Home / QBE / Determination 637690

Determination 637690

Flood claim cash settlement amount and handling of delayed repairs

FirmQBE
Decided2020-08-27
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$4,792
Non-financial loss$500
Amount claimed$95,845
SourceAFCA PDF

Summary

After a flood, the complainant's building claims were cash settled, and he later sought a further 20 percent for repairs delayed by mould remediation. AFCA ordered a 1 percent increase to the building settlements, continued temporary accommodation and loss of rent cover, and $500 for service issues.

Delays were outside the insurer's control, but the settlements were agreed months before handover, so a fair uplift for likely cost increases applies while the unsubstantiated 20 percent claim is rejected.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay non financial loss

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 637690 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 637690 Page 1 of 8 Case number: 637690 31 July 2020 1 Determination overview 1.1 Complaint The complainant lodged four claims under his home and contents policies held with the financial firm (insurer) following a flood event on 3 February 2019. The flood caused damage to the complainant’s residential property and his investment proper ty. The insurer cash settled each of the two building and the two contents claims for amounts agreed with the complainant at the time . However, the complainant now seeks an additional 20% of the cash settlement amount for repair costs for each building. He says delays in the properties being handed over to him following claim- related mould remediation meant costs (including for further temporary accommodation and loss of rent) increased by the time he was able to commence the work. The complainant also says the way in which the insurer handled the claims has caused him an unusual degree of stress and inconvenience. 1.2 Issues and key findings Is the insurer liable for further costs beyond the cash settlement made? While delays in the handover of the buildings after mould remediation were effectively outside the control of the insurer, those delays did, on balance, mean repair costs would likely be greater than the cash settlements which had been agreed based on a particular expected handover date. If the insurer had been undertaking the repairs itself, it would have had to meet any cost increase caused by the delays. So, it is fair in the particular circumstances that the settlement be adjusted to address the likelihood of increased costs for repairs, loss of rent and temporary accommodation because of the delayed handover. The complainant is also entitled to $500 in compensation for non-financial loss due to service-related issues. 1.3 Determination This determination is partly in favour of the complainant. The insurer is required to pay $500 as compensation for non-financial loss; to continue paying reasonable temporary accommodation costs and loss of rent until the respective properties are fit for occupation, subject to the policy limit and the complainant providing relevant receipts/evidence; and to increase the settlement for building repair costs by paying a further $4,792.23 (as set out in section 2.1 below). Determination | Case number: 637690 Page 2 of 8 2 Reasons for determination 2.1 Is the insurer liable for further costs beyond the cash settlement made? Circumstances of loss not in dispute The complainant lodged four claims with the insurer on or around 5 February 2019 after both his home and investment property were damaged in a flood event on 3 February 2019. The flood caused significant damage, including mould, and both properties were uninhabitable. This dispute is in relation to the two building claims only. The contents claims are considered resolved, as the insurer has cash settled both contents claims to the maximum policy limit. On 17 June 2019, the insurer cash settled both building claims for amounts agreed at the time. The complainant then arranged with his preferred builder for repairs, based on an anticipated handover on 15 July 2019, which is the date he had been told to expect by the insurer. The handover was delayed, however, as clearance certificates following mould remediation were not available and provided to the complainant until 21 September 2019. Mould remediation was appropriate and efficient, in the circumstances Following the flood, the insurer engaged mycologist M to lead mould remediation in both properties, together with the services of restorer C. It is accepted that building repairs could not be undertaken to the properties until they had been dried out and final certification received that all mould had been remediated and it was safe to commence work. Due to the extent of damage and overall weather conditions, a number of mould treatments and samples were required before the properties returned to normal ecology. The insurer appointed mycologist M in April 2019 and an initial report was provided on 16 May 2019. Mould remediation work by restorer C then proceeded over several months up until July 2019. M ’s final reports and clearances for both buildings were dated 18 September 2019 and were provided to the complainant by the insurer on 21 September 2019. (It is worth noting that, in the intervening months, other preliminary assessments/scopes of work for repair were also being undertaken to the extent reasonably required and possible in the circumstances.) The complainant is dissatisfied with the time taken by the insurer to finalise the mould remediation work, although the insurer has explained that prevailing moisture conditions caused similar timing issues at other properties in the area. I understand Determination | Case number: 637690 Page 3 of 8 the complainant also wanted the opportunity for his own expert to review M’s final reports. I have no reason to doubt the appointed restorer and mycologist were appropriately qualified to assess the mould damage and provide the necessary treatment and certifications. While there does appear to have been a delay in the final clearances being provided to the insurer by the mycologist, the evidence does not show the process undertaken by the insurer and its experts in relation to the mould works was in itself unnecessarily protracted, inefficient or inadequate. Nor is it clear that the complainant should have needed any further confirmation from his own expert (which then presumably resulted in further delays in repairs commencing). It is reasonable to accept that M’s capacity to act more promptly in providing its final certifications was likely to have been affected by the demands on its services given the major flooding event in the region , which is what gave rise to the complainant’s claims. That is something which is outside the insurer’s own control, and I note the insurer did provide M’s final certificatio ns to the complainant within three days of their being issued. I am satisfied, in the particular circumstances, the insurer has acted reasonably in dealing with the mould remediation issues. I do not consider it should be held responsible for delays which were essentially outside its control. Complainant seeks additional cash settlement The complainant seeks additional repair costs for both properties due to the delay in handover. He also wants extended cover for loss of rent and temporary accommodation until June 2020. In support of his position, the complainant has provided a letter dated 18 September 2019 from the construction company (GR) he had appointed directly to carry out the building repairs. GR points out:  the agreement was for properties to be handed over 15 July 2019  with the delay in handover there would be a 20% increase in pricing for repairs  as well, there are significant penalties with delaying subcontractors. Given the delayed start date, GR says there will be further consequential delays (with certain materials) and that would set back the anticipated completion date for repair work beyond April 2020. It is not clear what the current status of repair work is, whether it has now already been completed, and if so, when it was completed and at what actual cost. Increase of 20% in repair costs has not been substantiated When providing an insured with a cash settlement for repair costs, an insurer should also allow for builder’s margi n/contingencies and the transfer of risk. It is also Determination | Case number: 637690 Page 4 of 8 important to ensure, as far as possible, that any cash settlement is based on quotes actionable by the complainant as a retail customer. The cash settlement amounts from June 2019 were agreed by the parties based on scopes of works from the insurer’s service providers. The amounts settled for each property included an 18% margin on the repair costs and I consider this it a reasonable allowance in the circumstances to account for builder’s margin and tran sfer of risk. I have no reason to consider the building repair settlements as initially agreed by the parties were inadequate at the time. The question is whether there should be any increase to account for the delayed start of work because of the later than anticipated handover following mould remediation. I appreciate that delays in being able to commence repairs are likely to have disrupted scheduling of work and ordering of materials . As GR points out in his letter, the demand on suppliers and trades at the time was significant. In the meantime, however, the complainant/GR have not substantiated their anticipated 20% cost increase. On the available evidence, I am not persuaded the complainant has established that an additional 20% in repair costs over and above what has already been settled is reasonable or otherwise justified. Fair in the circumstances the insurer pays additional amount At the same time, however, the cash settlements for the repairs for both the home and landlord building claims were negotiated and agreed approximately three months before the properties were able to be handed over to the complainant. The purpose of a cash settlement is to discharge the insurer’s liability for repairs under the policy. That liability is essentially to cover the complainant’s claim -related loss by providing the cash reasonably required to enable the complainant to carry out the repairs himself. If the parties had agreed that the insurer was to carry out the repairs, then it is reasonable to expect the costs to the insurer are also likely to have risen given the time taken between itemised quotes being obtained and work being able to start. Quotes usually only have a limited period of validity. So the insurer would, on balance, have incurred cost increases itself in any case. In the particular circumstances, I consider it fair that the insurer pays a further amount to take account of possible likely increases in the costs of repair since the settlements were agreed. In the absence of clear evidence of actual costs incurred, I consider it fair that the respective cash settlement amounts - $269,223 for complainant’s home and $210,000 for the co mplainant’s investment property – be increased by 1%. The insurer is required to pay the complainant an additional $4,792.23. Determination | Case number: 637690 Page 5 of 8 Temporary accommodation and loss of rent is ongoing It is not disputed that as a result of the insured event the properties we re uninhabitable and required significant repairs. In those circumstances, the complainant’s policies provide cover for temporary accommodation and loss of rent for his home and investment property respectively. The insurer has already made a number of payments to the complainant based on $400 per week loss of rent, and $550 per week for temporary accommodation costs. The maximum allowance is $80,000 for each of these items, which has not yet been exhausted. Policy Residential property Investment property Benefit Temporary accommodation up to $20,000 or 20% of the sum insured, whichever the greater. Loss of rent up to $20,000 or 20% of the sum insured, whichever the greater . Sum Insured $400,000 $400,000 Maximum allowance Up to $80,000 Up to $80,000 The insurer previously offered to pay loss of rent up to March 2020 and temporary accommodation up to May 2020, but I am not satisfied, in the circumstances, this reasonably discharges its obligations under the policy given that finalising the rebuild works became protracted, through no fault of the complainant. (That is on the assumption that the complainant proceeded expeditiously with the repairs once the mould certification was obtained.) In the circumstances, the insurer is required to cover the reasonable costs of loss of rent and temporary accommodation respectively (up to the applicable policy limits) until the properties are fit to be lived in/let and otherwise in accordance with the policy terms. That is, subject to the complainant providing the insurer with any further evidence of those costs (and the completion of work to allow occupation) which the insurer reasonably requires. Determination | Case number: 637690 Page 6 of 8 2.2 Is the complainant entitled to compensation for non-financial loss? AFCA can award compensation for non-financial loss Under our Rules, AFCA may award compensation for non-financial loss in situations where there has been an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the applicant’s expectati on of enjoyment or peace of mind. Delays were not unreasonable in the circumstances The complainant has been dissatisfied with the dela ys experienced in the course of the two building claims. The insurer says it initially provided an estimated timeframe of six months to resolve the claims. This is because the flood was a catastrophic event, and it was also allowing for an appropriate drying out period for the homes. It is to be expected that some delays in assessing and settling claims following a widespread catastrophic flood event are likely to occur. That does not mean the insurer should necessarily be held responsible for those. As already considered above, I am not persuaded there was an unreasonable or avoidable delay (for which the insurer should be held responsible) in handing over the properties, as it was necessary to certify both properties were returned to normal ecology before repairs could commence, and the insurer was reliant on M providing that certification. $500 in compensation warranted for service-related issues The complainant says he has been inconvenienced due the poor service provided by the insurer, including a lack of proactive contact once he lodged his complaint. The insurer has not supplied a copy of its claim notes in response to this. It does appear, though, that the complainant has had to follow up responses and information from the insurer, during what has understandably been a difficult time for him. It is also worth noting that on one occasion he was told he had reached the maximum policy limit in respect of his temporary accommodation entitlement when that was not correct. That will only have added to his stress. I am satisfied the complainant has experienced an unusual degree of upset and inconvenience because of aspects of the insurer’s handling of his claims. It is fair in the circumstances that the insurer pays $500 as compensation for non-financial loss. Determination | Case number: 637690 Page 7 of 8 3 Supporting information 3.1 AFCA approach to this dispute This complaint has been determined based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous decisions of AFCA or its predecessor schemes (which are not binding). A full exchange of the relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any issues raised. All of the provided material has been reviewed and considered. The parties have raised numerous issues in their submissions to AFCA. However, commentary in this determination is restricted only to those issues considered relevant to the outcome. 3.2 Relevant policy wording for owner occupied property 21. Temporary accommodation If your home is so damaged by an event for which we agree to pay a claim that it cannot be lived in, we pay up to:  $20,000, or  20% of the sum insured for your home, or  20% of the sum insured for your contents whichever is the highest, for the additional cost of:  reasonable temporary accommodation,  emergency removal and storage of your contents,  emergency accommodation of your pets where the home is your principal place of residence. 3.3 Relevant policy wording for investment property 22. Loss of rent or temporary accommodation We pay the following benefit if your home is so damaged by an insured event that it cannot be lived in or let to tenants: Determination | Case number: 637690 Page 8 of 8 If this Policy insures your home We pay up to $20,000 or 20% of the sum insured for your home, whichever is the higher, for: (a) loss of rent or rentable value if the home is tenanted or is between tenants at the time the loss or damage occurred, (b) additional cost of: reasonable temporary accommodation, emergency storage of your contents, emergency accommodation of your pets, where the home is your principal place of residence.