Home / Allianz Australia / Determination 641912
Determination 641912
Cash settlement for escape of liquid and impact claims, scope of repairs and delay
Summary
The complainants' home was damaged by an escape of liquid and by a vehicle impact. AFCA accepted the insurer's repair scope but found the settlement too low, adding 15% for contingencies, and awarded $2,000 for delay; the complainants' broader scope including pre-existing damage was rejected.
An insured is not entitled to have pre-existing damage repaired at the insurer's cost, but a cash settlement must allow for contingencies and transfer of risk.
Issues
- Claim amount dispute primary · upheld
“The insurer is required to pay the complainant $23,892.04 as a cash settlement for building repairs, including 15% for contingencies.”
- Delay secondary · upheld
“The insurer's conduct has caused an unusual degree of inconvenience and time taken to resolve the situation.”
- Repairs or contractors secondary · not upheld
“The Panel does not accept J's quote as being a fair reflection of the damage caused by the insured events.”
Subjects and remedies
home or building damagemotor vehicle collisionpay claimpay interestpay non financial loss
Text of the determination
Determination
Case number 641912
Financial firm Allianz Australia Insurance Limited
Determination | Case number: 641912 Page 2 of 7
Case number: 641912 11 August 2020
1 Determination overview
1.1 Complaint
In January 2019, a determination was issued by AFCA saying the financial firm (the
insurer) was required to accept a claim for damage caused by a leaking pipe under
the complainants’ home and contents policy. The insurer was also instructed to
assess a second claim for damage to the home caused by a vehicle.
The insurer assessed both claims and issued a settlement to the complainants for
what it believes is the fair cost required to repair the damage caused by both events.
The complainants say the accepted scope of works does not include all the damage
caused by the two events, and the settlement amount offered by the insurer is
insufficient to cover the cost of repairs. The complainants want the insurer to accept
the additional areas of damage and increase its settlement to resolve the complaint.
1.2 Issues and key findings
Is the insurer required to increase its settlement?
Yes. The insurer is to increase the settlement amount as set out under section 2.1 .
Are the complainants entitled to compensation for non-financial loss?
Yes. The complainants have endured a significant and unnecessary delay in having
their entitlements under the policy paid.
1.3 Determination
This determination is partly in favour of the complainants. The insurer is required to
pay the complainant:
$23,892.04 as a cash settlement for building repairs
interest on the cash settlement in accordance with s57 of the Insurance Contracts
Act from 19 March 2018 until paid
compensation for non-financial loss in the sum of $2,000
Determination | Case number: 641912 Page 3 of 7
2 Reasons for determination
2.1 Is the insurer required to increase its settlement?
The insurer agrees it needs to increase its settlement offer
Following an AFCA determination of 8 January 2019, the insurer was required to
accept two claims submitted by the complainants for separate events; one being an
Escape of Liquid and the second being an Impact claim.
The insurer had previously engaged an assessor (C) to review the claim and C
appointed a Building Consultant and Engineer to review the loss (CRD). The damage
was assessed, and CRD provided a scope of work for each claim.
A quote was obtained on the scope of work from two builders (T) and (A) in April
2019. These initial quotes were not accepted as the insurer said they were not based
on the scope of works provided. As a result, T provided an amended quote for each
claim. The insurer accepted the quotes and provided the complainant with a cash
settlement.
The quote for the Escape of Liquid claim was $55,339.68 and the Impact claim was
$18,000.30. An excess of $700 was applied to each claim and a premium adjustment
was made. The insurer therefore has paid a cash settlement to the complainant as
follows:
Date A ction
Accepted loss $73,339.89
Less excess $1,400.00
Less premium $5,771.71
Sub total $ 66,168.18
Plus premium
adjustment
$4,665.71
Total cash settlement
paid
$ 70,833.44
Interest was paid on the cash settlement for the period 19 March 2018 to 17 May
2019.
The insurer has reviewed this settlement offer throughout this complaint process.
Determination | Case number: 641912 Page 4 of 7
Following a report from C of 13 January 2020 the insurer made an extra allowance of
$4,030 for Home Building Compensation Fund Certificate and Engineers Plans. This
increased its agreed settlement to $77,369.98.
Following a further review by C on 31 January 2020 the insurer proposed an
additional allowance of $2,000 increasing its agreed settlement to $79,369.98. Then
on 2 March 2020 C recommended a further increase in the settlement sum by $3,000
for previously unaccounted for Council costs bringing the insurer’s final position to
$82,369.98.
Based on the insurer’s amendments, and without consideration o f the merits of the
complainants ’ position, the insurer has admitted it owes the complainant ’s a further
$9,030.09.
For the reasons noted below, the insurer will be required to make a more significant
payment to the complainant.
Experts relied upon by the parties disagree as to the extent of the loss
The scope of works relied upon by the insurer for its cash settlement offer was
provided by CRD. The complainants have submitted various reports, including from
an engineer (G) but rely upon a quote and scope of works from its builder (J). The two
scopes of works vary significantly.
The differences between the parties can be summarised by the following extract from
the report of C dated 13 January 2020:
“… the scope of works submitted by (sic) (J) allows for reinstatement of all resultant damage
from the two claimed events, Escape of Liquid and Impact, however also allows for
reinstatement of the aforementioned pre- existing wear and tear to the insured property.”
The law is clear that an insured is not entitled to profit from an insurance claim and
have repairs completed to improve and make better a damaged home.
The initial quotes from T and A were for approximately $133,000 excluding most of
the council and administrative costs associated with obtaining approval for the work to
be completed.
The amended quote from J is for approximately $180,000. This is a varied quote from
the original two quotes provided which were for approximately $168,000 and
$187,000.
The complainant submitted a report from its engineer G. Of significance is the
acceptance from G all damage to the property needs to be repaired because of the
two insured events. G agreed there was evidence of subsidence but blames all the
damage on subsidence caused by the accepted escape of liquid, and not pre-existing
and prolonged water leakage from the downpipe.
Determination | Case number: 641912 Page 5 of 7
G also noted the presence of extensive wood rot due to terminates in the area of the
Impact. It is unclear how or if G considers this to be related to the insured events or
why this damage should be included in the scope of works.
J confirmed its quote was consistent with the opinion of G and the scope of works
suggested in its report of 1 July 2019.
The scope of work used to make the cash settlement offer is based on the scope of
work provided by CRD who does not agree all the work required to the house is
caused by the insured events.
The quotes for all the work to be completed are consistent. The issue in dispute is the
damage caused by the insured events and whether the scope of works accepted
include repair and replacement of pre -existing damage, thus enriching the
complainants in the process.
It is fair and reasonable to accept the quote from the insurer ’s builder
The Panel notes the original assessment of CRD when attending the house in
February 2018 has not changed. CRD noted the subsidence of the footings had
caused the cracking in the floor and resultant damage in the bathroom and laundry
area, especially to the concrete floor. CRD considered the differential movement of
the footings had been occurring for a prolonged period.
The initial report also noted the issue with the downpipes not being connected to the
stormwater system. The insured had used buckets to collect the water from the base
of the downpipes. These downpipes are located right outside the bathroom.
CRD noted the poor state of the house and referred to the pre-purchase report as
evidence of this. There are significant pictures. This is confirmed by the photos and
commentary of G in its report.
G referred to termite infested wood and the associated rot near the area of the
impact. Pictures were very clear as to the state of the wood.
The Panel accepts there is clear evidence of pre-existing damage and maintenance
required to the home at the time of the insured events. The work claimed by the
complainants would put them in a better position than before the insured events. Not
all the work relates to damage caused by the insured events.
The panel does not accept J’s quote as being a fair reflection of the damage caused
by the insured events. The quote includes the cost to repair the pre-existing damage.
In the circumstances the Panel accepts it is fair for the insurer to rely on the quote
provided by T when cash settling the claim.
Determination | Case number: 641912 Page 6 of 7
The insurer needs to make a more significant cash settlement
Although the Panel accepts that the insurer can rely on the scope of works by CRD
and quote from T, the offer made does not allow for the costs associated with the
unknown contingencies and transfer of risk.
Contingencies cover the unexpected additional costs possibly incurred when building
works commence; such costs not able to be determined until such building work
commences.
Contingencies include the insurers evidence increased concrete costs of 2.5% from
April 2020. Its own assessors agreed there were unknown costs.
Contingencies also cover the transfer of risk from the insurer to the complainant given
no warranty is provided by the insurer for the work to be completed.
The Panel is satisfied a cash settlement is appropriate given the pre-existing damage.
The Panel considers consistent with the AFCA approach that it is fair to add 15% to
the cash settlement for contingencies.
Following the conclusions above on the appropriate building costs, the insurer will
need to provide the complainant with a further cash settlement as follows:
Date Action
Accepted loss $ 82,369.98
Plus 15%
contingencies
$12,355.50
Sub total $94,725.48
Less sum paid $70,833.44
Additional amount
payable
$23,892.04
The complainants say that the payment previously sent by the insurer has not been
cashed. If this is correct, the insurer can cancel the previous cheques and settle the
claim for $94,725.48. The previous payment of $70,833.44 paid on 19 May 2019
included interest to that date. It is fair, if the payment has not been cashed that the
insurer pays additional interest on that amount from 19 May 2019 to date of payment
of the claim in accordance with s57 of the Insurance Contracts Act. The insurer is
required to pay interest on the balance of $23, 892.04 from 19 March 2018 to the date
of payment of the claim in accordance with s57 of the Insurance Contracts Act. The
insurer is entitled to reduce the amount paid by any outstanding premium.
Determination | Case number: 641912 Page 7 of 7
2.2 Is the complainant entitled to compensation for non-financial loss?
AFCA can award compensation for non-financial loss.
Under Rule D3.3 of the AFCA rules, AFCA can award compensation of up to $5,000
where there has been an unusual degree of physical inconvenience, time taken to
resolve a situation or interference with a Complainants expectation or enjoyment of
peace of mind.
The complainant is entitled to compensation for non-financial loss
The Panel notes that the complainants have suggested compensation of the
maximum amount of $5,000 each for non-financial loss is appropriate. As the policy is
only in the name of one of the complainants, the panel accepts the maximum
compensation available for non-financial loss is $5,000.
The panel accepts that there has been an unusual degree of inco nvenience and time
taken to resolve the situation. The insurer was required to accept the claim following a
determination of AFCA in January 2019. The cash settlement paid by the insurer in
May 2019 to resolve the complaint was not sufficient.
The cash settlement did not include all relevant fees and charges and the insurer did
not start to address this until January 2020. The insurer revised its calculations on
three occasions to March 2020.
Furthermore, the insurer despite clear evidence in its own reports indicating not all
damage was observed, did not make any allowance for the contingencies or transfer
of risk to the complainant. The insurer should be aware of AFCA’s approach on these
types of issues.
The delay in resolving the complaint is been significant. It is now over 16 months
since it was required to accept the claims and the repairs have not been affected.
Although not all delays can be attributed to the insurer the panel considers the
insurers conduct has caused an unusual degree of inconvenience and time taken to
resolve the situation. The panel is satisfied an award of $2,000 for non-financial loss
is fair and appropriate.