Determination 653569

Storm and rainwater damage claim refused under gradual deterioration and seepage exclusions

FirmHollard
Decided2020-02-17
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant claimed under a home and contents policy for storm and rainwater damage to a rumpus room. The insurer refused on seepage, gradual deterioration and design exclusions. AFCA found the insurer had not established an exclusion applied and ordered it to meet the claim after a scope of works and quote, with repair or cash settlement by agreement.

The insurer bears the onus of proving an exclusion applies and did not establish that seepage, deterioration or design faults caused the loss rather than the storm event.

Issues

Subjects and remedies

pay claim

Related

All Hollard determinations · Find similar determinations

Text of the determination

Determination Case number 653569 Financial firm The Hollard Insurance Company Pty Ltd Determination | Case number: 653569 Page 2 of 6 Case number: 653569 13 February 2020 1 Determination overview 1.1 Complaint The complainant held a home and contents policy with the financial firm (insurer) and lodged a claim on 23 May 2019 for damage following a storm on or about 27 January 2019. The insurer rejected the claim. It says the proximate cause of the damage was the gradual seepage of water that percolated through the wall due to insufficient weather proofing and inadequate drainage. It says the damage was caused by gradual deterioration, structural faults and faulty design., which is excluded from cover under the terms of the policy. The complainant disputes the insurer’s decision. 1.2 Issues and key findings Has the complainant established a claim within the terms of the policy? The complainant has established a claim within the terms of the policy. The policy provides cover for storm, rainwater and flood and there is no dispute that the damage occurred as a result of storm and rainwater. Is the insurer entitled to refuse payment of the claim? The insurer is liable to meet the complainant’s claim. For the reasons set out under section 2.1 and 2.2 of this determination, I am not satisfied the insurer has established, on the balance of probabilities, that the damage is excluded from cover under the terms of the policy. 1.3 Determination This determination is in favour of the complainant. The insurer is liable to meet the complainant’s claim in accordance with the terms and conditions of the policy . Within 14 days of the complainant’s acceptance of this determination the insurer is to arrange for a scope of works (SOW) to be prepared and an actionable quote obtained for the repair of the damage. The insurer can then subject to agreement with the complainant use its discretion to either repair or cash settle the claim. Determination | Case number: 653569 Page 3 of 6 2 Reasons for determination There has been a full exchange of material between the parties and each party has had the opportunity of addressing issues that arise from the information exchanged. This determination follows consideration of all of the information and is based on what is fair in all of the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice, including codes of practice and prior determinations, where applicable. 2.1 Has the complainant established a claim within the terms of the policy? Complainant has onus to establish a claim within the terms of the policy The complainant held a home and contents policy with the insurer covering the period 8 May 2018 to 8 May 2019. The policy is an insured events policy insuring the property for a series of events including loss or damage caused by storm, rainwater and flood, subject to several conditions and exclusions. Under the insured event for storm, rainwater and flood, the policy notes that it does not cover loss or damage caused by water that is seeped or percolated into the building or caused by gradual deterioration due to rainwater. The onus on the complainant is therefore to establish that the loss or damage was caused by storm, rainwater and flood within the terms of the policy. Damage first noticed after heavy rain in January 2019 The complainant did not lodge a claim until 23 May 2019. The claim records record the incident happening on 27 January 2019, with the complainant saying: “After last heavy rains we have noticed mould appearing on the wall and skirting – lot of run- off on the property.” Damage was identified to the wall of a rumpus room with rot to timber skirting and contents showing heavy mould growth. The carpet flooring had to be removed. The insurer noted that the rumpus room was at the bottom of the stair and water and mud had collected on the outside wall resulting in the skirtings rotting and the carpets being affected. The complainant says the rumpus room is only used when her adult children and grandchildren stay over. This is not very often. The damage was first identified after the storm in January 2019 when their adult son was staying at the property. Complainant has established claim falls within terms of policy The insurer has provided no evidence of prior claims by the complainant or evidence of prior work done to the property to rectify any long-term damage. It has provided no Determination | Case number: 653569 Page 4 of 6 information to dispute the complainant’s claim that the damage was first identified after the heavy rains of 27 January 2019. The insurer does not dispute that the damage itself was caused or contributed to by storm or rainwater. In the circumstances, I accept that the complainant has established a prima facie claim for loss or damage due to storm or rainwater. 2.2 Is the insurer entitled to refuse payment of the claim? Insurer has onus to prove exclusion applies The insurer says the damage was caused by water that had seeped or percolated into the building, gradual deterioration, an inherent defect, structural faults and faulty design, which are specifically excluded from cover. It says that the proximate cause of the damage is the gradual seeping of water through the external wall and to the rumpus room over a prolonged period due to insufficient weather-proofing and drainage Insurer’s report inconclusive The insurer provided a report from (SR). SR did not identify the cause of the damage or date of the loss. SR confirmed the water ingress into the property caused the internal damage with mould impacting the rumpus room. The insurer’s assessor (CC) conducted an inspection of the prop erty on 25 June 2019 five months after the event. CC considered that the damage was a result of building compliance and or design issue. CC’s opinion appears to be based on a view that the building was not compliant with the Building Code of Australia (BCA) 1996 edition and a view that as the block slopes from the front to rear and towards the dwelling, this would allow the collection of groundwater to enter the rumpus room due to the insufficient wall weather-proofing/ground water drainage. It is unclear whether CC had access to the plans and specifications or the approval documents and final certificate provided by the complainant. The complainant confirmed the rumpus room extension that was built approximately 14 years ago. The complainant provided:  the construction certificate confirming the work was completed following plans and specifications which had been approved and in compliance with Environmental Planning and Assessment Regulation 2000.  a copy of the drainage design and installation method  a copy of the insulation certificate  the notice of compliance inspection  the final occupation certificate issued on 28 October 2009, with the building was suitable for occupation and use in accordance with the Building Code of Australia. Determination | Case number: 653569 Page 5 of 6 The insurer has provided no information to dispute this. CC has not responded to the complainant’s additional information. I accept, based on the available information, that the building was completed to relevant design and planning specifications. I am not satisfied that the assessor has correctly identified the cause of the damage to be faulty design or structural faults. The insurer says the damage was caused by seepage. Seepage is defined as the slow escape of liquid through porous material. The building had been completed for 14 years. The evidence from the complainant is that the damage was first identified following rain on 27 January 2019. There is no suggestion from the photographs provided of any previous damage. The insurer also says the damage was due to gradual deterioration and wear and tear. As indicated there is no evidence of prior damage. The insurer’s inspections of the property (through no fault on its behalf) occurred proximately six months after the insured event. Although there is a comment that this damage occurred over time, this does not establish that the damage was present prior to the incident on 27 January 2019. In so far as the insurer has referred to the exclusion relating to mould and mildew, as I’m satisfied the proximate cause of the damage was storm and the mould is due to damage caused by the storm, the exclusion does not apply. While I accept that there may be some question as to the cause of the damage, I am not satisfied the insurer has established that a relevant exclusion or condition applies to defeat the complainant’s claim. Insurer to assess the loss No assessment or SOW has been provided to determine the extent of the damage or the cost to complete the repairs to the property. The policy provides the insurer with a discretion whether to repair, rebuild or cash settle the claim. Such discretion must be exercised fairly, reasonably and consistent with utmost good faith. Subject to the complainant accepting this determination, to assess the extent of the damage it is fair that the insurer appoints an independent assessor/ builder to assess the damage and prepare a SOW. Subject to the parties agreeing to the SOW, the insurer should then obtain an actionable quote from a suitably qualified builder and provide a copy of the quote to the complainant. Subject to agreement with the complainant the insurer can then elect to either cash settle the claim for the quoted amount or complete the repairs. Determination | Case number: 653569 Page 6 of 6 3 Supporting information  Complainant’s submissions.  Insurer’s submissions .

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.