Determination 654393
Denial of water damage claim for stormwater pipe and basement
Summary
The complainant's construction company claimed for water damage caused by a stormwater pipe, and the insurer denied it. AFCA found the pipe repair costs were covered but not the basement damage, and ordered interest on the amount payable.
Section 54 of the Insurance Contracts Act assists the insured for the pipe loss, because failing to detect the pipe damage did not prejudice the insurer, but not for the basement damage.
Issues
- Claim denial primary · upheld“the insurer is liable for the cost to identify and repair the stormwater pipe damage less any applicable excess. The insurer is not liable for the resultant damage to the basement.”
Subjects and remedies
home or building damagesmall businesspay claimpay interest
Related
Text of the determination
Determination
Case number 654393
Financial firm QBE Insurance (Australia) Limited
Determination | Case number: 654393 Page 2 of 7
Case number: 654393 24 June 2020
1 Determination overview
1.1 Complaint
The complainant lodged a claim under his construction policy for water damage to a
property built by his company. For the sake of convenience, reference to the
complainant will include both him and the company unless stated otherwise.
The financial firm (insurer) denied the claim saying the policy only responds if the
damage occurs and is detected or manifests during the construction or maintenance
periods. The insurer says the information does not show the damage was detected or
manifested in either period.
The complainant disagrees with the claims decision and says the damage manifested
within the maintenance period in the form of mould. However, the claim was lodged at
a later date, because the underlying cause was not identified at the time.
The complainant seeks full indemnity from the insurer to resolve the complaint.
1.2 Issue and key findings
Is the insurer entitled to deny the claim?
The insurer can only partially deny the claim. This is because:
the information does not show the damage was detected during the construction
period or that the damage manifested in the maintenance period
section 54 of Insurance Contracts Act 1984 (the Act) applies but only to the extent
that the insurer cannot deny liability for the damage to the stormwater pipe
Therefore, the insurer is liable for the cost to identify and repair the stormwater pipe
damage less any applicable excess. The insurer is not liable for the resultant damage
to the basement.
1.3 Determination
This determination is partially in favour of the complainant.
The insurer should indemnify the complainant as set out in section 2.1.
Determination | Case number: 654393 Page 3 of 7
2 Reasons for determination
2.1 Is the insurer entitled to deny the claim?
Circumstances of the loss
The complainant built the property between 2010 and 2011. After this, the
complainant rented it to a tenant. In 2013, the property was later sold to the tenants,
who are the current owners.
The complainant says during the construction of the property, a landscaper drove star
pickets into a storm water pipe. This led to damage to the property over time .
However, this was not identified until 2018.
The current owners provided an email dated 20 September 2018 that set out some
background. They say the presence of mould in the cupboard under the stairs was
first raised in 2012. This was not addressed by the complainant. The presence of a
small amount of mould was mentioned ‘on other occasions after purchasing the
property’ with no action taken by the complainant. It was o nly after mould started to
appear outside the cupboard and a smell was evident that the complainant took
action.
This action appeared to start around March 2018. Following investigation, the
complainant identified the likely cause of the water damage to the basement was from
the damaged stormwater pipe. Extensive work was done to the basement including
the removal of all the internal wall plasters and stud work.
The complainant then lodged a claim with the insurer. There is some discrepancy as
to when this was lodged. However, the precise date of the claim lodgement is not
material.
Policy covers damage caused and detected during the construction period
The policy is an annual construction and liability insurance policy which covers
damage caused and detected during the construction period.
The certificate of insurance lists the construction period as 3 March 2011 – 3 March
2012.
Specifically, the policy covers:
Construction period
We will cover you for insured damage unless excluded by this policy occurring and
detected at the contract site during the construction period.
Determination | Case number: 654393 Page 4 of 7
Construction period means:
the period commencing on the date of possession of each contract site by you or the
commencement date of the contract works provided such date is within the period
specified in the schedule and expiring:
at the time of practical completion of the contract works, and including up to fourteen
(14) days in excess of practical completion, or
on the date those completed portions of the contract works are taken over, occupied
or put into use, or
on the date specified in the schedule,
Whichever occurs first.
The policy also covers:
Maintenance period:
We will cover you for insured damage to the contract works which manifests itself
during the maintenance period provided such insured damage originates from:
(a) a cause (unless excluded) arising and occurring out of the contract works
carried out by you during the construction period at the contract site, or
(b) a cause (unless excluded) occurring and arising out of the course of operations
carried out by you in complying with the requirements of the maintenance
clause(s) of the contract.
Maintenance period means:
The period commencing at the end of the construction period or the testing period if
specified in the schedule and continuing for a maximum of twelve (12) months
thereafter or any lesser period as may be specified in the schedule for each contract.
A copy of the occupancy certificate has been provided. This was issued on 5 July
2011. According to the definition of construction period, this means the period would
have lapsed on 19 July 2011. The panel notes there is no evidence to indicate any
portions of the completed works were taken over, occupied or used before this.
Accordingly, the panel considers 19 July 2011 marks the end of the construction
period. The beginning of the maintenance period is therefore accepted to be from 19
July 2011 to 19 July 2012.
No dispute the stormwater pipe was damaged during the construction period
The following is not in dispute:
the damaged stormwater pipe has caused the damage to the basement
the stormwater pipe was likely damaged during the construction period
this pipe damage, and the resultant damage to the basement, was not detected
during the construction period.
Determination | Case number: 654393 Page 5 of 7
The parties dispute whether the damage manifested during the maintenance period.
The complainant relied on the current owners’ email which said mould began to form
around 2012. The difficulty with this email though is that the current owners do not
say when in 2012 this occurred.
The maintenance period lapsed on 19 July 2012. The information must show the
mould occurred before this. The evidence presented to the panel is unclear on this
point.
Further, it is not clear that this mould was caused by the stormwater leak. The current
owners say there was a small amount of mould in 2012. It then appeared on other
occasions after purchasing the property. They do not describe when those occasions
were. For instance, it is not clear if these other occurrences happened closer to 2018
or were spread out over the years.
If the leak from the stormwater pipe could cause damage within a year, it seems
unusual that it did not manifest into greater damage in a shorter time.
Given all this, the panel is not satisfied the evidence shows, on the balance of
probabilities, that the damage manifested in the maintenance period. Further, the
evidence is not clear that the mould identified in 2012 was caused by the stormwater
pipe.
Section 54 of the Insurance Contracts Act 1984
Broadly speaking, section 54 says an insurer cannot refuse a claim in whole or in part
by reason of some ‘act’ (which includes an omission) that occurs after the contract of
insurance was entered into unless it can show:
the level of prejudice sustained, or
establishes this act could reasonably be regarded as being capable of causing or
contributing to the loss.
However, section 54 cannot relieve an insured of restrictions or limitations that are
inherent in a claim.
The panel does not accept there is any restriction or limitation inherent in the
complainant’s claim. This is because this policy responds to insured damage during
the construction period. The complainant’s claim meets this criteria.
The panel considers the act in this case is the failure to detect the damage during the
construction period. This is because the effect of the contract of insurance is that the
insurer can deny the claim by reason of this act.
The panel accepts this act could reasonably be regarded as being capable of causing
or contributing to the loss but only to the extent of the resultant damage to the
Determination | Case number: 654393 Page 6 of 7
basement. This is because if the damage to the stormwater pipe was detected during
the construction period, then it is unlikely this would have extended to the basement.
However, the panel does not accept this act could reasonably be regarded as being
capable of causing or contributing to the loss regarding the stormwater pipe.
In terms of prejudice, the outcome would be the same. This is because if the damage
to the stormwater pipe was detected during the construction period, then it is unlikely
this would have extended to the basement. However, the failure to detect the damage
would not have prejudiced the insurer regarding the loss to the pipe itself.
Insurer should cover the costs to find and repair the stormwater pipe damage
Accordingly, after careful consideration of all the available information, the panel finds
the following.
Section 54 of the Act assists the complainant but only to the extent of the costs he
incurred in finding and repairing the stormwater pipe damage. Section 54 of the Act
does not assist the complainant for the basement damage. This is because the failure
to detect the damage during the construction period could reasonably be regarded as
being capable of causing or contributing to this aspect of the loss. Alternatively, the
act prejudiced the insurer to this extent.
Therefore, the insurer is only liable to indemnify the complainant for the costs of
finding and repairing the stormwater pipe damage.
The insurer should also pay interest on any sum paid for this pursuant to section 57 of
the Act. Interest is payable from 31 January 2019, being when the insurer decided to
deny the claim, until payment is made.
Determination | Case number: 654393 Page 7 of 7
3 Supporting information
Record Key points
financial firm ’s expert ( C )
Report
21 January 2019
It is suspected that whilst the landscape gardeners were obtaining
levels for the paved areas as depicted in Photograph 1 below, they
were utilising star pickets, which were inadvertently
driven int o the PVC stormwater network.
the CCTV survey undert aken of the stormwater net work, where as
you can see from Photographs 2 a nd 3 below, evidence of star
pickets is noted within the stormwater net work
The aforementioned impact into the PVC stormwater net work over
the preceding years 2011 - 2018 would have allowed water to have
escape the stormwater net work and infiltrate the basem ent
structure.
Current property owner
(Formerly a tenant)
Email
20 September 2018
The issue of the appearance of mould being present in the
cupboard under the stairs was first raised in 2012 with the landlord
(Complainant). It was a small amount and the complainant was not
concerned and did nothing to address it
It was only when mould started to appear outside the cupboard
and a smell was evident that the complainant took action