Home / Suncorp Group / Determination 638759
Determination 638759
Cash settlement of water damage building claim after prior FOS determination
Summary
The insurer offered a cash settlement for building water damage repairs and the complainant sought repairs instead. AFCA ordered cash settlement of $111,500, a 10% uplift on the offer, and an engineering assessment of foundations.
Cash settlement was a reasonable exercise of the policy discretion given the dispute history, and the offer was increased to allow for transfer of risk.
Issues
- Claim amount dispute primary · not upheld“the insurer has reasonably exercised its discretion to cash settle the balance of the claim”
- Poor claim handling secondary · not upheld“I am satisfied the insurer substantially complied with the FOS determination”
- Repairs or contractors secondary · not upheld“I do not consider the insurer's omission was entirely unreasonable in the circumstances”
Subjects and remedies
pay claimreassess claim
Related
All Suncorp Group determinations · Find similar determinations
Text of the determination
Determination
Case number 638759
Financial firm AAI Limited
Determination | Case number: 638759 Page 2 of 16
Case number: 638759 19 December 2019
1 Determination overview
1.1 Complaint
The complainant held home and contents insurance with the financial firm (insurer)
and lodged a claim on 30 November 2014 for water damage to his property. The
insurer accepted the claim and authorised repairs in accordance with an agreed
scope of works.
A dispute then arose as to the scope of the insurer’s liability for certain damage, the
quality of and timeframe for repairs, and consequential loss due to the insurer’s
actions. On 11 September 2018, the Financial Ombudsman Service (FOS) issued a
determination on these issues. The parties initially worked together to implement the
determination, but the relationship has now broken down. The insurer has offered a
cash settlement of $101,287.73 to resolve the dispute.
The complainant has approached AFCA for a further review because he says the
insurer failed to comply with the FOS determination and should authorise repairs
rather than cash settle the claim.
1.2 Issues and key findings
Has the insurer complied with the FOS determination?
The insurer has substantially complied with the FOS determination.
How should the claim be settled?
It is fair in the circumstances given the history of this complaint and the relationship
between the parties that the claim be cash settled. I am satisfied the cash settlement
offered based on the detailed scope of works obtained by the insurer is fair but should
be increased by 10% to allow for the transfer of risk to the complainant. The offer
should be rounded up to $111,500.00 .
In addition, the Insurer should arrange an inspection of the property foundations as
set out under section 2.2 of this determination.
1.3 Determination
This determination is substantially in favour of the insurer. Within 14 days of the
complainant’s acceptance of this determination, the insurer is to ca sh settle the claim
for $111,500.00.
The insurer must also arrange an inspection of the property’s foundations , as set out
in section 2.2 below, to determine whether there is any damage attributable to its
previous repairs to the ensuite bathroom and laundry floor drains.
Determination | Case number: 638759 Page 3 of 16
2 Reasons for determination
There has been a full exchange of material between the parties, and each party has
had the opportunity to address the issues arising from that.
This determination follows consideration o f all the information exchanged and is
based on what is fair in all the circumstances, having regard to the relevant legal
principles, terms of the policy, good industry practice including codes of practice and
previous AFCA decisions where applicable.
2.1 Has the insurer complied with the FOS determination?
Issues arising from the complainant’s claim have been before FOS in 2016 and 2018.
I attended the complainant’s property with the parties following the first complaint in
2016 and issued the determination in 2018 following the second complaint. At section
3 of this determination I have summarised the key events and documents from the
2018 determination to date.
In summary the FOS determination held that the insurer:
is to pay compensation for non-financial loss
is to appoint an a ssessor to inspect the complainant’s contents and settle this
aspect of the claim to the extent of its liability
is to appoint an independent assessor to identify further work required to complete
the repairs in line with the scope of works; the insurer is to then arrange those
repairs, as well as a final post-repair inspection of the work
is to arrange a post-repair inspection of any repair-related damage to
drainage/garden/plants, and to topsoil and seed the area around the water tank
is not liable for the damage to the patio, retaining wall, garage/living area.
I will address each of the directives to ascertain whether the insurer has complied with
the determination.
Insurer paid compensation and cash settled for contents
I note the parties agree the insurer complied with the determination by:
paying the complainant compensation for non-financial loss
appointing an assessor, restorer and hygienist to inspect and restore damaged
contents
cash settling the complainant for the damaged contents to the extent of its liability.
The most contentious aspect of this complaint relates to the independent assessment
of the repair work.
Determination | Case number: 638759 Page 4 of 16
Insurer appointed independent assessors to inspect repairs
By way of background, after the initial storm/sewerage inundation the insurer
appointed DC to carry out repairs; DC then appointed SC to do rectification works.
For this to happen, the whole building was stripped out of internal linings including
fixtures and fittings. The complainant was not happy with the works and pro vided a list
of defects to be addressed.
Following the FOS determination, the parties agreed on the list of defects and the
insurer briefed the engineer, KM, and the building consultant, SBC, to undertake a
forensic audit of the repairs. On 16 November 2018, the engineer provided its report
on structural defects. Between about January and March 2019, DC undertook
rectification works. On 26 April 2019, SBC provided its report and scope of works for
rectification repairs.
The complainant disputed the findings of SBC and, on 20 May 2019, the insurer
agreed to engage QBCC to conduct an additional independent assessment.
Between June and July 2019, the parties provided relevant documents to QBCC for
the inspection, but on 17 July 2019 the complainant withdrew his authority for the
insurer to deal with QBCC.
Between July and November 2019, the complainant attempted to arrange the
inspection.
However, on 13 November 2019, QBCC declined to conduct the inspection on the
basis that:
the complainant refused to provide a list of defects to be inspected
the complainant apparently wants a full repair audit, that is, an audit of all repairs
completed to date (not only a list of identified defects)
QBCC does not conduct full repair audits. This is a task for a building consultant.
In my view, by appointing KM and SBC the insurer complied with the FOS
determination. The determination held that the insurer was to arrange an independent
assessment of any additional work required to complete repairs according to the
scope of works. This means the inspection was to assess the repair defects and
outstanding repairs. The determination did not require a full repair audit
(encompassing completed repairs which were apparently not defective).
The complainant has not provided compelling information to establish the inspections
by KM and SBC were flawed or that they did not comply with the determination. The
complainant has not established that an additional full repair audit was necessary or
appropriate in the circumstances.
Determination | Case number: 638759 Page 5 of 16
Insurer’s failure to rectify defective repairs not unreasonable in the
circumstances
The FOS determination required the insurer to rectify the defects identified in SBC’s
assessment. The insurer did not do this, and the complainant says he never told AB
not to carry out the rectification.
The complainant says the only substantially complete repairs are those to the kitchen,
lounge room and dining room ceilings.
I do not consider the insurer’s omission was entirely unreasonable in the
circumstances, given:
the complainant disputed the scope of works between May and September 2019
the parties were in dispute about various other aspects of the claim through the
AFCA process
the complainant did not ask for AB to continue the repairs as per the SBC scope of
works in the meantime
the insurer says it had the impression the complainant did not want AB to do the
rectification work until the QBCC inspection was complete. Although I was unable
to find contemporaneous correspondence in support of this, I consider it was a
reasonable presumption in the circumstances described above.
I accept that, on about 22 August 2019, the complainant asked the insurer to
commence repairs even though the QBCC assessment was pending. The insurer did
not do so because it was concerned to ensure the scope of works was complete and
that defects remained in-situ for the QBCC inspection. The scope was finalised on 13
September, followed by the insurer’s cash settlement offer on 16 September 2019.
I accept that the insurer has acted reasonably in the circumstances. It is fair that the
insurer tried to resolve the issues with the scope of works before proceeding further
with the rectification work.
Given the available information, I do not consider the insurer failed to comply with the
FOS determination.
Insurer liable for repair-related damage and to soil/seed water tank
The FOS determination stated that, once repairs are complete, the insurer is required
to:
arrange an independent assessment of the drainage, garden and/or plants due to
the repair process
topsoil and seed the area around the water tank.
KM inspected the driveway drainage and garden damage. The insurer then cash
settled the complainant for the garden damage.
Determination | Case number: 638759 Page 6 of 16
The insurer has not yet had an opportunity to topsoil and seed the area around the
water tank, or repair the driveway, as the main repairs are not complete. The insurer
is still liable for this work. The cost for completing this work is included in the cash
settlement offer.
Insurer not liable for solar, damage to patio, retaining wall, garage/living area
As per the FOS determination, the insurer is entitled to deny the complainant’s claim
with respect to the solar power, damage sustained to the patio, retaining wall, and
termite damage to the back garage.
The complainant says AFCA should re-consider these issues considering the new
information he obtained after the previous determination.
Under rule A.15.3 of the AFCA rules a determination represents a final decision on
the issues. The complainant accepted the determination. Under rule C.1.2(c), where a
complaint raises the same events and facts by the same complainant and there is
insufficient additional events and facts raised to warrant a new complaint, AFCA must
exclude the complaint. No new issues have been raised to warrant a new complaint.
There are insufficient additional events or facts raised to warrant AFCA considering
the claim for the damage as a new complaint.
Insurer has substantially complied with the determination
In summary, for the reasons set out above, I am satisfied the insurer substantially
complied with the FOS determination.
2.2 How should the claim be settled?
Insurer is entitled to cash settle the claim
Under the terms of the policy, the insurer may settle a claim for damage to the
complainant’s property by:
repairing the damage or rebuilding the property, or
paying the complainant the reasonable cost of doing so.
The policy provides the insurer with a discretion as to the method of settlement. Such
discretion must be exercised fairly, reasonably and consistent with the principles of
utmost good faith.
The insurer has elected to cash settle the balance of the claim given the nature and
history of the dispute. The complainant rejects the offer and wants the insurer to
authorise repairs, principally so that he has the benefit of the lifetime repair guarantee
under the policy. He says that, given the extended delays and numerous repair
defects up to this point, a cash settlement would be unfair.
Having carefully considered the matter, in my view the insurer has reasonably
exercised its discretion to cash settle the balance of the claim because:
Determination | Case number: 638759 Page 7 of 16
the relationship between the parties has deteriorated to the point that the
complainant no longer trusts the insurer or its contractors
following multiple forensic repair audits, the scope of works is no longer in dispute
and the ultimate repair cost is relatively certain
the quote by AB underlying the insurer’s offe r is actionable by the complainant
the outstanding work – including defective repairs – is not complicated to address.
It is relatively straightforward, non-structural building work which should not require
extensive oversight by other construction specialists (for instance, engineers)
as set out below, the scope of the insurer’s offer is reasonable . It covers all
disputed items in the SBC report. It also covers the strip out of the bathroom,
ensuite and laundry, to address the complainant’s concerns about waterproofing
and quality of workmanship
the issues have been ongoing for five years and have been the subject of multiple
complaints before this Service. There is limited information to support the
complainant ’ s ongoing issues
a cash settlement will bring finality to the claim.
In these circumstances, it is appropriate for the claim to be resolved by way of a cash
settlement.
Cash settlement should reflect reasonable cost of repairs
Where a claim is to be settled by a cash settlement, the insurer is required to pay the
complainant the reasonable cost of repairing the damage to the property. A cash
settlement amount should be sufficient to ensure that the complainant is able to
engage his own contractors to complete the necessary repairs.
The insurer’s offer is based on a n actionable repair quote by AB which adheres to the
agreed scope of works.
Scope of works is comprehensive
The scope of works was initially prepared with the oversight of the engineer, KM, and
the forensic building consultant, SBC. It was amended – and finalised – in close
consultation with the complainant in the course of this complaint.
The complainant has not provided substantive evidence to undermine the accuracy of
the scope of works.
Whilst the complainant says the scope should also cover roof leaks, he has provided
insufficient information to substantiate this assertion. In addition, as noted above,
there is no basis to cover the damage previously dealt with by the FOS determination.
I also note the insurer previously covered termite damage on a goodwill basis only,
and the evidence does not establish the insurer is liable for it. Termite treatment is a
maintenance issue; its inclusion in the scope of works is not warranted.
Determination | Case number: 638759 Page 8 of 16
Based on my review of the available evidence, I accept the scope of works provides
an accurate assessment of the repairs required to restore the property to its pre -loss
condition.
It is fair the insurer increases cash settlement by 10%
AFCA needs to be satisfied the proposed cash settlement is sufficient to repair the
damage for which the insurer is liable under the policy.
Based on the available information, I consider the insurer’s offer of $101,287.73
represents a reasonable starting point for determining an appropriate cash settlement
amount. The quote on which that is based is relatively recent and should accurately
reflect the costs of undertaking the works.
The quote is actionable and comprehensive in its scope, extending even to items the
insurer is not strictly liable for (such as the non-defective works in the SBC report).
The complainant has not provided persuasive evidence to undermine the
completeness of either the scope of works or the quote.
I acknowledge that in cash settling the claim, the complainant gives up the lifetime
guarantee provided under the policy. Furthermore, a cash settlement transfers all the
risk from the insurer to the complainant of any unforeseen damage and any additional
work required once repairs commence (although in this case there is little to suggest
the likely requirement of additional works).
I consider it fair in the circumstances to allow a further 10%, on top of the quote to
account for the transfer of the risk to the complainant. It is fair that this figure be
rounded up to the nearest $500.00.
Accordingly, I determine that wi thin 14 days of the complainant’s acceptance of this
determination, the insurer is to cash settle the balance of the claim for building repairs
for $111,500.00. The insurer is not required to pay interest on the settlement sum.
Insurer must inspect foundations for repair-related damage
On 2 September 2019 AB engaged a plumber to review, among other things,
drainage and waste pipes to the ensuite bathroom and laundry. The plumber found
that the repairs were defective and suggested they may have led to water damage to
the foundations of the property.
The plumber’s comments are brief and speculative, and I do not consider him
appropriately qualified to determine whether structural damage has occurred. There is
no evidence of physical damage to the foundations. T he plumber’s report is
insufficient to establish a prima facie claim for repair-related foundation damage.
Nevertheless, the insurer has offered to pay for an engineering assessment of the
foundations to determine whether there is any such damage caused by previous
repairs to the ensuite bathroom and laundry floor drains / waste pipes.
Determination | Case number: 638759 Page 9 of 16
This is a reasonable offer. Subject to the complainants’ acceptance of this
determination, the insurer is to arrange for an engineering assessment. Once the
report is complete, the insurer is to determine its liability under the policy for any
repair-related damage.
Determination | Case number: 638759 Page 10 of 16
3 Supporting information
3.1 Summary of key information
Chronology of key events / documents
This chronology is a high-level summary of key events in the claims process. It does
not record every instance of contact between the parties.
Abbreviations:
AB = builder appointed to deal with outstanding repairs and rectification after the FOS
determination, who provided the final scope of works on which the insurer’s cash
settlement offer is based
Com = the complainant
DC = builder initially contracted by FF to conduct repairs
FF = the insurer, AAI
KM = engineer contracted to assess structural defects after the FOS determination
QBCC = building commission that the parties approached for an independent
assessment following the initial SBC repair audit
SBC = building consultant contracted to assess repair defects after the FOS
determination
SOW = scope of works
Date / document Event / details
11 Sep 2018 FOS determination
The dispute concerns:
quality of the repairs conducted by the FSP and delays
contamination of contents placed in storage containers
additional damage caused to the property during the repair process
damage to the rear patio and retaining wall
consequential loss suffered as a result of the FSP’s actions.
In summary, the determination held:
FSP t o appoint independent assessor and compl ete SOW
Within 14 days of the applicant’s acceptance of this Determination the
FSP is to appoint an independent building inspector as set out under
section 2.1 of this determination to identify the further work requi red to
complete the repairs in accordance with the scope of works.
Determination | Case number: 638759 Page 11 of 16
Date / document Event / details
FSP to inspect contents and cash settle
Within 14 days of the acceptanc e of this determination and subject to
the applicant providing access to the storage containers, the FSP is to
appoin t an independent assessor to inspect the stored contents and
identify those items contaminat ed and/or damaged whilst in storage.
The FSP is to then either restore/repair or cash settle the applicant for
the cost to repair/ replace the contaminated or damage d items.
FSP to arrange post - repair inspection of any repair - related damage
to drainage/garden/plants.
FSP to al so topsoil and seed area around water tank
Upon completion of all works to the property, the FSP is to arrange for
the independent building ins pector to assess and determine the extent
of damage to the drainage, garden and/or plants caused as a result of
the repair process. In addition, the FSP is to topsoil and seed the area
surrounding the new water tank.
FSP not liable for patio, retaining wal l, garage/living area
The FSP is otherwise entitled to deny the applicant’s claim with respect
to damage sustained to the patio and retaining wall and deny the
applicant’s claim with respect to termite damage to the back garage.
FSP to pay compensation for non - fin loss
The FSP is to pay the applicant $1,500 compensation for non - financial
loss pursuant to paragraph 9.3 of the Terms of Reference.
September 2018 27 Sep: FF pays non - financial loss compensation as required by
determination
28 Sep: KM engineer and SBC appointed to audit repairs. Re storer
also appointed
16 November 2018 KM engineering report on defects
Defects from FOS determination inspected; recommendations for repair
drafted.
4 Dec 2018 Restorer report / inventory on contents
Jan - March 2019 DC completes partial rectification
13 Feb: FF email update to Com:
- DC almost completed works. Once they do, SBC will do an audit of the
repairs to make sure they are up to standard, and any defects will be
rectified
- AB will then complete driveway repairs
11 Apr 2019 Onsite meeting to confirm outstanding repairs and Com concerns
over repair quality
In attendance: Com, DC, AB, FF
Determination | Case number: 638759 Page 12 of 16
Date / document Event / details
In summary:
Com shows everyone what he considers to be outstanding defects. List
to be provided to SBC for audit
DC to finalise repairs re water tank filter and turf around the water tank
AB to complete all remaining rectification identified by SBC
26 Apr 2019 SBC repair audit report and SOW
In summary:
Inspection carried out on 16 April 2019
As background, the complainant said following the storm/sewerage
inundation, the FF appointed DC to carry out repairs who appointed SC
to do rectification works. For this to happen, the whole building was
stripped out of internal linings including fixtures and fittings. The
complainant was not happy with the works and provided his own list of
defects which require fixing
Complaint It ems 1, 2, 4, 5, 8, 19, 20, 22, 24, 25, 29, 30, 34, 36, 38, 42,
43, 44, 45, 46, 47, 49, 52, and 53 are consider defect building works
and not carried out to an acceptable industry standard
Complaint It ems 3, 6, 7, 9, 10, 11, 12, 13, 14, 16, 17, 18, 21, 23, 26, 27,
28, 31, 32, 33, 35, 37, 39, 40, 41, and 48 are works considered carried
out to an acceptable industry standard with no defect sighte d
Complaint It em 51 has been rectified and withdrawn by the Insured
Complaint It ems 50 and 51 are considered to be pre - existing defects
that cannot be attributed towards the claimed event
A scope was provided addressing the defective works
May 2019 2 May: FF emails Com with SBC findings, offering to authori se
rectification of identified defects
7 May: Com di sputes SOW item s
10 - 13 May: Com di spute s re storer’s contents a sse ssment
8 May: AFCA complaint lodged
Complainant says:
FF has not complied with FOS determination
FF is obliged to rectify defects but has not done so
Given the history of FF’s failure to carry out repairs to standard, the FF
is obliged to arrange a ‘full building inspection’, rat her than an
inspection limited to the list of defects he p rovides
20 May: site meeting with senior AAI staff re claim
Agreement reached between parties:
Payment of the contents sum insured under the claim wit hout the need
for further assessment or particularisation of costing for non -
salvageable items [in late May FF pays sum insured]
Determination | Case number: 638759 Page 13 of 16
Date / document Event / details
Cont ents and storage containers to be removed from site as soon as
possible
Further testing by a hygienist of the remaining contents items which
had sentimental value stored in boxes in the garage and a storage
container
Further in dependent building assessment by QBCC to be arranged.
29 May: FF’ s final decision letter , FF completes contents settlement
payment up to sum insured
June – July 2019 1. Parties discuss / prepare for QBCC inspection
2. Contents a sse ssment reports finalised
17 July 2019 Com withdraws authority for FF to deal with QBCC on hi s behalf
August 2019 1. Com says QBCC ca se to be allocated in two weeks
2. Com also raise s i ssues re:
a) grey water drains
b) solar system (due to DC previously disconnecting and cleaning panels )
[raised in previous determination]
c) patio and retaining wall [raised in previous determination]
3. AB provides report on solar and drains
No solar damage caused by FF’s conduct or insured event. Connection
issue re solar fixed, solar working correctly now.
Blocked drains cleared. Complete pump - out and refill of system
recommended.
SOW updated.
September 2019 1. Com not happy with updated SOW
- FF is under impression Com does not want AB to complete works
pending inspection by QBCC
- however, Com denies this, saying he never told AB to stop working
- FF makes changes to SOW in line with Com’s suggestions
2. AAI’ s senior advisor (SA) and senior building coordinator (BC)
meet with Com on 9 Sep to discuss Com’ s i ssue s
3. Final AB SOW (13 Sep) and FF offer (16 Sep) :
to reimburse Com $1,330 for the screen door;
to add reconnection of lights in kitchen/dining/lounge area to SOW;
Determination | Case number: 638759 Page 14 of 16
Date / document Event / details
various items discussed at meeting of 9 Sep 2019 be included in the
SOW;
to settle outstanding works on the claim by way of cash settlement,
based on the AB building quote
the FF’s final offer also includes disputed items from SBC’s repair audit,
the driveway drainage and the garden bed edging
November 2019 13 Nov: QBCC refuse s to undertake inspection as complainant did
not provide list of defects
Key policy provisions
What you are covered for - Insured events
The policy covers various insured events including storm.
We do not cover
Loss or damage caused by:
…
• insects, vermin or rodents, but we will cov er damage they cause if it is covered
under the following insured events:
> ‘Fire’ (see page 18);
> ‘Escape of liquid’ (see page 23).
• animals pecking, biting, clawing, scratching, tearing or chewing your home or
contents, or damage caused by their urine or excrement…
General exclusions (cont.)
You are not covered under any section of this policy for damage, loss, cost or
legal liability that is caused by, arises from or involves:
…
Failing to take care of your home or contents
your failure to:
• take reasonable care of your home or unit and contents;
• keep your home or unit and any contents in good condition and well maintained.
For the meaning of ‘good condition’ see the ‘Glossary of important words and
phrases’ section on page 73 of PDS;
• fix fault s and defects as soon as you become aware of them.
Determination | Case number: 638759 Page 15 of 16
Ground movement
erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage
or any other earth movement, but we will cover landslide or subsidence that is
specifically covered under the following insured events:
• ‘Storm’ (see page 20);
• ‘Flood’ (see page 19);
• ‘Earthquake and Tsunami’ (see page 21);
• ‘Explosion’ (see page 25).
…
Wear, tear and gradual deterioration
wear, tear, rust, fading, rising damp, mould, mildew, corrosion, rot, action of light,
atmospheric or climatic conditions or gradual deterioration such as, but not limited
to:
• tiles and their adhesive or grouting breaking down;
• weathering of roof tiles or roof ridge capping;
• gradual weathering and breakdown of bric ks, mortar or concrete.
How we settle your claim
We choose how we settle home claims
If we agree to pay a claim for loss, theft or damage to your home, we will decide if
we will:
• repair damage to your home;
• rebuild your home;
• pay you what it would co st us to repair or rebuild your home;
• pay you the sum insured for your home.
Definitions
Good condition
means your home or unit and contents do not have any faults or defects that
might cause loss or damage to your home or unit and contents, loss or damage to
property of others or injury to people. This includes but is not limited to the
following:
• the roof does not leak when it rains;
Determination | Case number: 638759 Page 16 of 16
• there are no areas of the roof that are rusted through;
• there is no wood rot, termite or white ant damage to your h ome or unit;
• there are no holes in floors, walls, ceilings or any other parts of your home or
unit (e.g. external wall cladding, internal plaster, floorboards);
• there are no boarded up or broken windows;
• there are no steps, gutters, flooring, walls, ceilings or any other areas of your
home or unit that are loose, falling down, missing or rusted through;
• all previous damage including damage caused by flood has been repaired;
• your home or unit is not infested with vermin;
• there are no trespassers (squatters) or unauthorised persons occupying your
home or unit.