Home / Allianz Australia / Determination 641912

Determination 641912

Cash settlement for escape of liquid and impact claims, scope of repairs and delay

FirmAllianz Australia
Decided2020-08-17
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$23,892
Non-financial loss$2,000
Amount claimed—
SourceAFCA PDF

Summary

The complainants' home was damaged by an escape of liquid and by a vehicle impact. AFCA accepted the insurer's repair scope but found the settlement too low, adding 15% for contingencies, and awarded $2,000 for delay; the complainants' broader scope including pre-existing damage was rejected.

An insured is not entitled to have pre-existing damage repaired at the insurer's cost, but a cash settlement must allow for contingencies and transfer of risk.

Issues

Subjects and remedies

home or building damagemotor vehicle collisionpay claimpay interestpay non financial loss

Related

All Allianz Australia determinations · Find similar determinations

Text of the determination

Determination Case number 641912 Financial firm Allianz Australia Insurance Limited Determination | Case number: 641912 Page 2 of 7 Case number: 641912 11 August 2020 1 Determination overview 1.1 Complaint In January 2019, a determination was issued by AFCA saying the financial firm (the insurer) was required to accept a claim for damage caused by a leaking pipe under the complainants’ home and contents policy. The insurer was also instructed to assess a second claim for damage to the home caused by a vehicle. The insurer assessed both claims and issued a settlement to the complainants for what it believes is the fair cost required to repair the damage caused by both events. The complainants say the accepted scope of works does not include all the damage caused by the two events, and the settlement amount offered by the insurer is insufficient to cover the cost of repairs. The complainants want the insurer to accept the additional areas of damage and increase its settlement to resolve the complaint. 1.2 Issues and key findings Is the insurer required to increase its settlement? Yes. The insurer is to increase the settlement amount as set out under section 2.1 . Are the complainants entitled to compensation for non-financial loss? Yes. The complainants have endured a significant and unnecessary delay in having their entitlements under the policy paid. 1.3 Determination This determination is partly in favour of the complainants. The insurer is required to pay the complainant:  $23,892.04 as a cash settlement for building repairs  interest on the cash settlement in accordance with s57 of the Insurance Contracts Act from 19 March 2018 until paid  compensation for non-financial loss in the sum of $2,000 Determination | Case number: 641912 Page 3 of 7 2 Reasons for determination 2.1 Is the insurer required to increase its settlement? The insurer agrees it needs to increase its settlement offer Following an AFCA determination of 8 January 2019, the insurer was required to accept two claims submitted by the complainants for separate events; one being an Escape of Liquid and the second being an Impact claim. The insurer had previously engaged an assessor (C) to review the claim and C appointed a Building Consultant and Engineer to review the loss (CRD). The damage was assessed, and CRD provided a scope of work for each claim. A quote was obtained on the scope of work from two builders (T) and (A) in April 2019. These initial quotes were not accepted as the insurer said they were not based on the scope of works provided. As a result, T provided an amended quote for each claim. The insurer accepted the quotes and provided the complainant with a cash settlement. The quote for the Escape of Liquid claim was $55,339.68 and the Impact claim was $18,000.30. An excess of $700 was applied to each claim and a premium adjustment was made. The insurer therefore has paid a cash settlement to the complainant as follows: Date A ction Accepted loss $73,339.89 Less excess $1,400.00 Less premium $5,771.71 Sub total $ 66,168.18 Plus premium adjustment $4,665.71 Total cash settlement paid $ 70,833.44 Interest was paid on the cash settlement for the period 19 March 2018 to 17 May 2019. The insurer has reviewed this settlement offer throughout this complaint process. Determination | Case number: 641912 Page 4 of 7 Following a report from C of 13 January 2020 the insurer made an extra allowance of $4,030 for Home Building Compensation Fund Certificate and Engineers Plans. This increased its agreed settlement to $77,369.98. Following a further review by C on 31 January 2020 the insurer proposed an additional allowance of $2,000 increasing its agreed settlement to $79,369.98. Then on 2 March 2020 C recommended a further increase in the settlement sum by $3,000 for previously unaccounted for Council costs bringing the insurer’s final position to $82,369.98. Based on the insurer’s amendments, and without consideration o f the merits of the complainants ’ position, the insurer has admitted it owes the complainant ’s a further $9,030.09. For the reasons noted below, the insurer will be required to make a more significant payment to the complainant. Experts relied upon by the parties disagree as to the extent of the loss The scope of works relied upon by the insurer for its cash settlement offer was provided by CRD. The complainants have submitted various reports, including from an engineer (G) but rely upon a quote and scope of works from its builder (J). The two scopes of works vary significantly. The differences between the parties can be summarised by the following extract from the report of C dated 13 January 2020: “… the scope of works submitted by (sic) (J) allows for reinstatement of all resultant damage from the two claimed events, Escape of Liquid and Impact, however also allows for reinstatement of the aforementioned pre- existing wear and tear to the insured property.” The law is clear that an insured is not entitled to profit from an insurance claim and have repairs completed to improve and make better a damaged home. The initial quotes from T and A were for approximately $133,000 excluding most of the council and administrative costs associated with obtaining approval for the work to be completed. The amended quote from J is for approximately $180,000. This is a varied quote from the original two quotes provided which were for approximately $168,000 and $187,000. The complainant submitted a report from its engineer G. Of significance is the acceptance from G all damage to the property needs to be repaired because of the two insured events. G agreed there was evidence of subsidence but blames all the damage on subsidence caused by the accepted escape of liquid, and not pre-existing and prolonged water leakage from the downpipe. Determination | Case number: 641912 Page 5 of 7 G also noted the presence of extensive wood rot due to terminates in the area of the Impact. It is unclear how or if G considers this to be related to the insured events or why this damage should be included in the scope of works. J confirmed its quote was consistent with the opinion of G and the scope of works suggested in its report of 1 July 2019. The scope of work used to make the cash settlement offer is based on the scope of work provided by CRD who does not agree all the work required to the house is caused by the insured events. The quotes for all the work to be completed are consistent. The issue in dispute is the damage caused by the insured events and whether the scope of works accepted include repair and replacement of pre -existing damage, thus enriching the complainants in the process. It is fair and reasonable to accept the quote from the insurer ’s builder The Panel notes the original assessment of CRD when attending the house in February 2018 has not changed. CRD noted the subsidence of the footings had caused the cracking in the floor and resultant damage in the bathroom and laundry area, especially to the concrete floor. CRD considered the differential movement of the footings had been occurring for a prolonged period. The initial report also noted the issue with the downpipes not being connected to the stormwater system. The insured had used buckets to collect the water from the base of the downpipes. These downpipes are located right outside the bathroom. CRD noted the poor state of the house and referred to the pre-purchase report as evidence of this. There are significant pictures. This is confirmed by the photos and commentary of G in its report. G referred to termite infested wood and the associated rot near the area of the impact. Pictures were very clear as to the state of the wood. The Panel accepts there is clear evidence of pre-existing damage and maintenance required to the home at the time of the insured events. The work claimed by the complainants would put them in a better position than before the insured events. Not all the work relates to damage caused by the insured events. The panel does not accept J’s quote as being a fair reflection of the damage caused by the insured events. The quote includes the cost to repair the pre-existing damage. In the circumstances the Panel accepts it is fair for the insurer to rely on the quote provided by T when cash settling the claim. Determination | Case number: 641912 Page 6 of 7 The insurer needs to make a more significant cash settlement Although the Panel accepts that the insurer can rely on the scope of works by CRD and quote from T, the offer made does not allow for the costs associated with the unknown contingencies and transfer of risk. Contingencies cover the unexpected additional costs possibly incurred when building works commence; such costs not able to be determined until such building work commences. Contingencies include the insurers evidence increased concrete costs of 2.5% from April 2020. Its own assessors agreed there were unknown costs. Contingencies also cover the transfer of risk from the insurer to the complainant given no warranty is provided by the insurer for the work to be completed. The Panel is satisfied a cash settlement is appropriate given the pre-existing damage. The Panel considers consistent with the AFCA approach that it is fair to add 15% to the cash settlement for contingencies. Following the conclusions above on the appropriate building costs, the insurer will need to provide the complainant with a further cash settlement as follows: Date Action Accepted loss $ 82,369.98 Plus 15% contingencies $12,355.50 Sub total $94,725.48 Less sum paid $70,833.44 Additional amount payable $23,892.04 The complainants say that the payment previously sent by the insurer has not been cashed. If this is correct, the insurer can cancel the previous cheques and settle the claim for $94,725.48. The previous payment of $70,833.44 paid on 19 May 2019 included interest to that date. It is fair, if the payment has not been cashed that the insurer pays additional interest on that amount from 19 May 2019 to date of payment of the claim in accordance with s57 of the Insurance Contracts Act. The insurer is required to pay interest on the balance of $23, 892.04 from 19 March 2018 to the date of payment of the claim in accordance with s57 of the Insurance Contracts Act. The insurer is entitled to reduce the amount paid by any outstanding premium. Determination | Case number: 641912 Page 7 of 7 2.2 Is the complainant entitled to compensation for non-financial loss? AFCA can award compensation for non-financial loss. Under Rule D3.3 of the AFCA rules, AFCA can award compensation of up to $5,000 where there has been an unusual degree of physical inconvenience, time taken to resolve a situation or interference with a Complainants expectation or enjoyment of peace of mind. The complainant is entitled to compensation for non-financial loss The Panel notes that the complainants have suggested compensation of the maximum amount of $5,000 each for non-financial loss is appropriate. As the policy is only in the name of one of the complainants, the panel accepts the maximum compensation available for non-financial loss is $5,000. The panel accepts that there has been an unusual degree of inco nvenience and time taken to resolve the situation. The insurer was required to accept the claim following a determination of AFCA in January 2019. The cash settlement paid by the insurer in May 2019 to resolve the complaint was not sufficient. The cash settlement did not include all relevant fees and charges and the insurer did not start to address this until January 2020. The insurer revised its calculations on three occasions to March 2020. Furthermore, the insurer despite clear evidence in its own reports indicating not all damage was observed, did not make any allowance for the contingencies or transfer of risk to the complainant. The insurer should be aware of AFCA’s approach on these types of issues. The delay in resolving the complaint is been significant. It is now over 16 months since it was required to accept the claims and the repairs have not been affected. Although not all delays can be attributed to the insurer the panel considers the insurers conduct has caused an unusual degree of inconvenience and time taken to resolve the situation. The panel is satisfied an award of $2,000 for non-financial loss is fair and appropriate.