Home / QBE / Determination 649755

Determination 649755

Insurer refused to pay for balcony defect rectification and delayed garage ceiling repair

FirmQBE
Decided2020-03-20
ProductGeneral Insurance · Strata
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

Garage ceiling repairs were held up by balcony defects. AFCA found the insurer not liable for balcony rectification or for checking the complainant's work, but ordered it to complete the ceiling repairs once the balcony is fixed or cash settle.

The policy excludes faulty or defective workmanship, and the insurer had no duty to check rectification work it did not arrange.

Issues

Subjects and remedies

repair or rectify

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 649755 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 649755 Page 2 of 5 Case number: 649755 20 March 2020 1 Determination overview 1.1 Complaint The complainant is a beneficiary under a residential strata insurance policy held with the financial firm (insurer). The complainant lodged a claim in January 2016 for water damage to the plaster ceiling in his garage. The complainant repaired his balcony in May 2016 to stop water leaking into the ceiling. The insurer repaired the garage ceiling. Further water damage occurred to the complainant’s garage ceiling in 2017, and he made a further claim for ceiling repairs. The insurer offered to repair the damage to the garage ceiling again, but only once the complainant adequately rectified the building defects on his balcony. The complainant says he should not have to pay for further rectification works of his balcony, as the insurer should have tested the rectification works he arranged in May 2016. The insurer says the complainant is responsible for the rectification of the defects and water leak on his balcony, and that it was not responsible for checking if the previous balcony works were adequate. A preliminary assessment was provided to the parties on 20 December 2019 in favour of the insurer. 1.2 Issues and key findings Is the insurer liable for the rectification of the balcony defects? The policy does not cover the rectification of faulty or defective materials or work. The insurer is not liable to pay for the rectification of the balcony defects. Should the insurer have checked the balcony rectification work? It was the responsibility of the complainant to ensure that the rectification work done in May 2016 on the balcony defects was appropriate to stop the water leaks. The insurer was not responsible for checking if the rectification work was adequate. 1.3 Determination The determination is in favour of the insurer. The insurer is entitled to delay replacing the complainant’s garage ceiling until the complainant has rectified the balcony defects . Alternatively, the parties may agree as set out in section 2.2 of this determination to cash settle the claim to repair the garage ceiling. Determination | Case number: 649755 Page 3 of 5 2 Reasons for determination 2.1 Is the insurer liable for the rectification of the balcony defects? Circumstances of the claim The complainant lodged a claim with the insurer in January 2016 for water damage to the plaster ceiling in his garage. The insurer arranged for Builder S to inspect the damage at this time. Builder S found that the balcony directly above the garage was leaking and needed to be waterproofed. Builder S says that the complainant arranged rectification work for the balcony. The complainant provided an invoice to the insurer for tiling work done, as proof of “cause rectification”. Builder S then completed the repairs to the garage ceiling. Further water dam age occurred to the complainant’s garage ceiling in 2017, and he made a further claim for ceiling repairs. In September 2017, the insurer arranged for Builder S to inspect the property and determine the cause of the new water damage to the ceiling. Builder S inspected the balcony again and observed that the tiles had been “re - done” , but that the work had not been done well. Builder S carried out tests to determine if the balcony was still leaking, and found that:  the balcony leaked down the brick wall, indicating that waterproofing (membrane) had not been done correctly  the windows, and cracks in the render leaked  the membrane blocked drain holes for the window, causing leaks into the garage  the balcony area had issues with sealing. Engineering report supports that the balcony has defects The insurer appointed an engineer in 2018 to further assess the cause of the water damage to the garage ceiling. It provided its report on 12 December 2018. This report provided a comprehensive assessment of the cause of the water damage, and it concluded that the water damage to the garage ceiling is typical of problems that occur due to inadequate waterproofing of the balcony and sliding doors. The engineer’s opinion was that the water damage had occurred due to:  drainage holes to the sliding door being covered  inadequate steps being provided between the floor inside and the balcony  inadequate waterproofing of the balcony  no overflow being provided to the balcony to prevent flooding  a small outlet being prone to blockages. Determination | Case number: 649755 Page 4 of 5 The engineer’s opinion was that repairs to the plaster ceiling in the garage cannot be carried out again until the waterproofing to the balcony is rectified. The engineer recommended specific rectification work to be done, including a new waterproofing system. On available information and evidence, I am satisfied that the balcony defects had not been adequately rectified in May 2016, and these defects were the cause of the further water damage to the complainant’s garage ceiling in 2017. The insurer is not liable to pay for the rectification of the balcony defects On considering the engineer’s report, the insurer made an offer to the complainant for the insurer’s appointed builder to repair the damage to the garage ceiling again, but only once the complainant adequately rectified the building defects on his balcony. However, the policy does not cover the rectification of faulty or defective materials or workmanship. The insurer is not liable to pay for the rectification of the balcony defects identified by Builder S and the engineer. 2.2 Should the insurer have checked the balcony rectification work? The rectification work in May 2016 was arranged by the complainant As noted above, available information shows that the rectification work (re-tiling) done to the complainant’s balcony in May 20 16 was arranged by the complainant, presumably with the approval of the strata scheme’s owners’ corporation. The insurer was not responsible for the rectification work to the balcony The insurer was not a party to the contract for the services and materials provided by the person or business that did the balcony rectification work in May 2016. The insurer did not appoint the person or business that did the work on the complainant’s balcony in May 2016. The insurer was not responsible for the rectification work done to the balcony. The insurer was not required to check the balcony rectification work The terms and conditions of the policy do not require the insurer to check rectification work arranged by the complainant to fix a property defect, before a claim is settled for accidental loss or damage to the complainant’s property. The insurer was not required to check the balcony rectification work arranged by the complainant in May 2016. Insurer to complete repairs after balcony defects rectified, or cash settle The insurer is to complete the repairs to the garage ceiling once the complainant has completed repairs to rectify the balcony defects. Determination | Case number: 649755 Page 5 of 5 Alternatively, subject to the insurer obtaining an actionable quote, the parties may agree in accordance with the terms of the policy to cash settle the cost to repair the garage ceiling, in finalisation of this claim. 3 Supporting information 3.1 AFCA approach to this dispute This complaint has been determined based on what is fair in all the circumstances, having regards to the relevant law, good industry practice, codes of practice and previous decisions of AFCA or its predecessor schemes (which are not binding). A full exchange of relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any issues raised. All of the provided material has been reviewed and considered. The parties have raised various issues in their submissions to AFCA. Commentary in this determination is restricted to only those issues relevant to the outcome.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.