Home / Suncorp Group / Determination 649689
Determination 649689
Poor management and delayed handling of a water damage claim, including defective repairs by the insurer's repairer
Summary
After lodging a water damage claim, the complainant suffered delays and poor management by the insurer's repairer, leading to further water damage after repairs. The insurer later cash settled and settled the additional damage. AFCA ordered $2,000 for non-financial loss.
Non-financial loss compensation is available under AFCA Rule D3.3 where the complainant suffers an unusual degree of inconvenience caused by the insurer's claim handling.
Issues
- Poor claim handling primary · upheld
“Claim notes reveal poor claims management of initial claim; the insurer has not addressed those concerns.”
- Delay secondary · upheld
“Claim notes reveal delays in claims handling; the matter only proceeded to resolve after the complaint was referred to AFCA.”
- Third-party or outsourcing failure secondary · upheld
“The delay with maintenance repairs can be attributed to the failure by HR to properly identify the issues with the roof.”
Subjects and remedies
home or building damagepay non financial loss
Text of the determination
Determination
Case number 649689
Financial firm AAI Limited
Determination | Case number: 649689 Page 2 of 7
Case number: 649689 9 January 2020
1 Determination overview
1.1 Complaint
The complainant held a Home and Contents Insurance Policy with the financial firm
(insurer) and lodged a claim on 1 February 2019 for water damage. The claim
recorded that water had run through the roof and mould grown on the walls and
subsequently on the floors.
The insurer accepted liability for the damage, but a dispute arose over the
management and conduct of HR, the insurers repairer. This led to the cash settlement
of the claim for carpet damage after the initial repairs were said to have been
completed.
After settlement of the initial claim, the complainant notified the insurer on 2 May 2019
of further water damage due to the failure to adequately complete the previous
repairs.
When this further complaint was not resolved the complainant lodged the complaint
with AFCA. The complainant acknowledges that the insurer has now settled the claim
for the additional damage but seeks compensation for non-financial loss due to the
manner in which the insurer handled the claim and the stress and inconvenience
caused.
1.2 Issues and key findings
Is the complainant entitled to compensation for non-financial loss?
The complainant is entitled to compensation for non-financial loss.
The available information indicates the complainant suffered an unusual degree of
inconvenience after lodging the initial claim. Further the information exchanged
indicates the complainant suffered further inconvenience and delay following
notification of the additional damage.
I consider it fair in the circumstances the compensation for non-financial loss be paid
to the complainant.
1.3 Determination
This determination is in favour of the complainant.
The insurer is required to pay the complainant $2,000 compensation for non-financial
loss pursuant to Rule D3.3 of the AFCA Rules. Compensation is payable within 14
days of the complainant’s acceptance of this determination.
Determination | Case number: 649689 Page 3 of 7
2 Reasons for determination
There has been a full exchange of material between the parties and each party has
had the opportunity of addressing the issues that arise from the information
exchanged.
This determination follows consideration of all the information and is based on what is
fair in all the circumstances, having regard to the relevant legal principles, terms of
the policy, good industry practice including codes of practice and prior determinations
where applicable.
2.1 Is the complainant entitled to compensation for non-financial loss?
Compensation for non-financial loss is payable under the AFCA rules
Under Rule D3.3 of the AFCA Rules (as set out in section 3 of this determination),
AFCA may award compensation capped at $5,000 for non-financial loss where a
complainant incurs an unusual degree or extent of physical inconvenience or time
taken to resolve a complaint or interference with the expectation of enjoyment or
peace of mind.
AFCA takes a conservative approach when awarding compensation for non-financial
loss and does not award compensation merely because a complainant may have
suffered some degree of inconvenience and anxiety.
It is expected that a complainant will be moderately robust and bear a normal degree
of inconvenience when problems occur.
Particulars of complaint
The complainant says that after lodging her claim for water damage in February 2019,
nothing happened until 9 May 2019.
After repairs had allegedly been completed further water damage was sustained to
the property, in May 2019 because the insurer had not properly completed the
repairs.
The complainant says that for the next four and a half months nothing was done with
the only work completed being the clean up of surface mould.
At the time the complaint was lodged with AFCA in July 2019 the complainant wanted
the insurer to complete the repairs, settle the mould remediation and pay $4,000 by
way of compensation for non-financial loss.
Claim notes reveal poor claims management of initial claim
The insurer’s claim notes record:
1 February 2019 - complainant told that HR appointed to manage claim
Determination | Case number: 649689 Page 4 of 7
18 February 2019 – refers to a review from a spreadsheet with HR looking after
building and carpet repairs
14 March 2019 – complainant notifies insurer that there are issues with the carpet
selected by HR. It is not matching although matching carpet is available
18 March 2019 - complainant notifies insurer that HR wants her to sign off on non-
matching carpet despite matching carpet being available. Complainant also notes
that cabinets are not going to match
27 March 2019 - HR call insurer confirming the complainant is disputing the carpet
quote. HR says it will cash settle. There is no reference to further attempts to find
matching carpet
27 March 2019 – Insurer calls complainant to discuss cash settlement.
Complainant informs insurer that a wall also needed repainting. The insurer does
not follow this up as it is not mentioned by HR.
It is clear from the claim notes and the complainant’s comments that the complainant
was frustrated in dealing with HR. HR does not appear to have addressed the
complainant’s concerns. The insurer has not addressed those concerns. This
frustration has led to the complainant’s call for a cash settlement of the carpet claim.
Claim notes reveal delays in claims handling
The complainant contacted the insurer on 2 May 2019 following further water
damage. The claim note records:
……. After all repairs have been complete she has received a c/s for the carpet. It
has started raining again and the exact same issue has occurred….
The insurer advised the complainant that the claim was with HR. The complainant
advised she was not happy with this and wanted the insurer to deal with the matter.
Despite this, the insurer advised the complainant that as HR had completed the
previous repairs, HR would have to be the ones to fix the damage.
The complainant next contacted the insurer on 11 May 2019 with a further complaint
regarding HR. The claim note records:
- Cancelled …as was sitting ‘authorised awaiting consignment’
It would appear the make safe work had not been completed at that time.
On 14 May 2019 HR advised the insure r that a roof report was received and further
maintenance was required. A claim note dated 21 May 2019 records HR’s comment
that both maintenance issues could have contributed to damage and further that the
maintenance issues required repair before further work could be completed.
Determination | Case number: 649689 Page 5 of 7
Neither the insurer nor HR have explained why these maintenance issues were not
identified when HR originally attended the property in February 2019.
The complainant notified the insurer on 28 May 2019 that the maintenance had been
completed.
On 24 June 2019 the complainant sought an escalation of the matter as no further HR
had not completed any further repairs.
It is only after the complaint was referred to AFCA that the insurer has arranged for a
different repairer, BBS, to deal with the matter. This occurred on 16 July 2019.
BBS has roof plumber T to inspect the roof. T identified the additional maintenance
issues. Photographs accompanying the reports by T show clear issues with the roof.
This should have been seen by HR. T confirms that the complainant would not have
been aware of these damages.
BBS arranged for L to attend to inspect the mould. On 6 August 2019 L identified the
mould and confirmed that the mould restoration could not have been completed until
the maintenance was completed.
Complainant has suffered an unusual degree of inconvenience
In my view, the complainant has suffered considerable physical inconvenience and
stress associated with this dispute over two distinct periods, all relating to the conduct
of HR and the consequences of that conduct.
The delay with maintenance repairs can be attributed to the failure by HR to properly
identify the issues with the roof back in February 2019.
The complainant was inconvenienced because of HR’s failure to properly asses s the
nature of the damage and whether the carpet could be replaced with matching carpet.
This occurred during the first period of the claim between 1 February 2019 and 27
March 2019.
The complainant suffered further physical inconvenience and time taken during the
second period of the claim from 2 May 2019 because of the failure by HR to properly
identify the maintenance issues. There were delays added to this by the failure to
have repairs completed despite the complainant notifying that the maintenance
repairs had been completed on 28 May 2019.
It is not until the insurer appointed BBS in July 2019 that the matter proceeds to
resolve. It is then not until the insurer provides a further Notice of Response that any
resolution of the matter becomes availab le.
Determination | Case number: 649689 Page 6 of 7
Insurer has cash settled the claim
In a further Notice of Response on 3 October 2019, the insurer advised it would
review any quotes supplied by the complainant for mould and laundry damages,
although it required these costs to be broken down in order to be appropriately
assessed.
The complainant has subsequently provided the relevant quotes in the claim with
respect to the repairs has been cash settled.
Insurer to pay complainant compensation for non-financial loss
In my view, the complainant has experienced an unusual degree of inconvenience
arising from this claim from February 2019 through to October 2019.
Having considered the issues involved and the timeframe taken to resolve the claim, I
believe it is fair in the circumstances that the insurer pa y the complainant $2,000
compensation for non-financial loss pursuant to Rule D3.3 of the AFCA Rules.
Payment of the compensation should be made within 14 days of the complainant’s
acceptance of this determination.