Text of the determination
Determination
Case number 643786
Financial firm Allianz Australia Insurance Limited
Determination | Case number: 643786 Page 2 of 9
Case number: 643786 1 June 2020
1 Determination overview
1.1 Complaint
The complainants lodged a storm damage claim for their home building, which the
financial firm (insurer) accepted. After the complainants reported repair quality issues,
the insurer agreed to cash settle for rectification works. It declines liability for
replacing timber floorboards because it says the complainants and not its builder
caused this damage.
The complainants are dissatisfied with this response and the claim handling. They say
the insurer’s builder’s failure to install adequate expansion joints caused damage to
flooring, walls and windows.
1.2 Issues and key findings
Is the insurer required to pay the complainants’ floorboard quote?
The insurer is required to pay part of complainants’ builder’s flooring quote in
accordance with the terms of this determination.
Is the insurer required to pay other costs?
The insurer is required to pay the complainants for billiards table assembly ($595) and
windows/glass ($700). Statutory i nterest under section 57 of the Insurance Contracts
Act 1984 (the Act) applies to the two amounts payable, from 16 April 2019. The
insurer is required to pay a further amount of $3,750 for temporary accommodation.
Interest is not payable on this amount.
Th e insurer is not required to pay AA’s report cost ($880).
The insurer is required to compensate the complainants $1,000 (total) for non-
financial loss due to the inconvenience they experienced during the claim and repairs.
1.3 Determination
This determination is partially in favour of the complainants.
Within 14 days of the complainants’ acceptance, t he insurer is required to:
pay the complainants $45,000 (for the sake of clarity, this includes the $20,565.60
previously offered, if that amount has not already been paid)
pay the complainants $595 for billiard table assembly, $700 for window/glass and
$3,750 for temporary accommodation
pay the complainants $1,000 (total) in non-financial loss compensation.
Determination | Case number: 643786 Page 3 of 9
2 Reasons for determination
2.1 Is the insurer required to pay the complainants ’ floorboard quote?
Complainants say insurer’s rectification offer is insufficient
The complainants lodged a claim in March 2017, for storm damage to their home
building. The insurer accepted the claim and authorised repairs by builder JL. The
complainants reported repair quality issues. The insurer agreed to cash settle some
rectification works to flooring (including sanding and replacing some areas), skirting
boards and painting. JL’s costing of the agreed rectifications is $20,565.60.
The complainants are dissatisfied with this response and the claim handling and say:
repairs should have taken three months, but remain unfinished years later
the insurer and its agents caused inconvenience and delays through multiple
instances of inadequate works and responses
primarily, JL installed insufficient expansion joints in the floorboards, so JL’s repairs
have caused floor cupping and pushed walls and windows outwards.
The complainants want the insurer to cash settle the claim for $90,945. This is based
on their remedial builder’s quote for flooring rectification ($71,940), a billiard table
reassembly quote ($595), glass installation quote ($1,400) and accommodation quote
($17,010) during the works.
Insurer says complainants’ failure caused floor ing damage
The insurer declines liability for the cupped and warped flooring and damaged walls
and windows. It disputes this occurred due to the storm or because of JL’s repairs.
The insurer says the damage occurred due to building defects pre - dating JL’s repairs,
which the complainant did not address as requested. Based on this view of the cause
of damage, the insurer says:
the complainants have not established a valid claim, as they have not shown an
event the policy covers caused the damage
further, policy conditions excluding cover for pre-existing faulty design or
workmanship apply, allowing it to decline the claim.
As the parties dispute the cause of the damage, the proximate cause needs to be
ascertained based on the information the parties provided.
Proximate cause is the dominant or operative cause of the loss
Damage can have more than one cause. When deciding whether the policy covers
the damage, we need to identify what the proximate cause of the damage was.
This is a question of fact depending on the circumstances in each complaint. The
proximate cause is not necessarily the first or last or the sole cause of the loss. It is
Determination | Case number: 643786 Page 4 of 9
the effective, dominant or operative cause of the loss. If there are several causes
operating at the same time, AFCA will co nsider each one to determine which cause
set the train of events in motion.
Courts have said that if one cause would have resulted in the harm in any case and
the other would not have done so in the absence of the first, then the first is the
proximate cause.
Insurer says its experts confirm pre-existing faults caused flooring damage
The available materials confirm that JL included repairs to the surface of water
damaged timber flooring in the initial repair estimate, but not full flooring replacement.
Following variations on the repair SOW, in August 2018, JL appointed a licensed
building consultant (AA) to assess whether the flooring’s structure was also water
damaged.
AA completed a technical and defects inspection report, recommending replacement
of are as of the flooring’s structure due to water damage. These reflected the claimed
areas of storm-driven rain entry (through windows and the front door), plus near the
bathroom. He also recommended a barrier beneath the front door to prevent water
‘blow back’ during rain and inserting end plates in exterior windowsills to avoid the
likelihood of excess water entering the floor area.
The insurer says the complainants then told JL that they had carried out the
recommended works to the windowsill and door. JL then arranged for the floor
structure repairs and replacement of the timber flooring. After the complainants raised
concerns about the repair quality, the insurer arranged for a building consultant (RD)
to review and report on any substandard repair work by JL. RD completed a
causation report stating there were areas of substandard and incomplete work,
including incorrect sealant on the new timber flooring, misaligned skirting, poor
painting and damaged doors.
RD noted AA’s door and windowsill recommendations had not been completed by the
complainants and reported water staining near the front door, which the complainants
attributed to recent storms.
The complainants were dissatisfied with the extent of rectifications suggested and the
timber flooring ’s conditi on and said that the walls and windows were being pushed
outwards by the flooring. The insurer arranged a site meeting between the
complainants, JL and RD in March 2019. The insurer says at this meeting the
complainants agreed to carry out the windowsill-end and door-stop works. The insurer
provided RD’s meeting minutes , which it says confirm:
- … The insured accepts and agrees to rectify the moisture and water ingress
issues in the entry, snooker/rumpus room and hallway, detailed in the [AA]
report (dated 20/08/18) obtained.
Determination | Case number: 643786 Page 5 of 9
- The insured accepts and agrees to rectify the moisture and water ingress
issues in the entry as per the [RD] report, recommendations (dated 14/12/19).
The insurer says its loss assessor’s (CC’s) and experts’ (JL’s, RD’s and AA’s) views
confirm the windowsill and door allowed water entry. It says the complainants did not
address this or did so too late. On this basis the insurer says ongoing water entry is
the proximate cause of the timber flooring, wall and window damage , rather than JL’ s
installation. Further, the insurer says that if the complainants had not told JL that the
windows and door works were completed, JL would not have laid the flooring.
After the site meeting, the complainants arranged for AA to reattend in April 2019 and
complete a technical and defects report on the timber flooring. AA reported that
inadequacies in JL’s flooring installation caused the damage. Specifically, he stated:
The incidence of minor defects … is considered to be: Not Applicable . The
incidence of ma jor defects … is considered to be: poor relative to the flooring laid
on the ground floor … It is my opinion that the flooring has not been acclimatised
and the omission of expansion joints is the cause of the buckling and swelling of
the floorboards … Significant Items: Omission of expansion joints; Failure to
acclimatize flooring material appropriately prior to laying; Timber cupping and
pushing timber frame walls, window and door units out … The corking that would
have formed the expansion joint at the end of the flooring has been completely
squeezed out. The boards are hard up against the door frame.
After the insurer asked AA for further information, specifically regarding the cause of
the damage, he confirmed his view by email of 16 September 2019:
… My second report was after the flooring contractor installed the new flooring, he
did not follow my recommendations and failed to install adequate expansion joints
in the floor. The failure to install adequate expansion joints or acclimatise the
flooring correctly is the reason that the walls have been pushed out …
I note with sig nificant concern that within AA’s email of 16 September 2019, he also
says:
I have issued two reports for the property ... In neither of those reports did I
suggest that the minor water leaks were the cause behind the damaged [sic]. On
my first inspection of the property, there had been no damage caused to the
external walls. In my first report … I was not concerned about any minor leaks
that had occurred previously from the corner windows units, as I water tested
these units and found them to be satisfactory.
However, I am in satisfied that this is in stark contrast to AA’s report of 20 August
2018, wherein he says:
Determination | Case number: 643786 Page 6 of 9
I inspected the aluminium window and door units that are located in the living
room on at the northwest and southwest end of the building. These units are a
commercial type window and door frame and have a sub-sill which replaces the
need for a common type sill flashing such as Alcor or PVC. A commercial sub-sill
is an aluminium channel; generally, each side is approximately 30mm in height
and slightly wider than the width of the window or door frame. When installed the
sub sills need to be closed at each end as the sill acts as a water trap and has
weep holes for the water to disperse. Unfortunately, as these unit are commonly
used in commercial application the installer/s do not generally take into account
better building practices that are more suitable in a residential type application
and tend not to fold the ends of the sub sills up, but rather use a bead of Sikaflex
or similar to close of the end of the sub-sill. As the window units located on the
ground floor northwest and southwest corners of the building are subject to strong
wind and rain, it is likely that the sub-sill is unable to disperse that water quick
enough, and therefore water builds up in the sub-sill and overflows over the top of
the Sikaflex allowing water ingress into the floor area and this is why there is
severe water staining around these areas.
I am satisfied that this apparent contradiction in statements from AA raises concern
regarding the conclusions he has reached in subsequent correspondence.
I am also satisfied that whilst the complainants advised that the work suggested by
AA in his initial report had been completed, at that time it in fact had not been
completed.
This raises concerns regarding the credibility of the information provided by the
complainants and the reliability of any expert conclusions based upon that
information.
On the other hand, there is no doubt that the o riginal repairs completed by JL were
unsatisfactory and required rectification.
The parties dispute whether the current problems are related to the compl ainant’s
failure to conduct the work recommended by AA or the poor-quality rectification work
completed by JL, including an alleged failure to install adequate expansion joints and
an alleged failure to acclimatise the flooring. I note that the insurer challenges the
latter two allegations.
Each party has presented evidence as to whether the rectification work by JL included
expansion joints and whether the flooring was acclimatised.
The insurer provided JL’s written comments of 4 September 2019 , about the flooring
repairs and RD’s caus ation report of 12 July 2019. The insurer says that these reports
confirm that JL acclimatised the timber appropriately and installed expansion joints.
RD concluded the damage was caused by water ingress based on:
the inclusion of the windowsill /door defects in AA’s first report
Determination | Case number: 643786 Page 7 of 9
the complainants’ failure to address these
the subsequent flooring damage
his view is that, as AA omitted to consider the effect of moisture from the
windowsills/doors in his second report, AA’ s view on the cause of flooring damage
is flawed.
The insurer also relies on annotated photographs of the timber flooring in AA’s
second report. AA noted the cork in perimeter expansion joints would have been
totally pushed out by the timber s’ expansion. The insurer says this confirms JL
installed expansion joints. The insurer says this also contradicts the complainants’
and AA’s views on the cause of damage.
On the other hand, JL’s views on the steps they took during the building process are
retrospective and not supported by contemporaneous records or photographs. RD
noted the minimum necessary expansion joints included intermittent joints. No
evidence of these (as opposed to perimeter joints) was provided. No explanation as to
why the flooring had not cupped and pushed the walls out due to the windowsill/door
issues before JL’s installation was provided.
Having carefully reviewed all the exchanged information, I am not satisfied that there
is sufficient information to establish whether JL’s acclimatisation of the flooring was
adequate or whether it has contributed to the further damage requiring repair.
However, I am satisfied that whilst JL had installed some expansion joints, overall the
rectification work completed by JL was unsatisfactory and has contributed to further
damage.
Equally, I am satisfied that the complainants ’ failure to complete the works,
recommended by AA, has also contributed to the damage at the property in a
significant way.
The complainants provided a remedial bu ilder’s flooring quote of $71,940. They want
the insurer to cash settle the cost of the works, so they can arrange their own repairs.
The insurer has declined the claim for replacement of the flooring and has provided a
quote of $20,565.60, for rectification of the previous repairs.
I am not satisfied that the material exchanged is sufficient to reach a precise
conclusion as to the respective contribution to the damage, between the failure of the
complainants to complete the work recommended by AA and the inadequate repairs
of JL.
To bring finality to this complaint I propose to do what I consider is fair in the
circumstances, having reviewed all the exchanged material.
The insurer is required to pay the complainants $45,000, to finalise its obligations to
the complainant regarding the repairs. This includes the offered amount of
Determination | Case number: 643786 Page 8 of 9
$20,565.60, if it has not already been paid. The insurer is not required to pay interest
on this amount.
2.2 Is the insurer required to pay other costs?
Insurer is required to pay further costs
The insurer is required to pay the complainants’ quote for the billiards ’ table to be
reassembled ($595). This is because there is no dispute the insurer paid for the first
part of this quote (to dissemble the billiards table) and I accept the table will need
reassembly upon its return.
The complainants provided a window repair quote by PP for $700. The complainants
say glass repairs will cost double. The insurer did not challenge the amount of the
original quote.
Given PP did not support the complainants’ own view that repairs will cost double the
amount quoted, the insurer’s liability for this quote is limited to $700.
Statutory interest under section 57 of the Insurance Contracts Act 1984 (the Act) on
the two amounts applies from 16 April 2019, if they have not already been paid.
Insurer is not required to pay AA’s report c osts
Under our Rules, AFCA can require a financial firm to reimburse the cost of
professional reports, up to a maximum of $5,000.
Given the apparent contradiction in the information provided by AA, I am not satisfied
that the insurer should be required to pay for the cost of this report.
Insurer is required to pay temporary accommodation during floorboard repairs
During initial repairs, the insurer provided the complainants with temporary
accommodation in a serviced apartment.
The complainants provided a quote for 28 nights in this apartment at $375 per night,
for the further flooring repair period he says is now required.
Given my findings in relation to the proximate cause of the damage requiring repair, I
am not satisfied that 28 nights is appropriate However, there is little information on
which to determine the time the covered repairs will take.
Again, based upon all the exchanged material and doing what is fair in the
circumstances, the insurer is to pay the complaints the additional amount of $3,750,
for ten nights temporary accommodation.
This will finalise the insurer’s obligations and interest is not payable on this amount.
Determination | Case number: 643786 Page 9 of 9
Insurer is required to pay $1,000 non-financial loss compensation
Under our Rules, AFCA may require a financial firm to pay compensation for non-
financial loss. This includes claims for stress or inconvenience caused by an error of
the insurer. The maximum amount we can award for non-financial loss is $5,000 for
each claim of loss. We will only award this type of compensation if there has been an
unusual degree or extent of inconvenience. If we do award compensation, it is
unlikely to be substantial.
I accept the complainants experienced an undue extent of stress and inconvenience
caused by JL’s inadequate repairs.
They will now reside in temporary accommodation for a second attempt at repairs. I
accept this is a physical inconvenience they otherwise would have avoided.
Given the above, the insurer is required to pay the complainants $1,000 (in total) in
non-financial loss compensation. Interest is not payable on this amount.