Dispute over scope of repairs, rebuild versus repair, and cash settlement for defect-related wall cracking
Text of the determination
Determination
Case number 650004
Financial firm AAI Limited
Determination | Case number: 650004 Page 2 of 14
Case number: 650004 15 April 2020
1 Determination overview
1.1 Complaint
The complainant and his brother JN (referred to collectively as the complainant) hold
a home and contents insurance policy with the financial firm (the insurer). The
complainant lodged a claim for wall cracking and signs of moisture and mould in April
2018. The insurer declined the claim.
The complainant lodged a complaint (542599) with AFCA regarding the decline. A
determination was made by a panel finding that the insurer was liable to repair the
wall cracking of the upper level damaged because of an identified building defect.
The complainant says the insurer has not complied with the determination within 30
days. The complainant is dissatisfied with the scope of works.
1.2 Issues and key findings
Has the insurer appropriately determined its liability?
The insurer has appropriately determined its liability in relation to the resultant
damage. The available information does not establish the property is required to be
demolished and rebuilt.
How should the claim be settled?
The insurer is required to set tle the claim in accordance with its builder‟s quote and
mould remediation quote.
Is the complainant entitled to compensation?
The panel is satisfied the insurer did not delay assessing the claim. Therefore, no
award of compensation is warranted in the circumstances.
1.3 Determination
This determination is in favour of the insurer.
Should the complainant accept this determination, then within seven days of
notification of acceptance the insurer is to pay to the complainant the sum of
$142,761.06.
Otherwise, the insurer is not required to take any further action in relation to the claim
or the complaint.
Determination | Case number: 650004 Page 3 of 14
2 Reasons for determination
2.1 Has the insurer appropriately determined its liability?
Expert report obtained by the insurer determines the extent of liability
The complainant and his brother (the co-insured) had a previous complaint with AFCA
(542599). The determination stated the insurer is liable to repair the wall cracking
caused by building defects. The defect identified in the determination was replacing
the original cladding on the upper level with heavier material than the original design.
The remedy provided by the determination because of that defect is set out in
supporting section 3.4 of this determination.
The complainant and the insurer could not agree on a scope of works. This
determinat ion will determine the extent of the insurer‟s liability to the complainant and
his brother (the co-insured).
For the insurer to determine the extent of its liability for the resultant damage, it
arranged for an engineer (JHA) to prepare a scope of works and reports. The defect
was reported as being a change of construction methodology which was not designed
for resulting in sagging lintels. This accorded with the findings in the earlier
determination.
JHA attended the property on 13 May 2019 to consider the extent of damage caused
by the defect which would require rectification. His findings are summarised in the
supporting section 3.3 of this determination. He concluded the roof frame was stable
and the southern and northern walls did not require any rec tification work.
JHA said the rectification work required because of the sagging lintels was for the
eastern and western gables to be demolished and reconstruction of the walls with
timber framing and selected cladding. This work would also require the removal and
replacement of upper level timber decks.
JHA provided a scope of works to complete repairs for the resultant damage caused
by the defect. The insurer asked builders to provide a quote to repair the damage
based on JHA‟s scope of works.
The complainant appointed their own engineer (JDE) to provide a report. JDE
inspected the property on 26 September 2019. His findings are also summarised in
supporting section 3.3 of this determination.
JDE agrees the lintel above the sliding door is not designed for the load masonry
blocks and ridge beam and has deflected in the middle causing cracks in the masonry
blocks. This is the defect identified by both JHA and the other engineers in the earlier
determination. Although JDE identifies other issues, he concludes the role of the lintel
in the design is extremely important. He also says lack of bracing is one of the
Determination | Case number: 650004 Page 4 of 14
components which has contributed to cracks developing in the upper floor walls.
However, the issue of the cause of damage has been previously determined in the
previous determination. The issue now to be determined was in relation to the
rectification of the damage caused by the failed lintel due to a change of construction
methodology that was not designed for.
The panel notes JHA and the insurer‟s assessor have addressed the questions raised
by the complainants including whether the blockwork to the upper section of walls on
north and south elevations needed to be replaced. JHA determined that they have not
been damaged due to the failed lintels and therefore did not need to be replaced.
Rather, JHA says cracking on the north wall is attributed to a minor breach of
weatherproofing quality.
A summary of JHA‟s supplementary report is set out in supporting section 3.3 of the
determination.
Having considered all relevant material, the panel is satisfied JHA‟s report adequately
determines the extent of the insurer‟s liability for the resultant damage caused by the
defect identified in the earlier determination.
In review of JDE‟s report, the panel is not satisfied the information sufficiently
contradicts the findings in JHA‟s report. JDE does not say the upper floor cannot be
repaired. The scope of works provided by JDE is not extensive and does include the
extensive list of works recommended by JHA.
In consideration of the available information, the panel is satisfied the insurer has
appropriately determined its liability. It is accepted the resultant damage is a result of
the sagging lintels. The panel has reviewed both the findings of JHA and JDE a nd is
satisfied the findings of JHA are more extensive and pertinent in determining the
insurer‟s liability regarding the previous determination. JDE has not demonstrated that
the repairs relate to the resultant damage but include work to areas for which the
insurer is not liable to repair.
2.2 How should the claim be settled?
Insurer submits complainant‟s quote is insufficient
The complainant provided a quote from his builder (ABD). The quote totalled
$446,732.64. The insurer submits ABD‟s quote:
is insufficiently particularised
does not address the engineering evidence
does not address the Scope of Works provided by JHA
does not explain the need for demolition or rebuild.
The insurer also provided a report from a building coordinator which noted the quote
from ABD did not reflect the scope of works provided by JHA. Rather, the quote is
Determination | Case number: 650004 Page 5 of 14
based on the demolition of the existing dwelling and the construction of a completely
new dwelling. The panel further notes this quote is inconsistent with the c omplainant‟s
engineer‟s findings.
The panel reviewed ABD‟s quote and agrees with the submissions of the insurer that
the complainant has not demonstrated that the damage cannot be repaired. The
previous determination advised the insurer is only liable for the cracking damage
caused by the identified defect. There is no persuasive supporting information to
establish the dwelling is required to be demolished and rebuilt because of the defect
which has caused the sagging lintels. Therefore, the panel is not persuaded the
complainant‟s quotation should be accepted.
Insurer can cash settle the complainant
The relevant parts of the insurance policy are set out in supporting section 3.2 of this
determination. The insurer may determine how it settles a claim, including the option
to cash settle the complainant the costs to repair the damage to the home.
During the lodgement of this complaint, the insurer offered to cash settle the
complainant. The complainant does not dispute a cash settlement.
The panel is satisfied the insurer is entitled to cash settle the complainant the cost of
repairs.
Insurer‟s cash settlement offer is fair and reasonable
The insurer obtained a quote from a builder (DWC) based on the scope of works
prepared by JHA. DWC‟s quote totalled $8 2,855.13. Another builder quoted to repair
based on the scope of works prepared by JHA in the sum of $86,054.32.
In its offer to the complainant, the insurer offered to pay an additional 15% equalling
$12,428.27 for variations and contingencies in addition to the quote of $82,855.13.
The total offer for the repairs is $95,283.40.
In addition to the repairs, the insurer has also offered to pay the complainant the cost
for mould remediation. The quote obtained by the insurer for mould remediation from
SE is for $34,127.28. The insurer has offered an additional 15% ($5,119.09) for the
mould remediation considering variations and contingencies.
The total sum for mould remediation is $39,246.37.
Based on the available information, the panel is satisfied the cash settlement offer is
fair and reasonable. The offer is made based on current actionable quotations and in
accordance with the previous determination. In addition, the insurer has allowed an
additional 15% for variations and contingencies which may arise during repairs. The
panel is satisfied this is fair in the circumstances.
The insurer has estimated the time for remediation of the mould and to undertake
repairs is a total of 16 weeks. In the absence of any material to the contrary and
Determination | Case number: 650004 Page 6 of 14
considering the nature of the work required, the panel accept this estimate is
reasonable. The insurer‟s offer includes temporary accommodation for 16 weeks in
the sum of $5,600 for SN and $3,840 for JN.
The insurer‟s final offer dated 18 November 2019 totalled $142,761.06. The offer
assumed a remaining amount of $191.28 was payable for supplementary living
expenses. If this has not been paid, the panel is satisfied the overall total settlement
offer in the sum of $142,761.06 is fair in all the circumstances based on the available
information.
2.3 Is the complainant entitled to compensation?
Compensation paid in some circumstances
Under the AFCA Rules, we may award compensation (capped at $5,000) for non-
financial loss where a complainant has suffered an unusual degree or extent of
physical inconvenience, time taken to resolve the situation or interference with their
expectation of enjoyment or peace of mind.
AFCA adopts a conservative approach to the award of compensation for non-financial
loss and expect complainants to be moderately robust and bear the usual stress and
inconvenience associated with an insurance claim. However, AFCA considers the
complainant‟s circumstances and how the actions of the insurer have impacted.
Information does not establish the insurer delayed actions
The complainant says the insurer caused delays after acceptance of the previous
determination. The complainant says the insurer did not comply within 30 days of
acceptance of the previous determination. In review of the previous determination, the
panel notes the timeframe was not specified for the insurer to comply with the
determination.
The insurer submits it was required to assess the property to prepare a scope of
works for the resultant damage. There were difficulties for the parties to arrange a
time for the assessment due to the complainant‟s work commitments.
The complainant accepted the previous determination on 9 April 2019. An inspection
by JHA was completed on 13 May 2019. The panel does not consider this to be a
significant delay when taking into consideration the complainant ‟ s work commitments.
Information does not establish a make safe was required
The complainant states there was no make safe completed at the property. The
complainant says because of this, further damage has occurred.
The insurer submits there was no requirement for a make safe to be completed.
The engineer reports obtained did not establish a make safe was required.
Determination | Case number: 650004 Page 7 of 14
The panel is satisfied the available information does not establish a make safe was
required.
Compensation is not warranted in the circumstances
The panel has considered all the available information in determining whether an
award of compensation is warranted. The information provided shows the insurer did
not delay arranging an assessment of the property. There were difficulties arranging
the assessment due to the complainant‟s work commitments. Further, there was no
requirement for a make safe to be completed.
Based on the information provided, the panel is satisfied an award of compensation is
not warranted in all the circumstances.
Determination | Case number: 650004 Page 8 of 14
3 Supporting information
3.1 Our Approach
This complaint has not been the subject of a recommendation. Due to the nature of
the complaint, it has been referred directly to a panel for determination, in line with the
Operational Guidelines to the AFCA Rules. The panel consists of an ombudsman and
two representatives with consumer and insurance experience.
The panel has decided this complaint based on what is fair in all the circumstances ,
having regard to legal principles, applicable industry codes or guidance, good industry
practice and previous relevant determinations of AFCA or predecessor schemes
(which are not binding).
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other.
The panel has reviewed and considered all the material provided by the parties. While
the parties have raised numerous issues in their submissions, for the purposes of this
determination the panel has restricted its commentary to those issues that it considers
directly relevant to the outcome only.
It is an accepted principle of general insurance law that the insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an
event to which the policy responds. This is known as a prima facie claim. Once so
established, the onus shifts to the insurer to prove on the balance of probabilities that
an exclusion applies if it seeks to deny or limit its liability for the loss.
The complainant in this matter is SN. Some submissions were made by his brother
JN. The complainants in AFCA determination 542599 were S and J N. The findings in
this determination arise out of findings in determination 542599 and bind both SN and
his brother JN who is the co- insured under the insurer‟s policy, collectively referred to
as the complainant in this determination.
3.2 Relevant policy terms
What you are covered for (page 30)
Home cover
When you have home cover, your home is covered for accidental loss or damage at the insured
address and in the period of ins urance, subject to the conditions, limits and exclusions in this policy.
Accidental loss or damag e is loss or damage from incidents you did not intend or expect to happen,
e.g. accidentally breaking kitchen tiles, cracking a stone benc h top or breaking a window.
Determination | Case number: 650004 Page 9 of 14
What you are covered for (page 30)
Accidental damage
Accidental loss or damage includes loss or damage from incidents such as :
Flood;
Storm;
Lightning;
Fire;
Earthquake and Tsunami;
Theft and Burglary;
Escape of liquid;
Impact;
Damage by an animal;
Explosion;
Riot, civil commotion or public disturbance;
Malicious acts and vandalism.
General exclusions (pages 74 – 83)
You are not covered under any section of this policy for damage, loss, cost or legal liability that is
caused by, arises from or involves:
Defect, structural fault or design fault
a defect, structural fault or design fault that you knew about (or should reasonabl y have known
about) and did not fix before the loss or damage occurred (e. g. if there are signs that a defect
previously caused damage, we will not pay a later claim for further damage from this defect).
Wear, tear and gradual deterioration
wear, tear, rus t, fading, rising damp, mould, mildew, corrosion, rot, action of light or gradual
deterioration such as but not limited to:
tiles and their adhesive or grouting breaking down;
weat hering of roof tiles or roof ridge capping;
gradual weathering and breakdown of bricks, mortar or concrete.
How we settle your claim (pages 91 – 93)
We choose how we settle home claims
If we agree to pay a claim for loss, theft or damage to your home, we will decide if we will:
repair damage to your home;
rebuild your home;
Determination | Case number: 650004 Page 10 of 14
How we settle your claim (pages 91 – 93)
pay you what it would cost us to repair or rebuild your home;
pay you the sum insured for your home.
If we rebuild (or pay you what it would cost us to rebuild), we will do so on a „ new for old‟ basis.
If we repair (or pay you what it would cost us to rep air), we will at our option do so on a „ new for old‟
basis or to a similar condition to what your home was in before the loss or damage occurred.
We will not:
pay more than the relevant sum insured or policy limit;
pay extra to rebuild, replace or repair your home or contents to a better standard, specification or
quality than they were before the loss or damage occurred except as stated in the meaning of
„new for old‟;
fix a fault that existed before the loss or damage occurred;
„New for old‟ means:
we r ebuild, replace or repair with new items or new materials that are available at the time of
replacement or repair from Australian suppliers;
we rebuild, replace or repair new for old regardless of age, with no allowance for depreciation…
we repair, replace or repair to the same type, standard and specification as when new. If the
same is not available, it means of a similar type, standard and specification when new. It can be a
different brand.
„New for old‟ does not:
include paying the extra cost of repla cing or purchasing an extended warranty on any item;
mean of a better standard, specification or quality than when new.
Dealing with defects ( page 100)
If a known defect is the cause of the damage
We do not pay for loss or damage caus ed by a defect, structural fault or design fault at your home
that you knew about (or should reas onably have known about) and did not fix before the loss or
damage occurred.
If an unknown defect is the cause of the damage
If an incident covered by your policy da mages your home and an unk nown defect was the cause or
part of the cause, we will pay for the resulting damage. If the unk nown defective part of your home
is also damaged by the same incident, we will fix this as well.
Determination | Case number: 650004 Page 11 of 14
Dealing with defects ( page 100)
We do not rectify structural or desi gn faults
When we accept a claim, we will not pay extra to rectify a structural or design fault at your home
that you knew about (or should reas onably have known about). We will only pay you what it would
have cost us to fix the damage from the incident covered by your policy or if we agree, you can pay
us the extra amount it costs to rectify the structural or design fault at your home.
If undamaged defective parts of your building will not support repairs
If undamaged defective parts of your home you kne w about (or should reasonably have known
about) will not support repairing the damage caus ed by an incident covered by your policy, we will
only pay what it would have cost us to repair the damage had your home not been defective.
For known defects or faul ts
Once you become aware of a defect, structural or design fault at your home, you must rectify it as
soon as possible becaus e there is no cover for loss or damage due to that defect. If you do not
rectify the defect or fault, you may not be covered, or we might not offer a renewal of your policy.
Words with special meanings (pages 106 – 109)
“Accidental loss or damage” see page 30.
“Incident” means a single incident, accident or occurrence which you did not intend or ex pect to
happen.
3.3 Expert Reports
Record Key points
Insurer‟s expert (JHA)
Report
30 May 2019
On 13 May 2019, engineer attended the property and considered
the extent of damage which requires rectification.
Subject of the inspection is the damage caused to the external
walls resulting from the apparent deflection of the lintels over the
window opening. Extent of damage was discussed in earlier
reports from engineers.
Crux of those reports suggests that the cause of the sagging
lintels, i.e. beams over the window and door openings, is th e result
of failure of the lintels due to a change of construction
methodology that was possibly not designed for, i.e. concrete
blocks for wall areas above the lintels and not light - weight
construction such as timber framing and cladding, or inherent
cons truction defects of the concret e block lintels.
Determination | Case number: 650004 Page 12 of 14
Record Key points
Undertook a level survey of the lintels above the sliding door to the
upper level and confirmed the extent of the deflection remains
consistent with earlier measurements by engineer.
Conc ern of “roof spread” due to sagging of the large - s pan lint els
has not occurred.
Measurement of the eastern and western walls measured at both
ground floor level and at the pitching - plate height (top course of
the southern and northern block walls) confirm the roof frame is
s table.
Measurements of the eastern and western walls means the
southern and northern block walls do not require any remediation
work.
Earlier engineer reports confirm blockwork over the kitchen
window does not show evidence of disturbance from deflection of
the lintel. Stepped crack emanating from the lower left corner of
the opening is not considered to be or related as damage from any
movement of the lint el.
Rectification of the damage directly caused by the sagging lintels
will required demolition of t he eastern and western gables down to
the head - height of the lower floor window and reconstruction of the
walls with timber framing and selected cladding.
Work will also require removal and replacement of the upper level
timber decks and some minor repair and/or remediation internal
linings and finishes adjacent to the eastern and western gables.
Recommended that the new walls to the eastern and western
elevations are constructed to replicate the existing thickness of the
wall, i.e. 190mm, by constructing a 90mm wide external wall and
either 90mm or 70m wide internal walls. Both skins of the frames
are to be tied laterally.
Requested scope of works is attached to the report.
Insurer‟s expert (JHA)
Supplementary report
27 June 2019
Engineer responded to complainants‟ concerns.
Window frames to the eastern and western ground floor of the
dwelling are built in and do not require removal. The sliding door
frames require removal and will be reinstated and adjusted.
Construction of a timber wall frame in ac cordance with Australian
Standards will provide the structural adequacy to support the roof
beam. The roof is metal which is recognised as light weight.
Blockwork to the upper section of walls on nort h and south
elevations have not been damaged due to the failed lintels. The
cracking on the nort h wall outside of the stairwell is not structural
damage but is a minor breach of the weatherproofing quality of the
wall which can be a remedied with flexible sealant.
No damage seen to flooring due to compression b y the sliding
door frame. The flooring shows evidence of water staining only.
Complainant‟s expert (JDE)
Report
Inspected and photographed property 26 Sept ember 2019.
Building has multiple cracks in external masonry block walls.
Determination | Case number: 650004 Page 13 of 14
Record Key points
14 October 2019 Ridge beam support ed on internal stud wall on one side and on
brick wall at the front of the building directly above the mid span of
3.6m wide door opening.
Lintel above the 3.6m sliding door is obviously not designed for the
load mas onry blocks and ridge beam a nd has a noticeable
deflection in the middle causing also cracks in masonry blocks.
Rafters are support ed on ridge beam and on external walls.
Rafters do not have collar ties.
Although supported on ridge beam, without collar ties there is
significant pr essure that rafters exercise on supporting masonry
walls.
Lintel above 3.6m wide balcony door has deflected in the middle of
the span causing the bricks supporting ridge beam to move as
well.
Additional downward movement of the ridge beam has
significant ly increased the pressure rafters are putting on
perimeter block walls causing them to spread and develop cracks.
Role of lintel in this design is extremely important because if the
lintel would give in completely the pressure to external walls
caused by rafters would be so big that this would cause the whole
roof structure to collapse.
Some windows on the ground floor are also affected and walls
around window openings are also developing cracks.
Insufficient bracing to the roof and top floor due to lac k of bracing
walls.
Because of relatively steep roof pitch there is even more bracing
required than for standard 20 - degree roof pitch.
Lack of bracing is also one of the components that has contributed
to cracks developing in upper floor walls.
Sub floo r area appears in good shape and with no problems.
Brick piers are straight and timber bearers and joists appear in
good condition.
Ground floor is not in bad shape and cracks in masonry blocks
could be relatively easily repaired.
Upper storey has signif icant problems and full repair would be
complicated and substantial. It would require modification to all
rafters, installations of additional bracing walls and repair to
masonry attic walls that have been pushed outwards.
Suggests remedy.
Insurer‟s report (BCR)
21 January 2020
Reviewed reports and scope of works.
Independent structural engineering reports indicate existing
dwelling can be repaired.
Complainant‟s quot ation does not reflect the itemised scope of
works for rectification as per the indep endent structural
engineering report from JHA.
A fair review of both scopes is not possible.
Determination | Case number: 650004 Page 14 of 14
3.4 Extract from determination 542599
2.3 How should the claim be settled?
Insurer liable to repair the wall cracking
Page 100 of the PDS deals with defects. It says that if an unknown defect was the
cause of damage (or part of the cause), the insurer will pay for the resultant damage.
If the unknown defective part of the home is also damaged by the same incident, the
insurer will fix this as well.
The upper level of the building features masonry blockwork walls, and the lintels
supporting them are not strong enough to support their weight.
To the extent any upper walls are damaged, the insurer is liable to repair them. This
would include the cost of removing and replacing them with lighter materials pursuant
to the provision in page 100 of the PDS.
If there is any upper level wall that has not suffered damage, the insurer is not liable
to replace this. This is because the policy does not respond to fixing pre -existing
defects unless they have manifested into accidental damage during the period of
insurance. As those walls have not manifested into accidental damage during the
period of insurance, this is not covered.
The panel notes that for those walls, the complainants should rectify the defects
promptly. This is because the complainants are now aware of the issue and will be
effectively uninsured for any additional damage that is caused by this defect from this
point onwards.
It is possible a cash settlement would be appropriate given the cost of repairing the
building defect may not all be payable under the policy. If this is the case, then the
insurer‟s cash settlement should be based on an actionable quote available to the
complainants and consider any possible variations.
3.5 Other material considered
Parties‟ submissions/emails and all attachments to all submissions/emails.
Parties‟ expert reports.
Photographs.
Quotations.
Correspondence between the parties.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.