Determination 641573

Delay in first progress payment and loan drawdown calculations

FirmNAB
Decided2021-03-10
ProductCredit · Business lending
OutcomeFor the complainant in part
Amount awarded$4,603
Non-financial loss—
Amount claimed$178,656
SourceAFCA PDF

Summary

A company with a construction loan complained about the bank's handling of its first progress payment and related costs. AFCA found the bank unreasonably delayed a precondition to the first advance and ordered compensation for interest costs and a refund of one month's service fee, but rejected the claim to reimburse the full invoiced amount.

Under the business loan contract, drawdowns are limited to the quantity surveyor's cost-to-complete assessment less the company's own contribution, and the bank's delay in reviewing contracts of sale unreasonably delayed the first advance.

Issues

Subjects and remedies

small businesspay compensationpay interestrefund fees or charges

Related

All NAB determinations · Find similar determinations

Text of the determination

Determination Case number 641573 Financial firm National Australia Bank Limited Determination | Case number: 641573 Page 2 of 12 Case number: 641573 1 March 2021 1 Determination overview 1.1 Complaint The complainant (company) obtained a construction loan (loan) from the financial firm (bank) for $3,410,000 to build 5 townhouses on the property. The company says:  the bank unreasonably delayed making progress payments causing delay, personal stress for the company’s director (Mr C) and a damaged relationship with the builder and suppliers of the company  it incurred additional interest costs when it had to borrow from a private lender to meet the first delayed progress payment  the bank had advised it would reimburse the company for making the first progress payment, less the company’s contribution to the project, but has not done so  the bank has altered the amount the company would be required to contribute to the project on several occasions  the bank has failed to communicate in a timely manner  the above has caused a significant impact to the timeline and profitability of the project. The company says the bank should have made payment of the first progress payment from the loan in line with the amount of the invoice presented and should compensate it for the additional costs associated with the time and stress the bank has caused. 1.2 Issues and key findings Did the bank calculate loan advances in line with the business loan contract? Yes. The business loan contract sets out a project funding table and the basis for loan drawdowns at each stage of the project. The progress payments could only be made in accordance with the Quantity Surveyor’s assessment of the ‘cost to complete’ less the company’ s own contribution of funds according to the funding table. The company had to meet any costs outside the funding table. I am satisfied loan advances have been appropriately calculated on this basis. Did the bank unreasonably delay the progress payments? The bank’s delay in reviewing relevant contracts of sale led to a delay in the first progress payment. There is no evidence the bank has unreasonably delayed other progress payments. Determination | Case number: 641573 Page 3 of 12 Is the complainant entitled to compensation? Yes. The company is entitled to compensation for additional interest costs associated with alternate funding and the loan facility with the bank. It is also entitled to a refund of one month’s service fee. The company’s other claims are not made out and do not warrant any compensation payment. 1.3 Determination This determination is partially in favour of the complainant. The complainant has 30 days to accept the determination. If the complainant accepts, the financial firm must pay $6331.12 to the complainant’s n ominated bank account within 28 days of the acceptance. If the complainant does not accept the determination, then the financial firm is not required to pay compensation to the complainant. Determination | Case number: 641573 Page 4 of 12 2 Reasons for determination 2.1 Did the bank calculate loan advances in line with the business loan contract? Loan advances had to be calculated in line with the business loan contract The company signed the Business Letter of Offer, the Business Letter of Offer – Property Terms and Conditions and the Business Loan Letter of Offer Agreement Details on 26 January 2019 (the business loan contract). These documents set out the terms for the business loan contract which includes an overdraft facility for $25,000 and a business loan for $3,410,000. The Business Letter of Offer provides that loan drawdowns will be calculated on a ‘cost to complete’ basis subject to the assessment of a Quantity Sur veyor. It says on page 6: Any drawdown against the facility is to be assessed strictly on a cost to complete basis. The Financier [the bank] has to be fully satisfied, based on the most recent certificate of the Quantity Surveyor, that the amount available for drawdown pursuant to the Facility is sufficient to meet all amounts remaining able to be paid in respect of the completion of the project; Any cost overruns or variations are to be met by the customer [the company]. The following page includes a ‘Funding Table’ which sets out the budgeted costs of the project and which of those costs will be met by the loan (an initial $1,250,000 with a further $2,170,000 to follow) and which by the company’s own funds ($35,000 already paid and a further $114,000 to follow). I am satisfied on this basis that any loan drawdowns are to be calculated based on the quantity surveyor’s assessment that the builder has completed the relevant work, its assessment of the ‘cost to complete’ and the company’s own contributio n of funds as set out in the business loan contract. The company is to meet any costs additional to budgeted costs. The parties dispute the amount for the first progress payment The company and the bank dispute the amount to be paid for the first progress payment. The company says the bank should agree to pay the amount the builder invoiced being $177,856.20. The bank disputes this based on the quantity s urveyor’s report dated 27 March 2019 that says only the amount $130,330.04 should be paid. Both amounts exclude GST. The first progress payment was correctly assessed at $130,330.04 The quantity surveyor has assessed that of the builder’s invoice , $39,238 is for variations. Under the business loan contract the company is responsible for any costs Determination | Case number: 641573 Page 5 of 12 that fall outside the budgeted costs in the funding table. I am satisfied that reducing the amount to be drawn from the loan by that amount is in keeping with the business loan contract. This does not however, account entirely for the discrepancy. I am satisfied t hat the balance reflects a 5% retention and the difference between the builder’s assessment of the value of the work completed and that of the quantity surveyor. The business loan contract confirms that only the amount the quantity survey confirms is available to be drawn from the loan. On this basis I am satisfied that the bank has identified the correct amount for the first progress payment. The company says the bank changed amounts to be contributed and advanced As stated above, I am satisfied the identified amount for the first progress payment was in line with the business loan contract. For reasons that I cover in greater detail in section 2.2, the company independently met the first progress payment. The bank was going to reimburse the company from the loan, but this has not occurred. The company says the bank has continually shifted both the amount available for it to draw in reimbursement for that payment, and the amount of the company’s own contribution to the project detailed in the funding table. The bank has not changed the amount of the company’s contribution In an email on 2 April 2019 the bank indicated the company was to contribute $140,000 of its own funds instead of the $114,000 indicated in the business loan contract. That said, the bank corrected this in an email the following day stating: My apologies with the email yesterday The contribution amount is $114K ( not $140K as I had stated ). So why don’t you pay the builder this amount out of the $130K that the QS has verified as payable which will keep the builder happy. In a subsequent email the same day the company’s broker says that given other payments the company had already made, the remaining amount for the company’s contribution to the project was $99,867. The bank replies: That is OK All I am saying is pay the builder so they are happy, and then when the contracts are amended, we can make the adjustments Determination | Case number: 641573 Page 6 of 12 Whether the company contributed the full $114,000 or the reduced amount of $99,867 to the first progress payment, I am satisfied the bank has not changed the company’s contribution amount. Rather the bank made an error stating the contribution should be $140,000, which it quickly corrected. The further correspondence does not indicate a change in the amount for the company to contribute, rather discussion of how much of the $114,000 the company had already contributed at that point. The bank revised the loan advance available for the first progress payment Correspondence does reflect that the bank has continually revised the amount available to advance from the loan to reimburse the company for the delayed payment. First, the bank says it is only the difference between the agreed payment from the quantity surveyor and the $114,000 contribution of the company’s own funds that would be available to advance. However, rather than making that difference available the bank has varied the amounts it says can be drawn as follows:  18 April 2019: the bank said the amount to be advanced was $21,755  10 May 2019: the bank revised the figure to $56,755  14 May 2019: the bank again revised the figure to $10,111.67  5 July 2019: the bank again revised the figure to $41,130.22  8 August 2019: the bank again revised the figure to $25,593.01. Loan advances were calculated in line with the business loan contract I am satisfied that while the bank has changed the amount available under the first progress payment on several occasions, these amounts have been varied based on subsequent reports from the quantity surveyor, which continues to reassess the ‘cost to complete’ the project against the facility limit to recalculate the amount available to advance. I am satisfied this adequately explains why the amount available to reimburse the company varies. Where the quantity surveyor identifies cost overruns, the company is obliged to meet the costs in line with the business loan contract. Because the company did not draw the first payment, cost overruns can be met from the loan but it reduces the amount available for reimbursement to the company. I am satisfied this is consistent with the business loan contract. 2.2 Did the bank unreasonably delay the progress payments? The business loan contract allowed the bank to review contracts of sale The parties agree that the business loan contract allowed the bank to review contracts of sale for the project’s completed townhouses. The parties also agree that under the business loan contract, the bank had to confirm the contracts were satisfactory before the first loan advance could be made. Determination | Case number: 641573 Page 7 of 12 The bank’s delay in reviewing contracts delayed the first progress payment The bank was provided with contracts of sale in November 2018. It made an assessment that the contracts were not enforceable and requested new contracts on 29 March 2019. The first progress payment was due on 1 April 2019. The first progress payment could not be met because the contracts of sale had not been redrawn and signed to satisfy the bank’s concerns. I am satisfied that having had 4-5 months to review the contracts of sale, the bank unreasonably delayed completion of a precondition of the loan advance. This led to a delay in the first progress payment being made because the bank was unable to advance funds from the loan. While the company ultimately paid the first progress payment on 4 April 2019 using alternate funding I am satisfied the bank’s delay in reviewing the contracts delayed the first progress payment. The company used alternate funding for the first progress payment The complainant says the company borrowed funds to make the first progress payment. The bank says it was agreed the company would use the $114,000 agreed contribution from its own funds for that payme nt and that the bank would drawdown the difference once the issue with the contracts of sale was resolved. As noted in the correspondence above, the bank appears to agree in an email on 3 April 2019 that the company has already made contributions on other items in the funding table, so the company remaining contribution amount was just $99,867. The complainant says the company borrowed funds to make the progress payment, not its own funds as discussed. The company did not need to borrow the full amount Given the complainant’s agreement that there was at least $99,867 for the company to still contribute form its own funds, I do not accept that the company needed to borrow the full amount to meet the first progress payment. If the company’s own contribution was always going be met with borrowed funds, the bank is not responsible for those borrowing costs. I am satisfied that at most, the company needed the difference between the $130,330.04 and the $99,867 own funds contribution. Other progress payments were also delayed The parties have provided AFCA with information relating to the first 5 progress payments. This includes bank statements indicating when loan amounts were advanced and reports from the quantity surveyor indicating the amount assessed as available for advance. The reports also include copies of the builder’s invoices which indicate the amounts the builder has claimed and the due date for payment. This information supports that: Determination | Case number: 641573 Page 8 of 12  progress payment 2 was due 26 April 2019 and the loan payment advanced on 1 May 2019  progress payment 3 was due 28 May 2019 and the loan payment on 29 May 2019  progress payment 4 was due on 28 June 2019 and the loan payment on 1 July 2019  progress payment 5 was due on 28 July 2019 and the loan payment on 24 July 2019. Based on this information I am satisfied that the correct amount was advanced on each occasion, but progress payments 2, 3 and 4 were delayed between 1 and 5 days. I am satisfied that the company caused the delayed payment of progress payment 2. Email correspondence between the bank and the company’s broker indicates that one of the company’s directors was overs eas and unable to sign the relevant form. Further, the incorrect amount was entered on the form which meant it had to be amended and resubmitted. The reason for the delay for subsequent payments is unclear. Email correspondence supports that the bank provided the company with the relevant form for signing on 27 May 2019. It is unclear when this was returned. There is insufficient information to support the reason for the delayed payment of progress payment 4. The bank’s actions unreasonably delayed the fi rst progress payment For the reasons outlined above, I am satisfied the bank’s actions unreasonably delayed the first progress payment. If it is reviewed the contracts of sale in a timely manner, this delay would not have occurred. I am not satisfied the information supports the bank has unreasonably delayed subsequent progress payments. 2.3 Is the complainant entitled to compensation? It is fair the bank pays $111.54 for additional interest costs for 2 months The complainant says the bank’s delay in making th e first progress payment meant he incurred additional interest costs related to the alternate funding the company arranged. Given my finding that the company did not need to borrow the full amount, I am satisfied it cannot claim interest on a greater amount than $33,463.04, being the difference between the agreed remaining company contribution of $99,867 and the progress payment of $130,330.04. Further, the interest the company would otherwise having been paying on the loan from the bank, if that amount had been advanced, must be offset against the interest cost from the alternate funding source. Also, from at least 5 July 2019 the bank advised that amount was available to be drawn to reimburse the company for the payment. While that amount was subsequently revised down, I am satisfied this is due to legitimate recal culations relating to funding costs it was the company’s Determination | Case number: 641573 Page 9 of 12 responsibility to meet. For this reason, the interest additional interest cost can only apply for the period 3 April 2019 to 5 July 2019. I am satisfied on this basis that the company’s loss can be no greater than the difference in interest rate between the bank and the alternate funding source for the amount of $33,463.04 a little over a 2 month period. The complainant has not provided evidence to support that the alternate funding source has resulted in higher interest charges. He says the interest cost is 15% per annum but has not substantiated this. I am satisfied it is likely that short notice funding would incur a higher interest rate, but in the absence of clear information supporting the higher rate, it is fair the bank compensates an additional 2% is a fair estimate. 2% per annum on an amount of $33,463.04 for 2 months is. $111.54. The bank should pay interest costs for the 8 day delay The company says, and the bank accepts, the delayed payment led to a stop of work on the project. While the company met the progress payment on 4 April 2019, just 3 days after the invoice was due, work stopped on 2 April 2019 and did not recommence until 10 April 2019. This is a quantifiable 8 day delay to the project, which has delayed the company’s ultimate repayment of the loan facility by 8 days. It is entitled to a refund of interest for that period. This has been calculated at $1,616.58. See section 3.3 for full details. The company’s claimed indirect loss cannot be substantiated or quantified AFCA can award compensation up to $5,000 for indirect or consequential loss. The company says the delayed first payment led to a fractured relationship between the company and the builder which meant the builder did not prioritise the company’s project. The company said this meant resources and subcontractors were not brought to the site as quickly as they may otherwise. This is a claim for indirect rather than direct loss. Likewise, the company says the while work recommenced on 10 April 2019, it did not recommence at the same pace. It says this is because once subcontractors are moved to another project, that work needs to be completed before they can return. The company has provided a copy of correspondence from the builder who confirms the likelihood of this scenario but that he is unable to confirm this is a matter of fact given the time since. I accept it is likely that for the reasons outlined the delayed payment has indirectly caused a greater delay in the project work recommencing at full strength, but I am not satisfied this can be established with sufficient certainty, or sufficiently quanti fied, to warrant an award of compensation. Determination | Case number: 641573 Page 10 of 12 I am also not satisfied the company has established an ongoing delay due to lack of priority. This is because I cannot be satisfied on the information before me of the nature of the ongoing relationship between the builder and the company, or the various factors that may have contributed to that relationship. I also cannot be satisfied of how the nature of the relationship may have impacted the project’s progress. In other words, the company has not substantiated that the delay to the first progress payment impacted its relationship to the builder such that resources were diverted from the project causing an ultimate delay beyond the established 8 days. For these reasons I am satisfied the company’s claimed indir ect loss cannot be substantiated or quantified. It is fair that the bank refund the April 2019 service fee The company pays a monthly service fee on the loan facility of $4,603. Given that:  the bank delayed the first progress payment in April 2019  the delay led to an 8 day stop of work  there is a likely, although unquantifiable, impact on works recommencing at full strength  the delay required the company to source alternate funding at short notice to meet the payment I am satisfied it is fair in all the circumstances that the service fee for the month of April 2019 is refunded. I have considered whether the bank should pay additional compensation for non- financial loss. Mr C experienced significant stress due to the delayed payment. I am satisfied however, that the service fee refund appropriately remedies the stress caused. I am not satisfied that further stress claimed is the fault of the bank. The bank should not compensate the company for the additional QS fee The company says the bank should reimburse it $800 for the cost of an additional one month’s fee payable to the quantity surveyor. Under the terms of the contract, the bank was entitled to engage the quantity surveyor at the company’s expense. There is no information which supports the claim to reimburse the company for the additional expense. The complainant is entitled to $6331.12 in total compensation For the reasons outlined above I am satisfied it is fair in all the circumstances that the bank pay the company total compensation of $6331.12 made up as follows:  $111.54 for the additional interest costs associated with alternate funding  $1616.58 in additional interest costs relating to the 8 day work stop  $4,603 as a refund of the April 2019 monthly service fee. Determination | Case number: 641573 Page 11 of 12 3 Supporting information 3.1 Process AFCA’s approach to this complaint This complaint has been determined based on what is fair in all the circumstances, having regard to the legal principles, applicable industry codes or guidance, good industry practice and previous decisions of AFCA or its predecessor schemes (which are not binding). A full exchange of the relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any issues raised. All of the provided information has been reviewed and considered. The parties have raised numerous issues in their submissions to AFCA. However, commentary in this determination is restricted to those issues considered relevant to the outcome. How we assess complaints AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider available documents, the recollections of the parties, and all relevant circumstances. We give more weight to documents created at the time the events occurred. If there is no relevant documentation, we will decide what is most likely to have occurred based on the information provided to us. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Method for recalculating the available loan advance for first progress payment The 18 April 2019 calculation appropriately reflects the method for recalculating the available loan advance amount for the first progress payment. Facility Limit 2,160,000.00 Drawn - less: retention 18,370.00 Available 2,141,630.00 CTC 2,156,836.00 Addback Financing Cost in funding table 58,306.00 less Actual Financing Costs 19520 less Legal Fees (in addition to funding table) 1,825.00 Available 21,755.00 Determination | Case number: 641573 Page 12 of 12 3.3 Interest refund calculation Amount Loan balance for period 1 April 2019 – 9 April 2019 $1,250,000 Interest rate applicable as at 1 April 2019 5.245% pa Calculation Loan $1,250,000 @ 5.245% pa Daily interest expense ($65,562.50 / 365 days) Interest refundable 1 April 2019 – 9 April 2019 (9 days) $65,562.50 pa $179.62 $1,616.58

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.