Determination 653193
Loss of rent settlement amount and alleged insurer delay
Summary
A lot-owner disputed the cash settlement of her loss of rent after storm damage, which was delayed by roof defects and body corporate processes. AFCA found the insurer's settlement fair and no compensation was warranted.
The delays were caused by the body corporate and excluded roof defects, so the insurer could not reasonably be held responsible for the delay or the loss of rent beyond the amount paid.
Issues
- Claim amount dispute primary · not upheld“The available information shows the insurer settled its obligations for the loss of rent claim fairly and in line with the policy terms.”
- Delay secondary · not upheld“The delays in finalising the claim were largely due to the body corporate conducting its independent investigation.”
Subjects and remedies
home or building damagenatural disasterno remedy
Related
All Strata Unit Underwriters determinations · Find similar determinations
Text of the determination
Determination
Case number 653193
Financial firm Strata Unit Underwriters
Determination | Case number: 653193 Page 2 of 10
Case number: 653193 20 April 2020
1 Determination overview
1.1 Complaint
The complainant is a beneficiary under a residential strata insurance policy held with
the financial firm (insurer), as a lot-owner in the insured development.
A claim was lodged for damage that occurred during a violent storm on 25 November
2018. The insurer accepted the claim for the resulting damage in the complainant’s
property but declined liability for the rectification of the roof. This was because the
insurer’s experts found numerous design faults and maintenance issues in the roof,
which are specifically excluded from cover under the policy.
The body corporate then agreed to complete the required roof rectifications. The
insurer says it was unable to authorise repairs to the complainant’s property until that
work was completed.
The insurer cash settled the body corporate for the complainant’s property damage
and the complainant for her loss of rent. The complainant raised concerns regarding
the insurer’s handling of the claim, including the impact of that on her loss of rent.
She believes she is entitled to more for that component of the claim.
1.2 Issues and key findings
Has the insurer correctly settled the loss of rent claim?
The available information shows the insurer settled its obligations for the loss of rent
claim fairly and in line with the policy terms and conditions.
Is the complainant entitled to compensation?
The insurer handled the claim reasonably and appropriately overall. The evidence
shows the body corporate ’s actions contributed to delays in the insurer finalising its
claim decision and settlement, and so the insurer cannot be held responsible for any
additional upset and inconvenience caused to the complainant, or for financial loss.
Compensation is not warranted in the circumstances.
1.3 Determination
This determination is in favour of the insurer.
The insurer is not required to take any further action.
Determination | Case number: 653193 Page 3 of 10
2 Reasons for determination
I have decided this case on the basis of what I consider fair in all the circumstances,
having regard to the relevant law, good i ndustry practice, codes of practice and
previous AFCA decisions.
I have taken into account all the material submitted by the parties. I am satisfied that
the documentation I have relied on has been provided to both parties. For the
purposes of this determination, I will deal with only those points considered relevant.
2.1 Has the insurer correctly settled the loss of rent claim?
Policy provides cover subject to terms and conditions
The strata policy provides cover for loss or damage, including loss of rental income,
subject to certain terms, conditions and limitations.
The policy responds to sudden and accidental damage but specifically excludes loss
or damage arising from a structural defect, faulty design, faulty workmanship, error or
omission that the insured was aware of or should have reasonably been aware of.
The policy also provides a loss of rental income benefit in the circumstances where
the property suffers damage and is uninhabitable. The benefit is payable until the
property is re-leased following reinstatement works and includes the reasonable costs
of re-letting the property up to a maximum of $1,500.
The policy specifies the insurer is not responsible for any delays caused by the
complainant or anyone acting on behalf of the complainant commencing or
completing repair works.
Circumstances of the claim not in dispute
The complainant’s tenanted property sustained water damage to the flooring, walls in
the bedroom and lounge, and kitchen cupboards when storm water entered through
the roof.
The insurer accepted the claim and appointed A, a builder, to investigate the cause of
the damage. A reported the cause was:
insufficient fall in some roof sheets causing water to flow backwards and enter the
property
the box guttering not having gutter flashing
the roofing sheets not having been weathered, causing capillary action allowing
water to enter the property
the lack of tray flashing to penetrations on the roof
the single down pipe being insufficient and non-compliant
damage by foot traffic allowing water to pool and possibly ingress
Determination | Case number: 653193 Page 4 of 10
barge capping having been over-flashed with adhesive flashing material to prevent
leaks
insufficient fall to box gutter causing pooling in box gutter
a blockage in the downpipe by debris.
A did not find evidence of an opening caused by the storm, and concluded it was the
identified defects which resulted in overflowing and water entering the affected lots
during the severe rainfall.
Based on A ’s findings , the insurer declined liability for the rectification of the roof in
line with the policy exclusions, but it accepted the resultant damage caused by the
storm. The insurer requested the body corporate to rectify the identified defects in the
roof prior to authorising repairs to the complainant’s property. The insurer’s decision
to decline liability for the rectification of the roof is not in dispute.
The current complaint is about the settlement of the co mplainant’s claim relating to
loss of rent.
Insurer may decide how to settle claim
The body corporate was responsible for the rectification works on the roof.
The insurer points out the policy allows it discretion as to how it settles a claim for
which it is responsible. The insurer says it chose to cash settle the body corporate a
sum of $128,514.67 for the storm-related water damage to four lots in the insured
development, including $43,079.19 for the complainant’s property. This included a
10% contingency fee. The complainant provided a quotation of $35,500 for the repairs
and is not disputing th e insurer’s settlement for the repairs to her property.
The complainant also accepted a cash settlement for loss of rental income, as her
tenant vacated the property when it was damaged and became uninhabitable. Her
acceptance of the original settlement does not automatically preclude AFCA from
considering this dispute, although that will be taken into account along with all other
available evidence.
Complainant says settlement for loss of rent is inadequate
The complainant now wants the insurer to pay her loss of rent for a:
further four weeks, based on the delay in the insurer responding to the body
corporate’s scope of works
further four-week delay on the insu rer’s agreement to the report of the body
corporate’s engineer, P
further six- week delay in the insurer’s response to the body corporate’s request for
a cash settlement
further three to four weeks ’ delay when the insurer was negotiating the
complainant’s loss of rent settlement.
Determination | Case number: 653193 Page 5 of 10
The complainant also says her property only became uninhabitable because the
insurer’s contractors stripped the property of its floor and wall coverings and kitchen
cabinets for drying.
The complainant says she was unaware that her property would be rendered
uninhabitable. She says the stripping of her apartment prevented her from performing
a few cosmetic repairs and re-letting the property. The complainant says the insurer
led her to believe the repairs would be completed promptly, but then changed its mind
when the roof issues became apparent.
The complainant has not provided any expert or other compelling evidence to show
the insurer’s contractors acted unreasonably or inappropriately in taking the action
they did to strip out the water-affected areas of the apartment.
The complainant disputes the settlement for her loss of rent claim on the basis the
insurer limited the duration of her loss of rent benefit unreasonably.
She says:
the insurer was not willing to consider the entire duration the property remained
uninhabitable, since it declined liability for the roof rectification
the insurer took up to six to seven months to agree with the body corporate on the
required roof repairs
the insurer failed to take into account that no previous claims had been made
she is not liable for the delay completing roof rectification works and should not be
disadvantaged
the insurer’s expert failed to scope the roof rectifications adequately and this led
her to believe the rectifications required would be completed without delay
the body corporate was faced with more complex rectifications than what was
initially scoped, and this led to the delay.
The complainant says her property remained uninhabitable for almost a year and
says the insurer’s settlement for her loss of rent is inadequate to cover her costs. She
says her settlement was only $3,000 more than what her neighbour received for
alternative accommodation based on four weeks of repairs.
Information does not show insurer was responsible for delays
The available information shows:
following lodgement of the claim, the insurer appointed loss adjuster S to manage it
S inspected the property on 19 December 2018 and commenced make-safe works
S appointed A to investigate the cause of the damage
A inspected the roof on 21 December 2018 and provided its findings and a quote
for the repairs
Determination | Case number: 653193 Page 6 of 10
the insurer determined the roof was not damaged by storm, based on S’s report on
9 January 2019
a comparison quote for repairs was obtained by the insurer from R on 14 February
2019
the body corporate received a report by roofer P on 26 March 2019
the body corporate disputed some of A’s findings on 2 May 2019
the insurer referred P’s report to A for review on 2 May 2019
the body corporate requested insurer to complete repairs on 2 May 2019, subject
to roof issues being completed, and the insurer declined the request
insurer appointed roofer I to re-inspect the roof to corroborate the damage to the
roof by foot and a report was submitted on 17 May 2019
insurer decided to cash settle the claim on 29 May 2019
AFCA complaint was lodged on 15 July 2019
settlement for loss of rent paid on 15 August 2019.
P’s findings were largely consistent with the insurer’s findings on the cause of the
damage to the roof.
Given the roof damage was caused by excluded factors, the body corporate was
required to perform the necessary rectifications prior to the insurer authorising repairs.
In such circumstances, the insurer is entitled to delay authorising repairs until
rectification works are completed, in order to mitigate future loss or damage.
I have carefully reviewed the available information. The information shows:
the delays in finalising the claim were largely due to the body corporate conducting
its independent investigation of the cause of the damage
there was a delay while the body corporate and the insurer agreed on the scope of
rectification works
there was a delay when the body corporate had to arrange to impose a special levy
to fund the repairs
there was a delay in the body corporate carrying out maintenance and remediation
works on the roof
there was a delay when the insurer and the body corporate negotiated a
settlement.
The evidence shows the body corporate informed the insurer that it required a further
six to twelve months for the completing of repairs in May 2019, as it required time to
raise the necessary funds and identify and secure a suitable repairer. This led to the
insurer deciding to cash settle the claim.
The information also shows the insurer, in recognition of the delays faced by the body
corporate, agreed to provide a cash settlement of the claims on 29 May 2019. This
was subject to negotiation and was finalised in August 2019.
Determination | Case number: 653193 Page 7 of 10
I am not satisfied the insurer can reasonably be held responsible for delays.
Loss of rent settlement is reasonable in the circumstances
The insurer says it decided to pay a loss of rent benefit from the date of the event to
14 February 2019, which was th e date the insurer obtained R’s comparative quote for
the repairs. The insurer disagrees with the complainant’s request to increase its
settlement for loss of rental income. It says it is not liable for the loss of rent while the
body corporate carried out its investigation of the issues and agreed to the required
rectifications.
The insurer says the loss of rent settlement covered:
the period from the date of event (28 November 2018) to the date of R’s
comparative quote (14 February 2019) which is 78 days;
a further repair period of six weeks (42 days);
28 days for re-letting the property; and
14 days of lead time.
The insurer provided the following breakdown of the loss of rent settlement:
Item Amount
162 days of rent $13,156.02
Re - letting fee $ 627.00
Advertising fee $ 108.90
Tenancy agreement
fee
$ 33.00
Database search f ee $ 33.00
Total $13, 957.92
The insurer also paid additional amounts of $698.90 for the cost of gas and electricity
and a travel allowance of $250. The complainant is not disputing these amounts.
The information shows the complainant received a weekly rental of $570. The insurer
says it calculated the re-letting fee as the equivalent of one week of rent + GST and
based the advertising, tenancy agreement fee and database search fee on the
information provided by the complainant.
The complainant is not disputing the insurer’s calculations and has not provided
information to demonstrate this portion of the loss of rent settlement is inconsistent
with the costs associated with reletting the property.
Determination | Case number: 653193 Page 8 of 10
I acknowledge the complainant is a self-funded retiree and is dependant on the
income from her investment property. However, having reviewed the available
information, I am not persuaded the insurer should be liable for any increase in its
settlement for the loss of rent claim. That is because the delays in finalising the
settlement were due to the role of the body corporate in the claims process, and its
actions, not the insurer ’s .
The claim notes show the complainant recognised the delay on her loss of rent
settlement was caused by the body corporate and hoped the body corporate could
contribute towards her loss of rental income with any excess settlement funds
(although that is a matter between those parties and is not something I can decide or
require).
In the circumstances, I am satisfied the insurer is not responsible for the delay in
settling the claim and is not liable to increase its settlement for loss of rent.
2.2 Is the complainant entitled to compensation?
Complainant is not entitled to compensation
Under the AFCA Rules, AFCA may compensate a complainant for direct financial loss
and non-financial loss suffered because of the conduct of their insurer.
The complainant says the insurer failed to respond to her loss of rent entitlement in a
timely manner. She also says she was not able to re-let her property because the
insurer’s contractors stripped her property. She says the insurer’s delay caused direct
financial loss as well as non-financial loss.
The insurer says the complainant’s property sustained more water damage than her
neighbour’s property and the se make-safe actions were required and necessary to
prevent the development of mould and mitigate the risk of further damage.
I have seen nothing to suggest that is incorrect or unreasonable.
When considering if the insurer caused delays in managing an insurance claim, AFCA
will look at such factors as whether:
the insurer acted fairly and promptly to resolve the claim
there was an unreasonable delay
there were factors which were outside the control of the insurer or otherwise
unavoidable
the insured’s actions caused or contributed to the delay.
If AFCA decides the insurer unreasonably handled or delayed the claim, AFCA will
look at the loss (if any) that flowed from that conduct.
I have reviewed the available information carefully. I am satisfied that shows the
insurer acted fairly and promptly by accepting liability for the resultant damage to the
Determination | Case number: 653193 Page 9 of 10
complainant’s property. As set out above, the delay in finalising a settlement of the
claim was caused by the processes of the body corporate.
The claim notes suggest the insurer faced some difficulty when communicating with
the various parties involved and did fail to acknowledge the complainant’s
correspondence regarding her loss of rent claim. However, the available information
does not suggest this was intentional or protracted.
The evidence also does not suggest the insurer misled the complainant or
misrepresented the outcome of the claim. The policy terms entitle the insurer to insist
on the body corporate completing the recommended roof rectifications prior to the
insurer authorising the internal repair work. This is in order to prevent any further
damage which might then occur during a similar event, and is a common-sense and
reasonable requirement.
It is unfortunately to be expected that there will be some upset and inconvenience
when damage occurs and a claim needs to be made. The severity and nature of the
damage is likely to contribute to that. However, the insurer cannot necessarily be held
responsible for complications and delays which might reasonably be part of the claim
process where a number of parties are also involved.
In the particular circumstances, I am not satisfied any delay in providing a settlement
for the claim warrants compensation, either as a direct financial loss, or for non-
financial loss (on the basis of unusual upset or inconvenience caused).
Determination | Case number: 653193 Page 10 of 10
3 Supporting information
3.1 Policy wording
Record Key points
Loss o f r ent, r eletting c osts,
t emporary a ccommodation
a nd r emoval c osts
W e will pay the following costs where your unit or common area
suffers damage covered by this section and areas are uninhabitable
or when reas onable access to or occupancy of your unit or common
area is prevented by damage that would be covered by this section
happening to other property within the immediate vicinity of your unit
or common area:
L oss of rent
W here a unit or common area is leased out, or you can provide
evidence by means of a signed agreement that it would have been
leased out, we will pay an amount equal to the actual rent lost less
any recoveries available from the bond authority . W e will pay up until
the time your unit or common area is re - leased following completion
of reinstatement and/or repair of your insured property or access to
your unit or common property is re - established provided you can
demonstrate that you have taken all necessary steps to re - let your
unit or common area including the active marketing of your unit or
common area at current market rent.
R eletting costs
W here a lease agreement is terminated as a result of damage
covered by this section to your unit o r common area, we will pay the
reasonable re - letting costs of that unit or common area.
T he most we will pay is $1,500.
Exclusions W e will not pay any claims for damage to insured property arising
directly or indirectly from or in connection with:
defect in any item, structural defect, faulty design, faulty
workmanship, error or omission that you were aware of or should
have reasonably been aware of.
D elays I f you, the unit owner or anyone acting on your or the unit owners
behalf cause delays preve nting us from commencing and completing
reinstatement or replacement of your insured property or other
property insured under this policy, we will not pay for any extra costs
that result from that delay.