Home / IAG / Determination 659132

Determination 659132

Inadequate fire repairs to home; cash settlement amount; claim handling and compensation

FirmIAG
Decided2020-05-11
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$325,557
Non-financial loss$5,000
Amount claimed$500,000
SourceAFCA PDF

Summary

The complainant, whose fire-damaged home was poorly repaired under the insurer's scope, sought over $500,000. AFCA ordered a cash settlement of the $298,557 sum insured with interest, $27,000 temporary accommodation, reimbursement of expert and advocate costs, and $5,000 non-financial loss.

The insurer's repairs were inadequate and its claim management fell below good practice, but the expert estimate relied on for a larger settlement was not accepted, so settlement was set at the sum insured.

Issues

Subjects and remedies

home or building damagepay claimpay compensationpay interestpay non financial loss

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 659132 Financial firm Insurance Manufacturers of Australia Pty Ltd Determination | Case number: 659132 Page 2 of 17 Case number: 659132 7 May 2020 1 Determination overview 1.1 Complaint In July 2016 the complainant lodged a claim with the financial firm (insurer) for damage to her property caused by a fire. The insurer accepted the claim, arranged for a scope of works to be completed, and authorised repairs based on this scope of works. The complainant is dissatisfied with the repairs and says:  the fire damage was not repaired adequately  the insurer‟s contractors have caused further damage to the property  it is more economical to rebuild the property than undertake rectification repairs The insurer agrees rectification repairs are required. However, a dispute has arisen about the extent of the rectification repairs required. The insurer does not agree it has caused delays. 1.2 Issues and key findings Are the repairs to the property adequate? The panel is not satisfied the property has been adequately repaired. Several issues have been identified, the most serious being that the roof was replaced improperly. How should the claim be settled? The claim should be cash settled for the sum insured plus interest as set out in section 2.2. Is the complainant entitled to any compensation and other costs? The complainant is entitled to temporary accommodation, professional costs incurred in pursuing the complaint and non-financial loss compensation. 1.3 Determination This determination is substantially in favour of the complainant. The insurer is required to pay the complainant the following:  $298,557 plus interest  $27,000 for temporary accommodation  $5,000 for non-financial loss compensation. Determination | Case number: 659132 Page 3 of 17 The complainant is also entitled to the following subject to providing invoices for the costs incurred:  the full cost she incurred in engaging an engineer (RB) to provide expert reports and a cost estimate  up to $5,000 for the professional claims advocate. Determination | Case number: 659132 Page 4 of 17 2 Reasons for determination 2.1 Are the repairs to the property adequate? Building contract not correctly filled out A building contract signed by the builder was emailed to the complainant along with the scope of works (SOW). However, a copy of the building contract signed by the complainant has not been provided to AFCA and it is not clear if she signed it. The panel notes the contract title page says it is for „where the contract price is between $5,000 and $50,000‟. The BB repair quote was for $182,385.29. The contract has a construction period of 238 days, significantly longer than the approximate timeframe of 4 months originally indicated. It also has a construction price of $0.00. All other details including (but not limited to) plans, specifications, who is responsible for contract works insurance, progress payments, and provisional sums have been left blank or have $0.00 entered. Considering all this, the panel is not satisfied the building contract has been completed correctly. Asbestos not removed correctly BB submitted its first variation to the works on 3 October 2016 for the removal of asbestos. The variation is for $4,339.34 and says it includes the „cost of air monitoring and clearance certificates and asbestos removal‟. There is no information about how the asbestos was removed. The claim notes do not mention whether an asbestos clearance certificate for the asbestos was provided. No certificate or clearance document has been provided. Accordingly, given the lack of a clearance certificate or other information to show how the asbestos was removed, the panel is not satisfied asbestos has been removed correctly. Complainant’s expert says house need s to be rebuilt The complainant raised several concerns with the repairs. Following the SOW not being finalised in February 2019, she appointed an engineer (RB) to complete an assessment. RB provided a report dated 10 June 2019. Numerous issues were raised by RB in his report, including:  major structural repairs were undertaken with a limited building permit that has not been completed  the complainant has been allowed to live in the property, but no occupancy certificate has been completed  items were paid for but not installed Determination | Case number: 659132 Page 5 of 17  windows have been poorly prepared, damaged windows have been reused, and some of the new windows are damaged  finishing (skirtings, plasterboard, painting, etc.) is not to an acceptable standard  sewer vent has been terminated below the roof line when it should be above the roof line  Tasmanian Oak flooring has been replaced with particle board and in some places a floating floor has been used which is inconsistent with the SOW  the roof and supporting structure was replaced which changed the loading to the walls but no works were done to strengthen the walls and lintels at the time  roof tiling is not to the standard expected. RB concludes:  the insurer has spent over $200,000 repairing the property but does not have a certificate of occupancy  more than $400,000 will need to be spent again to fix the issues and complete the repairs  he believes the house has not been tested for mould or asbestos  the building works are of poor quality  items in the original SOW have not been completed  the most economical option would be to rebuild the house. Insurer’s expert identifies issues with repairs Following receipt of RB‟s report, the insurer appointed another engineer (RC) to inspect and report on the house and repairs. RC was provided with RB‟s report along with other relevant documents. RC provided a report dated 14 November 2019 and in it says:  the layout of the house has been changed  it is not clear why windows in some areas of the house were replaced  the new bathroom window is significantly smaller than the original  the quality of the new powder coated windows is normal  unevenness of the floors is not related to the fire  two areas of flooring have been replaced with particleboard and in other areas floating flooring and carpet was used. The SOW lists Tasmanian Oak for these areas  the finishing to the plaster and cornices is normal and cracking is typical and normal. Paint finish is also normal  areas of the property have not been cleaned properly and still have soots stains from the fire  three awnings have not been installed as per the SOW  there are plumbing defects related to the repairs including the sewer vent pipe Determination | Case number: 659132 Page 6 of 17  20% of the roof trusses were inspected for damage. Three required replacement or strengthening and six were not fully set in the timber. Based on the proportion inspected there is likely 15 damaged connections and 30 connections protruding  the load capacity is not sufficient to support the ducted gas heater in the roof space  two areas of undulating roof tiles are present and the eaves are incorrectly aligned  skylights have not been installed as per SOW  it has not been able to inspect all lintels, but the ones inspected would be sufficient  masonry piers recommended by the engineer have not been installed . RC notes it is highly unlikely the site supervisor decided to conduct changes to the layout and floor finishes without the complainant‟s agreement. The panel notes however, the changes are not in line with the updated SOW and no documentation has been provided to show the complainant agreed to the changes or why the changes occurred at all. Good building practice would be for all changes and work to be done to be fully documented. RC also recommended a hygienist be appointed along with a building surveyor to obtain the required occupancy certificate. Pool was not filled prior to event and contained rubbish The complainant says the pool was made inoperable by BB and is seeking for it to be repaired. RB said the pool was damaged when the filter was not running due to repairs and the pool requires repair. RC says the pool had been empty for several years prior to the fire and was full of rubbish including used cat litter, appliances, and general household waste. It says the pump and filter had been removed and were on the ground next to the pool. RC has provided satellite photos of the pool going back to 2009. A photo in July 2010 shows the water to be green and dirty. The pool appears to have been cleaned after this as a photo in March 2013 shows cleaner water however, by May 2013, the pool appeared dirty again. In November 2014 there appears to be rubbish in the pool water and by March 2015 it is not clear if there was any water in the pool. The photos from early 2016 show some rubbish in the pool but the bottom of the pool is still visible. RC says the issues with the pool are maintenance related. There is no information to indicate the pool was damaged by the fire. The complainant has the onus to show BB damaged the pool. Considering the available information, the panel is not satisfied the pool was damaged by the repairs. The insurer is not liable for this. Determination | Case number: 659132 Page 7 of 17 Co mplainant’s expert responded to RC RB responded to RC‟s report and say s he believes the engineering issues with the property are a symptom of the poor management of the repairs. RB says RC does not address this in its report. RB is of the view the property cannot be repaired and no builder would warrant the repairs. Property has not been adequately repaired A serious issue has been identified with the roof. This was replaced as part of the original repairs. Both RB and RC found issues with the roof‟s constr uction. RC examined 20% of roof truss connections for damage and found three connections that require replacement or strengthening and six that were not fully set. Based on this, he allowed for 15 damaged connections and 30 connections protruding but noted the following: Please note that this is subject to further investigation and should only be used indicatively for the costing of rectification works. He also agreed with RB that the treatment of the trusses was poor prior to their installation. They were left on site or subject to the elements for a period of time. He does not comment to what extent this would affect the longevity or integrity of the roof. RB maintains that given the extent of issues RC alone identified, this is enough to condemn the roof. This is further reinforced by the way the trusses were treated before installation. A further issue identified by another engineer engaged by the insurer (IL) was that the previous roof was traditional timber framed hip and valley roof construction. This was supported by both external perimeter walls and internal walls. In contrast, the new timber framed roof structure no longer places any loads on the internal framing. All loads were transferred to the external perimeter walls. This increased the loads o n the external perimeter walls greatly. This was not accounted for in the original works. IL noted a structural engineer should have checked the existing framing, including the lintels over windows and vertical studs. This was not done. Following this, IL was engaged to undertake further engineering design. IL did so. IL also recommended a new building permit be obtained, or the existing permit to be amended, with a building surveyor to be appointed. It does not appear a permit was obtained or amended, or a surveyor engaged as no documentation was provided to show this. Determination | Case number: 659132 Page 8 of 17 Part of IL‟s recommendation was the installation of masonry piers. Both RC and RB agree this is absent. Regarding the lintels, works had been done. Engineer HC and RC agree that of the ones inspected, these are adequate. RB disagrees this is clear and has raised concerns that they were adequately reinforced. Of significance, it does not appear the reinforcement works were subject to any inspection or certification by an engineer whilst the works were undertaken. It appears they were inspected by engineers after the works were complete. HC had to cut into the plaster to inspect them. Given all this, the panel prefers RB‟s evidence that the roof should be replaced. There are serious concerns with the way it has been repaired. This includes:  the poor treatment of the timber before it was installed  the number of failed connections identified  the failure to consider the loading to the external perimeter walls and to the extent this has been adequately addressed  the omission to construct masonry piers despite the passing of several years  the failure to obtain proper documentation and certification. There are also several other issues identified by the experts beyond the roof. This includes the failure to document the proper removal of asbestos, the change of flooring materials, leaving building materials on site and the installation of a heater in the roof system. Accordingly, the panel is satisfied the property has not been properly repaired. 2.2 How should the claim be settled? Claim should be cash settled The relationship between the parties has broken down and neither party has raised an objection to the claim being cash settled. This matter has been ongoing for almost four years. In the circumstances, the panel considers it is appropriate for the claim to be resolved by way of a cash settlement. This would provide finality to this long outstanding dispute. Complainant seeks more than $500,000 The complainant is seeking more than $500,000 in resolution of her claim and complaint. Determination | Case number: 659132 Page 9 of 17 Under the AFCA Rules, certain monetary caps apply to limit the maximum total remedy AFCA can award for direct financial loss if a complainant is successful. The monetary limit applicable to this complaint is $500,000 per claim. To support her claim for $500,000 the complainant provided RB‟s scope of works and estimate for the repairs required to her property. The estimate was for $489,158. Not appropriate t o base settlement on insurer’s SOW The insurer has provided an estimate from JP of $57,069.78 for the rectification repairs required to the property. This is based on RC‟s scope of works. The panel does not accept RC‟s scope of works is complete. This is m ainly due to the works required to the roof. RC‟s recommends certain repairs, but the panel accepts RB‟s evidence that it should be replaced. This difference alone increases the cost significantly. On a simple comparison between RB‟s estimate and JP‟s under the section of „Roof‟, this difference is $65,000. This does not include other incidentals associated with this such as the lintels, GST or builder‟s margin. Further, RC‟s scope of works does not make any allowance for possible asbestos remaining on site. In addition, JP‟s estimate is not based on an actionable quote. In the insurer‟s file note dated 2 November 2018, JP said: they don‟t touch rectification related repairs done by other builders due to structural issues that might affect repairs in future There are also many unknowns relating to the structural condition of the property and from mould and asbestos. Given all this, the panel is not satisfied it would be appropriate to base any cash settlement on JP ‟s estimate. Cash settlement to be based on sum insured RB ‟s estimate of $489,158 makes allowances for mould and asbestos along with addressing the structural concerns raised by the various engineers. The insurer has not raised any concerns or issues with the RB ‟s estimate for the scope of works. The panel accepts there are aspects of RB‟s scope of works that are not substantiated. For instance:  the panel is not persuaded the insurer is liable for the works to the pool Determination | Case number: 659132 Page 10 of 17  RB has assumed all of the painting has not been sealed correctly – RC disagreed with this and the evidence does not demonstrate this However, on the more significant aspects (e.g. roof), RB‟s scope of works and estimate is preferred. The panel notes the policy had a sum insured of $298,557 at the time of the loss. Much of the substantive works identified by RB would have been associated with the original repairs. This included the requirement to replace the roof, reinforce the lintels, engage structural engineers and construct masonry piers. All these should have been done as part of the original works. The original quote by BB was for $182,385.29. Several variations were provided that totalled over $30,000. It is not clear what the final cost was when the repairs were completed. However, it is clear this did not include the construction of the piers, the reinforcement of the external perimeter walls, obtaining the required documentation, conducting inspections and so forth. Further, it is clear this cost was based on substantive repair quality issues. Given all this, the panel accepts it is likely the original repair cost would have exceeded the sum insured if the works had been properly scoped and followed. Therefore, it would have been appropriate to cash settle the complainant‟s claim originally by paying out the sum insured plus any other applicable additional benefits that is not subject to this. The panel does not accept it is appropriate for the insurer to cash settle the claim based on RB‟s scope of works. This is because:  there are aspects that are not substantiated as set out above  it is likely that the original cost would have exceeded the sum insured and the complainant would have been out-of-pocket to a certain degree  it is not clear to what extent the cost to rectify the repairs is more than what the original cost of repairs should have been – given there are various aspects of the works that have not been shown to be inadequate, it is possible the cost to rectify is less Insurer should pay the sum insured plus interest The panel therefore accepts it is fair for the insurer to cash settle the claim based on the policy sum insured of $298,557 as well as interest pursuant to section 57 of the Insurance Contracts Act 1984. Interest should be payable from 29 September 2016, being about two months after the claim was lodged and the insurer was able to assess the extent of the loss, to when payment is issued. The application of interest is fair because:  it will account for the increased costs due to the time that has passed Determination | Case number: 659132 Page 11 of 17  the insurer has delayed settlement of the sum insured by attempting to repair the damage and doing so improperly 2.3 Is the complainant entitled to any compensation and other costs? Complainant entitled to further temporary accommodation costs. The policy also allows for reasonable and appropriate temporary accommodation costs for up to 12 months. The claim notes indicate the temporary accommodation costs incurred during the repairs were around $900 per week. RB estimated that the works would take about 30 weeks. The panel therefore considers an amount of $900 per week for 30 weeks to be appropriate. Therefore, i n the interests of providing a full and final resolution to the parties, the panel considers a fair settlement for temporary accommodation to be $27,000. Complainant is entitled to reimbursement of professional costs Paragraph D.5 of the AFCA Rules says AFCA may determine an insurer should contribute towards a complainant‟s professional costs in pursuing a complaint. Unless special circumstances apply, AFCA will not require an insurer contribute more than $5,000 to these costs. The complainant seeks payment towards her costs in pursuing this complaint. The complainant obtained and provided expert reports and a cost estimate from RB. She also engaged a professional claim advocate (DK) to provide submissions on her behalf. AFCA aims to provide a dispute resolution process which is accessible to complainants, without the need for professional advisors. Accordingly, professional costs will only be reimbursed where external advice is reasonably required, given the nature of the dispute. RB ‟s reports and scope of works materially assisted in determining the outcome of this complaint. In the panel ‟ s view it was reasonable for the complainant to be reimbursed RB‟s costs . Further, given the complex nature of the issues, the panel is satisfied it was reasonable for the complainant to engage a professional claim advocate. The conflicting and complex nature of the engineering advice provided by the insurer, combined with the failure of the ins urer‟s builder to adequately repair the property, means special circumstances should apply at least to the extent of RB‟s fees. Determination | Case number: 659132 Page 12 of 17 Therefore, the insurer should reimburse the complainant the full cost she incurred in engaging RB to provide expert reports and a cost estimate, subject to the complainant providing invoices for the costs incurred . Regarding the complainant‟s cost in engaging the professional claim advocate, the panel is satisfied the insurer should contribute to these costs. However, these costs are subject to the $5,000 cap and the complainant providing invoices for the costs she incurred. Complainant is entitled to compensation for non-financial loss Under paragraph D.3 of the AFCA Rules, we may award compensation for non- financial loss (capped at $5,000) where there has been an unusual amount of:  physical inconvenience  time taken to resolve the situation  interference with the complainant‟s expectation of enjoyment or peace of mind. We take a conservative approach to compensation and expect a complainant to bear a normal degree of inconvenience during a claim. As set out above, there were serious issues with the insurer‟s works. This was mainly to do with the roof and the fact the property became structurally compromised. It is also possible that the builders contaminated the site with asbestos. Further, the insurer‟s management and oversight of the repairs i s below the standard AFCA would expect on a repair of this nature and this has resulted in a lack of information documenting the repairs. Additionally, the panel is not satisfied the insurer has handled the claim and complainant in the manner expected or in line with good industry practice. This is demonstrated by the extensive issues identified almost four years after the claim was lodged. The panel acknowledges an award of $1,500 compensation for non-financial loss was paid for matters relating to this claim under the previous FOS dispute. However, the recommendation did not consider the specific issues identified in this complainant or the other matters that arose since it was issued. The panel considers the issues identified about the repairs and the claims handling are significant. These have also plainly caused the complainant to suffer a substantive degree of inconvenience and interference. Given all this, the panel considers it is fair in all the circumstances for the insurer to pay the complainant the maximum amount of $5,000 compensation for non-financial loss for these matters. Determination | Case number: 659132 Page 13 of 17 3 Supporting information 3.1 Our approach to this complaint We have considered it appropriate to expedite this complaint in accordance with the Operational Guidelines to the AFCA Rules, due to the nature of the complaint. Accordingly, this complaint has not been the subject of a preliminary assessment and has proceeded directly to determination. The determination is made by a panel consisting of the ombudsman together with a representative who has extensive experience in consumer claims and a representative who has extensive experience in the insurance industry. This complaint has been determined based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous decisions (which are not binding). There has been a full exchange of all material i nformation relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered. While the parties have raised numero us issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues considered directly relevant to the outcome only. 3.2 Expert reports Record Key points financial firm ’s expert ( HC ) Engineering Report 24 October 2018 CONCLUSIONS From our r e c e nt site inspection t h e following w ork s were confirmed to the timber f ramin g.  Double t op plate s have been prov ided throughout the residence t o suppo rt th e tru s s e d roof which confo rm s to codes .  Three new lintels have b een insta lled to the bedroom 1 & 2 and second lounge and these are new lint el s ar e per the members schedule.  The lin tel s to the front door, lounge and kitchen ar e the original OBHW lintels. According to the members schedule prepared by independent Link the se beams needed to be a 190 x 45 KDHW timber. From t he design check carried out by our offic e 1 90 x 35 OBHW lintels confo rm to current code s i t shou ld be noted th at KDHW only co mes in 45mm thicknesses an d not 35mm thicknesses .  Ope ni ngs were provided in t il e plaster w a lls by previous contractors to check the s t uds underneath the girder trusses. This has shown that double studs have been provided under the g irder trus ses . Determination | Case number: 659132 Page 14 of 17 Record Key points  No engaged piers have been provided unde rne ath the bearers to the sub - floor area underneath the girder trusse s. Therefore in our opinion all of the timber framing to the walls including lintel and top plates and stud s have been i nsta lle d as per the members schedule pr epared by independent li nk. T h e only area of works not completed i s the engaged piers und ernea t h t he girder trusses. financial firm ’s expert ( HC ) Engineering Report 18 December 2018 CONCLUSIONS From our recent site inspection several areas of fire reinstatement work have not been completed at the above property. A separate Scope of Works has been provided for the reinstatement of the house as a result of the fire reinstatement works. The reinstatement of the house required a new roof to be installed. It is possible that water can extend into the subfloor area whilst the roof it removed and reinstated with a new roof. Subsequent drying out can then result in movement occurring in the subfloor framing. Movement can also occur in subfloor framing due to normal seasonal changes in moisture content of the foundatio n material. In this case it is difficult to determine whether movement was evident in the floors prior to the recent fire. Therefore in our opinion it is possible that the reinstatement of the house has resulted in further movement occurring of the floor. Complainant’s expert ( R B) Engineering Report 10 June 2019 CONCLUSIONS I was requested to inspect this property and prepare a report that examines the state of the property, following recent repairs to rectify damage caus ed by a fire that occurred in July 2016. I was also requested to examine the management and state of progress of an insurance claim as administered by the Ins urer. The matter has been in progress for almost three years wit h significant faults and unresolved approvals, according to the Insu red. With reference to the body of this Report, I make the following comment:  The Insurer has spent over $200,000 on repairing this property, but it still has no Certificate of Occupancy. Much more than this amount will need to be spent again in order to overcome the problems found and make it fit for occupancy.  This claim has been extremely poorly managed. The Insurer appears to have delegat ed its authority to a collection of commercial builders and external advisers while reducing itself to the status of an observer. The repair process is a non - stop parade of poor management practices at the expense of both the Insurer and the Insured. It is still in process after almost three years.  I believe that the house has not been tested for mould and asbestos and is infested wit h rodents and insects, all of which Determination | Case number: 659132 Page 15 of 17 Record Key points represent a major threat to the health of the Insured and her family.  There is no Contract for the repair works. There is no Building Permit that covers the whole structure or other building elements and s uch Building Permit as exists is about to expire. There is no Occupancy Permit. The […] Council regards this property as a building site even though the Insured is living in it. All of this is contrary to various Acts and Regulations that the Insurer and B uilders should have ensured were complied with.  The building works are of a consistently poor quality throughout.  Many items specified in the original Scope of Works have not been delivered. I presume that the Builder was paid for them anyway.  In my opinion, the money spent by the Insurer on “repairing” this property has been a complete waste. The Insurer has also wasted time and its own credibility. If this house were to be properly repaired, I would estimate that it would require an ADDITIONAL $200, 000 AGAIN, over and above the figures shown in the Beacon Estimate – ie, a total of about $400,000 based on Beacon‟s original figures and an assessment of the situation found at this property, ignoring previous expendit ure. Given the quality of the house a nd its probable value, this expenditure would not be worth it. It would be better to write off the previous expenditure and reach an agreeable financial settlement with the Insured for replacement. financial firm ’s expert ( RC ) Engineering Report 14 November 2019  5.26 A review of the [JP] photographs (doc ument 20) showed the existing floor finishes. A summary of these finishes compared to what was in the scope of works and what was implement ed on site is shown in the table below. 6.0 Conclusion  6.1 . With the supplied information and the data gat hered on site, it is my opinion that [BB] and the Insured have agreed on many changes to the scope of works. Few of these changes have been documented, except for the changes listed in the updated scope of wo rks. I do not believe that these significant changes that are present on site would have been forced on the Ins ured without at least verbal agreement. In most cases, these changes appear to Determination | Case number: 659132 Page 16 of 17 Record Key points represent upgrades to the dwelling over the pre - event state. 7.0 Recommendations  7.1. Engage a hygienist to assess the dwelling and advise on mould remediation if necessary. I recommend that samples are taken from three random wall cavities and three surface samples; however, the extent of the investigation should be de t ermined by a mould specialist to give an acceptable level of confidence that mould is or is not present.  7.2. In order to obtain the required occupancy certificate, the current building survey or or a newly appointed building surveyor will need to request the as - built doc ument ation and engineering certification for the structur e. Complainant’s expert ( R B) Engineering Report 10 June 2019  At first sight, the document appears to be a competent and well researched Report. In fact, it misses the point of the problems associated with this claim and the reasons why the building is still essentially a potentially dangerous building site, despite appearances.  It is highly significant that a Structural Engineer has been sent to provide this investigation and not so meone with an understanding of management – particularly Project management. I note that [RC] was engaged via [ E …] , so this appointment should come as no surprise.  The real problem demonstrated clearly by the documents associated with this claim is a funda mental failure of the various parties involved to understand management practices and to implement those practices properly. Moreover, there has been a conspicuously obvious lack of documentation management and quality control throughout – again, a basic f ailure of management practice.  It needs to be emphasised that Engineering is not the problem – it is only a symptom of a much wider failure of management. The [RC] Report is an interesting but very limited overview of cert ain parts of the claim.  Fixing the problem is not as simple as taking over the house again and making a few alterations as the [insurer] letter implies. The problems are far too deeply ingrained for that. Moreover, no Builder would provide guarantees for this work as they are required to d o under Section 8 of the Domestic Building Cont racts Act 1995 . This is becaus e their work would rely on that of others and that work is known to be flawed. [RC] does not seem to understand that all work on a domestic building is governed by specific contra ctual laws that must be adhered to. By extension, neither does [E…] or the Insurer, otherwise they would have engaged a management consultant to provide a Report.  Neither [RC] or [insurer] have anything to say about the lack of any form of contract for the work done on this house. Neither do Determination | Case number: 659132 Page 17 of 17 Record Key points they propose how a contract would be negotiated for any repair work in future. They appear to believe that repairs can simply be made to happen without any thought about contractual obligations.  The irony of this is tha t [RC] has gone to some effort to promote [BB] ‟s idea that there must have been some unauthorised agreement bet ween subcontractors and the Insured in order to make some changes occur. If there was no contractual framework in place then nothing is unauthori sed. It would be interesting to see what form of contract existed bet ween [BB] and the various subcontractors. The lack of a Head Contract and an associated Financing Agreement should be explained by both the Insurer and Beacon and this explanation should be referred to the Victoria Building Authority.  The [insurer] letter is an attempt to plead a case with no apparent understanding of the issues and how to handle them. It appears to be a good reflection of the state of understanding the Insurer has of its contractual obligations. I dismiss this letter.  My final observation is as made above – that the Insured has been left with an appalling dilemma. Her house has suffered a massive assault and has no Occupancy Permit, which means that she should not be livin g there. But she cannot sell the house and has no resources to fix it, but has to face a continuing adverse attitude from the Insurer as clearly demonstrated by [insurer] ‟s letter.  I see no alternative but to provide enough money for the building to be dem olished and replaced with a new one.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.