Lender repossession, completion and sale of unfinished units, and resulting shortfall

FirmNAB
Decided2020-08-10
ProductCredit · Home loan
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A borrower under a construction loan, administered by a mortgage manager, complained that the lender's repossession, completion works and sale of three units were wrongful and caused a shortfall. AFCA found no error or breach and awarded nothing.

The lender's decision to complete and sell the units was reasonable in light of their incomplete condition, and the loan terms were complied with.

Issues

Subjects and remedies

financial hardshipno remedy

Related

All NAB determinations · Find similar determinations

Text of the determination

Determination Case number 642364 Financial firm Advantedge Financial Services Pty Ltd Determination | Case number: 642364 Page 2 of 9 Case number: 642364 10 August 2020 1 Determination overview 1.1 Complaint In 2007, the complainant entered into a contract with a lender who provided the complainant with finance to build three units (loan). The financial firm is the mortgage manager who was delegated with all responsibilities in managing the loan. For the purposes of this determination, most references have been made in regard to ‘the lender.’ The complainant began to encounter financial difficulties for a number of reasons. In February 2010, the lender repossessed the units before the units were completed. The lender engaged a new builder to complete construction and sold the units. There was a substantial shortfall for repayment of the loan which the lender ultimately wrote off. The complainant has raised multiple claims against the lender, including that it wrongfully repossessed the units, overspent on completing construction and under- sold the units as mortgagee in possession. On 1 May 2020, the AFCA case manager issued a recommendation on the issues in dispute. The recommendation was in favour of the financial firm. A copy of the recommendation is attached to this determination. The complainant has rejected the recommendation. His further submissions are outlined in section 2.1 below. 1.2 Issues and key findings Were the findings in the recommendation correct? Based on the available information, the substantive findings contained in the recommendation were correct and are adopted into this determination. I agree with the reasons for the recommendation and the recommended outcome. However, the case manager erred in stating the complainant is currently bankrupt. The complainant was discharged from his bankruptcy in July 2015. Do the complainant’s further submissions change the outcome? For reasons set out in section 2.2, the complainant’s further submissions do not change the outcome to this complainant. The recommendation adequately dealt with the issues raised and it is adopted into this decision. The complainant’s reasons for rejecting the recommendation do not provide a basis for changing the outcome. 1.3 Determination This determination in in favour of the financial firm. The financial firm is not required to compensate the complainant. Determination | Case number: 642364 Page 3 of 9 2 Reasons for determination 2.1 Were the findings in the recommendation correct? The findings in the recommendation were correct I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous AFCA decisions. I have taken into account all the material submitted by the parties, both before and after the recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. I am satisfied that the recommendation contains an accurate summary of the complaint, the issues to be determined, any applicable paragraphs of the Rules and any relevant law. Based on all the available information, I agree with the findings in the recommendation. Accordingly, the recommendation is adopted into this decision and attached. The complainant rejected the recommendation In rejecting the recommendation, the complainant says that:  The finance he received was a line of credit not a construction loan  From 2009 he received poor customer service as there were ‘constant delays’ which caused his building project to stall  The deed of agreement [to provide further funding to complete the units] did not mention the financial firm, yet AFCA found the financial firm administered the deed.  Schedule A of the deed is missing, so he queries how the case manager found that he received the correct amount of further funding to complete construction  The recommendation found the valuation report which said the units were 78% complete was irrelevant. Yet in other AFCA decisions, valuations obtained by lenders are deemed to be correct.  The recommendation found the lender wanted to avoid a shortfall. He cannot see how, given the balance on his statement increased by $1,000,000 in 18 months  He disagrees with the finding that the lender incurred reasonable costs to complete construction  He disagrees with the finding that the lende r did not delay the units’ completion. It took 17 months to complete even though a certified valuer determined the units were 78% complete  Excessive loan interest was charged to the account. The complainant also says that he was discharged from bankruptcy in 2015. As the complainant’s claims against the financial firm concern disputed conduct which occurred before or during the period of bankruptcy, his right to pursue those claims Determination | Case number: 642364 Page 4 of 9 remain vested in the Trustee in Bankruptcy even after discharge of bankruptcy. The Trustee in Bankruptcy provided authority for AFCA to consider this complaint. 2.2 Do the complainant’s further submissions change the outcome ? The complainant received a construction loan The complainant queries whether the finance he received was a loan or line of credit. In 2007, the complainant entered into a contract titled as a ‘loan agreement’ with the lender. Under this agreement, the loan had a $500,000 facility limit and a ten-year interest only period followed by principal and interest payments. The available information shows the complainant required upfront funding of $500,000, so the parties entered into a ‘ supplemental loan agreement.’ Under this agreem ent, the loan’s facility limit increased from $500,000 to $1,000,000. The opening loan statement shows the loan started on 12 June 2007 with an opening loan balance of $500,000. The loan was a construction loan as it was provided to fund the construction. Like most construction loans, the loan structure required progressive drawdowns. That is, the lender was to fund the loan by way of payment instalments (at various building stages) up to the facility limit. So, like a line of credit, the loan had a facility limit. However, monthly interest payments became payable when the loan commenced. The lender did not cause the complainant’s arrears The complainant says that from 2009 he received poor customer service from the lender because of ‘constant delays’ which cause d his building project to stall. I understand the complainant claims the lender delayed funding various instalments to cover invoiced building costs. I understand the complainant also experienced delays due to the builder he engaged. The complainant has previously said delays in construction caused him to fall into arrears and, by January 2010, the lender issued him with a default notice. AFCA has reviewed the loan statements and there is no information to show construction drawdowns (instalments) during 2009 were not advanced within reasonable timeframes. Even if there were unreasonable delays (which has not been established), this did not cause the loan to fall into arrears. The loan statements show there were regular dishonoured payments since 2007. In September 2009, the parties entered into a deed of agreement (deed) where the lender agreed to advance the complainant additional finance to complete construction. The lender made further advances totalling $103,469 to the complainant’s builder during October 2009, before finally issuing the complainant with a default notice in January 2010. Determination | Case number: 642364 Page 5 of 9 The deed was between the complainant and the lender The complainant says the deed did not mention the financial firm, ye t AFCA found the financial firm administered the deed. The financial firm’s role was clarified in section 3.1 of the recommendation. The financial firm is a mortgage manager who was delegated with all responsibilities in managing the loan. The complainant’s contract was with the lender (not the financial firm) and the lender funded the loan to the complainant (not the financial firm). The deed was also a contract between the complainant and the lender (not the financial firm). When the complainant lodged his complaint with AFCA, he said his complaint was with the lender (not the financial firm). However, when AFCA receives complaints about the lender, the complaint will generally be considered against the financial firm (not the lender). This is because the financial firm, as the mortgage manager, has accepted all responsibilities regarding the management of the loan. AFCA may draw inferences and conclusions based on available information There was a schedule to the deed of September 2009 labelled ‘Schedule A’ (the schedule) which cannot be located by either party. The schedule outlined details about the further advances the lender was going to provide the complainant, including the approximate amounts. The complainant queries how the case manager found the lender provided him the correct amount of additional finance, if the schedule is missing. I note the case manager concluded that:  A valuer’s inspection report (valuer’s report) from early 2009 said that $133,100 was still required to complete construction. It was therefore likely the lender had committed to ‘further advances’ in the vicinity of this amount rather than amounts in excess of $300,000. The lender had not yet discovered the costs for completion far exceeded $133,100 and  In November 2009, the complainan t’s lawyer informed the lender that the complainant’s builder was seriously unwell, unable to complete construction and that $350,000 was now required to complete construction. Based on this information, the recommendation found the lender was not obliged to provide the complainant funding under the deed up to $350,000. I agree with the case manager’s assessment of the available information. AFCA is entitled to draw inferences and conclusions about what most likely occurred based on available information. In this case the available information shows it is unlikely the lender had committed to further advances approximating $350,000 and there is no information to support that position. Relevantly, the complainant says that by September 2009, he required about $170,000 to complete the units. He says he then signed a deed where the lender Determination | Case number: 642364 Page 6 of 9 agreed to advance him further funds to complete the units. The complainant would have discussed the further funding he required to complete construction with the lender before the deed was signed . It is reasonable to infer that the schedule’s details regarding further advances reflected those discussions. In any case, the schedule states that further advances are to be paid to the comp lainant’s builder or the builder’s contractors. The complainant’s lawyer confirmed the complainant’s builder was unable to complete construction. In these circumstances, even if the lender had committed to complete construction for $350,000, it was premise d on the complainant’s builder completing the units. The valuation report is not as accurate as the building quotes The val uer’s report stated that, as at 23 February 2009, construction was 78% complete and $133,100 was required for completion. The complainant queries why the recommendation gave little weight to the valu er’s report when previous AFCA decisions have deemed lenders’ valuations to be correct. In considering whether a property has been correctly valued, AFCA will generally accept the findings of an independent valuer. The valuation report was not a valuation regarding the value of the units. It was an inspection report regarding the progress of the units’ construction. On its face, it indicates that construction was 78% complete. However, certified valuers are not certified/expert builders. The valuation report even said it was undertaken in the valuer’s capacity as a valuer, not a building expert. It was not an expert building report on the condition of the units. There is available information from two expert builders which contradicts the valuation report. The recommendation explained why this was the case. I will not repeat the recommendation’s findings on this matter. The information from these builders regarding the works required to complete construction, carries more weight than the valuation report. This information shows the units were far less than 78% complete. It was reasonable for the lender to complete construction By August 2010, after the lender received a second/comparative quote from builder B, the lender had two options: a. Option A was to sell the units in their incomplete state (‘as is) b. Option B was to complete the units’ construction and then sell them . By August 2010, the loan balance was $1,1 58,847 and the units’ estimated selling value ‘as is’ was $1,147,500. This equates to a surplus of about $10,500 before selling costs for three units, legal fees and further loan interest is applied. Once these additional costs were accounted for, option A would have led to a significant shortfall. Determination | Case number: 642364 Page 7 of 9 The recommendation found the lender acted reasonably in pursuing option B. I agree with that conclusion for the reasons set out in the recommendation. Ultimately, option B also led to a significant shortfall. The complainant has advised AFCA that pursuing option A was still preferable as the shortfall would have been lower. He says this is because the lender was aware it would take nearly six months to complete construction, over which time, loan interest would continue to accrue. The complainant says builder B would have provided lender A with an estimated timeframe to complete construction. It is difficult to determine whether option B would have likely led to a lower shortfall than option A, or if so, by how much. It would have been equally difficult for the lender at the time. In a metropolitan market it usually takes up to 6 months to sell a property. However, if the units were sold ‘as is’ the prospect of selling the units in a timely period would have been unlikely because:  The units were not marketable to consumers wishing to purchase a new unit as they were incomplete and required extensive building works  The units were unattractive to consumers wishing to build a new home. This would attract demolition costs and additional costs to apply to council to repurpose the land. This cohort of consumers are therefore more likely to purchase vacant land.  The units were not marketable to developers wishing to take on a new development project. Not only were the units incomplete, but there were structural defects, council regulations were not met, and contact with the previous architect (who had not been paid for his work) was required. The design of the units would also have to appeal to a new developer. In all the circumstances, I am unable to speculate on whether option A would have led to a lower shortfall than option B. In option A, the units may have remained unsold for an indefinite period (maybe more than 18 months). In any case, the lender did not pursue the complainant for the shortfall which eventuated after pursuing option B. From a loss perspective, the complainant did not become worse off either way by the lender’s decision . The available information shows the lender incurred reasonable costs The complainant disagrees with the recommendation’s finding that the lender incurred reasonable costs to complete the units’ construction to occupancy stage. The recommendation dealt with this issue in detail, so I will not repeat its findings. The complainant has not provided any new or relevant information to change the recommendation’s conclusion on this matter. For reasons explained in the recommendation, I am satisfied that:  The units were less than 78% complete  The units required extensive building works to reach occupancy stage Determination | Case number: 642364 Page 8 of 9  All building works were appropriately quoted, costed and accounted for. The lender did not delay completing construction The complainant disagrees with the recommendation’s finding that the lender did not delay the units’ completion. He says it took 17 months to complete even though a certified valuer determined the units were 78% complete. For reasons established, I am satisfied the timeline of events shows it took about six months to complete the units (not 17 months). Given the units required extensive works, I am unable to find that six months was unreasonable. I acknowledge the lender sold (all) the units by July 2011, which was some 17 months after the lender took possession of them. This was because it also took several months for the lender to obtain comparative building quotes and five months to finish selling (all) the units after they were ready for sale. The recommendation explained why these timeframes were reasonable. I will not repeat the recommendation’s findings here. There is no new or relevant information to change the recommendation’s findings on this matter. There is no information to show interest was incorrectly charged During a recent phone call with AFCA the complainant said the lender charged high interest toward the loan account and the interest rates should have been lowered. AFCA will not audit the interest charges. There is no information to show the lender incorrectly charged interest to the loan account or applied incorrect rates and AFCA cannot compel a lender to lower interest rates if charged in accordance with the loan contract. In this case, the loan balance exceeded $1,000,000 all the while monthly regular loan interest and default interest remained unpaid. As the arrears compounded, the interest compounded, and the monthly unpaid interest charges increased. It is evident the complainant is dissatisfied with the rates which were charged. T he lender’s rates are a matter for the lender. AFCA will not interfere with the lending rates financial firms offer borrowers. These are commercial policy decisions for financial firms based on its own credit risk assessment. Determination | Case number: 642364 Page 9 of 9 3 Supporting information 3.1 The loan was a joint loan The complainant and his former wife were joint borrowers under the loan. The complainant’s former wife is not a co -complainant. For the purposes of this determination, I have not referred to the complainant being a joint borrower.