Water escape damage claim partly declined on exclusion grounds and cash settlement offer
Text of the determination
Determination
Case number 657374
Financial firm AAI Limited
Determination | Case number: 528118 Page 2 of 18
Case number: 657374 30 October 2019
1 Determination overview
1.1 Complaint
The complainant holds a landlord insurance policy with the financial firm (the insurer)
and lodged a claim in July 2018 for water damage to his property which was first
observed in March 2016.
Relying on expert reports, the insurer says some of the damage arose from
circumstances which are excluded from cover under the policy.
Whilst the insurer has accepted the portion of damage caused by the leaking pipe, a
dispute has arisen over the extent of the insurer‟s liability relating to damage caused
by the leaking pipe and by excluded events.
Issues and key findings
Is the insurer’s offer to settle the claim adequate?
The panel:
is satisfied the complainant has established a prima facie claim because the
available information establishes on the balance of probabilities the proximate
cause of the claimed damage was escape of liquid which is an insured event.
is not satisfied the available information establishes the excluded events relied on
by the insurer were the proximate cause of the damage.
considers the insurer‟s offer is not adequate as the panel is satisfied the insurer is
liable for 85% of the claimed damage.
Is the complainant entitled to any other benefits under the policy?
The claim for loss of rent is to be settled according to the policy terms.
Is the complainant entitled compensation?
Upon provision of proof of the cost, the insurer is to contribute up to $5,000 to the cost
of the complainant‟s engineering reports.
1.2 Determination
This determination is substantially in favour of the complainant.
Should the complainant accept this determination then within 14 days of notification of
acceptance, the insurer is to settle the claim as set out in the determination under the
heading “settlement options proposed by the panel”.
Determination | Case number: 528118 Page 3 of 18
The insurer is also to settle the claim for loss of rent according to the policy terms.
Within seven days of acceptance, the complainant is to provide the insurer with any
invoices evidencing the cost of the complainant‟s engineering reports.
The insurer is to immediately reimburse the complainant up to $5,000 upon receipt of
those invoices.
The insurer is also to pay interest pursuant to the section 57 of the Insurance
Contracts Act (the Act) on the cost of the complainant‟s engineering reports from the
date the reports were paid for by the complainant until settlement.
Determination | Case number: 528118 Page 4 of 18
2 Reasons for determination
2.1 Is the insurer’s offer to settle the claim adequate?
Complainant says damage was caused by leaking pipes
The complainant says he discovered cracking damage to his investment property in
March 2016. He appointed a design engineer (R) to investigate the cause of the
damage noted to the southern elevation.
In a report dated 14 March 2016, R noted:
highly reactive soil
fill uncontrolled and uncompacted particularly towards the rear of the building
minor internal defects suggesting minor differential foundation movement
external cracking damage
the relief valve outlet from the hot water system was leaking causing ground near
to the eastern corner of the bathroom to be moist.
R said the defects were primarily located along the southern elevation towards the
eastern end of the house which correlated with the leaking hot water unit, shading
from the fence and an increased depth in highly reactive fill.
He submitted these were the causes of the excessive heaving noted within the
foundation along the southern elevation.
He also said the moisture control along the southern elevation was poor and
recommended certain remedial works.
The complainant says the hot water system relief valve was repaired in July 2016 as
was the brickwork along the affected side.
Subsequently, the complainant‟s tenant advised the main shower was leaking into the
adjoining room. The complainant attributed this to a damaged shower membrane
caused by foundation movement linked to the leaking hot water pipe.
The complainant appointed a plumber (F) to investigate the cause of the damage. F
carried out an inspection using CCTV in the main bathroom fixtures and the storm
water lines around the entire property. F reported the bathroom floor waste and
shower waste pipes did not meet buildi ng code. He also said the leak from the
stormwater line contributed to the slab dropping.
Insurer says damage caused by non-insured events
The insurer declined the claim for damage to the bathroom on the basis the damage
was caused by plumbing defects as identified by F. The complainant disputed the
decline and submitted a further report from F on 7 August 2018. F acknowledged the
Determination | Case number: 528118 Page 5 of 18
plumbing defects but argued that the damage was not caused by these defects. F
attributes the damage to broken pipes located under the foundation slab.
Differing expert opinion provided by the parties
The insurer‟s assessor (BC) attended the property on 30 August 2018, together with
its engineer (S). BC reported cracking damage in most of the rooms, evidence of
internal and external damage which had been repaired in the past and re -opened and
the presence of expansion joints that had been installed post construction. BC says
this demonstrates ongoing movement damage at the property.
BC also refers to excavation under the slab by S and the inadequate construction of
the foundation slab and piers of the property. He concluded if the property was not
properly constructed, then it is possible movement in the highly reactive soil would
cause the pipework to fail.
S determined the damage arose due to foundation movement because of inadequate
foundation preparations. S said any damage to the pipes are symptoms only of the
proximate cause which was the inadequate foundation preparations.
Based on this information, the insurer denied the claim because the damage was not
caused by an insurable event such as escape of liquid, but by an excluded event
being construction defects.
The complainant disagreed with the insurer‟s findings. Based on his own expert
reports, the complainant said the damage arose due to water escaping from damaged
pipes. He also contends the policy exclusion relied on by the insurer has no
application to his claim because he was not aware of the defect.
The insurer accepted the complainant was not aware of the defect. To resolve the
impasse, a further engineer (J) was appointed. In late November 2018, both J and R
inspected the property again to assess the damage caused by the leaking pipes.
J also undertook a level survey which showed the lowest point of subsidence was at
the back right-hand side of the house near the main bathroom.
Insurer accepts liability for a portion of damage
On 5 December 2018, J reported there were several reasons for excessive ground
movement in the area. He concluded there was long -term differential foundation
movement and long-term leaking pipes which damaged the back right-hand side of
the house. He said:
the movement damage in the right hand rear corner of the dwelling was primarily
due to leaking pipes
the movement damage at other locations throughout the house was due to ground
movement and not due to leaking pipes.
Determination | Case number: 528118 Page 6 of 18
Based on J‟s findings, and subject to further assessment and excavation, the insurer
agreed to pay for the damage caused by the leaking pipe. Otherwise, it said it was not
obliged to pay for damage caused by ground movement and construction defects.
The engineers attended the property again in late January 2019. The structural
design plans for the slab and pier system were reviewed and the site excavated to
investigate whether the slab and piers had been installed as designed.
J submitted a report dated 6 February 2019 which says:
the original foundation plans depicted the presence of seven concrete piers along
the rear of the dwelling. J‟s inspection located only four piers and a disengaged
fifth pier which was providing no support.
a geotechnical survey indicated significant fill at the rear of the dwelling which had
not been adequately compacted and the piers were not founded in sound natural
ground. This does not comply with the relevant building standard
a floor level survey showed an excessive variation of 131mm across the dwelling
the survey showed the lowest point was still at the rear right-hand side and was
12mm lower when compared with the earlier survey indicating further movement
over time significant differential foundation movement has occurred which has
damaged the pipes under the bathroom resulting in leaks in the subsoil, softening
the soils and causing further movement of the piers
over 50% of the movement of rear right of the house is attributable to pipe leaks
the rear half of the house will require rectification including underpinning
the estimated cost of the work was $95,000.
R reviewed J‟s findings. In a report dated 9 February 2019, R says:
six foundation piers were installed at the time of construction and five of these
remained connected to the slab
excavations suggest the fill depth was between 800mm and 1000mm
investigations did not determine the depth of the piers nor the founding material to
which the piers bear
the level survey shows vertical displacement o f the foundation and piers varies
from -49mm to -130mm along the rear of the dwelling
plumbing diagrams suggest increased settlement suggesting moisture in the soils
the central pier not being connected to the slab does not have a significant impact
as the soil would have shrunken away during hot weather and frictional resistance
would be minimal
highly probable the settlement of the piers was caused by softening of the founding
material that the piers bear into due to the moisture from the leaking pipes.
R also argues that:
Determination | Case number: 528118 Page 7 of 18
the foundation performed suitably for 10 years after construction until 2016
based on loading and environment conditions , 70% of the initial settlement of
foundation soil would have occurred in the first 5 years after construction
while the construction of the piers differs from the original design, given the
measured settlements and the timing of the reported defects , moisture has induced
excessive movement
primary cause of the defects noted since 2016 is excessive moisture within the soil
caused by the leaking and the fracture of the plumbing
the moisture within the soil instigated the settlement of the foundation and piers
the impact of moisture on foundation movement is underestimated and a
contribution greater than 50% should be attributed to it
failure of the plumbing has attributed to at least 85% of the settlement and the
defects recorded
agrees with J‟s recommendations about remedial works but suggests an additional
$15,000 (total sum of works $110,000 plus GST) is necessary for greater moisture
controls around the perimeter of the dwelling.
Scope of works, underpin design, and costings obtained
In February 2019, J provided a scope of works and an underpin design based on the
level survey and geotechnical testing. 10 underpins were located around the rear and
sides of the house.
In a report dated 8 May 2019, J submitted a supplementary report noting its initial
scope of works included remediation of all movement damage to the rear of the
dwelling. J says the remedial work caused by the plumbing leak was limited to the
underpinning works at the rear right of the dwelling. These works were estimated to
be approximately $40,000 plus GST.
The insurer engaged a builder (RC) to cost all the works in the sum of $98,958.
A summary of the expert opinions is provided in supporting section 3 this
determination.
Improvement works not covered and internal repairs not costed
The insurer said remedial works covered under the claim would not include
improvement works required to prevent future damage or upgrade the efficiency of
the site drainage.
As a settling period is required following underpinning, internal repairs were not
costed.
The insurer reiterated it is liable for the cost of rectification caused by the plumbing
leak only and not for the areas affected by the building defect or ground movement.
Determination | Case number: 528118 Page 8 of 18
Insurer offered to cash the claim for $30,239.50
In circumstances where some of the required remediation was covered by the policy
and some excluded by the policy, the insurer opted to cash settle the claim.
The insurer offered the complainant $30,239.50 calculated on 25% of the total costs
quoted by RC plus an allowance for the establishment and overhead costs.
The complainant required the claim to be met in full saying the damage was caused
by the escape of liquid and he was not aware of the defective construction of the
foundations.
Complainant has established a prima facie claim
The complainant must establish on the balance of probabilities he has suffered a loss
caused by an event to which the policy responds. This is known as a prima facie
claim. In this claim, the complainant must establish the proximate cause of the
claimed damage is the escape of liquid.
The insurer has not declined the claim. The dispute is about the policy response to
the claim, the extent of cover and the scope of works for which the insurer is
responsible.
The insurer accepts escape of liquid has damaged the property and has attempted to
determine what damage was caused by the escape of liquid and what damage was
caused by construction defects.
It is not in dispute:
there is escape of liquid near right-hand side of the rear of the building
the foundations were not constructed according to design
the complainant did not know about the construction defects
the soil is highly reactive
there is ongoing movement damage
S says the proximate cause of the loss is the inadequate foundation preparations.
According to S, the pipes were broken by ground movement caused by the
inadequate foundation preparations.
J says there are two events which have caused damage. The first being the
inadequate construction of the foundations and the second being the escape of liquid
from the broken plumbing.
R says the primary cause of the defects is excessive moisture in the soil caused by
the leaking and fracturing of the plumbing. R says it is the moisture within the soil
which caused the settlement of the foundations and piers.
Determination | Case number: 528118 Page 9 of 18
Having carefully considered all the reports, the panel finds R‟s findings more
persuasive.
R has visited the site on several occasions from 2016. He was present when J
undertook investigations and excavations in December 2018.
The panel considers R persuasively challenges the findings made by J about the
construction defects and the number of piers which were installed, and assumptions
made by J about the depth of the piers. J has not rebutted these observations.
Although R agrees the construction of the piers differs from the original design, R
points out there were no problems until 2016, some 10 years after construction.
This contention has not been rebutted by S or J.
In the circumstances, on the available information, the panel is persuaded on the
balance of probabilities the proximate cause of the loss is the escape of liquid. The
panel is satisfied the complainant has established a prima facie claim.
Proximate cause of the damage is not an excluded event
Once so established, the onus shifts to the insurer to prove on the balance of
probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss.
In this claim, the insurer must prove the damage was caused by a defect the
complainant knew about or by ground movement.
The panel does not accept the available information establishes the proximate cause
of the damage is ground movement. While ground movement has caused the claimed
damage, the panel is satisfied the available information establishes on the balance of
probabilities the real or effective cause of the ground movement is water escaping
from the leaking pipes into the reactive soil.
If the damage was caused by inadequate construction of the foundations, the insurer
accepts the complainant did not know of the defect.
As for the argument about the interpretation of the “dealing with defects” clause, the
panel need not make a finding thereon, because the panel is not satisfied the
proximate cause of the damage was an unknown defect.
Settlement options proposed by the panel
R says the insured event has caused at least 85% of the settlement and the defects
recorded. R agreed with J‟s recommendations about remedial work but suggested an
additional $15,000 was necessary for greater moisture controls around the perimeter
of the building.
The panel does not accept the insurer is liable for work regarding greater moisture
controls around the outside of the building. This is work required to mitigate future
Determination | Case number: 528118 Page 10 of 18
damage and is not covered by the policy. It is not work required to repair the damage
caused by the insured event.
RC has provided costing on J‟s scope of works in the sum of $98,958. However,
under the heading “notes”, RC refers to work which has not been quoted for or for
which he has not made an allowance.
The insurer‟s policy provides that if it agrees to pay a claim, it will decide whether it
will repair the damage or pay the complainant what it would cost the insurer to repair
the damage.
Because of its view that its liability was limited, the insurer opted to cash se ttle the
claim.
The panel notes the complainant has opted to install an additional concrete pad under
the water tank. Therefore, there is also some work to be undertaken which is not part
of the accepted claim.
However, in circumstances where the panel is satisfied the bulk of the cost of repairs
is to be borne by the insurer and there are possible variations (as noted by RC), the
panel considers it is fair in the circumstances the insurer repairs the damage. If the
complainant agrees to this settlement approach, then the complainant is to pay 15%
of the cost of repairs.
If the insurer repairs the damage, the insurer is not liable to pay statutory interest on
the cost of repairs.
If the parties agree to cash settle the claim, then the insurer is required to pay 85% of
the cost of repairs. In addition, the insurer is to make a further percentage allowance
to take into account the following:
the complainant no longer has the benefit of the insurer‟s lifetime guarantee
variations and contingencies which may occur during repairs including the
variations and contingencies already noted by RC under „Notes” .
In the event the insurer elects to cash settle, the panel considers a 10% increase on
the insurer‟s assessed 85% of the cost, will adequately address the ab ove dot points.
Should the parties agree to a cash settlement, the insurer is also required to pay
interest on any cash settlement pursuant to section 57 of the Insurance Contracts Act
(the Act) from 27 May 2019 (when it made the cash settlement offer to the
complainant) until settlement.
The panel encourages the parties to work together to resolve the claim.
The panel acknowledges once the underpinning is done, time should be allowed for
the building to settle. Only then can internal repairs take place. Due to the paucity of
Determination | Case number: 528118 Page 11 of 18
information about the cost of these future internal repairs, this determination does not
deal with the cost of future internal repairs after the underpinning is done.
Should the parties be unable to resolve the cost of future internal repairs, the parties
can return to Australian Financial Complaints Authority (AFCA).
2.2 Is the complainant entitled to any other benefits under the policy?
Claim for loss of rent to be settled according to the policy terms
If the insurer accepts the claim and agrees the building cannot be lived in, the insurer
will pay the weekly rental amount for the reasonable amount of time it decides it
should take to repair the building, so it can be lived in again.
The policy limits this benefit to 52 weeks and the most it will pay in total is $25,000.
The complainant advised the tenant vacated on 21 January 2019.
The insurer accepted the claim for loss of rent. The panel understands the insurer has
paid the complainant $10,703 for loss of rent.
The insurer indicates this aspect of the claim is not in dispute.
The panel is satisfied the insurer is required to settle the claim for loss of rent
according to the policy terms.
2.3 Is the complainant entitled to compensation?
Insurer to contribute to the cost of the complainant’s engineering reports
Pursuant to the AFCA Rules, AFCA may decide the insurer is to contribute to the
legal or other professional costs incurred by the complainant during the complaint.
Unless special circumstances apply, AFCA will not require the insurer to contribute
more than $5,000 to these costs.
The complainant has engaged a lawyer to advise on policy interpretation. AFCA
provides a service which is free for complainants. It is not usually necessary for a
party to engage a lawyer. If a complainant chooses to engage a lawyer, they will
usually cover their legal fees themselves.
In the claim circumstances, the panel considers the claim and complaint did not raise
legal issues which reasonably required legal advice.
However, the technical aspects of the dispute were complex. The insurer engaged
expert assistance. Therefore, the panel considers it is fair in the circumstances the
insurer contributes to the cost of the complainant‟s engineering report s.
Determination | Case number: 528118 Page 12 of 18
Should the complainant accept this determination, then within seven days of
acceptance, the complainant is to provide the insurer with any invoices evidencing the
cost of the complainant‟s engineering reports.
The insurer is to immediately reimburse the complainant upon receipt of those
invoices.
The insurer is also to pay interest pursuant to the Act on the cost of the complainant‟s
engineering reports from the date the reports were paid for by the complainant until
settlement.
Determination | Case number: 528118 Page 13 of 18
3 Supporting information
3.1 Our Approach
This complaint has not been the subject of a recommendation. Due to the nature of
the complaint, it has been referred directly to a panel for determination, in line with the
Operational Guidelines to the AFCA Rules. The panel consists of an Ombudsman
and two representatives with consumer and insurance experience.
The panel has decided this complaint based on what is fair in all the circumstances,
having regard to legal principles, applicable industry codes or guidance, good industry
practice and previous relevant determinations of AFCA or predecessor schemes
(which are not binding).
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other.
The panel has reviewed and considered all the material provided by the parties. While
the parties have raised numerous issues in their submissions, for the purposes of this
determination the panel has restricted its commentary to those issues that it considers
directly relevant to the outcome only.
It is an accepted principle of general insurance law that the insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an
event to which the policy responds. This is known as a prima facie claim. Once so
established, the onus shifts to the insurer to prove on the balance of probabilities that
an exclusion applies if it seeks to deny or limit its liability for the loss.
3.2 Case law and proximate cause
Case law establishes:
The proximate cause of the loss is the dominant or effective or operative cause of
the loss whether or not that be the last in time or the sole cause.
If there are several causes operating contemporaneous ly, each must be examined
for the qualities of reality, predominance and efficiency as the active, efficient
cause that sets a relevant chain of events in action. If one cause would have
caused the harm in any case, and the other would not have done so in the
absence of the first, the first is the proximate cause.
A common-sense approach is taken to determine proximate cause.
3.3 Extract from reports
Record Key points
Determination | Case number: 528118 Page 14 of 18
Record Key points
Financial firm ’s engineer ( S )
Report
12 September 2018
Observed and claimed building movement damage is a direct
result of damaging foundation movements, particularly settlements
and self - compaction/consolidation of loosely compacted
uncontrolled site fill over the premis es.
Observed raft slab construction, together with an apparent
absenc e of effective bored pier foundation improvements, is
contrary to the requirements of the relevant standard at
the time of construction and is a building defect.
Observed and claimed building movement damage is not the
result of initial breaks through plumbing around the region of the
main bat hroom. Any damage to pipework and wet areas,
particularly to the subject main bathroom, are symptoms only of
the proximate cause being inadequate foundation
preparations/pier improvements and resultant foundation
s ettlements to the placed uncont rolled fill across the site.
Observed and claimed building movement damage across the
whole premises has been present for an extended period,
represents a significant maintenance issue for the Ins ured and
cannot possibly be a ttributed to an isolated plumbing leak event in
one bathroom of the premis es.
Financial firm’s engineer (J)
Report
5 December 2018
Inspected and photographed with the complainant‟s engineer 29
November 2018.
Many internal wall and ceiling cracks as well as cracks in the
external concrete slabs.
Reviewed plumbing reports which confirm the leak in the main
bathroom and a leak in one of the stormwater pipes and a leak in
the main line of the sewer. Leaks to be repaired immediately.
Hydraulic level survey showed an excessive variation ac ross the
home with the lowest point at the back right - hand side of the
house near the main bathroom.
This area has excessive ground movement for several reasons
including subgrade movement, inadequate fill, highly reactive soil,
environmental conditions and tree growth.
Concluded there was long - term differential foundation movement
and long - term leaking pipes which have caused damage to the
back right - hand side of the house.
Based on the report from S , there should be an investigation as to
whet her the original bored piers were installed.
Foundations at the rear of the house should be underpinned.
M ovement and damage at the right hand rear corner of the house
is primarily due to leaking pipes. The move ment and damage at
other loc ations throughout the hous e is due to ground movement
and is not due to leaking pipes.
Financial firm’s engineer (J)
Report
6 February 2019
Reins pected wit h the complainant‟s engineer on 30 January 2019
and carried out a geotec hnical investigation.
Reviewed structural design plans for the slab and pier system
(supposed to be seven concrete piers along the back of the
house).
Determination | Case number: 528118 Page 15 of 18
Record Key points
Used an excavator to check the location of the concret e piers
along the back of the house to ensure they were adequately
founded.
Four concrete piers were found. A disengaged fifth pier was found
but it provided no support.
Geotechnical investigation car ried out on soil profile showing
significant fill at the rear of the house. Fill at the rear of the house
has not been adequately compacted. Works do not comply with
Australian standard.
Further hydraulic level survey carried out which shows the low
point is still at the back right - hand side of the house which has
dropped a further 12mm since the last survey. Further movement
still occurring at the rear of the house.
Plumbing should be repaired. Bathroom should not be used.
Based on the available informatio n obtained from the forensic
investigation the following is known :
Home suffering from long term differential foundation movement.
F oundations have not been installed as required by the plan. S ite
inspection confirmed that there are piers missing and that the piers
are not adequately founded.
O ver time significant differential foundation movement has
occurred. Because of this movement damage to the plumbing
pipes under the bathroom has occurred . This has resulted in leaks
to the subsoil under the dwelling.
G eneral direction of moisture movement is towards the rear left of
the dwelling which is the deepest area of fill. The bathroom that is
leaking is on the right of the dwelling.
Mo isture move ment has resulted in a softening of the soils at
depth resulting in further gross movement of the piers and hence
further gross movement of the rear of the dwelling.
Further gross movement is anticipated. E vidence suggest s over
50% of the movement of the dwelling at the rear right is
attributable to the broken pipes.
Significant remediation is required to rectify the problem at the rear
of the house including underpinning, lifting and stabilising.
Estimated cost works $95,000.
Financial firm’s engineer (J)
Report
28 February 2019
Provided underpinned design and underpinning details (10
underpins) and scope of works based on its hydraulic level survey
and geotechnical testing.
Engineered solution is to underpin the slab at the rear and sides of
the hous e to reinstate the stability of the foundation.
Financial firm’s engineer (J)
Report
8 May 2019
Provided more detailed report about the area directly affected by
the leaking pipes.
Earlier report related to rectification of all rear movement.
Firstly, there were settlement due to inadequately founded and
inadequate number of piers installed at construction.
Secondly, there was additional movement caused due to the
Determination | Case number: 528118 Page 16 of 18
Record Key points
breaks in the pipes.
The first event was the caus e of the breaks to the pipes.
If only movement caused by second event, then six underpins at
right hand rear of property.
Rectification of both events is required at the same time.
Estimated cost of installing the underpins for the second event
only and remediation of the bat hroom ar ea and associated
damage would be about $40,000 plus GST.
Complainant’s engineer ( R )
Report
14 March 2016
Relief valve outlet from the hot water system is leaking as noted
during the ins pection wit h the leaking occurring at approximately
2 - 3 second inte rvals. This continual leak had caus ed the ground
around near to the eastern corner of the bathroom to be damp and
moist. The moisture levels at the bathroom were wet when
compared to other areas along the southern elevation.
In general, the observed defec ts were primarily located along the
southern elevation toward the eastern end of the dwelling. This
correlated to wit h the leaking of the hot water unit, shading from
the southern fenc e and increased depth in highly reactive fill.
These factors were consid ered the driving parameters in the
excessive heaving noted wit hin the foundation along the southern
elevation.
Complainant’s plumber ( F )
Quote
10 July 2018
CCTV main bat hroom fixtures and describes cracking and
dislodged pipes and non - complianc e with the plumbing codes.
CCTV stormwat er lines around property. Leak from the stormwater
line is contributing to the slab dropping on the hous e.
Plumb quicks (rubbe r connectors used to join pipes together) were
found on stormwater lines which are causing them not to be able
to hold water and leaking.
Quoted to repair
Complainant’s plumber (F)
Email
7 August 2018
Pipes under the slab are not broken because of defective
plumbing.
Plumb quicks met Australian Standards and can be used on sewer
and stormwater lines.
Complainant’s engineer (R)
Report
9 February 2019
Complainant‟s engineer reviewed the report prepared by J.
Incorrect only four concrete piers were f ound. A connected pier
was located under the rear northern corner of the building.
Suggests six piers were installed with five piers still being
connected to the raft.
Excavations suggest fill depth varies from 800mm to 1000m and
investigations never det er mined the depth of the piers nor the
founding mat erial.
Conc rete pier depths within the soils in the area tend to be
2400mm to 2700mm deep.
Regarding the hydraulic level survey, probable settlement noted to
the piers induced by a softening of the founding material because
of water from the leaking pipes.
Determination | Case number: 528118 Page 17 of 18
Record Key points
As the constructive foundations have performed suitably for
several years suggest external factor (moisture) has induced the
excessive movement
Primary cause of the defects is excessive moisture caused by t he
leaking and fracturing of the plumbing. This caused the excessive
settlement of the foundation and the piers. Impact of moisture on
the soil has been underestimated by J and contributes to greater
than 50% of the movement.
Agrees with suggested remedial works and suggests other work
required which would incur an additional cost of $15,000 making
the total sum of the works to about $110,000 plus GST.
Based on observations since 2016 and the subsequent det ailed
investigation works undertaken as not ed within the detailed reports
prepared by J, say the primary cause of the damage as noted is
the failure and fracturing of the plumbing .
I ntroduction of the moisture caused by the plumbing has caused
the settlement in the slab and piers, thus resulting in the damage
noted to the dwelling.
Ag ree the construction of the piers does differ from that as detailed
by the designer, however, the timing of the defects in 2016 some
ten (10) years later suggest s external factor ( excessive moisture
resulting from the failure of the internal plumbing ).
F ailure of the plumbing has attributed to at least 85% of the
settlement and therefore the defects as recorded.
Agr ee in p rinciple with the suggested remedial works, plus greater
moisture cont rols around the perimeter of the dwelling are also
required ( add s approximately $15,000 ).
RC liability quote Work on slab side patio and reinstall water tank $3,531.
Repair to concrete slab and pier positions to the rear half of the
building $98,958.
3.4 Policy wording
The relevant policy extracts are referred to in the correspondence between the parties
and in the insurer‟s Notices of Response dated 14 December 2018 and 25 July 2019.
Both the policy document and the Notices have been exchanged with the
complainant.
Record Extract
What you are covered for Insured events
If you have a building insurance policy, we cover the building for loss
or damage at the insured address caused by a n insured event
during the period of insurance .
Escape of liquid Loss or damage caused by liquid leaking, overflowing or bursting
from any of the following:
Determination | Case number: 528118 Page 18 of 18
Record Extract
refrigerators, freezers, dishwas hers and washing machines;
any drain, fixed pipes, roof gutters or guttering and rainwater
downpipes, drainage and sewage systems;
fixed tanks;
swimming pools or spas;
waterbeds;
baths, sinks, toilets and basins;
fixed heating or cooling system;
water main, fire hydrant or water supply pipe;
an aquarium
What we do not cover -
general exclusions
You are not covered under any section of the policy for damage,
loss, cost or legal liability that is caused by, arises from or involves:
Ground movement
erosion, vibration, subsidence, landslip, landslide, mudslide,
collapse, shrinkage or any other earth movement …
We will not pay more than the relevant sum insured (unless you have the
Building Complete Replacement Cover option) or policy limit;
pay extra to replace the building or landl ord contents to a better
standard, specification or quality than they were before the loss or
damage occurred except as stated in the meaning “new for old”;
fix a fault that existed before the loss or damage occurred.
Dealing with defects If a known defect is the cause of the damage
We do not pay for loss or damage caus ed by a defect, structural
fault or design fault at the building that you knew about (or should
reasonably have known about) and did not fix before the loss or
damage occurred.
If an un known defect is the cause of the damage
If an incident covered by your policy damages the building and an
unknown defect was the cause or part of the cause, we will pay for
the resulting damage. If the unknown defective part of the building is
also damaged by the same incident, we will fix this as well.
We do not rectify structural or design faults
When we accept a claim, we will not pay extra to rectify a structural
or design fault at the building that you knew about (or should
reasonably have known about) . We will only pay you what it would
have cost us to fix the damage from the incident covered by your
policy or, if we agree, you can pay us the extra amount it costs to
rectify the structural or design fault at the building.
3.5 Other relevant material considered and relied on
Parties‟ submissions and emails and all attachments to all submissions and emails .
Parties‟ expert reports .
Photographs.
Scopes of work and costings.
Correspondence between the parties.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.