Home / NAB / Determination 644777
Determination 644777
Default interest charged on construction loan after bank failed to follow drawdown inspection policy
Summary
A property development company complained that the bank advanced construction funds without the site inspections required by its policy and then charged default interest. AFCA found the bank failed to exercise care and skill and ordered a refund of 30% of the default interest.
The bank owed a duty of care and skill as a diligent banker and failed to follow its own inspection policy, so default interest was unfair given its contribution to the cost overruns.
Issues
- Incorrect fees or charges primary · upheld“I do not consider it was fair for the bank to charge default interest on the loan in circumstances where the bank did not adequately manage the risk at the start of the project.”
- Other secondary · upheld“the bank did not exercise care and skill in its dealing with the company when it advanced progress payments without conducting site inspections”
Subjects and remedies
small businessrefund fees or charges
Related
Text of the determination
Determination
Case number 644777
Financial firm National Australia Bank Limited
Determination | Case number: 644777 Page 2 of 9
Case number: 644777 26 February 2021
1 Determination overview
1.1 Complaint
The complaint is about the following facilities which the financial firm (the bank)
provided to the complainant company in September 2010:
a market rate facility loan (loan) of $1,497,200 to finance the construction of
townhouse development project (the project)
a $50,000 overdraft facility (the overdraft), which was cancelled on 7 July 2015.
The company says:
the bank did not follow its internal policies around the drawdown of the loan funds
in the initial stages of the project, in that it failed to have progress valuation reports
completed or site inspections completed by the banker
the loan term was extended, and further loan advances made when the bank
would have known the project was impaired and would need tighter restrictions on
the advance of further funds
the bank should not have charged default interest on the loan as its failure to follow
internal policy contributed to the need for extra funds to be required to complete
the project.
1.2 Issues and key findings
Did the bank follow its internal policy when funds were advanced?
The bank has failed to produce documentation to show it completed site inspections.
It would have been evident that progress payments were being advanced without the
works being completed had site inspections been completed in line with its policy.
What is an appropriate outcome for this complaint?
It is fair the bank should refund the company 30% of the default interest charges.
1.3 Determination
This determination is partly in favour of the complainant.
The complainant company has 30 days to accept the determination. If the
determination is accepted, the bank has 14 days to pay $90,066.16 to the company‟s
nominated account.
The bank will not be required to pay the compensation if the determination is not
accepted by the complainant company.
Determination | Case number: 644777 Page 3 of 9
2 Reasons for determination
2.1 Did the bank follow its internal policy when funds were advanced?
The bank had obligations to exercise care and skill
The bank had obligations to the company when the loan was provided to the
complainant company in 2010. These obligations arose under:
section 12ED of the Australian Securities and Investment Commission Act 2001
(ASIC Act) – where the bank warrants to supply financial services with due care
and skill and
section 25.1 of the 2004 version Code of Banking Practice (COBP) – where the
bank must exercise the care and skill of a diligent and prudent banker when
forming its opinion about the company‟s ability to repay the facilities .
The bank ’s internal policy required site inspections be completed
The bank has provided a copy of its internal policy for progress drawdowns for
property developments like the project in this complaint. The policy requires the
banker to request its internal valuation team:
“…to comp lete an initial internal inspection and valuation and then a subsequent
inspection at each stage of the building construction…”
The purpose of a site inspection is to verify that the invoiced works have been
completed and to confirm that the construction works are progressing as per the
drawdown schedule.
Once the site inspection has been completed, a report (either a formal report or a
short file note) should be completed to document the progress and confirm the works
are complete. Photographs are often taken to document the progress at the time of
the inspection.
The bank has been unable to provide copies of the file notes documenting site
inspections or copies of internal valuations completed. The bank advised the file
notes and valuation reports had been archived.
The case manager requested the bank provide a statutory declaration to confirm this
on 31 January 2020, and the bank subsequently confirmed the original file had been
archived and it was endeavouring to locate it in its response of 14 February 2020. As
of the date of this determination, the file has not been found. This means there is no
information to show the bank complied with its policy requiring inspections and
valuations.
Determination | Case number: 644777 Page 4 of 9
The loan was fully drawn before the construction was finished
The land was purchased in 2008 and a loan for $700,000 was provided by the bank.
The bank was provided with a fixed price contract stating the cost of the project was
$800,000 and that the project would take 368 days to complete.
The first loan advance occurred in May 2011 and the loan was fully drawn by
December 2012.
If regular site inspections had been completed, it is reasonable to infer that:
the bank would have realised that the property was not completed at the time of
the final loan advance in December 2012 and
with the loan fully drawn and the project an estimated 80% complete, it would have
been evident that funds had either been advanced for works invoiced but not yet
completed, or that funds had been used to cover costs that had not been budgeted
for or included in the original project costings.
I infer from the bank‟s failure to provide evidence of its site inspections throughout the
period May 2011 to December 2012 that the bank either did not instruct its internal
valuation team to complete the site inspections or had failed to complete their own
inspections and simply advanced the funds when requested by the company.
The bank did not act on any red flags with the project
The bank obtained a valuation report at the expiry of the loan in October 2014 and
approved an increase of $205,000. The valuation report:
raised several concerns about the project, noting the improvements to the
premises presented as a „shell‟ and that construction works were underway but
had not progressed for a period of time
noted that discussions with the borrower (presumed to be the builder) confirmed
that the funds spent on the project to that point were in line with costs indicated in
the building contracts
confirmed the funds invested into the project at that stage would be $532,843
(exclusive of GST). At the time the report was prepared, the full amount of
construction funding provided by the bank ($797,200) had been drawn. There is no
information to show the bank contacted the valuer to confirm this and allow the
valuer a chance to amend the report.
recommended a Quantity Surveyor be appointed to confirm the cost estimate to
complete the project.
I accept that it is not normal practice for a Quantity Surveyor to be appointed to
overview a project of this size, as the cost of doing may be prohibitive in relation to
the overall cost of the project. However, I consider it would have been prudent to do
so having regard to the concerns raised in the valuation report.
Determination | Case number: 644777 Page 5 of 9
I am also satisfied that a Quantity Surveyor (if appointed) would have identified the
funds advanced for the project to October 2014 had been either spent on variations or
overruns (which should have been paid by the company) or that they were not spent
on the construction project at all.
Had the bank promptly addressed the matters raised in the valuation report, the bank
would have been in a better position to impose tighter controls on the payment of
subsequent invoices presented by the builder.
The bank imposed tighter controls on the project in May 2015
The fixed price building contract showed a n expected build time of 368 days at a cost
of $800,000. At the time the loan was fully drawn in December 2012, a period of more
than 580 days had passed, and by the time the valuation report was received in
October 2014, more than 1,250 days had passed.
At this time, the bank changed its approach on how loan proceeds were advanced.
The variation to the loan contract extended a further $402,800 to the company to
cover $95,000 of projected interest expense, $50,000 in interest expense already
incurred and $258,000 to complete the works on the project.
The contract confirmed funds were to be advanced only upon presentation of
invoices. By implementing these tighter restrictions , the funds should only have been
advanced upon the presentation of invoices.
The invoices issued by the company saw the loan balance increase from $1,497,200
to $1,900,000 between June 2015 to February 2016, when a further $50,000 was
approved to allow the company to finalise the project and have the certificate of
occupancy issued.
The bank agreed to advance further funds to finalise the project
In May 2017, the bank met with the majority shareholder of the company and a
second mortgagee who had taken a financial interest in the project in May 2015 to
assist with resolving a dispute between the company‟s shareholders.
The builder had advised there was further funding required to finalise the project a nd
the director and second mortgagee were seeking an understanding of where things
stood.
The bank advised them that it had opted to impose default interest in September 2016
after the second mortgagee had declined to sign a new contract and security
documents in July 2016.
Following further investigation, the majority shareholder and second mortgagee
authorised the bank to advance the funds required to finish the project as long as the
bank sought their authorisation to do so. Accordingly, further amounts totalling
Determination | Case number: 644777 Page 6 of 9
$83,640 were advanced to allow certificates of occupancy to be issued and the
properties sold.
The bank continued to charge default interest
Following the discussions between the bank, majority shareholder and second
mortgagee, the parties worked together to push the project to completion. The bank
continued to charge default interest.
Despite the project being five years past its expected completion date and additional
borrowings of $452,800, the bank charged default interest approximately 10% higher
each month until the property sales occurred.
The bank did not exercise care and skill
In the circumstances, I find the bank did not exercise care and skill in its dealing with
the company when it advanced progress payments without conducting site
inspections and failing to address the matters raised in the October 2014 valuation
report.
2.2 What is an appropriate outcome for this complaint?
The company was responsible for the major problems with the project
As previously noted, the bank has obligations to its customer when it provides a loan.
However, t he bank‟s role is not to manage the project but to act as a financier for the
project. It is the company‟s role to manage the project and ensure timely completion.
If the shareholders of the company place control of the project in the hands of one
director and leave the project to him, the responsibility to manage the project in all
aspects (timeliness, cost management etc.) falls to that person.
It is not the fault of the bank if the project was not profitable. In this instance, the
directors and shareholders placed their faith in the builder to responsibly manage the
project and produce a profitable investment.
It appears from the available information that the project had been on foot for over five
years before a director (and majority shareholder) sought to understand why the
project was so far behind the projected completion date. In my view, this shows that
the company contributed heavily to the failure to generate the expected profitability.
The bank’s failure to follow policy has contributed to the increased costs
However, the bank‟s failure to complete site inspections prior to advancing progress
payments from the loan has also contributed to the increased total cost of the project.
I do not consider it appropriate or fair for the bank to contribute to the costs
associated with the construction work itself. That was the responsibility of the
complainant company. However, the bank‟s decision in August 2016 to impose
Determination | Case number: 644777 Page 7 of 9
default interest does not account for its failure in the earliest stages of the project to
appropriately manage its role which would have brought the progress issues to the
parties‟ attention and given impetus to the project .
I do not consider it was fair for the bank to charge default interest on the loan in
circumstances where the bank did not adequately manage the risk at the start of the
project.
The bank should compensate the company
The bank commenced charging default interest in August 2016 and did so until the
property settlements were completed, and the loan was repaid in full (other than a
period of 14 days in September 2016).
I consider it fair for the bank to refund 30% of the default interest charged on the loan
to appropriately and fairly reflect the impact of its failure to follow its policy in the initial
drawdown phase of the loan had to the costs of the project. It also fairly reflects my
view that the company should be responsible for 70% of default interest because of
its failures identified above.
In calculating the amount to be reimbursed to the company, I have applied the interest
rate applicable just prior to the default interest being charged (5.945% pa, per the
loan account statement) for the period 2 August 2016 to 16 September 2016 and the
rate applied to the loan for the period 17 September 2016 to 30 September 2016
(5.76% pa as per the loan account statement) for the remaining period (1 October
2016 -19 March 2018).
In applying these rates, I have considered the Reserve Bank of Australia‟s Official
Cash Rate (OCR) as an appropriate indicator as to whether further rate movements
should be applied. The OCR was unchanged at 1.50% between 3 August 2016 and 4
June 2019. Accordingly, I have left the rates applied to my calculations unchanged.
The total default interest charged on the loan account between 2 August 2016 and the
loan closure on 19 March 2018 was $300,220.53. The bank should reimburse
$90,066.16 to the company‟s nominated account if the complainant accepts this
determination.
Determination | Case number: 644777 Page 8 of 9
3 Supporting information
3.1 AFCA process and approach
This complaint has been determined based on what I consider is fair in all the
circumstances having regard to legal principles, good industry practice, applicable
industry codes or guidance, and previous relevant determinations of AFCA or its
predecessor schemes (which are not binding).
There has been a full exchange of all material information relied on for this
determination and each party has had the opportunity to address any issues raised by
the other. I have considered all relevant information provided by the parties, both
before and after the preliminary assessment was issued, to reach my decision.
3.2 Reimbursement calculation
Date Actual
rate
Interest
charged
Amended
rate
Amended
interest
charged
Difference
31/08/ 2016 15.870% $24,580.24 5.945% $9,207.91 $15,372.33
05/09/ 2016 15.870% $4,237.97 5.945% $1,587.57 $2,650.40
16/09/ 2016 15.870% $9,323.54 5.945% $3,492.66 $5,830.88
30/09/ 2016 5.760% $4,306.87 5.760% $4,306.87 $ -
31/10/ 2016 15.770% $ 26,109.86 5.760% $9,536.64 $16,573.22
30/11/ 2016 15.770% $ 25,267.61 5.760% $9,229.01 $16,038.60
30/12/ 2016 15.770% $ 25,267.61 5.760% $9,536.64 $15,730.97
31/01/ 2017 15.770% $ 26,952.12 5.760% $9,536.64 $17,415.48
28/02/ 2017 15.770% $ 23,583.10 5.760% $8,613.74 $14,969.36
31/03/ 2017 15.770% $ 26,109.86 5.760% $9,536.64 $16,573.22
Determination | Case number: 644777 Page 9 of 9
Date Actual
rate
Interest
charged
Amended
rate
Amended
interest
charged
Difference
28/04/ 2017 15.770% $ 23,583.10 5.760% $8,613.74 $14,969.36
31/05/ 2017 15.770% $27,794.37 5.760% $10,151.91 $17,642.46
30/06/ 2017 15.770% $25,267.61 5.760% $9,229.01 $16,038.60
31/07/ 2017 15.770% $26,109.86 5.760% $9,536.64 $16,573.22
31/08/ 2017 15.770% $26,109.86 5.760% $9,536.64 $16,573.22
29/09/ 2017 15.770% $24,425.36 5.760% $8,921.37 $15,503.99
31/10/ 2017 15.770% $26,952.12 5.760% $9,844.28 $17,107.84
30/11/ 2017 15.770% $25,267.61 5.760% $9,229.01 $16,038.60
29/12/ 2017 15.770% $24,425.36 5.760% $8,921.37 $15,503.99
31/01/ 2018 15.770% $27,794.37 5.760% $10,151.91 $17,642.46
28/02/ 2018 15.770% $15,207.79 5.760% $1,475.88 $13,731.91
19/03/ 2018 15.770% $2,741.91 5.760% $1,001.49 $1,740.42
TOTAL $300,220.53
30% of $300,220.53 = $90,066.16
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.