Partial decline of flood/storm building damage claim as pre-existing or earth movement damage; cash settlement amount disputed
Text of the determination
Determination
Case number 643774
Financial firm RACQ Insurance Limited
Determination | Case number: 643774 Page 2 of 12
Case number: 643774 20 December 2019
1 Determination overview
1.1 Complaint
The complainant holds a home and contents insurance policy with the financial firm
(insurer) and lodged a claim on 5 February 2019 for flood/storm related damage to his
property.
The insurer accepted liability for the damage and settled the contents claim for the
sum insured of $30,000 less $500 excess.
A dispute has arisen as to the extent of flood/storm damage to the building. The
insurer says some of the damage claimed is not flood/storm related but most likely
was pre-existing and caused by soil movement. The insurer offered to settle the
building damage for $11,909.04.
The complainant disputes the insurer’s decision and says all the damage is a result of
the event.
1.2 Issue and key findings
Is the insurer entitled to partially decline the claim?
The panel accepts that the insurer is entitled to limit its liability as some of the
damage claimed was on balance, pre-existing and most likely caused by earth
movement excluded from cover under the terms of the policy. Further the available
information does not prove any damage to the roof or drains was caused by the
flood/storm.
The panel accepts the insurer can cash settle the claim but considers the cash
settlement should be increased by 20% to take into account the transfer of the risk of
the repairs to the complainant. The settlement offer should be increased from
$11,909.04 by 20% to $14,290.85.
1.3 Determination
This determination is partially in favour of the complainant.
Within 14 days of the complainant accepting this determination, the insurer is required
to pay the complainant $14,290.85 in settlement of the building claim.
Determination | Case number: 643774 Page 3 of 12
2 Reasons for determination
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome.
This decision has been made by a panel consisting of an Ombudsman, an individual
with extensive insurance experience and another individual with extensive consumer
experience.
The decision follows consideration of all the material exchanged. It is based on what
is fair in all the circumstances having regard to the relevant legal principles, terms of
the policy, good industry practice including codes of practice and previous decisions
where applicable.
2.1 Is the insurer entitled to partially decline the claim?
Complainant is required to establish a valid claim
It is accepted insurance law, the complainant is required to show on the balance of
probabilities, a loss occurred because of an insured event covered under the terms
and conditions of the policy. This is known as establishing a valid claim.
If the complainant can establish a valid claim, the burden shifts to the insurer to
establish it is entitled to decline the claim, if it seeks to do so.
The policy provides cover for damage to the insured property caused by listed insured
events, subject to certain exclusions and conditions. The policy provides cover for the
listed events of flood, storm and leaks.
Circumstances of the loss
The complainant lodged a claim on 5 February 2019 for damage to his property
caused by the Townsville Floods. He claimed:
damage to drains
roof damage
water damage to the skirting board and paint throughout the house
movement of the dining room with it rising in height compared to the other rooms
causing a lip where the tiles meet
further damage to the walls and skirting boards where the room meet other rooms
multiple tiles popped throughout the house.
Determination | Case number: 643774 Page 4 of 12
Insurer offered partial settlement based on expert reports
The insurer appointed (CC) to attend the property to undertake an inspection and
report on the extent of the damage at the property. CC appointed builder (BB) to
prepare a scope of works. Restoration company (WR) was appointed to attend the
property for to complete remediation works. An engineer (CR) was also appointed to
assist with determining the cause of the cracking in the property. Plumbers (NQ)
completed a roof inspection and a leak detection test at the property.
In consideration of the reports provided by CR, BB, WR and NQ, the insurer found the
flood event did not cause damage to:
drains
roof
the skirting boards in bedroom three
the tiles
cracking in the property.
The insurer accepted the resultant damage to:
front room
main bedroom
second bedroom cupboard.
The insurer offered a cash settlement of $11,909.04 for the accepted claim related
damage.
No evidence of storm damage to the drains or roof
NQ found no storm damage to the drains or roof.
NQ considered the roof to be in a fair condition. The gutters were blocked and a tree
was growing over the roof at the back of the home. NQ found no obvious signs of rust
or holes. The screws are in ok condition although some of the seals were starting to
perish. NQ provided several recommendations for the complainant including:
the gutters and down pipes be cleaned out
the large tree growing in the back of the roof be trimmed
an extra step the dektites and flashings to be resealed and the screws replaced
with cyclone assemblies.
At the beginning of the AFCA process, the complainant raised a concern regarding
the roof eave at the rear door and the outside sunshade at the property. The insurer
obtained a response from BB. BB advised no damage was noted to an awning or
blind or the eaves. BB also advised the complainant did not raised this concern at the
time the property was assessed.
The complainant has not provided a report in response to the findings of NQ.
Determination | Case number: 643774 Page 5 of 12
The panel accepts the available information establishes that most likely the drains
and/or roof were not damaged by the event. The panel further agrees, the
complainant should consider attending to the recommendations provided by NQ.
Damage to the flooring is not related to the flood/storm event
CR considered the differential heights of the floor tiling occurred across the expansion
joints due to normal foundation soil movements.
In relation to the cracking in the tiles, CR concluded:
the cracking damage is likely to be the result of a lack of glue adhesive to the entire
underside of the individual tiles during the time of installation, which leaves hollow
voids
continual foot traffic over this part of the floor tiling (where the hollow voids are
situated) has ultimately allowed for such cracking to occur, a weak spot in the tiles.
as for the stone floor feature, the internal water ingress did not cause this part of
the tiling to delaminate
some of the floor tiles in various parts of the dwelling were exhibiting drummy
‘hollow -soun ds’ when the surface was tapped
this hollow-sounding surface on some of the floor tiles is not a function of the
recent rain storm
these hollow sounds are caused by when there is a lack of glue adhesive to the
entire underside of the individual tile, in areas where there are hollow voids
the cracked floor tile in bedroom three is not the result of the recent rain storm
it is likely the cracking has developed because of the tile being subjected to an
impact
the movement and cracking identified in the dwelling is the result of normal and
ongoing footing movements due to varying moisture fluctuations in the foundation
soil because of seasonal and climate changes.
The complainant was asked to provide the pre-purchase report. The report identified
some areas had drummy tiles. The complainant has provided no other information to
dispute CR’s findings.
Based on the available information, the panel is satisfied the issues with the flooring
pre-dated the flood/storm. Pre-existing damage is excluded from cover under the
terms of the policy and the insurer is not liable for this damage.
Damage to the skirting in bedroom two is not a result of the event
BB considered the damage behind the desk in the second bedroom was caused by a
leak within the shower recess waterproofing membrane. This would allow water to
escape when the shower was in use and pass through the wall causing damage to
the lower wall skirting board.
Determination | Case number: 643774 Page 6 of 12
A leak detection test was completed by plumber (NQ). NQ found no signs of leaks but
noted several cracks in the tiles and silicone seals. NQ concluded the cracks in the
tiles and silicone seals may be compromising the water proofing. NQ recommended
the shower needed replacement.
WR also noted the water damage was in the corner of the bedroom and adjacent to
the shower. WR’s comments regarding the water damage are similar to those of BB
and NQ, that the water is leaking from the shower.
The panel accepts that most likely the damage to the skirting is not related to the
flood/storm event. The information provided shows the damage is a result of water
escape for the shower recess. Therefore, the insurer is not liable for the damage.
Cracking in the property was caused by ground movement
CR noted the building is constructed on reactive clay foundation soils which are
susceptible to shrink/swell movements with changes in soil moisture content. CR
states, the cracking and movement was predominantly caused by long-term
volumetric changes in the foundation soil beneath the dwelling due to soil moisture
fluctuations, none of which has been result of the recent flood/storm. CR further noted
the presence of patch repairs at the location of the cracking, which indicates the
movement has been ongoing for an extended period.
The complainant disputes the findings of CR. The complainant provided photographs
to show the extent of the cracking before the event. It is noted the photographs are up
to and more than 18 months prior to the loss. The panel is not satisfied the
photographs support the complainant’s position.
The complainant also refutes the comments of CR regarding the repairs. The
complainant advised he has not conducted any repairs to the walls of the house.
While the panel acknowledges the complainant’s comments regarding repairs, the
panel has reviewed the pre-purchase report. There are references and photographs
which show patch repairs completed at the property.
The policy excludes loss or damage caused by or arising in connection with erosion,
landslide, subsidence, vibration, earth shrinkage or expansion or any other earth
movement unless the landslide or subsidence happens within 72 hours of the first
loss or damage caused by the flood or water runoff.
The available information indicates the damage first occurred prior to the flood/storm.
It establishes that most likely the damage was caused by earth movement due to the
reactive clay soil. The panel is satisfied the cracking was most likely caused by earth
movement. The panel has considered the information provided by the complainant,
however does not consider the information supports the complainant’s position. The
insurer is entitled to rely on the terms and conditions of the policy to refuse this part of
the claim.
Determination | Case number: 643774 Page 7 of 12
No evidence of mould growth in the property
The complainant raised concerns regarding mould growth within the property. WR
completed remediation works, which including drying the property and testings. After
the drying was completed, the complainant had concerns regarding mould. The
insurer arranged for WR to reattend.
During the attendance, WR found areas to be of dry standard and no evidence of
microbial growth. WR noted there were areas which are general dirt, grime and dust
clumps.
Based on the information provided by WR, the panel is satisfied there is no evidence
of mould growth in the property.
Insurer to settle the claim in accordance with the quote provided by BB
BB ’s concluded some of the damage to the complainant’s home was due to the
flood/storm. The insurer accepted this damage.
The areas identified by the BB were:
front room
second bedroom cupboard
main bedroom.
Based on BB’s findings, the insured to accept some of the damage. BB provided a
quote for the accepted resultant damage. The insurer offered a cash settlement of
$11,909.04 (based on the quote provided by BB) for the accepted resultant damage.
The insurer further accepted the damage to the contents and paid the complainant
$29,500 being the sum insured for the contents less the applicable excess.
The panel is of the view that any cash settlement must be reasonable, fair and
consistent with utmost good faith. It must be sufficient to restore the complainant to
the position he was in prior to the event and should consider the ‘unknowns’ and the
transfer of the risk.
Allowing for the contingencies or unknowns, the possible additional unidentified
damage and the transfer of risk, the panel considers that it is fair to increase the
quote by 20% to $14,290.85.
The insurer is required to make payment within 14 days of acceptance by the
complainant. The insurer is not liable for any additional damage.
Determination | Case number: 643774 Page 8 of 12
3 Supporting information
3.1 Relevant policy wording
Flood – page 22
Flood means the covering of normally dry land by water that has escaped or been
released from the normal confines of any of the following:
a lake, river, creek or other natural watercourse (whether or not it has
been altered or modified)
a reservoir, canal or dam.
Water runoff means water which enters your home as a result of it running off or
overflowing from any origin or cause.
General exclusions – pages 61-63
These general exclusions apply to all of the cover we provide under your policy.
We don’t cover you under your policy for loss or damage to your home or
contents or for legal liability which is caused by or arises in connection with any of
the following items, events or circumstances:
….
Erosion, landslide, subsidence, vibration, earth shrinkage or expansion or any
other earth movement no matter how it is caused (but we do cover earthquake
and we cover some landslide or subsidence that happens within 72 hours of the
first loss or damage to your home or contents caused by the flood or water runoff
– see page 22).
3.2 Expert reports
Record Key points
insurer’s expert (CC )
First Report
21 February 2019
there has been black water inundation throughout the lower level
of the property, reaching approxi mately 400mm high.
however there has been significant building damage sustained to
the structure wit h water damage to the floor tiles, walls, skirting
and architraves, cabinetry, robes and doors.
there has also been a build of debris in the pool.
recommend settlement for t he full contents sum insured.
insurer ’s expert ( WR )
First Report
5 March 2019
inspected site, checked moisture readings, took thermal images
and photographed damage.
relative humidity was recorded at 56% outside at 34 degrees and
49% at 24 degrees.
t he baseplates were reading 18 - 20%.
builder have complet e strip and ins ured advised an engineer has
been engaged to assess property.
extended drying time of five days is required to dry block walls and
structure.
Determination | Case number: 643774 Page 9 of 12
Record Key points
insurer ’s expert ( WR )
Second Report
13 March 2019
re - attended site, HEPA vacuumed, cleaned and treat ed affected
area.
a pplied antimicrobial treatment.
took Hygenia System Sure Swab to confirm sanitisation.
swab passed testing as per sanitisation certificate.
all building materials were of d ry standard and drying equipment is
not required in this instance.
insurer ’s expert ( CC )
Second Report
31 March 2019
attached is BB’s partial quotation limited to reinstatement of the
front room stripped put by WR.
within the quotation, recommend the appointment of an engineer
to inspect extensive cracking throughout the residence following
the flood event, as well as a scope of works for the repairs
required to return the residence to its pre - loss condition.
insur er ’s expert ( CR )
Engineer Report
9 April 2019
dwelling is constructed on reactive clay foundation soils which are
susceptible to shrink/swell movements with changes in soil
moisture content.
based on the available evidence, the house cracking and
movemen t has been predominantly caused by long - term
volumetric changes in the foundation soil beneath the dwelling due
to soil moisture fluctuations, none of which has been result of the
recent rain storm.
the presence of the widespread patch repairs at the loca tion of the
cracking indicates these building movements have been ongoing
for an extended period of time and are of no recent origins.
aspects related to the drummy ‘hollow sounding’ floor tiles to some
parts of the dwelling are a function of how the tiles have been
installed and not related to the recent rain storm.
2.25mm wide cracking in the brick wall at the location of the front
archway.
the cracking was evident towards the right side of the arch.
cracking also reflected in the external wall, with pa rts of the feature
blockwork having undergone downward movement.
evidence of previous application of flexible sealant at the location
of the cracking.
10mm wide stepped cracking also evident in the upper section of
the eastern block wall of bedroom 1.
evidence of previous repairs at the location of the cracking.
external and internal wall cracking was evident in various parts of
the perimeter dingle blockwork wall of the dwelling.
at the location of some of the cracking, there was evidence of
previous repairs such as the application of flexible sealant.
Previous patch repairs, together wit h an absence of wall
movement articulation jointing that is typically built into modern
day domestic buildings, have highlighted the claimed uncontrolled
movement cr acking in the perimet er blockwork wall.
as for the internal parts of the dwelling, there was noticeable
separation occurring at some of the cornice and wall interfaces.
Determination | Case number: 643774 Page 10 of 12
Record Key points
this separation is not uncommon and is of a cosmetic issue and
regarded to be unsight ly.
in relation to the differential heights of the floor tiling, this has
occurred at a location where there was an expansion joint in the
floor tiling.
across this joint, there have been slight building movements due to
normal foundation soil movements.
overall, the cracking damage in the walls of the dwelling are of no
structural consequence – the building’s structural integrity has not
been significantly or adversely affected by the limited degree of
differential movement that has occurred.
the floor tiles in the sunroom adjacent to the stone floor feature
had not cracked as a result of the recent rain storm.
the cracking damage is likely to be the result of a lack of glue
adhesive to the entire underside of the individual tiles during the
time of in stallation, which leaves hollow voids.
continual foot traffic over this part of the floor tiling (where the
hollow voids are situated) has ultimately allowed for such cracking
to occur, a weak spot in the tiles.
as for the stone floor feature, the intern al water ingress did not
cause this part of the tiling to delaminate.
the internal water entry is likely to have contributed to further
damage.
some of the floor tiles in various parts of the dwelling were
exhibiting drummy ‘hollow - sounds’ when the surf ace was tapped.
this hollow - sounding surface on some of the floor tiles is not a
function of the recent rain storm.
these hollow sounds are caused by when there is a lack of glue
adhesive to the entire underside of the individual tile, in areas
where ther e are hollow voids.
the cracked floor tile in bedroom 3 is not the result of the recent
rain storm.
it is likely the cracking has developed as a result of the tile being
subjected to an impact.
the movement and cracking identified in the dwelling is the result
of normal and ongoing footing movements due to varying moisture
fluctuations in the foundation soil as a result of seasonal and
climate changes.
in consideration of extent of inundation, we do not consider this
rain storm has contributed to the dam age.
the presence of previous patch repairs at the location of the
cracking indicates these building movements have been ongoing
for an extended period of time.
there was no identifiable damage in the dwelling to suggest the
movement was the result of a pipe leakage.
further building movement are expected to occur and thes e,
together with the currently claimed movements, present an
ongoing maintenanc e issue for the insured.
Determination | Case number: 643774 Page 11 of 12
Record Key points
insurer ’s expert ( WR )
Third Report
24 April 2019
inspected site, checked moisture readings, took thermal images
and photographed damage.
upon inspecting the rear master and bedroom 2, what was pointed
out did not appear to be microbial growth.
it appeared to be general dirt and grime and dust clumps.
used thermal hygrometers and moisture meters in these rooms,
and everything was at dry standard.
in bedroom 3, however, the thermal showed that the walls were
intact wet and high reading of moisture.
Noted that this was probably due to membrane failure o r a leak
around the shower.
the rest of bedroom 3 structures as dry, apart from the corner of
the room through backed straight into the shower recess in the
bathroom that backs onto this room.
the water damage in bedroom 3 relates to leak from shower try
and is not a result of recent flooding.
insurer ’s expert ( BB )
Building Report
14 June 2019
noted four separate areas over two attendances.
front room – this has been directly caused by water entry during
the monsoonal rain event.
water had built up in the side yard and entered through the weep
holes of the block wall flooding the room to a minor level.
this required a strip out and structural drying (complet ed).
main bedroom, w ater has built up in the rear yard and entered
through the weep holes in the block wall.
this did not flood the room, however caused minor separation of
the skirting board on the external facing wall.
second bedroom cupboard – this is again external yard water that
has built up and entered through the weep holes on the externa l
facing wall and where that wall adjoins the main bedroom wall.
second bedroom behind desk – this is separat e to the flooding
event.
a leak within the shower recess waterproofing membrane.
the membrane is allowing water to escape when the shower is
use d which is passing through the wall and directly causing
damage to the lower wall skirting board.
structural cracking – this is separate issue and not relate to the
rain event.
the cracking is directly caused by structural movement within the
building.
the rain event may have caused the house to move showing the
cracking in a worse light, however believe this is pre - existing and
not caused by any one - off event.
no maint enance issues contributing to the front room, main
bed room or second bedroom external wall damages.
maintenance issues existing with the structure directly relating to
movement and waterproofing issues within the shower recess.
the event has caused some minor damages to the property
however other issues and explained above have no relati on to the
Determination | Case number: 643774 Page 12 of 12
Record Key points
rain event.
insurer ’s expert ( NQ )
Leak Detection Report
14 June 2019
the pressure tests passed.
there are a number of cracks in the tiles and silicone seals.
the cracks in the tiles and silicone seals may be compromising the
waterproofing, henc e causing leaking.
the shower cubicle needs to be res ealed or replaced.
insurer ’s expert ( NQ )
Roof Report
21 June 2019
upon inspection of the hous e there is no obvious sign of water
marks or mould.
note cracks in the walls and cornice.
upon inspection of the roof, we found the metal deck wrap roof to
be in fair condition.
there is no obvious signs of rust or holes and t he screws are in ok
condition.
some of the seals only just starting to peris h.
the gutters are currently blocked and a tree is growing over the
roof at the back of the house.
the amount of water rec eived during the monsoonal rain event has
over saturated the ground, henc e caused movement within the
house.
with regards to the roof - recommend the gutters and down pipes
be cleaned out.
the large tree growing in the back of the roof trimmed.
an extra step the dektites and flashings can be resealed and the
screws replaced with cyclone assemblies.
3.3 Other material considered
pre-purchase report
pest report
complainant’s submissions.