Home / Lloyd's / Determination 656415

Determination 656415

Storm damage claim partly declined and settlement offer disputed

FirmLloyd's
Decided2020-08-13
ProductGeneral Insurance · Strata
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$10,000
SourceAFCA PDF

Summary

The complainant claimed storm damage to four rental units under a Strata Protection policy. The insurer paid part of the claim, offered $5,191.46 net of excess and declined the rest, and AFCA found the offer fair and no further payment or compensation was required.

The complainant bears the onus of proving a storm-caused loss, and the engineer's evidence established only limited storm damage.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Lloyd's determinations · Find similar determinations

Text of the determination

Determination Case number 656415 Financial firm Lloyd's Australia Limited Determination | Case number: 656415 Page 2 of 15 Case number: 656415 13 August 2020 1 Determination overview 1.1 Complaint The complainant holds a Strata Protection policy (the policy) with the financial firm (the insurer) for accidental loss or damage. The complainant made a claim for damage to four rental units following a storm event on 7 February 2019. The claimed damage later included two air conditioning units. The insurer accepted part of the damage was caused by the storm and declined the claim for the rest of the damage because:  the complainant did not provide sufficient information about units 1 and 2 (repairs to the se units were completed before the insurer’s assessment) to show the cause of damage, detail of works undertaken and prior condition of property  investigation/assessment of units 3 and 4 showed the damage was pre-existing and/or caused by events excluded under the policy  the complainant has not provided sufficient information to show how the air conditioners were damaged and the extent of damage. The complainant says the claim should be accepted because:  he reported the damage to his broker, but it took 6 weeks before the assessor attended, so he completed repairs to units 1 and 2 so as not to lose rental income  he has provided the information requested by the insurer The insurer has offered the complainant $6,191.46 (less $1,000 excess) for the accepted damage. The complainant is seeking $10,000 in total net of the policy excess. The case analyst provided the parties with a preliminary assessment on the issues in dispute. The preliminary assessment was in favour of the insurer. As the complainant did not accept the preliminary assessment, the complaint has been referred to me for determination . 1.2 Issues and key findings Is the offer made by the insurer fair and in accordance with policy terms? Yes. The available information establishes on the balance of probabilities the offer made by the insurer is fair and in accordance with the policy terms. Determination | Case number: 656415 Page 3 of 15 Is the complainant entitled to compensation? No. The available information does not establish an award of compensation is warranted. 1.3 Determination This determination is in favour of the insurer. The insurer is not required to take any further action in relation to the claim or the complaint. Determination | Case number: 656415 Page 4 of 15 2 Reasons for determination I have decided this complaint based on what is fair in all the circumstances, having regard to legal principles, applicable industry codes or guidance, good industry practice and previous relevant determinations of AFCA or predecessor schemes (which are not binding). I have considered all the material submitted by the parties, both before and after the preliminary assessment. I am satisfied that the documentation I have relied on has been provided to both parties. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues considered directly relevant to the outcome only. No new information after preliminary assessment After the preliminary assessment was rejected, the parties made no further submissions and provided no new material. 2.1 Is the offer made by the insurer fair and in accordance with policy terms? Circumstances of the claim On 11 February 2019 the complainant notified his broker of water damage to four units. He arranged for a builder to inspect the damage. He provided photographs from tenants. He obtained various quotes to repair the damage including a quote from a builder (L) to repair the garage ceilings in units 1 and 2 in the sum of $11,968 including GST. The insure r’s assessor (S) inspected the four units on 13 April 2019. Repairs to units 1 and 2 had been completed. The complainant was asked to provide invoices and quotes along with certain rental documentation such as exit/entry reports and inspection reports. In the absence of certain requested documentation and in view of the findings of the assessor, the claim was declined. In August 2019, the insurer arranged for an engineer to inspect the property. Because of the engineer’s f indings, the insurer offered to settle the claim for $5,191.46 net of the policy excess of $1,000. Parties’ submissions The complainant says this is inadequate. He says the repairs to the garages in units 1 and 2 (excluding other non-storm related repairs) is about $6,000. He says a n equal amount is required to repair the garages in units 3 and 4. Considering the policy excess of $1,000 and rounding down, he says the offer is inadequate. He requires a net $10,000 to repair the storm damage in all four units. Determination | Case number: 656415 Page 5 of 15 In support of his position, the complainant challenges the reliability of the assessment and says:  the assessment did not take place until six weeks after the damage  he had to make repairs, or he would lose a tenant  evidence from tenants may not be completely reliable  he was given permission to repair the damage in units 1 and 2  he acted in good faith and provided photographs and invoices for the repairs done to units 1 and 2  there is evidence of water damage in units 3 and 4 which has not been repaired  he is only claiming the cost of repairs for the water damage not the other cited damage. With a view to resolving the issues in dispute the insurer arranged for an engineer to inspect the property. As the engineer accepted there was some damage to units 1 and 4 because of the storm, the insurer agreed to pay to repair the damage to these areas. The insurer says:  the complainant has not been specific in relation to what areas of damage he is claiming, nor the dollar amount he wishes to claim, nor has he provided requested documentation  repairs to units 1 and 2 were completed before the claim was lodged and proof of authorisation was not forthcoming  its offer to the insurer is fair as it is based on engineering opinion and based on available information  it will review its offer upon provision of itemised quotes and invoices, and rental documentation. The complainant provided some entry and exit report for the four units and asked the property manager for further copies. The insurer said this information was not useful and what was required was routine inspection reports just prior to the event. Engineer’s opinion establishes extent of storm damage I have considered all the available information and submissions of the parties. A summary of the relevant policy terms is set out in supporting section 3.2 of the determination. A summary of the material relied on by the parties is set out in supporting section 3.3 of the determination. Determination | Case number: 656415 Page 6 of 15 The complainant must establish on the balance of probabilities that he has suffered a loss caused by an event to which the policy responds. This is known as a prima facie claim. It is not in dispute there was a storm event February 2019 which caused accidental damage to the insured property. However, the complainant must establish all the claimed damage was caused by that storm event. The complainant has provided material which shows the cost of repairs to the garage ceilings in units 1 and 2 and he has provided an estimate of the cost to repair the garage ceilings in units 3 and 4. He has also provided photographs and four entry condition reports. I am not satisfied the material provided by the complainant sufficiently establishes the cause of and extent of water damage to the four units. The insurer arranged for the property to be assessed by its assessor in April 2019 and by an engineer in September 2019. While the complainant had some criticism of the assessor, the complainant has provided no compelling rebuttal of the opinion of the engineer. I am satisfied the engineer has the relevant expertise to comment. Having reviewed his report and the photographs provided and his detailed analysis and observations, I accept the engineer’s opinion. I accept the available information establishes the damage caused in the storm event in February 2019 was to the stepped-up section of the garage ceiling to unit 1 and to a small area of the stepped-up section of garage ceiling and ensuite ceiling of unit 4. Otherwise, I am satisfied the other damage noted by the engineer in the four units is unrelated to the storm event. Insurer’s offer of $5,191.46 is fair in the circumstances The engineer reviewed the complainant’s documents and says the works required for unit 1 were overstated and the works required for unit 2 were completely overstated. As the material provided by the complainant for the cost of repairs to garage ceilings in units 3 and 4 was provided after the engineer inspected the property, the engineer has made no comment on these costs. However, the insurer arranged for a scope of works for the water damage in units 1 and 4. The scope and estimate for $6,191.46 includes an 18% builders’ margin and 10% GST. I am satisfied this is an actionable quote. In those circumstances, I am satisfied the offer of settlement made by the insurer of $5,191.46 net of the policy excess of Determination | Case number: 656415 Page 7 of 15 $1,000 represents the extent of water damage to the two garage ceilings identified by the engineer and is fair and in accordance with the policy terms. On the available material, and for the reasons stated, I am satisfied the insurer is not required to pay anything further to the complainant for water damage to the four units because of the storm event in February 2019. Available information does not show air-conditioners damaged in storm event During the complaint with AFCA, the complainant also claimed for damage to the air- conditioners. The insurer required confirmation of the cost of repairs and the cause of damage. The complainant advised AFCA he could not determine when this became an issue and the repairers have not been able to determine the origin nor the cause which may be a separate issue from the damage done in February 2019. He says it was not part of the original claim as the tenants did not report it at that time. He says the air conditioning cover is $750 for each machine and will not cover the cost of replacement in any case. He provided two invoices for the cost of repairs. The insurer is not willing to reimb urse the complainant these costs. It points out the invoices provided are dated 13 December 2019 and 8 January 2020, but the date of loss is 7 February 2019. It says the invoices identify the old air conditioning units were removed and new ones were installed, but they do not identify the cause of the damage nor the date the units were damaged. The insurer provided the invoices to the assessor who confirmed the damage to the air conditioning units was not discussed at the time of the assessment, and so was not included in this claim. I have considered the relevant information on this issue. I am satisfied the insurer is entitled to decline the claim for repairs to the air conditioning units as the result of the storm event in February 2019 because:  the complainant provided invoices for repairs to two air conditioning units, but the invoices do not identify the cause of damage  the invoices are almost a year after the storm event  the initial assessment and claims correspondence contains no reference to damaged air conditioning units  While the policy provides cover for accidental breakdown to machinery including air-conditioners, this cover is subject to exclusions and the information provided is insufficient to establish the claimed damage was caused in the storm event in February 2019 and insufficient for the insurer to make a claims decision without knowing how the damage occurred and the cause of the damage. Determination | Case number: 656415 Page 8 of 15 The information provided does not establish on the balance of probabilities the air conditioning units were damaged in the storm event. Based on the available information, the insurer is not required to pay the complainant for the claimed damage to the air conditioning units because of the storm event in February 2019. Should the complainant have any further evidence about the date of and cause of damage, the complainant may consider lodging a separate claim for accidental breakdown. 2.2 Is the complainant entitled to compensation? Compensation paid only in some circumstances The complainant complained the insurer unreasonably delayed assessing the property. He says the insurer did not attend and inspect the property for six weeks after the event. AFCA will award compensation (capped at $5,000) if there has been an unusual degree or extent of physical inconvenience, time taken to resolve a complaint or interference with the complainant’s expectation of enjoyment or peace of mind caused by the insurer’s condu ct. AFCA takes a conservative approach to awarding compensation. We do not award compensation because the complainant has suffered some inconvenience and anxiety. AFCA expects complainants to be moderately robust and to bear the normal degree of inconvenience experienced when a problem occurs and to take reasonable steps to manage the situation. Delay not caused by the insurer and compensation not warranted Having reviewed the available information, I am satisfied the relevant timeline is as follows: Date Action 07/02/ 2019  storm event 11/02/ 2019  c omplainant advised his broker of claim for storm damage 15/03/ 2019  repairs on units 1 & 2 completed 21/03/ 2019  complainant emailed his broker saying he has wait ed 5 weeks for assessor, des pite being advised he could commence repairs to the property 26/03/ 2019  complainant followed up wit h broker via email 26/03/ 2019  broker submitted claim to insurer 11/04/ 2019  the insurer appointed S to assess the claim Determination | Case number: 656415 Page 9 of 15 Date Action 13/04/ 2019  S attended property 28/06/ 2019  based on available mat erial, claim denied 24/07/ 2019  decision reviewed and maintained 24/08/ 2019  engineer (F) attended and inspected damage 09/09/ 2019  report from engineer (F) 11/09/ 2019  insurer offered $6,191.46 less policy excess of $1 , 000 to the complainant for the cost of repairs to the garage ceilings in units 1 and 4 In the circumstances, I do not accept there has been an unusual delay caused by the insurer’s conduct. It was notified of the claim on 26 March 2019 and its assessor attended to assess the damage on 13 April 2019. As the parties could not agree on an outcome, an engineer was appointed, and he inspected the damage on 24 August 2019. His report was provided a few weeks later and at that time the insurer made a fair offer to settle the claim on 11 September 2019. In all the circumstances, I am not satisfied an award of compensation is warranted. Determination | Case number: 656415 Page 10 of 15 3 Supporting information 3.1 Our Approach It is an accepted principle of general insurance law that the insured bears the onus to establish on the balance of probabilities that they have suffered a loss caused by an event to which the policy responds. This is known as a prima facie claim. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss. 3.2 Relevant policy terms The relevant policy extracts are referred to in the correspondence between the parties and in the insurer’s Notice of Response. Both the policy document and the Notice have been exchanged with the complainant. Page 5 Making a CLAIM HOW TO CLAIM All Claims If You become aware of an event that may lead to a claim, or if any oral or written demand, notification or complaint is made against You, you must: 1. Tell Us about it as soon as You can 2. Within the next 30 days give Us in writing full details of the event. This must include all proofs for which We may ask … 8. Give Us all the help that We need to: [a] Assess, investigate or settle a claim... WHO CONTROLS CLAIMS We control all claims. Unless We agree in writing You must not: 1. Admit, deny, negotiate, settle or in any way compromise a claim. 2. Incur any costs in making good any damage. You may make temporary repairs to Your property to prevent further loss or damage. Page 7 Determination | Case number: 656415 Page 11 of 15 Cover Sections BUILDINGS AND COMMON CONTENTS WHAT’S COVERED Your buildings and common contents that are at the location. They are covered against accidental loss or damage. WHAT’S NOT COVERED This section does not cover any claims of any kind whatsoever directly or indirectly relating to, arising out of or in connection with: (1) Chips or scratches. (2) Fault, error or omission in design. (3) Gradual deterioration. (5) Loss or damage that arises from… [d] Insects, mildew, Mould, rot or vermin. [e] Land movement unless it is caused by and occurs within 72 hours of an earthquake, storm, rainwater or wind event. [f] Latent, structural or inherent defect. [l] Water that seeps into Your Buildings Page 2 SIGNIFICANT MATTERS TO BE AWARE OF…. We may refuse to pay or reduce the amount We pay under a claim in certain circumstances. In particular, where an exclusion applies… (2) If You do not comply with Your duty of disclosure or make a misrepresentation. 3.3 Relevant extracts from material relied on by parties Date Action Quote L P/L 15 March 2019  Repairs to unit 1 and unit 2 Garage ceilings $11,968 including GST. Scope of works unit 1 26 March 2019  Areas for repair include garage, kitchen living, front bedroom, middle bedroom, stairwell, hallway, ensuite, toilet, $7,180. Scope of works unit 2  A s for repair garage, kitchen living, main bedroom, Determination | Case number: 656415 Page 12 of 15 Date Action stairwell hallway, ensuite, toilet, $4,787. Tax invoice (G Air - conditioning ) 13 December 2019  Unit 4 Living Room $1,815 including GST. Tax invoice (G Air - conditioning ) 8 January 2020  Unit 2 Re - installation of split Aircon and removal of old split Aircon $1,199. Estimate (CDM) 4 February 2020  Repair water damage ceilings to garages units 3 and 4 including builders margin (18%) and GST $7,559.55. Asse ssment report (S) 17 April 2019  Attended and photographed four units in the company of tenants on 13 April 2019.  Instructed water damage caused by tropical cyclone.  Cont acted complainant. As works completed in units 1 and 2 asked for invoices and quotes and rental documents.  Property manager advised they do not have any rental records anymore and said complainant instructed her not to release information.  Inspected unit 4 with the tenant and shown garage where could see mould on the ceiling (see photograph) and slight warping gyprock which tenant said happened after the heavy rain in February.  Tenant said cracks in the ceilings in the kitchen, living room and upstairs bedrooms but did not inspect the upstairs bedrooms because wife asleep. Cracks appear to be on all gyprock jo ins. No expansion joints which would be recommended. Tenant said when they moved in there were cracks in the ceiling and loose tiles in the hall and ent ry to the ensuite.  Inspected unit 3 with the tenant and saw water leaking in the garage and warping of the gy prock sheeting in the garage ceiling.  Inspected upstairs ensuite: loose tiles on bathroom floor and in poor condition indicating water leak for some time – confirmed by tenant.  Gyprock join cracks not result of water damage but movement over time an d poor workmanship.  Unit 2 inspected with tenant . Shown all repairs in the unit which were completed recently and reviewed scope of works.  Tenant said leak in ensuite. Inspection holes cut in ceiling of garage. Holes and plaster in garage repaired. Repai rs undertaken to tiles, grout and silicon seal in hall and ensuite $1,340. Tenant said gyprock joint cracks present prior to moving in over 12 mont hs ago.  Unit 1 seen with new tenant . All repair works complete. Scope supplied. Tenant 2 said unit 1 was in a worse state than unit 2. Further variation submitted for repairs to the tiles, grout and silicon seal in hall and ensuite.  Concluded from information from tenants and inspection and after reviewing scope of works that all Determination | Case number: 656415 Page 13 of 15 Date Action gyprock joint cracks are pre - exi sting and caused by movement overtime and poor workmanship. There were pre - existing water leaks from the ensuite. Found no evidence of damage except mould growth on the ceiling in unit 4 which could be explained by the leak above in the ensuite.  Provided correspondence with complainant requesting information. Waiting rental entry reports and periodic inspection reports; plumbing reports; builder said he would supply his invoice and original quotes. Corre spondence between complainant and asse ssor 28 May 2019  Do not have any itemised quot es to appt 3 and 4. There was only verbal discussion that repairs would be in line with those provided to appt 1 and 2. I did not ask for those scope of works as the insurers were to provide the assessment and no work was initiated before approval from insurers assessment.  Have already provided scope of works completed by W for appt 1 and 2 which was sent to me by W.  Any work done as a result of holes created in ceilings was done prior to me buying these properties. I have not initiated any repairs to bathrooms in any of those apartments and therefore I do not have any information that I can provide you regarding said works. Asse ssment report (S) 25 June 2019  Attended 13 April 2019.  From information from tenants, and our ins pection and reviewing the scope of works all gyprock join cracks are existing and caused by movement over time and poor workmanship.  All units had issues with wat er leaks from ensuite.  Complainant said no repairs to ens uites, yet builders invoic e itemised some repairs to tiled areas.  Found no evidence of damage caus ed by storm.  On many occasions have asked the complainant and the property manager for all appropriate documentation and in the absence of that documentation and based on our initial f indings from our site inspection recommend claim they declined.  Will reopen file should the requested rental documentation - periodic inspection reports and entry/exit notices provided. Insurer’s Scope (E Pty Ltd) 11 August 2019  Repairs to water damaged ceilings to garages in units 1 and 4 - $6,191.46 including 18% builders’ margin and 10% GST. Insurer’s engineer (F) Report 9 September 2019  Senior structural engineer inspected and photographed 4 units on 24 August 2019. He rev iewed original building approval documentation, reviewed photographs, discussed the damage history with the complainant and 3 of the 4 tenants and completed a visual inspection of the units’ external walls, internal walls, ceiling claddings, and upper leve l roof cavities. No attendance from Determination | Case number: 656415 Page 14 of 15 Date Action property manager.  Built in 2005. Purchased by complainant in 2015.  All four units had significant building damage which was described.  Damage to all four units was associated with a small number of common problems inclu ding minor non - structural cracking of external mas onry block walls, internal walls and ceiling claddings, internal water leaks from upper level ensuites and external roof water ingress over garage ceilings noted.  Reviewed provided scopes of work for units 1 and 2 and tax invoice from L P/L.  Unit 1 scope of work allows valid repair of storm event related roof water ingress damage to the stepped - up section of the garage ceiling. All other work items unrelated to rai n event.  Unit 2 scope of works unrelated to the rain event.  L P/L invoice refers to works to units 1 and 2 but quotes not received. Scope for unit 1 considerably overstated. Scope for unit 2 unrelated.  Summarised findings as follows:  1 .Roof water ingress related damage was evident to the stepped - up section of garage ceiling to Unit 1 and to a small area of the stepped - up section of garage ceiling and the ensuite ceiling of Unit 4. This was the only damage observed by us which we consider having bee n directly caused by the February 2019 rain and flood event;  2. Roof water ingress related damage from the February 2019 rain event is still required to Unit 4;  3. Other widespread damage that was consistent in nature across all four units and considered b y us to have been caused by internal water leaks from the ensuites, defective building work, normally occurring building and foundation movements and from gradual deterioration / wear and tear was evident to all units. This damage is not considered by us t o have been caused by the February 2019 rain event and in our view should not form part of this claim relating to the February 2019 rain event;  4. Much of the “other” damage observed was consistently claimed by the various tenants to have been present prio r to the February 2019 rain event and this is reasonably consistent with verbal advic e provided to us by the insured and our own visual observations;  5 . Further investigation of possible ongoing water leakage from the ensuites of all units is recommended, as is repair of cause and all remaining resultant damage from ensuite leakage;  6. The provided repair scope of work documents were considered by us to overstate the works required for Unit 1 and complet ely overstate the works required to Unit 2 that result from the February 2019 rain event;  7. Repair and owner maintenance is required to address all other building damage and building Determination | Case number: 656415 Page 15 of 15 Date Action defect items. 3.4 Other relevant material considered and relied on  Parties’ submissions/emails and all attachments to all submiss ions/emails.  Parties’ expert reports.  Photographs, invoices, scopes and estimates.  Entry condition reports.  Correspondence between the parties

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.