Alleged misleading advisor draft report, undisclosed fees and pressure to sign funding deed
Text of the determination
Determination
Case number 656871
Financial firm National Australia Bank Limited
Determination | Case number: 656871 Page 2 of 10
Case number: 656871 30 March 2021
1 Determination overview
1.1 Complaint
The complainants and their associated companies (collectively referred to as the AH
group) were involved in residential and commercial property development. The
financial firm (the bank) provided loan facilities to the AH group including the
complainants for this purpose. The loans were secured by the properties being
developed (the properties) and the complainants‟ residential homes.
In 2016, AH group requested additional funding from the bank. On 10 August 2016,
the complainants and Mrs M put a proposal to the bank for a debt restructure and
business recapitalisation (the directors‟ proposal).
The bank engaged a major accounting firm (the advisor) to assist it to assess the
directors‟ proposal. O n 19 August 2016, the advisor provided the complainants with a
copy of its draft independent business review (the advisor‟s draft report) to review for
accuracy. The advisor‟s draft report included questions and answers (Q&As) for the
complainants to respond to. It also had certain analysis and recommendations to the
bank redacted. Following receipt of the answers, and the complainants‟ confirmation
the advisor‟s draft report was factually accurate, the advisor prepared the final version
of its independent business review of the proposal dated 22 August 2016 for the bank
(the final report).
Following the final report‟s recommendations, the bank agreed to provide additional
funding to the AH group. The bank‟s agreement was on the terms set out in a Deed of
Funding, Repayment and Release between the AH group including the complainants
and the bank dated 30 August 2016 (the deed).
The complainants say:
the deed was different from the bank‟s advisor‟s draft report and as such, they
were misled by the bank into signing the deed
the bank did not comply with the deed
the bank did not disclose fees, including the advisor‟s fees and the bank‟s legal
costs, which affected the group‟s cashflow and ability to pay creditors on time to
complete the construction of the properties.
The AFCA case manager provided the parties with a recommendation on the issues
in dispute. The recommendation was in favour of the bank. A copy of the
recommendation is attached to this determination.
Determination | Case number: 656871 Page 3 of 10
The complainants rejected the recommendation for the reasons set out in section 2.1
below. The bank has offered an outcome better than the recommendation by
continuing to offer to release the complainants from their respective obligations to it.
1.2 Issues and key findings
Were the findings of the recommendation correct?
Based on all the relevant information, the findings contained in the recommendation
were correct and are adopted in this determination. Further submissions provided
after the recommendation have been considered.
Do the complainants’ further submissions c hange the outcome?
The complainants‟ further submissions do not change the outcome for the reasons set
out in section 2.2 below.
Is the bank’s offer to release the complainants is a more favourable outcome?
Where the bank has not made an error or breached an obligation to the complainants,
no compensation is payable to them and they remain bound by the terms and
conditions of the deed. The bank‟s offer to release the complainants from their
respective obligations is a better than this AFCA outcome.
1.3 Determination
This determination is in favour of the bank.
The complainants should contact the bank if they want to accept the bank‟s offer to
release the complainants from their respective obligations.
Determination | Case number: 656871 Page 4 of 10
2 Reasons for determination
2.1 Were the findings in the recommendation correct?
The findings in the recommendation are correct
I have decided this case on its merits, having regard to the relevant law, good industry
practice, codes of practice and previous AFCA decisions. I have taken into account all
the material submitted by the parties, both before and after the recommendation. I am
satisfied that the documentation I have relied on has been provided to both parties.
I am satisfied that the case manager‟s recommendation contains an accurate
summary of the complaint, the issues to be determined, any applicable paragraphs of
the Rules and any relevant law.
I agree with the case manager‟s reasons and findings in the recommendation and
adopt them as part of this determination. As I have attached the recommendation to
this determination, I have not repeated most of those reasons and findings.
Although I agree with the case manager‟s recommended outcome, the bank has
offered an outcome better than the AFCA recommendation by offer to release the
complainants from their respective obligations to it.
The complainants rejected the recommendation
In rejecting the recommendation, the complainants say:
they were misled by the bank where it admits the advisor ‟ s fees were not included
in the cash flow presented in the advisor‟s draft report
the bank debiting advisor fees left them with insufficient funds to pay creditors
they signed the deed on 25 August 2016 after receiving legal and financial advice
the bank is bound by the version of the deed executed on 25 August 2016
the deed was subsequently amended, however a marked-up version of the deed
highlighting the changes between 25 and 30 August 2016 was not provided to
them
the subsequent variation was significant because a party to the deed (Mrs JM) and
a security property 15 T St was removed without the subsequent changes to the
deed being highlighted to them in a marked-up version
the bank (lawyers letter dated 30 August 2016) only recommended Mrs JM seek
independent legal advice not the AH group
Mr M of the bank pressured them into signing the deed on 30 August 2016 so there
was insufficient time for them to seek legal advice regarding the variation.
Determination | Case number: 656871 Page 5 of 10
2.2 Do the complainants’ further submissions change the outcome?
The complainants’ further submissions do not change the outc ome
The complainants‟ further submissions do not change the outcome or progress their
claim because:
the bank has not engaged in misleading or deceptive conduct and for the reasons
set out in the recommendation, it has not been established that the bank engaged
in such conduct
before signing the deed on 30 August 2016, the complainants were given time to
review it and seek their own legal and financial advice
e ven if the conclusion could be reached that by reviewing the advisor‟s draft report
including the cash flow information, the complainants were misled by the bank,
there is no information to show the complainants relied on the draft report to make
the decision to enter the deed and it is speculative to assume that they suffered
financial loss by doing so
the complainants are bound by the terms of the deed dated 30 August 2016 and
AFCA will not set aside the deed and
the bank was entitled to pass on the advisor‟ fees to the AH group .
Each of these reasons is discussed separately below.
The bank did not mislead the complainants
The complainants maintain the bank misled them and relying on this misleading
conduct they entered the deed. They say where the bank admits the advisor‟s fees
were not included in the cash flow presented in the advisor‟s draft report the y were
misled.
The bank engaged the advisors to undertake a review of the AH group, so it could
assess their request for additional funding set out in their proposal dated 17 August
2016. The advis or‟s report included an an alysis of the cashflow provided by the AH
group which in the normal course did not include the advisor‟s fees.
I agree with the case manager ‟s recommendation the advisor‟s final repor t including
the draft report were prepared for the bank‟s purposes only. The provision of the
advisor‟s draft report to the complainants to check for factual accuracy and respond to
questions did not lead them to make an error by entering the deed. The complainants
were not entitled to rely on the advisor‟s report for the purposes of entering the deed.
The AH group‟s need for additional funding to complete their construction projects
and turn its financial fortunes around drove it and the complainants desire to enter the
deed. The complainants asked the bank to provide additional funding which the bank
agreed to do on the terms set out in the deed. This included the clauses by which the
bank could pass the advisors costs onto the AH group.
Determination | Case number: 656871 Page 6 of 10
Even if the con clusion can be reached that by reviewing the advisor‟s draft report the
complainants were misled by the bank, there is no information to show the
complainants relied on the draft report to make the decision to enter the deed.
The bank was entitled to pass on advisor ’ s fees to the AH group
The complainants say the bank debiting advisor fees left them with insufficient funds
to pay creditors. At the time the parties entered the deed the extent to which the bank
would continue to engage the advisors was not known. Consequently, the amount of
fees the advisors would charge the bank was unknown.
Clause 4 of the deed included a mechanism by which the bank could continue to
monitor the financial performance of the AH group. This required the AH group to
provide weekly and fortnightly reports to the bank‟s advisors. I agree with the case
manager ‟ s recommendation that the deed disclosed to the complainants that the bank
had the right to pass on both its advisor‟s fees and legal fees to the AH group, and
that it would do so.
The complainants have provided information to show payment of advisor ‟ s fees
ahead of other creditors on 25 September 2016 and 3 February 2017. They have also
provided information regarding an alleged decision by Mr M of the bank to reduce
assistance by $61,000 on 12 December 2016.
The complainants and the bank were working toward a common goal, so the AH
group could continue to trade. They entered the deed to record the basis on which the
bank would continue to provide financial assistance, so the construction projects
could be completed, and assets sold. This would enable to AH group to generate
cash flow to pay creditors including costs and fees under the deed . The timing for
completion and sale of assets was critical for continued cash flow, the AH group could
not simply rely on additional funds being provided by the bank.
Unfortunately, the time frames set under the deed were not reached. This impacted
the cashflow of the AH group. There may have been instances in September 2016
and Febr uary 2017 of advisor‟s fees being paid so the amount of cash available to
meet other creditors was short for a period. There is not enough information to show
Mr M of the bank reduced assistance by $61,000 in December 2016.
There is however information to show the bank continued to support the AH group
agreeing to vary the deed six times including providing additional funding in 2017.
Prior to providing further funding, in February 2017, the bank commissioned the
advisors to undertake a further independent business review of the AH group to
assess the impact of completion delays and subsequent lack of property sales.
Despite this additional assistance and support by the bank, the AH group was unable
to repay the money owing to the bank within the terms agreed.
The information does not support the proposition that the bank affected the AH group
because the advisor‟s fees were paid ahead of other creditors. The advisors were
Determination | Case number: 656871 Page 7 of 10
involved in supporting the bank through these variations and the bank was entitled to
pass these costs onto the AH group.
The complainants executed an earlier version of the deed on 25 August 2016
The complainants say:
they signed the deed on 25 August 2016 after receiving legal and financial advice
and
the bank is bound by the version of the deed executed on 25 August 2016.
The copy of the deed singed by the complainants on 25 August 2016 was not signed
by Mrs JM or the bank and therefore cannot be binding. Instead a further version of
the deed was created and provided to the complainants.
Where the bank:
did not sign the 25 August 2016 version of the deed
required further amendments to the deed to accommodate Mrs JM‟s refusal to
enter the 25 August 2016 version of the deed,
the 25 August 2016 version cannot be taken as the final deed agreed between the
parties.
Mrs JM would not sign the deed
The complainants say:
the deed was subsequently amended, however a marked-up version of the deed
highlighting the changes between 25 and 30 August 2016 was not provided to
them
the changes made were significant because a party to the deed (Mrs JM) and a
security property 15 T St was removed and these changes should have been
highlighted to them in a marked-up version of the 25 August 2016 deed.
At the time the property at 15 T St was offered as security for loans, Mrs JM was the
registered proprietor. The property at 15 T St was her home with the complainant Mr
GM. It appears the marriage between Mr GM and Mrs JM broke down.
The chronology in section 3 of the recommendation shows on 26 August 2016, Mrs
JM told the complainants and the bank she would not sign the proposed deed and
was selling the property at 15 T St in satisfaction of her guarantee obligations. Mrs JM
provided a selling agency agreement she had executed that day as evidence of her
intention to sell the property.
Where the 25 August 2016 version of the deed was unsigned by both Mrs JM and the
bank:
Determination | Case number: 656871 Page 8 of 10
the bank and Mrs JM are not bound by that version of the deed
it cannot be viewed as the final deed agreed between the parties.
The parties are bound by the deed dated 30 August 2016
In the recommendation it states that in relation to the final version of the deed
provided to the complainants and signed on 30 August 2016, “The only significant
change from the previous version was the defin ition of “Proposed New Guarantees”
on page 7 of each document. The properties required to be sold and the time for sale
did not change from the original to the amended version.” This was not entirely
accurate.
Following Mrs JM‟s advice to the parties on 26 August 2016, further changes were
made to the deed to accommodate Mrs JM‟s request. She was removed as a security
provider from schedule 1, the property at 15 T St was removed from schedule 2, the
definitions of Securities were changed to exclude the property at 15 T St and Mrs JM
was not required to execute the deed.
T he bank‟s lawyers‟ letter dated 30 A ugust 2016, to the complainants‟ advisor , says
Mrs JM will need to execute the deed and guarantee and indemnity for $520,000 in
her capacity as a director of two companies as well as in her own capacity as
guarantor. Ultimately this was not done. Instead, Mr GM executed the deed and a
guarantee for the two relevant companies as the sole director. The reference to the
requirement for guarantees and indemnities for $520,000 was removed from the final
deed. The complainants did however provide guarantees and indemnities for
$2,200,000.
It is this final deed, executed by the complainants and the bank and dated 30 August
2016, which records the terms of the agreement reached.
The property at 15 T St secured loans provided by the bank
Both the 25 August and 30 August 2016 versions of the deed required the
complainants to ensure the sale of the properties listed in the schedules by the time
specified. The properties listed in schedule 2 were required to be under co ntract of
sale by 31 October 2016. The property at 15 T St was removed from schedule 2 of
the final 30 August version of the deed. Consequently, the complainants did not have
to have that property under a contract for sale by 31 October 2016.
Mrs JM did not want to be a party to the deed or to extend the property at 15 T St as
security for the additional lending provided to the AH group under th e deed. Mrs JM‟s
and 15 T St‟s removal , from schedule 2, of the deed did not prevent the complainants
entering the deed and receiving the additional funding sought under the deed.
The property at 15 T St was sold and proceeds applied to reduce money owing
There is information to show the bank communicated directly with Mrs JM regarding
the sale of 15 T St to satisfy her obligations as mortgagor to the bank. The bank for
Determination | Case number: 656871 Page 9 of 10
confidentiality reasons would not disclose information regarding the 15 T St security
to the complainants.
The complainants provided an account statement for account *9859 in the name of Mr
GM and Mrs JM. The statement shows in May 2018, 15 T St was sold and the
proceeds of sale of $1,619,135.52 were applied to reduce the balance owing from
$2,053,432.72 to $434,297.20.
The complainants say the inclusion of 15 T St would have reduced the AH group‟s
liability once it was sold. Where the sale proceeds were not sufficient to pay out the
balance owing on the facility in the name of Mr GM & Mrs JM this assumption is not
supported.
The complainants gave warranties and acknowledgements regarding advice
The complainants say:
they signed the deed on 25 August 2016 after receiving legal and financial advice
although their lawyer was present when they executed the deed on 30 August
2016, they did not receive legal advice regarding the variations to the deed
Mr M of the bank pressured them into signing the deed on 30 August 2016.
In both the 25 August 2016 version and final 30 August 2016 version of the deed, it
provided for the following:
clause 6.2 (qq), the complainants acknowledge they enter the deed voluntarily on
their own information and investigation
clauses 6.2 (rr), the complainants acknowledged they had taken independent legal
advice
clause 15, required the complainants to seek independent legal and financial
advice regarding the deed. This clause 15 incorporated the complainants‟ warranty
to this effect.
The requirements of clause 15 was highlighted in the letter from the bank‟s lawyers to
the complainants‟ advisor dated 30 August 2016 , enclosing the deed.
The complainants received advice
The complainants were aware:
Mrs JM would not sign the version of the deed originally signed by them on 25
August 2016
the deed needed to be varied to accommodate the removal of Mrs JM and 15 T St
which they were not required to sell as Mrs JM was selling as mortgagor
acknowledged and warranted they received independent legal and financial advice
regarding the deed before entering it on 30 August 2016.
Determination | Case number: 656871 Page 10 of 10
Other than the changes the complainants were already aware of, there were no
significant changes between the deed the complainants signed on 25 August 2016, to
which they agree they received legal and financial advice, and the deed they signed
on 30 August 2016.
The AH group was facing a funding shortfall which needed to be filled to complete
their construction projects. Before signing the proposed deed and guarantees the
complainants were given time to review the documents and seek their own legal and
financial advice which they did.
I agree with the case managers recommendation, the information shows that before
signing the proposed deed on 25 August and again on 30 August 2016 , the
complainants were given time to review the documents and seek their own legal and
financial advice which they warrant, under the terms of the deed, they did.
The bank was entitled to rely on the complainants‟ warranties and acknowledgements
in the deed regarding advice. There is no information to support the complainants
claim Mr T M of the bank said on 30 August 2016, „sign the deed now or we will shut
you down‟.
2.3 Is the bank’s offer more favourable outcome ?
The complainants remain bound by the terms of the deed
Where the bank has not made an error or breached an obligation to the complainants
no compensation is payable to them. The complainants remain bound by the terms
and conditions of the deed including the Facilities and the Securities defined in the
deed. AFCA will not set aside the deed.
The bank has offered to release the complainants from their obligations
The bank has offered to offer to release the complainants from their respective
obligations to it. This means the bank will not hold the complainants liable for any
outstanding amount under the loans, mortgage or guarantee terms. This is an offer
which the bank has reinstated on several occasions, after it was rejected by the
complainants. The bank has offered a resolution on better terms and represents a
more favourable outcome to the complainants than the AFCA outcome.
Recommendation
Case number 656871
Financial firm National Australia Bank Limited
Recommendation | Case number: 656871 Page 1 of 21
Case number: 656871 14 August 2020
3 Overview
3.1 Complaint
The complainants and their associated companies (collectively referred to as the AH
group) were involved in residential and commercial property development. The
financial firm (the bank) provided loan facilities to the AH group including the
complainants for this purpose. The loans were secured by the properties being
developed (the properties) and the complainants‟ residential homes.
In 2016, AH group requested additional funding from the bank. On 10 August 2016,
the complainants and Mrs M put a proposal to the bank for a debt restructure and
business recapitalisation (the directors‟ proposal).
The bank engaged a major accounting firm (the advisor) to assist it to assess the
direc tors‟ proposal. O n 19 August 2016, the advisor provided the complainants with
its draft independent business review (the advisor‟s draft report).
The advisor‟s draft report had assumptions, analysis and recommendations for the
bank redacted and included questions and answers (Q&As) for the complainants to
respond to. Following receipt of these answers, and the complainants‟ confirmation
the advisor‟s draft report was factually accurate, the advisor prepared the final version
of its independent business rev iew of the directors‟ proposal dated 22 August 2016
(the final report).
Following the final report‟s recommendations, the bank agreed to provide additional
funding to the AH group. The bank‟s agreement was on the terms set out in a Deed of
Funding, Repayment and Release between the AH group including the complainants
and the bank dated 30 August 2016 (the deed).
The complainants say:
the deed was different from the bank‟s advisor‟s draft report and as such, they
were misled by the bank into signing the deed
the bank did not comply with the deed
the bank did not disclose fees, including the advisor‟s fees and the bank‟s legal
costs, which affected the group‟s cashflow and ability to pay creditors on time to
complete the construction of the properties.
Recommendation | Case number: 656871 Page 2 of 21
3.2 Issues and key findings
Did the bank mislead the complainants into signing the deed?
The bank did not mislead the complainants. The provision of the advisor‟s draft report
to the complainants to check for factual accuracy and respond to questions did not
lead them to make an error by entering the deed.
Did the bank comply with the deed?
The bank complied with the terms of the deed however, the AH group was unable to
do so.
Did the bank disclose it would pass on fees to the AH group?
The deed disclosed to the complainants that the bank had the right to pass on both its
advisor‟s fees and legal fees to the AH group, and that it would do so.
Are the complainants entitled to compensation?
Because the complainants were not misled by the bank when they entered the deed,
they are bound by its terms. The bank has not made an error or breached an
obligation to the complainants. No compensation is payable to them.
3.3 Recommendation
This recommendation is in favour of the bank.
No compensation is payable to the complainants.
Recommendation | Case number: 656871 Page 3 of 21
4 Reasons for recommendation
4.1 Did the bank mislead the complainants into signing the deed?
The bank did not mislead the complainants
The complainants say:
they were misled about matters in the advisor‟s draft report which they relied on in
entering the deed
they believed the advisor‟s draft report was for their benefit as well as the bank‟s
if they had been provided with the unredacted final report it would have put them in
a better position to negotiate terms and conditions such as
> reasonable property sale and settlement dates, drawdowns by staggered
payments, cross securities
> non-provision of weekly cash flow reports and funding requests to traders and
suppliers which were used by the bank to determine who and how much was
paid.
The sending of the adv isor‟s draft report to the complainants was part of a sequence
of events which followed from the directors‟ proposal and ended with the parties
entering the deed. This sequence of events is set out in the chronology in section 3.2
below.
The purpose of:
the advisor‟s draft report and final report was for the bank to undertake an
assessment of the AH group and the directors‟ proposal before making its decision
to offer additional funding
the deed was to set out the terms on which the additional funding was being
offered to the AH group.
AFCA‟s approach to misleading conduct is set out in section 3.1 below. Since :
the bank was not required to disclose its advisor‟s advice to the complainants
receipt of the advisor‟s draft report did not change the complainants‟ position,
there is no information to show that the provision of the draft report to the
complainants to check for factual accuracy and respond to questions, led them to
make an error by entering the deed.
The bank has not engaged in misleading or deceptive conduct, so the deed remains
binding on the complainants.
Recommendation | Case number: 656871 Page 4 of 21
The parties met to discuss the AH group’s position
In 2016, the AH group required additional funding. There was a meeting between the
parties on 14 July 2016.
Before the bank would agree to the complainants‟ funding request, it required a
review/due diligence of the AH group to be conducted. The review was to assess
what funding was required for the AH group to continue to trade to complete and sell
assets to reduce debt.
At the meeting the bank said:
it was prepared to release $200,000 that day but required a proposal from the AH
group as to what was required
the proposal was to include asset sales at market value to achieve debt reduction.
The complainants put a proposal to the bank
On 10 August 2016, the directors‟ proposal was provided to the bank. The directors‟
proposal included a request for $1,500,000 additional funding for the completion of
four property developments. The developments were to be completed and sold
between October 2016 and June 2017, and the proceeds were to be used to repay
the bank and other creditors.
On 17 August 2016, the bank responded that it was generally supportive of the
proposal, and:
listed the group‟s assets which it required to be under contract of sale by 31
October 2016 or within 60 days of the development reaching practical completion
said the additional request of Mrs JM, Mr GM complainant‟s ex -wife, was to be
resolved directly between the couple
said the proposal was to be documented in a deed.
The complainants were given a redacted copy of the advisor’s draft report
The bank engaged the advisor to obtain information including cash flow, progress
updates for the construction, creditor and trade debtor details to:
undertake a review of the AH group
qualify and quantify the funding that was required and how it would be repaid.
On 19 August 2016, the advisor provided the complainants with the advisor‟s draft
report with assumptions, analysis and recommendations redacted.
The correspondence to the complainants and the advisor‟s draft report state clearly
the draft report was provided for the complainants to review as to its factual accuracy
and for the Q&As. The advisor‟s analysis and recommendations were stated to be
confidential between the advisor and the bank.
Recommendation | Case number: 656871 Page 5 of 21
The complainants were given time to review the advisor’s draft report
The complainants say the bank‟s advisor put immense pressure on them to state the
draft report was factual and did not provide them with adequate time to check the
contents.
The bank‟s advisor provided the advisor‟s draft report to the complainant Mr GM at
8:58 am on 19 August 2016. Mr GM and Mr AB were asked to review the draft for
factual accuracy and answer some questions . The complainants‟ Mr AB responded to
some questions before 1:00 pm the same day but noted they had not had time to go
through it in detail.
At 10:17 am on 22 August 2016, in response to a follow up email from the bank‟s
advisor, Mr GM said „we have chec ked it to the best of our ability with the time limits
permitted and believe it to be factual‟.
There is information to show the AH group and the complainants were under
increasing pressure from other creditors and suppliers. Mr GM‟s email dated 25
August 2016 to the bank‟s advisor provides a list of creditors that were commencing
legal action and suppliers with which they were trying to negotiate part payment for
debts totalling over $125,000. This was in addition to the payment obligations to the
bank.
The proposed funding from the bank, requested by the complainants, was time
critical. Despite this, the bank gave the complainants three days to review the
advisor‟s draft report and confirm its factual accuracy. This was reasonable in the
circumstances.
The advisor’s final report was provided to the bank for its purposes
Following receipt of the complainants‟ answers and confirmation as to factually
accuracy, the advisor prepared the final report.
The final report was provided to the bank the same day. As is to be expected, there
are differences between the redacted advisor‟s draft report provided to the
complainants and the final report which the bank relied on to make its decision to offer
additional funding. Like the advisor‟s draft report, the final repo rt included information
for the bank which it did not disclose to the complainants before they entered the
deed.
Prior to offering additional funding, the bank undertook a detailed assessment of the
AH group to meet its obligations to act as a diligent and prudent the banker. It:
engaged an experienced advisor to assist it
requested information in relation to cash flow and the timing for the completion and
sale of assets
received advice, analysis and recommendations from its advisor.
Recommendation | Case number: 656871 Page 6 of 21
It was not reasonable for the complainants to expect the bank to disclose
commercially sensitive information to them. The final report was to assist the bank to
reach its credit decision and not for the benefit of the complainants.
The bank agreed to provide additional funding on the terms in the deed
The bank agreed to offer the AH group additional funding and time to complete and
sell its construction projects. The terms of the additional funding were recorded in t he
deed.
The complainants agree the purpose of the deed was to provide funding to complete
current developments and client homes. Once the developments were complete, they
were to be sold at market prices to pay down the loans with the bank and other
creditors.
The purpose of the deed was consistent with the directors ‟ proposal.
The complainants received advice before they signed the deed
The complainants say they did not receive legal advice on the deed, because it was
presented to them on the day it was signed.
There is information to show on 24 August 2016, the ban k‟s lawyers sent the
proposed deed to the complainants‟ advisor Mr DV. The documents included two
deeds, a guarantee and indemnity and four guarantee advice certificates. These
documents were returned to the bank‟s advisor signed by the complainants the ne xt
day. These documents included three guarantee advice certificates completed by the
complainants‟ lawyer Ms CD.
With the return of these documents, the bank released $125,200 to the AH group to
pay creditors.
On 26 August 2016, the fourth proposed guara ntor Mrs JM advised the complainants
she would not sign the proposed deed. The complainants asked the bank to continue
with the support offered under the proposed deed relying on the documents including
the guarantees which the complainants had signed and the existing securities and
guarantee it already held for Mrs JM.
The bank agreed to the request, but required the complainants to sign a further
amended version of the deed and guarantees, to account for this change. These
amended guarantees were signed by the complainants with the three guarantee
advice certificates completed by the complainants‟ lawyer Ms CD on 29 August 2016.
The amended deed was provided to the complainants‟ advisor Mr DV by midday on
30 August 2016. The only significant change from the previous version was the
definition of “Proposed New Guarantees” on page 7 of each document. The
properties required to be sold and the time for sale did not change from the original to
the amended version.
Recommendation | Case number: 656871 Page 7 of 21
This final version of the deed was signed by the complainants at the bank at a
meeting between the parties on 30 August 2016 at 5:30 pm. The complainants
attended the meeting with their lawyer Ms CD. Under the deed the complainants
acknowledged they had taken legal advice as to its terms (clause 6.2 (rr)).
The available information clearly shows the complainants received independent legal
and financial advice before they singed the guarantees and deed on 30 August 2016.
The bank was not required to disclose its advisor’s advice to the complainants
The advisor‟s draft report and accompanying communications with the complainants
clearly state:
the advisor acted for the bank
the advisor‟s draft report excluded redacted information which was confidential
between the advisor and the bank
the advisor‟s d raft and final reports were solely to assist the bank
the complainants may not place any reliance on the information, findings or
conclusions in the draft advisor‟s report.
In these circumstanced it was not reasonable for the complainants to expect the bank
to disclose to them:
redacted parts of the advisor‟s draft report
the final report which contained commercially sensitive information.
Receipt of the advisor’s draft report did not change the complainants’ position
Even if the conclusion could be reach that the complainants were misled by
information contained in the advisor‟s draft report, there is no information to show the
complainants‟ relied on the report to change their behaviour or position to their
detriment.
The AH group:
was a long-term customer of the bank and owed the bank over $19,000,000
was experiencing financial difficulty
required additional funding to complete construction projects to generate income to
return capital to the business
was facing increasing pressure from unpaid creditors and seeking finance from
other third-party lenders.
Before responding to the directors‟ proposal, the bank:
instructed the advisor to prepare the draft report
sent the advisor‟s draft report to the complainants to check for factual accuracy and
answer questions
Recommendation | Case number: 656871 Page 8 of 21
received the final report and relied on it as part of its credit risk assessment.
The bank then offered additional business finance on the terms set out in the deed.
There is no information to show the complainants were misled by what was written in
the advisor‟s draft report or that by relying on this misleading conduct they changed
their position and entered the deed to their detriment.
The complainants did not rely on the draft report
The complainants say if they had seen the unredacted advisor‟s draft report they
would have been in a better position to negotiate the terms of the deed regarding:
the sale of security properties
settlement dates
draw down by staggered payments and cross securitised several projects.
The advisor‟s final report was prepared for the bank‟s purposes. It was to assist it to
assess and then decide the basis on which it was prepared to provide further funding
support to the AH group. The terms of the bank‟s offer were set out in the deed.
Both the advisor‟s draft report a t page 20 and the deed (schedules 2 and 3) list the
same properties for sale. The only property not included in the deed was Mrs JM‟s.
The advisor‟s draft report does not set out timeframes for property sales but says the
timely sale of property assets is key to mitigate risk. Clause 3.1 of the deed provides
for the timing of the sale of property assets.
The complainants do not say they would have refused to sign the deed if they had
seen the unredacted draft report. Instead they say:
they could have made a more informed decision to move forward
if they had seen the comment in the final report “By advancing $1.38m to the
group, it will enhance [the bank‟s] position by $4.36m” they would not have sought
and secured further funding from a third -party lender.
The AH group was facing a funding shortfall which needed to be filled to complete
their construction projects. Before entering the deed, they had already taken steps to
secure additional funding from another third party. It seems improbable they would
not have continued to do so because of a comment with respect to the benefit to the
bank of providing the further funding in the advisor‟s final report.
Before signing the proposed deed and guarantees the complainants were given time
to review the documents and seek their own legal and financial advice which they did.
Even if the conclusion could be reached that by reviewing the advisor‟s draft report
the complainants were misled by the bank, there is no information to show the
complainants relied on the draft report to make the decision to enter the deed and that
they suffered financial loss as a result of doing so.
Recommendation | Case number: 656871 Page 9 of 21
The complainants continued to negotiate ongoing bank support
Once the deed was entered, the bank continued to fund the AH group. To
accommodate subsequent changes including the AH group:
borrowing additional funds from a third party
extending the timing of the sale and settlement of assets
requesting additional funding from the bank,
the bank agreed to vary the terms of the deed.
4.2 Did the bank comply with the deed?
The bank complied with the deed
The available information shows that while the bank complied with the terms of the
deed, the AH group was unable to do so. Consequently, the bank agreed to vary the
deed six times to assist the AH group further. Despite these variations, the AH group
was unable to repay the money owing to the bank on the agreed terms.
The deed was varied
The available information shows that by February 2017, the AH group‟s property
sales had not completed and settled as quickly as proposed in the deed. This had a
detrimental effect on the cash flow of the AH group and its ability to pay its creditors
on time. Consequently, the AH group requested more funding from the bank.
The bank instructed the advisor to conduct a further review of the AH group in
February 2017 to provide advice as to whether the bank should provide additional
funding. The final report, dated 17 February 2017, recommended funding be provided
subject to conditions regarding the timing of asset sales, the release of funds and the
duration of the funding, provided milestones were met.
The AH group, not the bank, sold the security properties. The deed did not require the
property assets be sold at a set price. Prior to each sale, the AH group sought the
bank‟s a greement as mortgagee to ensure the release of each mortgage security at
settlement.
The bank says the sale proceeds were applied first to facilities secured by the
property being sold and then to other facilities and securities. It also agreed to release
some sale proceeds to the AH group for business and personal expenses. The bank
has provided information to show it complied with clause 5 of the deed in applying the
proceeds of sale.
Following execution of the deed on 30 August 2016, it was varied six times as set out
in section 3.2 below. The variations assisted the AH group where the bank agreed to:
facilitate secured lending to the AH group by a third party
Recommendation | Case number: 656871 Page 10 of 21
change when funds were paid
extend the date for sale and settlement of some securities
provide additional funds of $105,000
extend the expiry dated of facilities.
Release of funds was provided for in the deed
The complainants say the additional funding under the deed should have been
provided in a lump sum or line of credit for the AH group to utilise when it wished.
Clause 2 of the deed set out what funds would be released, when and on what
conditions. Funds were to be drawn down progressively in instalments tied to key
milestones on asset sales and/or completion of projects.
The deed did not provide for funding in a lump sum or line of credit. The deed funding
did include continuation of the existing overdraft. It was anticipated the overdraft
would be repaid by December 2016 after which surplus funds from asset sales would
be available to the AH group.
Both the complainants and the bank were working toward the construction projects
being completed so the AH group could continue to trade. When the timing and
realisable value of assets sales were not reached as anticipated, the parties agreed to
vary clause 2 with the second, third and fourth deeds of variation. However, even with
the additional funding provided by the bank to the AH group under the fifth deed of
variation and further time extensions under the sixth deed, the AH group was unable
to repay the money owing to the bank within the terms agreed.
4.3 Did the bank disclose it would pass on fees to the AH group?
The bank disclosed it would pass on fees to the AH group
The complainants say the bank did not disclose fees, including the advisor‟s f ees and
legal costs which affected the AH group‟s cashflow and ability to pay creditors on time
to complete the properties.
The bank says:
t he advisor‟s fees were not included in the cashflow in the draft report
t he advisor‟s fees were only debited to the AH group‟s facilities when there were
funds available to meet those fees
the debiting of the fees did not prevent the A H group making critical payments in
line with its cashflow needs and projections at each point in time
it provided increased funding to the AH group on numerous occasions throughout
the period of the deed to support the AH group‟s attempted workout and
restructure strategy , and the additional funding exceeded the advisor‟s fees and
the bank‟s legal fees
Recommendation | Case number: 656871 Page 11 of 21
at each stage, the additional fundin g was provided based on the AH group‟s
projected cashflow needs and available funds at that point in time, which factored
in the payment of the advisor‟s fees (or fees previously paid) by the AH group
the advisor‟s fees were one of many expenses of the A H group which were met
from additional funds advanced by the bank under the deed which now form part of
the remaining balance owing to the bank which will not be recoverable by the bank.
Set out in section 3.3 are the clauses of the deed setting out the bank‟s right to pass
on both the advisor‟s fees and legal fees to the AH group. This includes fees for the
restructure, establishment and performance of the deed.
The bank disclosed it would pass on these fees to the complainants.
4.4 Are the complainants entitle to compensation?
No compensation is payable to the complainants
Where the bank has not made an error or breached an obligation to the complainants
no compensation is payable to them.
The deed includes acknowledgments and general release clause
By entering the deed, the complainants:
acknowledged the enforceability of the Facilities, Securities, the Guarantee and
the Guarantee Securities in issue (clause 6.2 (a))
acknowledged they entered the deed voluntarily on their own information and
investigation (Clause 6.2 (qq))
acknowledged they had taken advice as to the terms of the deed (clause 6.2 (rr))
agreed to release the bank from „…. all claims, actions, suits, causes of action or
damages which it has or may have as at the date of this Deed arising from or
relating to any one or more of the following ‟ :
> the Facilities and/or the Securities;
> the relationship of banker and customer between the Bank (and its officers,
agents and employees) and the Security Provider;
> the relationship of banker (and its officers, agents and employees) and guarantor
between the Bank and each of the Guarantors; or
> any statements, representations or promises made or allegedly made by or on
behalf of the Bank (and its officers, agents and employees).‟ (clause 6.3)
agreed the deed constitutes the entire agreement between the parties relating in
any way to its subject matter (clause 14.1).
The complainants remain bound by the terms and conditions of the deed including the
Facilities and the Securities defined in the deed.
Recommendation | Case number: 656871 Page 12 of 21
The complainants were required to provide weekly cash flow reports
The complainants say the advisor‟s draft report did not require the AH group to
provide weekly cash flow reports and funding requests to traders and suppliers for the
bank to determine who and how much was paid.
For the bank to monitor ongoing performance of the AH group and funding
requirements, it required cash flow information including details of creditors being paid
a nd sales progress. This information was provided by the complainants to the bank‟s
advisor prior to the bank‟s offer of additional funding under the deed.
Under the terms of the deed the AH group was required to provide the bank‟s
advisors with:
weekly reports of „ actual to budget cash flow, highlighting material variances ‟ ,
fortnightly reports of the sale of the properties, reports on all other conditions of the
deed (clause 4).
The bank’s offer is better than the AFCA outcome
Despite the bank providing additional funding to the AH group under the deed and
subsequent variations, the proceeds of sale from the completed developments were
insufficient to repay the AH group‟s creditors. With the business unable to trade,
several of the AH group companies have been placed into external administration.
Following the sale of the security properties and negotiations with the complainants to
resolve the issues between them, the bank offered to release the complainants from
their respective obligations to it.
Since:
the complainants are bound by the terms of the deed, Facilities and the Securities
defined in the deed
the bank did not breach the deed
the bank is not precluded from enforcing any recovery rights under those agreement.
The bank‟s offer to release the complainants from their respective obligations to it
appears to be better than any outcome AFCA could award.
Recommendation | Case number: 656871 Page 13 of 21
5 Supporting information
5.1 AFCA’s approach
Misleading or deceptive conduct
Section 12DA (1) of the Australian Securities and Invest ments Commission Ac t provides:
“A person must not, in trade or commerce, engage in conduct in relation to financial services that is
misleading or deceptive or likely to mislead or deceive.” .
AFCA approach
A financial firm must not engage in misleading or deceptive conduct. For AFCA to
award compensation for misleading conduct, a complainant must show:
the financial firm made a statement or engaged in conduct that was (or was likely
to be) misleading and deceptive (misrepresentation)
the complainant relied on the misreprese ntation to change their position, and
the complainant suffered loss as a result.
Conduct can be doing or saying something. It can also be not doing or not saying
something. It can also be a pattern of behaviour over time.
If we find that the complainant was misled, we will consider how much worse off they
are because they relied on the misrepresentation and compensate them for that loss.
The remedy for misleading conduct is not to put the complainant in the position they
would be in, if the misrepresenta tion came true.
5.2 Chronology
Prepared from documents provided by both parties
Dated Source Key points
15.07. 16
at 9:56
am
Email the
bank‟s
advis or to Mr
GM
Subject [bank‟s advisor] Review
…Thanks for your time on the phone yesterday to discuss the [bank‟s
advis or] review from the bank]
Set out below is the scope of the review that I will walk you through at
our meeting this afternoon.
..
Summarise the debt repayment strategy being propos ed by the AH
group (including sale of collat eral property) and assess the achievability
and impact of the strategy
Recommendation as to the level structure, and term of additional
funding from the [bank] if appropriate
Recommendation | Case number: 656871 Page 1 4 of 21
Dated Source Key points
The focus will be on the costs to complete as well as the size of the
funding need. I look forward to see ing you this afternoon.
15.07. 16 Meeting Between the bank, Mr GM, Mr AB and the bank‟s advisors and the
complainants ‟ advisor.
10.08. 16 Letter
complainants‟
advis or to Mr
TM of the
bank
Proposal for debt restructure and business recapit alisation
…
excess of $700,000 on overdraft to continue until asset sales permit
reduction
provide additional $1,500,000 facility to facilitate completion of projects
taking the overdraft limit to $2.7M [ the bank allowed a temporary
excess to $1.2M on the $500,000 ove rdraft]
individuals to stay in homes while being sold
individuals to drawdown funds to meet living expenses
agree to second mortgage over XXX one Pty Ltd with the bank to
retain priority for the loan, OD and any interest and costs
enable to group to contin ue with XXX 4
The bank release Mrs JM & Mr SB from any further liability one the
principal places of residence have been sold
17.08. 16 Letter the
bank to the
complainants‟
advis or
…the bank is generally supportive of the Proposal, however has the
following comments it wished to make to progress the matter.
1. Third party loan…. the bank required the third - party loan be
subordinated behind the bank‟s security
2. Proposed new facility of $1. 5m
3. Timing of asset sales. The Group Assets that in appear in sched ule
2 annexed to this letter are to be under contract of sale by 31
October 2016.
The Group Assets that appear in schedule 3…to be under
unconditional contract of sale within 60 days of each
development reaching practical completion…developments are
to r each the date of practical completion in accordance with
schedule 2.
4. Equity in Group Assets…equity released to be direct to repay the
Proposed New Facility or otherwise in accordance with the bank‟s
securities…bank may consider requests ...to redirect…at t he bank‟s
absolute discretion
5. Request for early release of guarantee and indemnities... of Sharon
Bisignano and Joanne Masiello…once principal place of residences
sold…bank not willing ...will consider a request at a later date
6. Additional request of Mrs JM …. matter to be resolved direct
between Mr and Mrs Mo
7. Documentation…proposal is subject to documentation by way of
formal Deed...
Recommendation | Case number: 656871 Page 15 of 21
Dated Source Key points
19.08. 16
at 8:58
am
Email the
bank‟s
advis or to Mr
GM
Please find enclosed our Draft Report to the [bank] for your review as to
its factual accuracy.
You will see that we have redacted various areas of the report which
include our analysis pertaining to our recommendations to the bank.
This is because our recommendations are confidential between [the
bank‟s advisor] and the ba nk. You will also note a few outstanding
queries which we have tagged “ [Q&A] ” in the report. Rather than close
these out first with you, we thought we could do that contemporaneously
with your review of the draft.
Once you have had an opportunity to revie w the report, pleas e provide
your ans wers to the Q&A and let me know if you would like to discuss
any factual aspects of the report.
18.08. 16 The bank‟s
advis or‟s
DRAFT
Independent
Business
Review
Overview – AH group is currently undercapitalised as a result of bot h
the downturn in the residential property market, but also the investment
of working capital in various property developments that have failed to
complete and settle as expected.
19.08. 16
at 11:30
am
Email Mr AB
to the bank‟s
advis ors
The answers to Q&A are as follows
<image011. png>
No
<image012. png>
Brindley has been handed over
<image013. png>
No
<image014. png>
Historically the maintenance is within the Purchase Order allowance that
is included in the Cost to complete for the job.
Please a dvise if I have missed any other Q&As
19.08. 16
at 12:40
pm
Email the
bank‟s
advis ors to Mr
AB
Thank you [Mr AB] , we will make those updates in the draft report.
Just one Q&A remains outstanding, on page 25 – to confirm that all
homes have home indemnity insurance taken out by the builder and
certificates provided to owners
19.08. 16
at 12:49
pm
Email Mr AB
to the bank‟s
advis ors
The answer to this is YES
19.08. 16
at 12:52
pm
Email the
bank‟s
advis ors to Mr
AB
Thank you [Mr AB] .
Are you in a position to confirm whether the contents of the report are
factually accurate (with those updat es you have provided below), or do
you require further time to consider the report in this respect?
19.08. 16
at 12:56
pm
Email Mr GM
to the bank‟s
advis ors
Hi [Ms K]
We only received the report this morning so we have not had to time to
go through it in detail
Thanks
Recommendation | Case number: 656871 Page 16 of 21
Dated Source Key points
19.08. 16
at 1:12
pm
Email the
bank‟s
advis ors to Mr
GM
Understand [Mr GM] , just thought we would check.
Cheers
22.08. 16
at 8:25
am
Email the
bank‟s
advis ors to Mr
GM
Good morning [Mr GM] ,
Please let us know if you have any queries regarding the factual
contents of the report. If not, we look forward to receiving your
confirmation that the contents of the report are factually accurate.
We would like to close out with you in this respect as soon as able to
this morning, and be in a position to issue our final report to the bank
today.
Please do not hesitate to contact me if you would like to discuss.
22.08. 16
at 10:17
am
Email Mr GM
to the bank‟s
advis ors
Hi [Ms K]
We have checked it with to the best of our ability with the time limits
permitted and believe it to be factual
Thanks
22.08. 16
at 12:19
pm
Email the
bank‟s
advis ors to Mr
GM
Thank you [Mr GM] ,
On that basis, we will proceed to finalise the report.
22.08. 16
at 3:29
pm
Email the
bank‟s
advis ors to Mr
TM of the
bank
Please find enclosed our final report including recommendations. As
requested, we have also included a copy of the final report with the
recommendations redacted.
Plea se let us know if you would like hard copies and if so, how many.
22.08. 16 The bank‟s
advis ors
Independent
Business
Review
Letter to the bank - We have been engaged by [the bank] to undert ake
an Independent Business Review of [the AH group]…scope of work
outlined in our engagement letter…
This report has been prepared on the basis of fieldwork commenced
on 14 July 2016 and carried out to the date of this report…This report
is solely to assist [the bank] in connection with its considerations with
respond to the AH group of companies.
Overview – AH group is currently severely undercapitalised as a result
of both the downturn in the residential property market, but also the
investment of working capital in various property developments that
have failed to com plete and settle as expected…
The case flow forecast (CFF) prior to any additional financial
accommodation, indicat es a present short fall of $1.0m which grows to
$2.5m by the end of September 2016. The current shortfall manifests
in current overdue credito rs of $2.0m. Looking out past December can
be deceiving bas ed on the assumption of no new work in the CFF
work …..
Recommendation | Case number: 656871 Page 17 of 21
Dated Source Key points
Recommendations
In terms of the additional $1.5m requested, we recommend that the
funding be provided to the Group, subject to the following:
Loan to [ XXX One]
- In additional to the $1.5m the proposed $0. 5 creditor loan be receipted
to [XXX One] and subordinated behind the bank.
Borrowing party to be [R Property]
- The $700k currently extended to Amano Homes and additional
funding of $1.5m be lent to [R Property] by the bank, given that the
predominant purpose of the funding is to complete the development
properties that are either owned by [R Property] or its subsidiaries
along with the equity that exists, and considering the key risks that
im pact the ongoing solvency of [AH group].
Formalisation of agreement
- The Group‟s debt restructure be formalised under a Deed of Funding
Release of funding
- The funding to [R Property] be lent instalments, the timing of which
are tied to key milestones on a sset sales and/or completion of projects
(refer page 26)
Timing of asset sales
- To de - risk to the recapitalisation of [AH group], the timeframe of the
assets sales is to be brought forward mitigate the working capital
shortfall (refer page 26))
24.08. 16
at 2:38
pm
Email bank‟s
lawyers to
complainants‟
advis or
Please see the attached letter and the Deed of Funding, Repayment
and Release (" Deed" ).
We note that we will shortly be couriering hard copies of the letter, the
Deed and Guarantee and Indemnity documents to your offices for your
clients' execution.
Attaching Letter to complainants‟ advisor from bank‟s lawyers
(24.8. 16). pdf; AARLEG - #37246782 - v2 -
Deed_of_Funding__Repayment _and_Release - _[bank].pdf
25.08. 16
at 4:48
pm
Email Mr GM
to bank‟s
advis or
Please see below the list of creditors that are commencing legal action,
we have managed to negotiate with some for only a part payment.
I have als o included a couple of suppliers that we desperately need to
go back to some jobs so that we can complet e and issue PCI
The total being $125189.18
Recommendation | Case number: 656871 Page 18 of 21
Dated Source Key points
25.08. 16
at 5:21
pm
Email Mr GM
to bank‟s
advis or and
complainants‟
advis or
The documents have been executed by myself, [Mr AB & Mrs SB] and
the originals have been delivered to [bank‟s advisors].
I am uns ure if [Mrs JM] will sign them as she is seeking advice
tomorrow. In the meantime can we please have some funds released to
satisfy some suppliers that are commencing with legal proceedings?
If [Mrs JM] does not sign we request that [the bank] proceed under [Mrs
JM‟s] existing securities and the new security/loan documents that we
have signed.
25.08. 16
at 5:23
pm
Email bank‟s
advis or to Mr
TM of bank
and bank‟s
lawyers
Please find attached copies of the documentation delivered by [Mr GM]
to our office just now, including:
- 2x Deed of Funding document
- 1x Guarant ee and Indemnity document
- 4x Guarant ee advice certificates
I note it appears they are signed, except for the signat ure of Mrs JM.
I will arrange these to be delivered this aft ernoon to [the bank] to th e
attention of [Mr TM].
26.08. 16
at 1:07
pm
Email bank‟s
advis ors to Mr
GM
Please be advised that [the bank] have no objection to uploading
payment today for the purposes set out in your email below, for $125.2k.
26.08. 16
at 3:34
pm
Email Mrs JM
to
complainants;
advis or cc Mr
AB, Mr TM of
the bank and
bank‟s
advis or
I have had advis e today from a Commercial Lawy er. I will not be signing
the Deed. I have attached a listing agreement for the sale of [15 T St].
Once the sale of this is complete my guara ntees will be satisfied and my
liability we be finalised.
Attaches selling agency agreement for [15 T St]
26.08. 16
at 5:41
pm
Email
complainants‟
advis or to Mr
TM of the
bank and the
bank‟s
advis or
We have been advised by Joanne as per attached email that following
the meeting with her solicitor she has been advised not to sign the
documents and as such will not be signing them.
[Mr GM, Mr AB & Mrs SB] have all signed the documents.
On the basis of the above they request that the bank continue wit h the
support outlined in the bank doc uments using the new securities in so
far as the parties that have signed and utilising existing securities in so
far as [Mrs JM] is concerned.
Do you wish [Mr GM] to return the signed documents today as Mrs JM]
has returne d them unsigned?
29.08. 16 Guarant ee
and indemnity
Customer [R Property]
Guarant ors coms and ot hers
Guarant ee of all amounts with the customer owes [the bank] up to
$2,200,00 limit
Solicitor‟s certificate provided by Ms CD from [MLS] for the excution of
the guarantee by each complainants on 29.08.16
30.08. 16
at 11:54
Email bank‟s
lawyers to
Please see the attached letter and the amended Deed of Funding,
Repayment and Release.
We note that we will shortly be couriering hard copies of the letter and
Recommendation | Case number: 656871 Page 19 of 21
Dated Source Key points
am complainants‟
advis or
the Deed to your offices for your clients' execution.
30.08. 16 Letter bank‟s
lawyers to
complainants‟
advis or
We refer to our letter of 24 August 2016 and to your correspondences
with [Mr TM] of our client, [the bank] ( Bank ) in relation to your clients'
request for further funding from the Bank.
We attach an amended version of the Deed of Funding, Repayment and
Release ( Deed ) for your clients' execution. We understand that fresh
copies of the guarantees have already been p rovided to you by the
Bank.
We again draw your attention to clause 2.1(a) of the Deed in relation to
the timing of execution of the Deed, as well as the requirements under
clause 15 of the Deed.
We note that [Mrs JM] will need to execute the Deed in he r capacity as a
director of [M Investments Pty Ltd] and LDDV Investments Pty Ltd.
Further, [Mrs JM] will need to execute the Guarantee and Indemnity for
$520,000 both in her capacity as director of the above companies, as
well as in her personal capacity a s a guarantor.
Our client requires that [Mrs JM] to take independent legal and financial
advic e as to the nature, effect and extent of the Deed, as well as the
Guarant ee and Indemnity for $520,000. We note that our client will
require written confirmatio n from [Mrs JM‟s] solicitors that [Mrs JM] has
taken independent legal advice in relation to the above.
30.08. 16
at 4:02
pm
Email
complainants‟
advis er to
bank‟s
advis or and
Mr AB
I Confirm that the parties with their solicitor will be at [the bank] at 5.30
to sign all documents.
[Mr GM] has confirmed that [Mr AB] is a director of [A and E]
Can you advise what floor so I can let solicitor know.
30.08. 16 Deed of
Funding,
Repayment
and Release
Signed by the complainants and dat ed 30. 08.6
5.3 The deed - terms and conditions
The deed
The deed is between the bank and the complainants as borrowers and security
providers and dated 30 August 2016. The deed includes the following clauses
Recommendation | Case number: 656871 Page 20 of 21
….
….
Variations to the deed
The deed was varied six times as follows:
2 September 2016, to accommodate additional secured lending by a third party to
the AH group
1 November 2016, to adjust when funds were paid to the AH group, extend the
date for sale of some securities from 31 October 2016 to 30 November 2016 and
subsequent settlement provide additional funds of $105,000, extend the date for
asset sales
Recommendation | Case number: 656871 Page 21 of 21
19 April 2017, recording the new facility limit of $3,580,000 which included new
funding of $477,480, the guarantee limit was increased from $2,200,000 to
$3,580,000 and the schedule for the sale of security properties was adjusted
29 May 2017, the date for expiry of facilities was extended from 31 May 2017 to 16
June 2017 or 30 June 2017 subject to conditions being met
14 June 2017, this was by way of a letter from the bank proposing to extend dates
in the deed by a further 7 days
14 July 2017, the dates under the deed were further extended to 28 July 2017.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.