Determination 641910

Dispute over cash settlement for fire repairs and lost rent after tenant eviction

FirmQBE
Decided2020-02-28
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$65,055
Non-financial loss$2,500
Amount claimed$61,009
SourceAFCA PDF

Summary

After a fire at her tenanted industrial building, the complainant disputed the insurer's cash settlement for outstanding repairs and sought lost rent. AFCA increased the cash settlement to $54,508.91, ordered reimbursement of a $1,320 engineering report and $9,226.25 lost rent, and awarded $2,500 non-financial loss.

The quantity surveyor's report was a reasonable starting point, increased for evidentiary uncertainty and the loss of the insurer-backed repair warranty, while lost rent from the existing tenancy was not caused by the fire.

Issues

Subjects and remedies

business interruptionhome or building damagepay claimpay compensationpay interestpay non financial loss

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 641910 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 641910 Page 1 of 15 Case number: 641910 14 January 2020 1 Determination overview 1.1 Complaint The complainant held building insurance for her tenanted industrial property. The property was leased to a motor vehicle repair business. On 14 August 2017, she lodged a claim for fire damage to the building which the insurer accepted. In April 2018, the insurer authorised repairs by AJG. In October 2018, the relationship between the builder and the complainants broke down, and certain repairs remain outstanding. A dispute has arisen as to the scope of the insurer‟s liability for any deficient and outstanding work, and the complainant‟s claim for loss of rent al income. 1.2 Issues and key findings Is the insurer required to increase the cash settlement? Yes. The evidence does not establish the complainant‟s repair quote most accurately reflects the reasonable cost of repairs. The quantity surveyor‟s report is an appropriate starting point to determine a fair cash settlement, since it reasonably reflects the scope of works and the average market value of repairs. QBE‟s offer – based on this report – is $45,424.09. The settlement sum should be increased by a further 20% to account for various evidentiary uncertainties (and possible increased costs), unforeseen variations and the additional risks assumed by the complainant in undertaking the work directly (since she loses the benefit of the insurer‟s lifetime guarantee on repairs). The insurer must also reimburse the complainant for her engineering report and pay compensation for delays and upset caused by the insurer‟s claims handling . Is the insurer liable to compensate the complainant for lost rent ? Yes. Given the delay in the repair process, it is fair in the circumstances that the insurer compensate the complainant for three months of lost rent. 1.3 Determination This determination is substantially in favour of the complainant. Within 14 days of the complainant‟s acceptance of this determination, the insurer is required to: Determination | Case number: 641910 Page 2 of 15  cash settle the complainant‟s claim for building repairs for $54,508.91 (inclusive of GST)  reimburse the complaina nt $1,320 for the cost of her engineering report.  pay $2,500 in compensation for non-financial loss  pay the complainant $9,226.25 (inclusive of GST) for lost rent. The insurer is required to pay statutory interest on the settlement sum from 22 November 2019 (the date of its final offer) until the payment is made. Determination | Case number: 641910 Page 3 of 15 2 Reasons for determination 2.1 Is the insurer required to increase the cash settlement for repairs? Due to concerns with appointed builder and repairs, QBE offered cash settlement On 14 August 2017, fire damaged the insured property. The loss adjuster, CL, appointed a panel builder, AJG, to undertake repairs. Following delays in cleaning and repair concerns, the relationship between the complainant and AJG broke down. The complainant evidently lost confidence in the builder‟s ability to manage the repair process and, on about 31 October 2018, the builder resigned from the project. CL offered a cash settlement based on AJG‟s quote for the outstanding works, which the complainant rejected. It was then decided that the complainant would obtain a quote from a local builder for the cost of repairing any rectification issues and outstanding damage. After some time, on 12 February 2019, the complainant managed to obtain a quote from AMC. However, CL said it did not adhere to the scope of works and was not sufficiently itemised. CL then appointed a building consultant, SDS, to audit the repairs and draft a revised scope of works for rectification and outstanding repairs. SDS did this on 21 March 2019. Based on this revised scope, CL‟s quantity surveyor, QS, then compiled a costings report. On 22 November 2019, CL put fo rward the insurer‟s f inal cash settlement offer based on QS‟s costings. The complainant says the settlement sum is inadequate for her to engage a local builder to carry out repairs. The complainant wants the insurer to:  authorise AMC to carry out repairs, or  authorise repairs using a competent builder, with certain alterations to the scope of work and costings, including increased allowances for repair time and supervision of the project, or  increase the cash settlement so she can contract a builder to do the work. Determination | Case number: 641910 Page 4 of 15 Cash settlement should reflect reasonable cost of repairs Under the terms of the policy, the insurer may settle a claim for damage to the complainant‟s property by:  repairing the damage or rebuilding the property, or  paying the complainant the reasonable cost of doing so. Where a claim is to be settled by a cash settlement, the insurer is required to pay the complainant the reasonable cost of repairing the damage to the property. This means the cash settlement amount should be sufficient to ensure that the complainant is able to engage their own contractors to complete the necessary repairs. Parties agree on basic scope of works In general terms the parties agree that SDS‟s scope of works based on their repair audit dated 29 March 2019 essentially represents the work that needs to be done. However, the parties do disagree about a few items in the scope of works, which I discuss below. More fundamentally, the parties disagree about the costings for the scope of works. I reviewed the available information about costings, including the quote by the original builder, AJG, one by the complainant‟s preferred builder, AMC, and the report provided by the quantity surveyor (QS). AJG’s quote not appropriate The original builder quoted $10,346.43 (inc GST) for the outstanding works. Based on the information to hand, there is no question this quote should be rejected. It does not adhere to the scope of works, lacks critical detail and is demonstrably too low. AMC’s quote does not adhere to scope of works and lacks detail The complainant submitted a quote for repairs from her preferred builder, AMC, for $61,009.41 (inc GST). The quote covers both rectification issues as well as outstanding repairs. However, the quote is insufficiently detailed to be reasonably scrutinised by th e insurer or AFCA. In addition, it appears to be based on the builder‟s inspection of the damage rather than on the agreed scope of works. Therefore, I am unable to conclude it accurately reflects the scope of works or reasonable cost of repairs. QS’s repo rt is a reasonable starting place for determining cash settlement The insurer engaged the QS to assess the reasonable industry or market cost of the outstanding work. The most recent revision of this report puts the costings at $51,724.00 (incl. GST). The insurer‟s final settlement offer dated 22 November 2019 is based on this report, less certain deductions which the parties do not dispute. After Determination | Case number: 641910 Page 5 of 15 the deductions are accounted for, the insurer‟s offer is $45,424.09 ($41,294.63 + $4,129.46 GST). The report is authored by a suitably qualified professional and is based closely on the detailed repair audit and agreed scope of works. As it happens, the parties have not provided any other actionable quotes. However, I am satisfied that QS‟s report , in general, represents the average market value for repairs. I accept the QS is a construction industry professional with expert knowledge on construction costs. The valuation was apparently derived from research and/or internal databases. Ideally the valuation process (including its sources) should have been explained in more detail (I deal with this further below). However, the lack of such an explanation does not invalidate the report. I consider the report represents a reasonable starting place for determining a fair cash settlement. The complainant criticises QS‟s costings on a number of grounds, which I reviewed in light of AFCA‟s approach to assessing evidence. AFCA approach to assessing evidence AFCA forms a view of the dispute based on the weight of available information. We consider documents, submissions, and all relevant circumstances. We tend to give more weight to reports authored by those with relevant expertise. Therefore, where there is a conflict between an opinion of a less qualified party and that of an expert, we tend to prefer the expert‟s opinion unless there are compelling reasons to do otherwise. In addition, AFCA makes findings about the key issues in dispute. This means where information provided by the parties is not directly relevant to those issues or is otherwise extraneous, I have not referred to it as part of my decision. With this in mind, I carefully reviewed the available evidence about the scope of works and costings. Complainant has not established additional items should be included in SOW In her final submission to AFCA, the complainant seeks various additions to the scope of works which are unaccounted for by QS‟s costings. These items total about $ 3,565. The insurer stands by the repair audit report and QS‟s costings and says the complainant has not provided professional evidence to establish her claims. Having reviewed the complainant‟s submissions, I consider that they have generally either been accounted for by QS‟s final report or there is insufficient information to support them. Determination | Case number: 641910 Page 6 of 15 Complainant has not shown roof replacement should be included in SOW The roof originally required cleaning. However, the complainant says that, due to delays in the cleaning process, the roof now requires replacement. She says over time the soot from the fire has probably corroded the metal. In my view, the complainant has not provided sufficient evidence to support her assertion. The assessment evidence does not establish, on balance, the roof requires replacement due to corrosion. Neither has it been shown the insurer was solely responsible for the delays which allegedly resulted in the corrosion. Liability for render to bricks of front office / bathroom unclear The complainant says the scope of works and costings omit the render to the bricks of the front office and bathroom. The complainant estimates the cost of the work to be about $1,500. The insurer maintains it is not liable for the render and that in fact the complainant was cash settled for it. The complainant denies this. Based on the available information, the liability for and cost of this work are not entirely clear, although it seems the render was not part of the agreed scope of works. Considering the complainant‟s detailed concerns and the lack of a comprehensive response by the insurer, it is fair some increased allowance be made for this item. Cost of internal northern wall repair unclear The complainant says the cost of the repairs to the northern walls brickwork should be higher. The complainant‟s preferred builder, AMC, says it will cost $2,400 for the repairs to the internal wall, which is higher than QS‟s estimate. The complainant has provided insufficient evidence to support her view in this regard. The fact AMC‟s estimate is higher than QS‟s does not establish it is more a ccurate. However, neither the insurer nor QS has provided a comprehensive reply to the matter. Therefore, there remains some uncertainty about this item, which I address below. Cleaning, demolition, windows, painting – allowance to be increased The complai nant submits that some of QS‟s costings have been incorrectly calculated and/or are based on incorrect dimensions. These relate to cleaning, demolition, windows and painting. The insurer stands by QS‟s costings and says the complainant has not provided professional evidence to support her position. Determination | Case number: 641910 Page 7 of 15 However, in my view, the complainant‟s submission is cogent and appears consistent with the available evidence. In relation to the bathroom window, the complainant says:  the window was damaged by the fire, as reflected in the original scope of works. It was to be cleaned  however, a builder for AJG, PA, simply replaced the window without consulting the complainant or submitting a variation for the work  the glazier‟s work was „haphazard‟; the window is bright re d and misaligned. The complainant wants the window restored to its original colour and quality. The insurer asserts AJG replaced the small bathroom window outside of the scope of works but has not addressed the other aspects of the complainant‟s argument. The complainant also submits that the original restorer, SCR, should be called to quote on the work as their first quote was comprehensive and included appropriate allowances for OH& S and HEPA filtration. Whilst I acknowledge the complainant‟s submissions and her criticisms of the assessment and cleaning process to date, I do not consider they warrant S re-quoting at this stage. However, given that neither the insurer nor QS have substantively answered the complainant‟s concerns, it is fair that some allowance be made for potential additional requirements in relation to cleaning and the items referred to above. Other costing concerns unsubstantiated, but increase is fair for repair period In addition to the matters discussed above, the complainant disputes a number of items in QS‟s costings and has set out her concerns at length. She says the costings are too low to enable her to contract a local builder to do the work. In particular, she says the insurer has not answered her submission of 28 Oct 2019, which impugns 24 items in QS‟s report . I have addressed some of these items above (for instance, demolition, cleaning). The majority of the outstanding items have either been accounted for in the most recent revision of QS‟s costings or are unsupported by professional evidence. I acknowledge the complainant‟s submission for „equity‟ between the AJG allowances and the QS allowances, on the basis AJG is a local builder and the loss adjuster thought their pricing was fair. However, in my view AJG‟s allowances are not strictly relevant to a determination of the fair market rate by QS; in any case, I would prefer QS‟s figures because they are more recent. Some of the outstanding salient items raised by the complainant relate to: Determination | Case number: 641910 Page 8 of 15  scaffolding and supervision – the complainant says it is likely the works will take longer than QS anticipates  site manager – instead of a part time site manager, the complainant says one should be appointed for a minimum of three months  builder‟s margin – the complainant says the margin of 17% should be closer to 20% or even 25%. There is little evidence to support the complainant‟s figures for these items. However, the insurer has not provided an explanation from QS to justify these items, particularly the reasonable repair period. It is fair some increased allowance applies to account for, at least, a potentially longer repair period. Complainant entitled to be reimbursed for cost of CE’s report The complainant seeks reimbursement for the cost of the engineering report of CE. In my view, this cost was reasonably incurred and the report materially assisted the complainant‟s position in relation to the crack in the northern walls and the bent lintels. The insurer must reimburse the complainant $1,320 for this report. It is fair the insurer increases its cash settlement AFCA needs to be satisfied the proposed cash settlement is sufficient to repair the damage for which the insurer is liable under the policy. Based on the available information, I consider the insurer‟s offer of $45,424.09 represents a reasonable starting point for determining an appropriate cash settlement. QS‟s report draws on figures which are relatively recent and so should accurately reflect the costs of undertaking the works. In addition, I consider the cash settlement amount should be further increased to account for the following matters. Firstly, as I have noted above, there remains evidentiary uncertainty (and potential for increased costs) around the cleaning, render to the bricks of the front office and bathroom , internal northern wall repair, repair period, scaffolding, supervision and managemen t costs . In addition, the complainant has made sound arguments in relation to demolition, windows and painting. Whilst the complainant may not have conclusively made out her claim in respect of all of these items, she has raised concerns which are at least plausible and which the insurer has not comprehensively answered. QS was in a position to justify or clarify some of these items but did not do so. This omission is more significant considering the multiple revisions of QS‟s report and the fact QS has not explained in detail the basis of its market rate appraisal. Determination | Case number: 641910 Page 9 of 15 Secondly, there is the potential for unexpected or other necessary variations to the works which may be required during the course of repairs. Whilst QS has added a contingency of 3%, this may be insufficient. Finally, in accepting a cash settlement, the complainant assumes additional risks on the basis that she loses the benefit of the insurer-backed repair warranty. Therefore, I consider it is fair in all the circumstances that the cash settlement of $45,424.09 be increased by an additional 20% ($9,084.82) to make appropriate allowance for the factors outlined above. In summary, the insurer is required to :  cash settle the com plainant‟s claim for building repairs for $54,508.91  reimburse the complainant $1,320 for the cost of her engineering report. The insurer is required to pay statutory interest on the settlement sum from 22 November 2019 (the date of its final offer) until the payment is made. Compensation for non-financial loss is warranted Under our Rules, AFCA may award up to $5,000 in compensation for non-financial loss due to an insurer‟s claims mismanagement. We award compensation conservatively. This is because complainants are expected to be moderately robust and bear the normal degree of inconvenience associated with the insurance claims process or arranging of insurance. In this case, compensation is warranted because the insurer handled the claim unreasonably overall and this caused undue stress and inconvenience to the complainant. Based on my review of the available information, I am satisfied:  there were unreasonable delays in the cleaning and repair process  the initial cleaning and repairs arranged by AJG were , at least in part, deficient. At one stage the complainant and her husband had to do the cleaning themselves  some of the delays were the responsibility of the complainant and the tenant  it took the complainant over three months (from 1 November 2018 until 12 February 2019) to obtain AMC‟s quote. Whilst the loss adjuster (CL) and the insurer put the responsibility for this delay on the complainant, the complainant says it was unavoidable and the loss adjuster asked her to get the quote. Considering AJG‟s in accurate and unreasonable quote for the outstanding work, it was reasonable for the complainant to obtain her own quote Determination | Case number: 641910 Page 10 of 15  the most substantial delays arose from AJG‟s conduct, the cleaning process and the failure by CL to arrange a repair audit at an earlier stage (or at least offer that option to the insured)  there is a significant difference between the repair quote by AJG for the outstanding repairs and the figure reached by the QS. An insured should not have to second-guess the validity, thoroughness and fairness of figures and proposals put forward by an insurer when having a claim dealt with. The complainant is entitled to $2,500 in compensation for non-financial loss. 2.2 Is the insurer liable to compensate the complainant for lost rent ? Policy covers loss of rental income due to business interruption The complainant ‟s business derived income from renting the insured premises to a tenant, who himself ran a motor mechanic business. The policy covers loss of income that results from an interruption of the business caused by any insured damage that happens at the premises. This is calculated by subtracting the income earned during the indemnity period from the income the business would have earned during the indemnity period had the damage not occurred. Tenant evicted due to refusal to remove contents The complainant evicted the tenant and he vacated the premises on 5 March 2018. The insurer says that, in doing so, the complainant caused the loss of rent. The complainant disagrees, saying:  she evicted the tenant because he consistently refused to reduce the amount of goods he was storing at the premises  it was apparent the premises could not be effectively restored while the tenant‟s contents cluttered the area  both quotes for cleaning by AJG and SCR state that the tenant‟s clutter would have to be removed for the quotes to be valid  the tenant could have stayed if he had cleaned up, but he would in all probability need to be re located to continue to trade while the premises were restored . The policy makes it clear that, for loss of income to be covered, the interruption to the business resulting in loss of income must be caused by the insured damage. Based on the available information, on the balance of probabilities, I am satisfied:  the i nitial „business interruption‟ here was the termination of the tenancy between the insured and the tenant Determination | Case number: 641910 Page 11 of 15  the dominant cause of this was the tenant‟s refusal to remove his contents , rather than the fire damage. Indeed, despite the fire damage, the tenant continued to trade and to pay rent  the evidence does not establish on balance that the tenant‟s removal of contents was essential to permit the cleaning and repairs. The notes about the contents in the cleaning quotes are insufficient, and the complainant‟s contention is not supported by the contemporaneous correspondence and reports by the loss adjuster  it may not have been necessary to evict the tenant in the circumstances. It is unclear whether any other options were explored, for instance, relocating the tenant on a temporary basis. Therefore, on balance, the complainant has not established the loss of rental income from the existing tenancy was caused by the insured damage. Insufficient evidence of misleading conduct or estoppel I also note there is some suggestion in the correspondence that the loss adjuster told the complainant they could be covered for loss of rent if they evicted the tenant. In this regard, I note the loss adjuster‟s report dated 10 August 2018 says: We further wish to advise we verbally informed the Insured that should they evict the tenant then loss of rent would apply. However, in my view there is insufficient information to establish a claim for misleading conduct or equitable estoppel. In this regard, I note:  there are no contemporaneous records explaining when or what CL told the complainant  the tenant vacated five months prior to the comments in the report, so CL may well have made the comments after the eviction (meaning there would have been no reliance by the complainant on what was said)  the above quoted words are followed by this statement :” we have referred the file to our Forensic Advisory Service to review the possibility of claiming loss of income under their Business Interruption policy as a resu lt of the event” . This suggests any statement CL made to the complainant may have been qualified  it seems the complainant relied not on the statement of the loss adjuster, but rather on her own judgment that the tenant should be evicted in order to facilitating restoration of the premises. It is fair that the insurer compensate the complainant for lost rent due to delays Apart from the lost rent from the existing tenancy, the complainant says she is entitled to compensation for lost rental income due to the insurer‟s delays in handling the Determination | Case number: 641910 Page 12 of 15 claim. The submission is that, had the repairs been completed in a timely manner, the complainant could have re-tenanted the property. The complainant has not technically established the policy would respond to such a claim. It does not appear the complainant attempted to rent out the property. This may have been fair enough given the shifting repair completion date and fire damage. Yet the likelihood of obtaining a new tenant post-repairs is not entirely clear, as is the probable amount of rental income. However, I consider it quite plausible that, had the repairs been completed in a timely manner, the complainant would have secured a new tenancy for a rental income comparable to the previous tenancy. According to the insured‟s accountant, the rent was $39,500 (ex GST) in 2016 and $33,550 (ex GST) in 2017. The policy stipulates any loss of rent during the indemnity period is to be calculated by reference to the year preceding the insured event, so for this purpose I have adopted the figure of $33,550 (ex GST). I accept that, but for the mismanagement of this claim by the insurer‟s agents – including the builder and the loss adjuster – the property could have been repaired in a timely manner. It is not entirely clear how long the repairs should have taken from start to finish. However, the loss adjuster CL (in an email of 24 September 2018) suggests an average repair period of 12-16 weeks. It is not a straightforward exercise to calculate the precise period of delay caused by the insurer. At a very high level, the timeline of the claim is as follows:  August 2017 – the claim is lodged  2 February 2018 – AJG is appointed  5 March 2018 – the tenant vacates  5 April 2018 – AJG authorised to start repairs  31 October 2018 – relationship between complainant and AJG breaks down. AJG resigns. Parties decide complainant will get her own quote  12 February 2019 – complainant provides AMC‟s quote, but CL rejects it on the basis it lacks detail and does not abide by scope of works  29 March 2019 – SDS audits repairs and provides revised scope of works  6 June 2019 – quantity surveyor QS‟s report (first draft)  20 November 2019 – final (fourth) draft of QS‟s report  22 November 2019 – QBE‟s final cash settlement offer. Had a competent builder been appointed from the outset, works theoretically could have been completed 12-16 weeks after the tenant vacated, that is, by between about late May and late June 2018. Determination | Case number: 641910 Page 13 of 15 Alternatively, had CL arranged the repair audit in early November 2018, the delays may have been mitigated by about five months. The delays in the cleaning process alone exceeded three months. As I have said, there were certain delays attributable to the tenant and the complainant and the complainant did not seek to undertake repairs to mitigate their loss once the final scope of works was agreed upon. In addition, as noted, it is unknown how long the complainant would take to secure a tenant following completion of repairs. Finally, I note that the policy stipulates that loss of income is calculated by subtracting income earned during the indemnity period from the income that would have been earned during this period had the damage not occurred. The indemnity period in this instance is from 13 August 2017 (the date of damage) until 13 August 2018. Having regard to these matters and the intent of the business interruption coverage, I consider it fair in the circumstances that the insurer compensate the complainant for three months of lost income, at a rate of $33,550 (exclusive of GST) per annum. The insurer must therefore pay the complainant $9,226.25 (inclusive of GST). Determination | Case number: 641910 Page 14 of 15 3 Supporting information 3.1 Summary of key information Policy provisions Business Interruption – Income “This cover section only forms part of your Policy when 'Business interruption section – Income' is shown in the Policy Schedule and is limited to the period of insurance indicated.” Cover “We will pay in accordance with the basis of settlement, for loss of income that results from an interruption of your business caused by any insured damage that happens at the premises. Provided that this insured damage happens during the period of insurance shown for this business interruption cover section.” Basis of settlement 1. Loss of income “ Loss of income will be calculated by subtracting the income earned during the indemnity period from the income you would have earned during the indemnity period had the damage not occurred. Provided that the income you would have earned during the indemnity period had the damage not occurred: (a) will be calculated by reference to the income for: (i) a period of the same duration as the indemnity period that starts a year prior to the date of the damage; or (ii) a period of your normal business operations that corresponds most closely to the indemnity period if your business has operated for less than a year at the start of the indemnity period; and (b) will be adjusted to take into account any: (i) trends of the business and other influences that would vary the income; (ii) variation of normal trading whereby income is maintained during the indemnity period from increased sales of low margin goods; Determination | Case number: 641910 Page 15 of 15 (iii) changes to how stock, materials, finished goods or partially finished goods are used, purchased or sold including salvage sales of stock following insured damage; and (iv) savings made during the indemnity period that reduce the normal cost of running your business. ” Definitions Income “1. Income received from the renting or leasing of any part of the premises including monies paid by the lessee as outgoings under the terms of the rental or leasing agreement; and 2. income from your business at the premises for goods sold, work done, electrical power generated and sold, services rendered or any government approved incentives, subsidies or market development allowances you are entitled to in relation to your business, less: (a) working expenses for freight, packing, bad debts, and the purchase of goods, materials, components, or stock; (b) any other additional uninsured working expenses shown in the Policy Schedule; and (c) payroll if this is shown in the Policy Schedule.” Indemnity period “The period that starts on the date of the damage and ends not later than the number of weeks or months stated in the Policy Schedule after the date Indemnity period of the damage during which results of your business are affected as a conseq uence of the damage.” [the certificate of insurance lists an indemnity period of 12 months]