Alleged misleading statements about council approval of off-the-plan property plans

FirmFinancewerx Pty Ltd
Decided2020-04-30
ProductInvestments · Other financial advice
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant alleged the broker misled her into believing the off-the-plan dual residency plans had council approval before she bought. AFCA found jurisdiction existed but that the firm did not mislead her and was not liable for her loss.

Showing a brochure and plans did not amount to an implied representation of council approval, and the complainant had lawyers and prior investment experience, so no reliance or caused loss was shown.

Issues

Subjects and remedies

no remedy

Related

Find similar determinations

Text of the determination

Determination Case number 653390 Financial firm Financewerx Pty Ltd Determination | Case number: 653390 Page 1 of 8 Case number: 653390 30 April 2020 1 Determination overview 1.1 Complaint In December 2015, the complainant entered into an „off -the- plan‟ transaction to purchase land on which a dual residency property would be built ( property ). The transaction involved the complainant entering into a contract of sale of land and a building contract. The complainant retained a lawyer to assist her in the transaction. The financial firm is a broker who arranged finance for the complainant in relation to the purchase of the property and other investment properties. The complainant says that Ms B of the financial firm represented to her that the plans for the property had received council approval, whereas this was not the case. The process of obtaining formal council approval proved more difficult than the developer and builder expected and:  in around November 2016, the builder asked the developer to submit alternative single residency plans to the council for approval, which it did;  the complainant says she was pressured by the builder into, but did not accept, the alternative single residency arrangement;  three years of protracted, complex interactions between the complainant, builder, developer, and council has left the complainant in a position where plans for her dual residency property have been ultimately approved by council, but not built by the builder;  the complainant says the builder is making the process of proceeding with the original build more difficult and more expensive than under the building contract; and  the developer is now proposing to take legal action against the complainant for her failure to commence construction on the land. This complaint is about whether:  the financial firm misled the complainant into believing the plans for the property had council approval before she purchased the property; and  the financial firm is responsible for the complainant‟s alleged loss arising from the position in which she finds herself. On 25 February 2020, the case manager issued a recommendation in this matter which was in favour of the financial firm. The complainant rejected the recommendation and the matter proceeded to determination. Determination | Case number: 653390 Page 2 of 8 1.2 Issues and key findings Were the findings in the recommendation correct? Based on all the available information, save as noted below, the findings in the recommendation were correct and are adopted in this determination. Is the financial firm liable for the complainant’s alleged loss? Based on all the available information, for the reasons set out in Section 2.2 below, the financial firm is not liable for loss arising from the complainant‟s current position. 1.3 Determination This determination is in favour of the financial firm. No compensation is payable by the financial firm to the complainant. The complainant is encouraged to consider obtaining professional advice about:  her obligations with respect to the property; and  alternative avenues for pursuing any rights she may have with respect to the property, including against third parties. Determination | Case number: 653390 Page 3 of 8 2 Reasons for determination 2.1 Were the findings in the recommendation correct? The findings in the recommendation were mostly correct I have decided this complaint based on what is fair in all the circumstances having regard to the relevant law, good industry practice, codes or guidance as to practice and previous AFCA decisions. I have considered all material submitted by the parties and I am satisfied that the material I relied upon in reaching my findings has been exchanged between the parties. Save as noted below, I am satisfied that the case manager ‟s recommendation contains an accurate summary of the complaint, the issues to be determined, any applicable paragraphs of the Rules and any relevant law. I am also satisfied that the findings in the attached recommendation were correct, and I adopt them in this determination, subject to the following:  the available information shows that the financial firm did assist the complainant to obtain finance (secured over another property) which was used, in part, to purchase the property (contrary to the finding in the recommendation). Ms B‟s statement, in an email to a third party, that the complainant was a cash buyer and that progress payments were to be made by cash, is not inconsistent with the financial firm having assisted the complainant in this way. Rather, it reflects the fact that a lender was not directly involved in the transaction. My conclusion that the financial firm did assist the complainant to obtain finance for the purchase of the property provides further support for the finding that the complaint is within AFCA‟s jurisdiction under our Rules.  the fact that the property was purchased „off -the- plan‟ does not necessarily mean that the plans had not yet been submitted to council for approval (contrary to the conclusion in the recommendation). Some off-the-plan purchases will have been council-approved at the time of purchase, while others will be subject to council approval. There is no blanket inference that can be drawn about council approval merely because a property is described as having been purchased „off -the- plan‟ . However, my finding does not affect the outcome of the complaint. The complainant rejected the recommendation without further submissions The complainant rejected the recommendation but did not make further submissions. Although the complainant did not make further submissions, I have nevertheless reconsidered all information on file including all submissions made by the parties throughout the complaint. Determination | Case number: 653390 Page 4 of 8 Having reviewed all the available information, I agree with the case manager‟s findings that:  AFCA has jurisdiction to consider this complaint; and  the available information does not support a finding that the financial firm misled the complainant about council approval of the plans for the property. I make some further observations and findings below. 2.2 Is the financial firm liable for th e complainant’s alleged loss? AFCA is a dispute resolution scheme not a court AFCA is a dispute resolution scheme, not a court of law. AFCA does not have the power to require third parties to produce documents or to take or test evidence on oath. It also does not have the power to make third parties (such as the builder, developer or lawyer) do, or not do, certain things. Nevertheless, when determining the extent to which a financial firm is responsible for a complainant‟s loss , AFCA will evaluate, as far as possible, the role of third parties in causing or contributing to the complainant‟s loss. A financial firm will not be held liable for a complainant‟s loss where it was caused by third parties. The complainant has not shown that the financial firm misled her Having reviewed all the available information, I am not satisfied that the financial firm engaged in misleading or deceptive conduct about council approval of plans for the property or that the complainant relied on that conduct when she entered into the transaction. The complainant was introduced to the financial firm by her friend JY, for the purposes of arranging finance to purchase other investment properties. During those discussions, Ms B showed the complainant some brochures for the property and encouraged her to consider purchasing it. The complainant says:  Ms B showed her brochures which had artistic impressions of the dual residency property and showed her the plans for the property;  Ms B said that it would be built in about 10 months to a year‟s time;  she is unable to confirm that Ms B said council approval had been obtained, but Ms B did not advise that council approval had not been obtained or was uncertain; and  she presumed the plans had been approved by co uncil at the time she purchased the property. Determination | Case number: 653390 Page 5 of 8 While it is understandable that the complainant presumed or assumed that the plans had been approved by the council at the time she purchased the property, there is insufficient information to show that the financial firm misled her about this. While Ms B later wrote to the complainant on 7 May 2018 expressing sympathy for her position and indicating she would try to assist the complainant, this does not show that Ms B misled the complainant about council approval at the time they discussed the property. As the complainant accepts, Ms B did not say anything at all about council approval, and I find that simply showing the complainant a brochure and the plans (which were also in the building contract) did not amount to an implied representation that the plans had been approved by council. At the time of the complainant‟s discussions with Ms B about the property, there was no indication that Ms B knew that the council had not approved the plans – the complainant herself says this is the case. In fact, it appears that the builder and developer had assumed, based on a series of preliminary meetings with the council from March 2015, that the plans would be approved by the council in a relatively straightforward manner. The builder explains as much in its letter to the complainant dated 14 November 2016 and confirms that “the allocated lots that [the developer] presents to us are already pre-determined for dual occupancy dwellings as per the registration of their planning scheme with Council”. Consequently, this is not a case where Ms B knew that council had not approved the plans, or that it would be difficult to obtain council approval of the plans, and withheld that information from the complainant. The complainant had lawyers acting for her on the transaction, and although there is a question about whether they advised on the building contract, the complainant signed the building contract and accepted its terms and conditions. The building contract included the following provisions at page 4: PERSON RESPONSIBLE FOR OBTAINING AND PAYING FOR PLANNING APPROVAL The Owner. NUMBER OF DAYS TO OBTAIN PLANNING APPROVAL within 45 days of the date of this Contract. Even if I were to accept that the financial firm made an implied misrepresentation that council had approved the plans (which I do not), given the complainant‟s previous experience with purchasing investment properties and her engagement of lawyers on the transaction, I am not satisfied that she relevantly relied on any such misrepresentation when she entered into the transaction. Determination | Case number: 653390 Page 6 of 8 The financial firm’s conduct has not caused the alleged loss In any event, the complainant ‟s alleged loss has not been shown to have been caused by any conduct by the financial firm. I have reached this view including because:  there has been protracted, complex interactions over more than 3 years (from when the builder sent the complainant a letter on 14 November 2016 about the difficulties involved in obtaining council approval) which have involved the complainant, the developer, the builder and the council – and it is unclear who is responsible for the delays, complexities and increased costs (and, in any event, the financial firm is not responsible);  it is unclear who is responsible for the fact that the construction of the property has not progressed after council approval was finally obtained (and, in any event, the financial firm is not responsible);  the builder has offered various alternative arrangements to the complainant which have been rejected by her – giving rise to questions about whether the complainant has, in part, contributed to her own loss, or at least failed to mitigate it; and  given the potential increase in land and property value over the 4 years since the complainant entered into the transaction (agreed to by both parties but not quantified) it is unclear whether any financial loss has, or will be, sustained by the complainant if she proceeds to build and sell the property. Consequently, I am not satisfied that:  the complainant has established that she has to-date suffered any financial loss; or  the financial firm should fairly be found to have caused any such loss. Given the remedy for misleading and deceptive conduct is not to make the representation come true - but to compensate the complainant for loss suffered due to having relied on it - I am unable to find that the alleged misleading and deceptive conduct has cau sed the complainant‟s alleged loss. The complainant is encouraged to seek professional advice The complainant is in a difficult position. She entered into the transaction with a clear understanding that she would receive a dual residency property, built in accordance with the plans, at the contracted price. She has not received what she was expecting to receive. The complainant is experiencing ongoing difficulties with the builder and is being legally pursued by the developer. AFCA is unable to assist her with these issues. Determination | Case number: 653390 Page 7 of 8 Given the complainant‟s curren t situation and the limitations on AFCA‟s jurisdiction , the complainant is encouraged to consider obtaining professional advice about:  her obligations with respect to the property; and  alternative avenues for pursuing any rights she may have with respect to the property, including against third parties. Determination | Case number: 653390 Page 8 of 8 3 Supporting information 3.1 A FCA’s approach to misleading or deceptive conduct claims The financial firm has obligations to its customers not to engage in conduct that is misleading or deceptive, or likely to mislead or deceive ( misleading or deceptive conduct ). For the complainant to establish a claim for misleading or deceptive conduct, AFCA must be satisfied on the balance of probabilities that:  the financial firm engaged in misleading or deceptive conduct;  the complainant relied on that conduct when she did something or avoided doing something; and  doing so caused the complainant to suffer loss or detriment. Conduct can be doing or saying something, or, not doing or saying something. It can also be a pattern of behaviour over time. It is important to note that if AFCA finds that the complainant was misled by the financial firm, the remedy is not to make the financial firm‟s promise or statement come true. Rather, the complainant is to be compensated for the loss caused by her reliance on that conduct. Recommendation Case number 653390 Financial firm Financewerx Pty Ltd Recommendation | Case number: 653390 Page 1 of 5 Case number: 653390 25 February 2020 4 Overview 4.1 Complaint The financial firm initially helped the complainant obtain finance to purchase some investment properties in October 2015. In December 2015, the complainant purchased an off-the-plan house and land package in Victoria ( the property ) for investment purposes. The build contract was for a dual residence ( duo ) single storey residential property. On 14 November 2016, the builders sent the complainant a letter saying that council had rejected plans for the duo buildings. The complainant says that the financial firm:  advertised and sold her the house and land package  showed her the plan of the duo property and she agreed to purchase the property based off those plans  misled her to believe that the duo concept had been council approved when she purchased the package  advertised and sold her a product that was not delivered. The financial firm disputes our jurisdiction as it says it did not provide a financial service to the complainant. 4.2 Issues and key findings Did the financial firm provide the complainant a financial service? Yes. Investment property advice is considered a financial service under our Rules. Did the financial firm mislead the complainant about council approval? No. While it was the financial firm who told the complainant about the property, there is no information to show the financial firm told the complainant that council had already approved the duo plans. 4.3 Recommendation This recommendation is in favour of the financial firm. The financial firm are not required to provide any compensation to the complainant or take any further action. Recommendation | Case number: 653390 Page 2 of 5 5 Reasons for recommendation 5.1 Did the financial firm provide a financial service? The financial firm did provide a financial service the complainant. This complaint is within our Rules. The financial firm did not organise a loan for the purchase of the property The financial firm says that it did not provide the complainant with a financial service in relation to the property, as the complainant made a cash purchase and it did not help her get any loans. The financial firm has provided us documentation to show that it helped the complainant previously with obtaining three loans. On 14 January 2016, there is an email from the financial firm to another party discussing the construction contract funds. The financial firm confirmed that the complainant would be purchasing and making the progress payments with cash and no finance was required. There is no information to show that the financial firm arranged a loan for the complainant to purchase the property. The complainant believed she was dealing with the financial firm The complainant says that the financial firm advertised and sold the property to her. The financial firm say that one of their referrers ( JY ) as an agent of its investment real estate agency ( UPI ) advertised and sold the property to the complainant. The complainant says their friend JY introduced her to the financial firm for assistance obtaining a loan to purchase a property in Queensland. JY attended the first meeting between the complainant and the financial firm, then the complainant and financial firm arranged to meet again without JY on 30 October 2015. The complainant says it was during the meeting on 30 October 2015 that Ms B of the financial firm showed her the plans for the property. The complainant says that she did not know the difference between UPI and the financial firm and was never told the difference. The complainant provided emails from October 2015 (included in section 3.1). The complainant emailed Ms B, at the financial firm‟s email address, thanking her for the advice regardi ng her investments. Ms B responds, from the financial firm‟s email address, confirming the next meeting and that she had sent some other properties to JY for her to look at, or Ms B can show the complainant the properties in their next meeting. Recommendation | Case number: 653390 Page 3 of 5 I consider it reasonable for the complainant to have formed the belief that the financial firm was providing her with this service. Investment property advice is a financial service Our definition of a „financial service‟ is set out in section E.1.1 of the AFCA R ules. Our definition of a „financial service‟ includes „financial or investment advice‟. Therefore, we consider this complaint to be within our Rules as it relates to investment property advice. I consider the subject of this complaint to be a financial service under our Rules. 5.2 Did the financial firm mislead the complainant about council approval? There is no contemperonous information to show what was discussed during the meeting on 30 October 2015 The complainant says that Mrs B of the finanical firm:  mislead her to believe that the duo house and land package had already been approved by council  showed her pictures and plans of the duo property  did not tell her that the duo property was uncertain. The complainant says that had she known the duo buliding had not been approved, she would not have gone ahead with the purchase. The financial firm say that:  the property package was sold as a duo property  there are clauses in the contracts which say that the plans are subject to any council approvals and changes. We asked the financial firm to provide all information and documentation on the property, including all pamphlets, brochures and advertising materials, but it has not done so. There is no contemperonous information to show what was discussed during the meeting on 30 October 2015. The only information to show what occurred on 30 October 2015 is the email correspondence set out in 3.1. However, these emails do not provide any particular details on the conversation. The complainant purchased ‘off -the- plan’ The only information about the status of council approval is the real estate and construction contracts, which show that these were „off -the- plan‟ purchases. The real estate and construction contracts do not say that council had approved the Recommendation | Case number: 653390 Page 4 of 5 construction plans. In fact, the construction contract specifically contains clauses about which party is responsible for getting planning approval and a building permit. The property was an „off -the- plan‟ purchase. The complainant provided the real estate and constru ction contracts which confirm this. An „off -the- plan‟ purchase, by definition, means that the plans for the property or construction have not yet been submitted to council for approval. An „off -the- plan‟ purchase can be risky as the purchaser is purchasin g without seeing the final product. A purchaser will have to rely on artist impressions, draft plans and advertising material, as well as the terms and conditions of the contract in circumstances where the plans or finishes change. There is no information to show that the financial firm misled the complainant about council approval Taking into consideration:  the nature of „off -the- plan‟ purchases as outlined above  that the complainant is unable to show or confirm the financial firm told her that council already approved the construction plans  the construction contract specifically provides information about obtaining planning approval and a building permit I cannot find that the financial firm misled the complainant about the plan approval. Recommendation | Case number: 653390 Page 5 of 5 6 Supporting information 6.1 Correspondence between the complainant and the financial firm on 28 October 2015 Date and time From To Message 28 October 2015 1.09pm Complainant Ms B Dear [Ms B], Thanking you very much for your advic e regarding my investments. The attachmen ts are part of your requirement. I‟ll let you know soon as I talk to [Mr W] my accountant that (sic) you‟ll ring him. When do you want me to come on Friday for your treatment? Talk to you soon! Warm regards, [complainant] 28 October 2015 2.19pm Ms B financial firm email Complainant Thanks so much [complainant] Friday about 4pm? Is that too late? By the way I sent [JY] some properties in Victoria near Melbourne Have a look Or otherwise I can show you Friday when you come here Thanks again Kind Regards , [Ms B] [financial firm] Finance brok er – Principal

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.