warranted.
Determination | Case number: 659549 Page 10 of 14
3 Supporting information
3.1 Brief timeline of events
Date Action
21 - 12 - 2015 Claim lodged
22 - 12 - 2015 Insurer assessor appointed
07 - 01 - 2016 Insurer informed builder „M‟ appoint ed
02 - 02 - 2016 M informed insurer complainants had indicated attendance/repairs to occur after 04 -
03 - 2016
14 - 03 - 2016 M raised concerns about repairing floor due to installation without joists
M suggested potential for cash settlement du e to disagreement on having
expansions joists and unable to warrant
recommended obtaining flooring consultant report
29 - 04 - 2016 flooring expert (A) appointed
18 - 05 - 2016 complainant advised insurer of mould at premis es
27 - 05 - 2016 insurer‟s restorer ( W ) advis ed insurer mould covering everything at premises and
that the temporary accommodation (TA) would be required
insurer tried to cont act complainant to arrange emergency TA
07 - 06 - 2016 complainant contacted insurer and says:
> mould making her sick
> she does not want repairs cash settled, she wants repairs done her way (no
expansion joists) by insurer
> wants pets placed in TA/boarding and has submitted quotes
FF advis ed
> to obtain quote from repairer (A) to see if same repair process
> TA extension until premises stable/liveable environment after mould remediation
10 - 06 - 2016 Mould review re - attendance requested as initial test seem to have come back
clear (likely incorrect)
14 - 06 - 2016 Insurer notes it will appoint engineers (JH) as concerns with excessiv e mould
situation and whether linked to historic event ( s)
17 - 06 - 2016 Insurer‟s r e - inspection report
attended premises with flooring consultant (A)
await „A‟ report before “establishing final direction/findings, however,
from discussion s flooring would not need to be replaced , a further 6 month drying
period, then a sand/polish of the affected rooms (Kitchen/living, Long hallway,
Toilet, Master bedroom, WIR, Butler's pantry, Formal lounge & pantry cupboard)
was all that is required. No need for expansion joints to be installed”
mould issues: await report from expert
JH to attend on 21 June to “review the downstairs retaining wall and the possibility
Determination | Case number: 659549 Page 11 of 14
Date Action
of mould/moisture issues to be occurring due to some other means”
22 - 06 - 2016 complainant cancelled JH inspection for 21 - 06 - 2016
27 - 06 - 2016 Male complainant advises insurer to only contact him (not female complainant )
Male complainant questioned requirement for JH to attend and insurer explained
“ so we need to determine what is going on ” wit h mould, “ we ne ed to know where
the mould is coming from asap ”. Insurer p ointed out previous assessment in 2012
following a malicious damage claim and that the report noted “rear block wall of
the lower level is dug into the sloping block of land … at this time that it is possible
that there is a fault with the waterproofing membrane to the block wall that is
causing moisture to the lower level to stay high ” .
insurer raised issue with complainant‟s delay resulting in furt her TA being needed
and that it may cease cover for TA
insurer provided complainant with JH details to arrange urgent assessment as
need to determine mould issue – origin b efore remediation work is done.
30 - 06 - 2016 JH and insurer‟s assessor attended premises
01 - 07 - 2016 JH report - mould related to wat er leak from fridge
04 - 07 - 2016 insurer‟s notes indicate after reviewing JH report, mould due to escape of liquid
( EOL ) event. Re mediation authorised
insurer to extend TA till mould remediation done
Flooring expert report from „A‟
07 - 0 7 - 2016 Complainant rais ed concern wit h insurer about insurer‟s remediator doing mould
remediation. Insurer advised the remediat or will complete work in line with SOW
insurer say s a waiting report but will need to allow about 6 month drying period to
do flooring/timber repairs
08 - 07 - 2016 Insurer received escalation of female complainant‟s concern with remediation
company
Insurer contacted remediator W who confirmed it can complete the job, therefore
insurer appointed new remediation company to complete remediation
13 - 07 - 2016 W commenced remediation
14 - 07 - 2016 W report ed secondary cause of mould/leak – lower level bedrooms 2&3
27 - 09 - 2016 Onsite meeting bet ween insurer‟s assessors and complainants. Matters discussed
includ es :
> building SOW “ $209, 089.63 changed to $223,089.63 following onsite
clarification that scope is likely to be higher ”, as well as contents settlement and
TA
> trying to work out suitable settlement ( insu rer suggest ed its builder does not
want to do the work)
07 - 10 - 2016 Com plainant suggests cash settlement of contents sum insured due to W‟s failure
in remediation
Determination | Case number: 659549 Page 12 of 14
Date Action
October 2016 Third EOL claim lodged for leak from toilet
“called [ E …] samples indicate higher than normal mould issues >underside sub -
floor is extremely mouldy, DNA will clarify if fridge leak, bathroom leak or other
[indicates full sub - floor replacement required] >… [ E ] mould testing results to verify
extent of covered clai m building repairs – provide written formal outcome to
customer of options of fulfilment pending mould testing results”
October -
November
2016
W completed mould remediation and cont ents removal
builder (R ) and floorer (H ) completed quotes/SOW (R als o sai d work could not be
warranted)
insurer cash settled content sum insured = $109K
Com plainants raised complaint. Insurer‟s notes of 4 Octob er 2016 suggest
reasons include dissatisfaction with supervision by insurer‟s vendors
Insurer‟s notes show it advised complainants it d oes not accept that vendors can
“provide safety liability for customer being onsite during co nstruction” Insurer also
notes complainant‟s interference with works being done to date
on 21 October 2016 insurer informed complainants building claim will be cash
settled.
on 6 November insurer wrote to complainant outlining cash settlement decision
c omplainant s dispute about settlement went through insurer‟ s IDR
on 10 November 2016, IDR maintained cash settlement decision
on 25 November 2016, in surer cash settled $295, 149 for home repairs based on
R ‟s building quote
03 - 02 - 2017 Complainants‟ builder (D) wrote to them saying among other things:
> “ entire first - floor structural flooring has been in contact with moisture as the
water has travelled bet ween the spotted gum floating floor and the structural
flooring beneath, therefore mould is present ”
> “cannot remove the structural flooring underneath the internal wall frames
without first removing all of the framework. Because like all homes, the structu ral
flooring is installed before the wall frames and trusses are installed on top”
> “We have pulled up all the flooring except underneath the wall frames
> “We have tried multiple methods of removing the flooring underneat h the
frames, including trying to cut the fixings with a sabre saw, chiselling out the
flooring in small pieces, jacking the frames and flooring up slightly with a car
jack to give enough cl earance to remove the flooring. All of which are
unfort unately doing more harm than good to the structural int egrity of your home
and unsuccessfully removing the contaminated material”.
> “To remove the wall frames all gyprock must be removed from the frame s, all
cornice will need to be removed, the ceiling battens are also connected to the
wall frames which means the ceiling must come down and the ceiling battens
removed”
> “There is no guarant ee that the framework can be removed without damaging
the frames. If this is the case you will require new steel internal wall frames
installed throughout the first floor of your home”
09 - 02 - 2017 R, insurer‟s building consult ant, D an d complainant(s) met at premises
10 - 02 - 2017 R emailed complainants requesting copy of home building plan
Determination | Case number: 659549 Page 13 of 14
Date Action
06 - 03 - 2017 Insurer wrote to complainants advising :
> it had r eviewed request for additional payment bas ed on complainant‟s builder‟s
(D) scope of works and
> had req uested that R its B uilding Co - ordinator (BC) and Assessor, re - inspect the
damage to consider the R and D‟s scope of works against one another
> follo wing re - inspection, it is satisfied that the R Scope of Works sufficiently
allows for the cost of the repairs to damage caused by the leak from your fridge,
the bathroom leak and the air - condit ioning leak.
> its cash settlement decision of as set out in N ovember 2016 is maintained
09 - 03 - 2017 Complainants ‟ response to insurer‟s 6 March 2017 decision inc luded that:
> the repair quote from R “ advises the method of removing the structural floor ing
is to raise each wall frame”
> when R inspected the “ work carried out to date by our repair contractor it was
shown that this method could not be carried out due to the way the wall frames
were glued and fixed to the met al joists and block exterior walls ”
> R and BC “ both agreed verbally with our construction contractor and ourselves
that the way the structural flooring was removed is the only possibly way it could
have been carried out successfully and efficiently. ”
27 - 06 - 2017 complainant letter to insurer outlining additional payment required due to D not
being able to successfully remove structural flooring to complete claim related
repairs. Complainants note s:
> D t ried different methods but only way resulted in damage to the remaining
gyprock sheeting, cornices and ceiling sheets which then had to be removed.
> R‟s representative and insurer‟s assessor attended the premises and agreed
“ the only remaining course of action that could successfully have been taken
was to completely remove each of the wall frames in order to be able to remove
the damaged and contaminated structural flooring”.
25 - 07 - 2017 Insurer‟s BC provides statement:
> about onsite meeting at insured pr emises on 9 February 2017
> with outcome of his reviews additional submission by complainant dated 27
June 2017
> specifying items from the complainant‟s request he considered admissible,
partly admissible and not admissible and why
> recommen ding that insurer obtain costing from R for the admissible/partly
admissible items for payment
12 - 08 - 2019 AFCA complaint lodged
3.2 Additional costs claimed by complainants
building = $292,831.35
mould remediation = $24,556.27
temporary accommodation = $18,012.14
electricity/power connection and usage at temporary accommodation = $5552
gas connection and usage at temporary accommodation = $450
Determination | Case number: 659549 Page 14 of 14
telephone and internet connection at temporary accommodation = $400
storage of personal items, furniture and clothing = $6900
3.3 Relevant policy terms
Pages 26 – 28 PDS
Additional features
If we accept your claim for loss or damage due to an insured event, we will also provide
the following additional features.
...
Below is an overview of the additional features and the limits that apply for each level of
cover. For full details read the PDS.
…
Temporary accommodation when you have home cover
We cover
When an ins ured event damages your home to the extent you cannot live there, and we
agree, we will pay for your reasonable temporary accommodation costs for the time it will
take to repair or rebuild your home to a liveable condition. (emphasis added)
…
We will also pay the reasonable and necessary costs for:
– redirection of mail from the insured address for up to …
– utility connection costs at the temporary accommodation residence;
– relocation of your contents to and from the temporary accommodation residence if you
have contents cover under this policy;
…
Limits
…
The most we will pay under this feature is 10% of your home sum insured and the longest
period you can claim for is 12 months
...
Page 69 -PDS:
How we settle your claim
We choose how we settle home claims
If we agree to pay a claim for loss, theft or damage to your home, we will decide if we will:
– repair damage to your home;
– rebuild your home;
– pay you what it would cost us to repair or rebuild your home;
– pay you the sum insured for your home.
If we rebuild (or pay you what it would cost us to rebuild), we will do so on a „new for old‟
basis.
If we repair (or pay you what it would cost us to repair), we will at our option do so on a
„new for old‟ basis or to a similar condition to wha t your home was in before the loss or
damage occurred.
We may offer you a voucher, store credit or stored value card for the amount it would cost
us to repair or rebuild an item
…
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.