Home / QBE / Determination 653683
Determination 653683
Insurer denied building and contents flood-storm damage claim relying on flood exclusion
Summary
A Townsville construction business claimed for water damage to its building and contents after the January-February 2019 rain event. AFCA found the insurer had not proven the flood exclusion applied, ordered payment of the building quote plus 20 per cent and the remaining contents with statutory interest, and left the business interruption claim pending documents.
The insurer bears the onus of proving the policy's flood definition applies, and it failed to show the drains were natural watercourses, so the storm-water damage is covered.
Issues
- Claim denial primary · upheld
“the insurer is not entitled to decline the claim as it has not established the claimed damage was caused by flood as defined by the policy”
- Product terms interpretation secondary · upheld
“The panel is not satisfied that the insurer has met its onus to establish that either Drain is a Creek or other natural water course”
Subjects and remedies
business interruptionhome or building damagenatural disasterpay claimpay interest
Text of the determination
Determination
Case number 653683
Financial firm QBE Insurance (Australia) Limited
Determination | Case number: 653683 Page 2 of 10
Case number: 653683 20 March 2020
Determination overview
1.1 Complaint
The complainant is a business that holds an insurance policy with the financial firm
(insurer). The complainant lodged a claim with the insurer for damage to its building
and contents and business interruption, following a heavy rainfall event in January
and February 2019 in Northern Queensland.
The insurer partially accepted the claim, saying some of the damage was caused by
rainwater entering the property via the roof and windows. The insurer declined the
rest of the claim for damaged property, saying the damage was caused by floodwater.
Damage caused by flood is an optional cover under the policy, however, the
complainant did not elect this additional cover.
The insurer also requested information from the complainant to assess the claim for
business interruption. To date the complainant has not provided this.
The complainant disagrees with the insurer and says the damage at his property was
caused by storm water.
1.2 Issues and key findings
Is the insurer entitled to rely on its exclusions to deny the claim?
Based on the available material, the insurer is not entitled to decline the claim as it
has not established the claimed damage was caused by flood as defined by the
policy.
Is the insurer liable for any further costs for damaged content items?
As the insurer is unable to rely on its exclusion for flood damage, it is required to pay
for the contents items it previously declined under the flood exclusion.
Is the complainant entitled to cover under the business interruption section of
the policy?
It is not clear if the complainant is entitled to cover for business interruption. The
complainant is required to provide the requested documentation to the insurer for this
aspect of the claim to be reviewed.
The insurer is not required to take any action until the complainant provides the
requested information.
Determination | Case number: 653683 Page 3 of 10
1.3 Determination
This determination is substantially in favour of the complainant.
The insurer is required to pay the complainant $45,938.48 for the cost of the building
repairs. The insurer is to add 20% to cover for any unforeseen additional costs ,
contingencies and the transfer of risk.
The insurer is required to pay the complainant $11,971.71 for the remaining damaged
contents.
The insurer is required to pay statutory interest on these two settlements calculated
from 11 April 2019 (the date the insurer denied the claim, or if the repairs have been
completed, from the date the complainant paid for the repairs) until the date of
settlement.
The insurer is not required to take any further action for the business interruption
claim until the complainant provides the requested documentation.
Determination | Case number: 653683 Page 4 of 10
Reasons for determination
2.1 Is the insurer entitled to rely on its exclusions to deny the claim?
We have considered it appropriate to expedite this complaint in accordance with the
Operational Guidelines to the AFCA Rules, due to the nature of the complaint.
Accordingly, this complaint has not been the subject of a preliminary assessment and
has proceeded directly to determination.
The determination is made by a panel consisting of the ombudsman together with a
consumer representative who has extensive experience in consumer claims and an
industry representative who has extensive experience in the insurance industry.
The Ombudsman, who has extensive experience with flood complaints, viewed the
general area and specific site in November 2019.
This complaint has been determined based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous decisions (which are not binding).
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other. All of the material provided by the parties has been reviewed and
considered.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome only.
Complainant does not have cover for damage by flood
The complainant’s business policy with the insurer is a listed event policy which
provides cover for physical loss or destruction of or damage to buildings and common
contents occurring during the period of insurance, caused by a list of covered events.
The policy includes cover for accidental damage under the event of “Unspecified
Damage” . However, this cover excludes damage coverable or excluded under any of
the other listed insured events, including damage caused by storm and rainwater and
excludes damage caused by Flood, unless the policy schedule specifies that optional
flood cover is included.
Flood is defined on page 11 of the product disclosure statement (PDS) as:
Flood means the covering of normally dry land by water that has escaped or been
released from the normal confines of any of the following:
(a) a lake (whether or not it has been altered or modified);
(b) a river (whether or not it has been altered or modified);
(c) a creek (whether or not it has been altered or modified);
Determination | Case number: 653683 Page 5 of 10
(d) another natural watercourse (whether or not it has been altered or modified);
(e) a reservoir (whether or not it has been altered or modified);
(f) a canal (whether or not it has been altered or modified); and
(g) a damn (whether or not it has been altered or modified).
The policy schedule states the complainant was not insured for flood.
The complainant accepts there is no cover provided for damage caused by flood.
Circumstances of the loss
The complainant is a construction and pest control business operating out of Garbutt,
a suburb of Townsville. The complainant holds a business policy with the insurer
which provides cover for the building and contents of the business as well as some
limited cover for additional working costs relating to business interruption.
In late January and early February 2019, the city of Townsville and surrounding areas
of north Queensland experienced a significant weather event.
Heavy rainfall occurred over the Townsville catchment over several days and at or
about the complainants' property.
The complainant says water inundated the property on four separate days between
30 January 2019 and 3 February 2019. The complainant says the inundation of the
property coincided with heavy periods of rainfall with the water subsiding when the
rainfall ceased, reaching heights within the property of around 0.1 m to 0.18 m on
each occasion. It is not clear what time during these four days each inundation
occurred.
Insurer partially accepted the claim
The insurer engaged hydrologist WR to attend the complainant’s business and submit
a report on the rainfall event and cause of damage. WR provided photographs of
water marks on the walls that confirm water inundated the building up to a height of
around 0.18 m.
WR says there were two separate causes of water entry into the property: storm
water entering through the roof, walls and windows of the buildi ng and a combination
of water runoff that ponded in the local area mixed with an overflow of water from two
nearby drains.
WR says based on the topography of the local area and rainfall records recorded from
a nearby measuring station the inundation of the property up to 0.18 m , could not
have occurred from water entering the property via the roof, walls and windows. WR
says the inundation was caused by stormwater pooling near the property and
combining with overflows from the nearby drains.
Determination | Case number: 653683 Page 6 of 10
Based on this, the insurer declined the damage to the building saying the damage
was caused by flood water from the drains behind the property.
The insurer accepted some of the damaged contents. It says these were damaged by
storm water coming through the walls and roof of the building. The insurer declined
the remaining contents, saying they were damaged by the flood water inundating the
property.
Hydrologist says combined water inundated the property
The insured property faces south on H Street. The building has a floor level of around
4.65 mAHD. Storm water runoff flows west along H Street to a sag at the bend of the
street. This sag is drained by a pit and pipe network that flows into an unnamed
grassed channel to the west of the property (Drain 1) which runs north/south.
A second unnamed grassed channel (Drain 2) running east/west lies behind the
property to the north. These two channels meet to the north west and continue as one
channel north, with the channel then bending to the west to join into the nearby
Louisa Creek.
WR says the catchment area that drains into this sag on H Street is around 2.6 ha,
although it advises the data to confirm this is incomplete and the catchment area may
be larger. During periods of heavy rain fall the drainage system can become
overwhelmed and storm water will pond at the H Street sag. This ponded water is
able to rise to a level of around 4.1 mAHD before it overtops the low point north west
of the sag and drains through a neighbouring property on H Street and into Drain 1.
No official information was provided to confirm the water levels of each of these
grassed channels during the event. WR says rail tracks found north of the Drain 2 are
about 4.6 mAHD. Based on the debris found on those tracks, the water level from
Drain 2 at least reached this height at some stage during the event.
WR provided both rainfall and water level records from the nearby Louisa Creek Alert
station, which is located around 0.9 kms south west of the property. The data
recorded at this station shows across the four days the property was inundated,
heavy rainfall directly correlated with rises and falls of the creek’s water level. It is
reasonable to assume that water levels around the property will have experienced a
similar response to the rainfall.
WR says while Louisa Creek does eventually connect downstream with Drain 1 and
Drain 2, the overflows of these grassed channels did not contain any overflow from
Louisa Creek (or for that matter, Bohle River and Ross River). The recorded water
levels throughout the event also show this part of Louisa Creek was unaffected by the
large release of water from Ross River Dam experienced on the night of Sunday 3
February 2019.
Determination | Case number: 653683 Page 7 of 10
WR says the storm water ponding in H Street alone was not enough to inundate the
property. WR also says it is unclear whether the overflows from the grassed channels
alone were sufficient to inundate the property.
Onus on insurer to prove its exclusion
The insurer says the inundations at the property were caused by the ponded storm
water combined with the overflows from the two grassed channels.
The complainant says the water entering the property above floor level was reportedly
quite clear, with little to no debris or silt left in the property after water receded.
Photographs received confirm this.
The complainant also says each of the four inundation events coincided with heavy
rainfall in the area, with water receding from the property and H Street within hours of
the rainfall easing and/or ceasing.
WR confirms these two statements are consistent with the available rainfall and water
level data.
WR says the complainant provided a short video showing the drainage behaviour of H
Street. While the footage was not dated, it showed an instance where the water at the
sag point had ponded and overtopped the overflow point between the sag and the
grassed channel. The water was shown to be po nding onto the complainant’s
property but not high enough to enter the building.
WR says the footage also showed there was no discernible flow velocity in the
ponded water, which would indicate water either flowing towards the property from the
grassed channels overflowing or excess water from the H Street catchment area
flowing towards the grassed channels.
Insurer unable to rely on its flood exclusion
It is not clear as to the exact time the inundations occurred. On balance the panel
considers it likely that each inundation occurred during periods of heavy rainfall.
The insurer carries the onus to establish the application of its policy flood definition to
deny the complainant’s claim.
The panel accepts, on balance, WR’s conclusion that it is lik ely that the initial and
above floor level inundation was caused by stormwater runoff ponded in H Street,
combined with overflow from Drain 1 and Drain 2.
The panel also accepts WR’s conclusion that Drain 1 and Drain 2 did not contain any
Ross River, Bohle River or Louisa Creek overflows.
As detailed above, the policy provides that flood means water that has escaped or
been released from the normal confines of, amongst other things, “another natural
watercourse (whether or not it has been altered or modifie d)…”
Determination | Case number: 653683 Page 8 of 10
The issue is whether Drain 1 or Drain 2 can be regarded as another natural
watercourse (whether or not it has been altered or modified) for the purposes of the
policy definition of flood?
WR says that Drain 1 flows in a northerly direction, joining with Drain 2 and that at I
Road, Drain 1 is signposted as Pee-Wee Creek and Pee-Wee Creek joins Louisa
Creek.
WR also describes Drain 2 as an unnamed grass channel.
But are the 2 Drains other natural watercourses (whether or not they have been
altered or modified) for the purposes of the policy definition of flood?
The only evidence offered by WR is the Pee-Wee Creek signposting at I Street.
Unfortunately, WR does not provide any probative evidence to make a call one way or
the other.
From the evidence exchanged, the panel does not know where Pee-Wee Creek starts
and whether it extends down to Drain 1.
It may be that Drain 1 is a Creek or another natural watercourse as it ultimately flows
into Louisa Creek, but it is not entirely clear.
In the panel’s view it is not sufficient for the insurer to rely upon a sign 200+ meters
away from the site, to prove its case.
At the very least the panel believes that WR should have provided some reference of
mapping or historical data about the origins of the drains.
The panel is not satisfied that the insurer has met its onus to establish that either
Drain is a Creek or other natural water course as required by the policy definition.
As a result, the panel is also not satisfied the insurer has met its onus to show that the
water that inundated the complainant’s business is flood water as defined by the
policy.
Complainant has provided building repair quote
The complainant provided a quote to repair the damage caused to the building in the
amount of $45,938.48. The insurer is required to base its settlement to the
complainant on this quote.
As the claim is to be cash settled, the complainant would be assuming the risk of
unforeseen issues and costs potentially increasing. To fairly account for the transfer
of risk and contingencies the cash settlement is to be increased by a further 20% of
the quoted cost.
Determination | Case number: 653683 Page 9 of 10
In addition to this amount, the insurer is also required to pay statutory interest
(pursuant to section 57 of the Insurance Contracts Act 1984) calculated from 11 April
2019 until the date of settlement, or if the repairs have been completed, from the date
the complainant paid for the repairs.
2.2 Is the insurer liable for any further costs for damaged content items?
Insurer to cover the claim in full
The complainant is claiming for damages caused by the weather event in
January/February 2019. As per section 2.1 of this determination, the panel is satisfied
the insurer is not entitled to rely on its flood exclusion to deny the claim. This means
the insurer must accept all damaged content items claimed by the complainant.
The insurer appointed an assessor (C) to assist in assessing the claim. The
complainant sent a list of damaged content items to the assessor totalling $19,116.14.
The insurer has already made a settlement covering $7,144.43 worth of items from
this list.
The insurer is required to make an additional settlement for the remaining $11,971.71
for the balance of these contents.
In addition to this amount, the insurer is also required to pay statutory interest
(pursuant to section 57 of the Insurance Contracts Act 1984) calculated from 11 April
2019 until the date of settlement.
2.3 Is the complainant entitled to cover under the business interruption
section of the policy?
Coverage unclear without supporting evidence
The complainant holds cover under Section 5 of the policy for Business Interruption.
Cover is provided for when damage from an insured event causes a loss from
interruption or interference with the business.
The policy schedule shows the complainant has cover for two items in this section
that are relevant to this matter:
item 3: Claims preparation costs
item 4: Additional increased cost of working.
The insurer has provided correspondence sent to the complainant requesting
information to assess this part of the claim. An email was sent by C to the
complainant requesting the following documentation in order for this part of the claim
to be assessed:
Determination | Case number: 653683 Page 10 of 10
1. Payroll reports on a weekly basis from November 2018 to March 2019 or up until
when payroll expenses were back to normal levels.
2. Turnover reports on a monthly basis for the same period as above.
C says the cover is not limited to payroll expenses and requested any information that
relates to any additional costs the complainant has incurred to review cover.
The complainant has not provided this information. In material submitted to AFCA the
complainant says:
Given the onerous task the whole affair has been, I am far happier to concede on
this matter. There just are no avenues (time, money to pay an accountant) open
to me to interpret and justify this claim. The insurer is asking for details,
documents and proof of additional costs and loss of income etc, etc, etc
It is reasonable for the insurer to request information to allow it to assess the claim
under this section. The information the insurer is requesting is reasonable.
Until the complainant provides the requested information, the insurer is not required to
take any action on this part of the claim.
To this effect, the insurer may be able to assist the complainant in quantifying its loss
for business interruption by engaging a service provider on the complainants ’ behalf,
if the costs of the service provider are coverable under the claims preparation costs
section of the policy.