Home / QBE / Determination 637690
Determination 637690
Flood claim cash settlement amount and handling of delayed repairs
Summary
After a flood, the complainant's building claims were cash settled, and he later sought a further 20 percent for repairs delayed by mould remediation. AFCA ordered a 1 percent increase to the building settlements, continued temporary accommodation and loss of rent cover, and $500 for service issues.
Delays were outside the insurer's control, but the settlements were agreed months before handover, so a fair uplift for likely cost increases applies while the unsubstantiated 20 percent claim is rejected.
Issues
- Claim amount dispute primary · upheld“it is fair in the particular circumstances that the settlement be adjusted to address the likelihood of increased costs for repairs”
- Delay secondary · not upheld“I am not persuaded there was an unreasonable or avoidable delay (for which the insurer should be held responsible) in handing over the properties”
- Poor communication secondary · upheld“$500 in compensation warranted for service-related issues”
Subjects and remedies
home or building damagenatural disasterpay claimpay non financial loss
Related
Text of the determination
Determination
Case number 637690
Financial firm QBE Insurance (Australia) Limited
Determination | Case number: 637690 Page 1 of 8
Case number: 637690 31 July 2020
1 Determination overview
1.1 Complaint
The complainant lodged four claims under his home and contents policies held with
the financial firm (insurer) following a flood event on 3 February 2019. The flood
caused damage to the complainant’s residential property and his investment proper ty.
The insurer cash settled each of the two building and the two contents claims for
amounts agreed with the complainant at the time . However, the complainant now
seeks an additional 20% of the cash settlement amount for repair costs for each
building. He says delays in the properties being handed over to him following claim-
related mould remediation meant costs (including for further temporary
accommodation and loss of rent) increased by the time he was able to commence the
work. The complainant also says the way in which the insurer handled the claims has
caused him an unusual degree of stress and inconvenience.
1.2 Issues and key findings
Is the insurer liable for further costs beyond the cash settlement made?
While delays in the handover of the buildings after mould remediation were effectively
outside the control of the insurer, those delays did, on balance, mean repair costs
would likely be greater than the cash settlements which had been agreed based on a
particular expected handover date. If the insurer had been undertaking the repairs
itself, it would have had to meet any cost increase caused by the delays. So, it is fair
in the particular circumstances that the settlement be adjusted to address the
likelihood of increased costs for repairs, loss of rent and temporary accommodation
because of the delayed handover.
The complainant is also entitled to $500 in compensation for non-financial loss due to
service-related issues.
1.3 Determination
This determination is partly in favour of the complainant. The insurer is required to
pay $500 as compensation for non-financial loss; to continue paying reasonable
temporary accommodation costs and loss of rent until the respective properties are fit
for occupation, subject to the policy limit and the complainant providing relevant
receipts/evidence; and to increase the settlement for building repair costs by paying a
further $4,792.23 (as set out in section 2.1 below).
Determination | Case number: 637690 Page 2 of 8
2 Reasons for determination
2.1 Is the insurer liable for further costs beyond the cash settlement made?
Circumstances of loss not in dispute
The complainant lodged four claims with the insurer on or around 5 February 2019
after both his home and investment property were damaged in a flood event on 3
February 2019.
The flood caused significant damage, including mould, and both properties were
uninhabitable.
This dispute is in relation to the two building claims only. The contents claims are
considered resolved, as the insurer has cash settled both contents claims to the
maximum policy limit.
On 17 June 2019, the insurer cash settled both building claims for amounts agreed at
the time. The complainant then arranged with his preferred builder for repairs, based
on an anticipated handover on 15 July 2019, which is the date he had been told to
expect by the insurer.
The handover was delayed, however, as clearance certificates following mould
remediation were not available and provided to the complainant until 21 September
2019.
Mould remediation was appropriate and efficient, in the circumstances
Following the flood, the insurer engaged mycologist M to lead mould remediation in
both properties, together with the services of restorer C.
It is accepted that building repairs could not be undertaken to the properties until they
had been dried out and final certification received that all mould had been remediated
and it was safe to commence work. Due to the extent of damage and overall weather
conditions, a number of mould treatments and samples were required before the
properties returned to normal ecology.
The insurer appointed mycologist M in April 2019 and an initial report was provided on
16 May 2019. Mould remediation work by restorer C then proceeded over several
months up until July 2019. M ’s final reports and clearances for both buildings were
dated 18 September 2019 and were provided to the complainant by the insurer on 21
September 2019. (It is worth noting that, in the intervening months, other preliminary
assessments/scopes of work for repair were also being undertaken to the extent
reasonably required and possible in the circumstances.)
The complainant is dissatisfied with the time taken by the insurer to finalise the mould
remediation work, although the insurer has explained that prevailing moisture
conditions caused similar timing issues at other properties in the area. I understand
Determination | Case number: 637690 Page 3 of 8
the complainant also wanted the opportunity for his own expert to review M’s final
reports.
I have no reason to doubt the appointed restorer and mycologist were appropriately
qualified to assess the mould damage and provide the necessary treatment and
certifications. While there does appear to have been a delay in the final clearances
being provided to the insurer by the mycologist, the evidence does not show the
process undertaken by the insurer and its experts in relation to the mould works was
in itself unnecessarily protracted, inefficient or inadequate. Nor is it clear that the
complainant should have needed any further confirmation from his own expert (which
then presumably resulted in further delays in repairs commencing).
It is reasonable to accept that M’s capacity to act more promptly in providing its final
certifications was likely to have been affected by the demands on its services given
the major flooding event in the region , which is what gave rise to the complainant’s
claims. That is something which is outside the insurer’s own control, and I note the
insurer did provide M’s final certificatio ns to the complainant within three days of their
being issued.
I am satisfied, in the particular circumstances, the insurer has acted reasonably in
dealing with the mould remediation issues. I do not consider it should be held
responsible for delays which were essentially outside its control.
Complainant seeks additional cash settlement
The complainant seeks additional repair costs for both properties due to the delay in
handover. He also wants extended cover for loss of rent and temporary
accommodation until June 2020.
In support of his position, the complainant has provided a letter dated 18 September
2019 from the construction company (GR) he had appointed directly to carry out the
building repairs. GR points out:
the agreement was for properties to be handed over 15 July 2019
with the delay in handover there would be a 20% increase in pricing for repairs
as well, there are significant penalties with delaying subcontractors.
Given the delayed start date, GR says there will be further consequential delays (with
certain materials) and that would set back the anticipated completion date for repair
work beyond April 2020.
It is not clear what the current status of repair work is, whether it has now already
been completed, and if so, when it was completed and at what actual cost.
Increase of 20% in repair costs has not been substantiated
When providing an insured with a cash settlement for repair costs, an insurer should
also allow for builder’s margi n/contingencies and the transfer of risk. It is also
Determination | Case number: 637690 Page 4 of 8
important to ensure, as far as possible, that any cash settlement is based on quotes
actionable by the complainant as a retail customer. The cash settlement amounts
from June 2019 were agreed by the parties based on scopes of works from the
insurer’s service providers. The amounts settled for each property included an 18%
margin on the repair costs and I consider this it a reasonable allowance in the
circumstances to account for builder’s margin and tran sfer of risk. I have no reason to
consider the building repair settlements as initially agreed by the parties were
inadequate at the time.
The question is whether there should be any increase to account for the delayed start
of work because of the later than anticipated handover following mould remediation.
I appreciate that delays in being able to commence repairs are likely to have
disrupted scheduling of work and ordering of materials . As GR points out in his letter,
the demand on suppliers and trades at the time was significant. In the meantime,
however, the complainant/GR have not substantiated their anticipated 20% cost
increase.
On the available evidence, I am not persuaded the complainant has established that
an additional 20% in repair costs over and above what has already been settled is
reasonable or otherwise justified.
Fair in the circumstances the insurer pays additional amount
At the same time, however, the cash settlements for the repairs for both the home
and landlord building claims were negotiated and agreed approximately three months
before the properties were able to be handed over to the complainant. The purpose of
a cash settlement is to discharge the insurer’s liability for repairs under the policy.
That liability is essentially to cover the complainant’s claim -related loss by providing
the cash reasonably required to enable the complainant to carry out the repairs
himself.
If the parties had agreed that the insurer was to carry out the repairs, then it is
reasonable to expect the costs to the insurer are also likely to have risen given the
time taken between itemised quotes being obtained and work being able to start.
Quotes usually only have a limited period of validity. So the insurer would, on
balance, have incurred cost increases itself in any case.
In the particular circumstances, I consider it fair that the insurer pays a further amount
to take account of possible likely increases in the costs of repair since the settlements
were agreed.
In the absence of clear evidence of actual costs incurred, I consider it fair that the
respective cash settlement amounts - $269,223 for complainant’s home and $210,000
for the co mplainant’s investment property – be increased by 1%.
The insurer is required to pay the complainant an additional $4,792.23.
Determination | Case number: 637690 Page 5 of 8
Temporary accommodation and loss of rent is ongoing
It is not disputed that as a result of the insured event the properties we re
uninhabitable and required significant repairs. In those circumstances, the
complainant’s policies provide cover for temporary accommodation and loss of rent
for his home and investment property respectively.
The insurer has already made a number of payments to the complainant based on
$400 per week loss of rent, and $550 per week for temporary accommodation costs.
The maximum allowance is $80,000 for each of these items, which has not yet been
exhausted.
Policy Residential property Investment property
Benefit Temporary accommodation up to
$20,000 or 20% of the sum
insured, whichever the greater.
Loss of rent up to $20,000 or 20% of
the sum insured, whichever the
greater .
Sum Insured $400,000 $400,000
Maximum allowance Up to $80,000 Up to $80,000
The insurer previously offered to pay loss of rent up to March 2020 and temporary
accommodation up to May 2020, but I am not satisfied, in the circumstances, this
reasonably discharges its obligations under the policy given that finalising the rebuild
works became protracted, through no fault of the complainant. (That is on the
assumption that the complainant proceeded expeditiously with the repairs once the
mould certification was obtained.)
In the circumstances, the insurer is required to cover the reasonable costs of loss of
rent and temporary accommodation respectively (up to the applicable policy limits)
until the properties are fit to be lived in/let and otherwise in accordance with the policy
terms.
That is, subject to the complainant providing the insurer with any further evidence of
those costs (and the completion of work to allow occupation) which the insurer
reasonably requires.
Determination | Case number: 637690 Page 6 of 8
2.2 Is the complainant entitled to compensation for non-financial loss?
AFCA can award compensation for non-financial loss
Under our Rules, AFCA may award compensation for non-financial loss in situations
where there has been an unusual degree or extent of physical inconvenience, time
taken to resolve the situation or interference with the applicant’s expectati on of
enjoyment or peace of mind.
Delays were not unreasonable in the circumstances
The complainant has been dissatisfied with the dela ys experienced in the course of
the two building claims.
The insurer says it initially provided an estimated timeframe of six months to resolve
the claims. This is because the flood was a catastrophic event, and it was also
allowing for an appropriate drying out period for the homes.
It is to be expected that some delays in assessing and settling claims following a
widespread catastrophic flood event are likely to occur. That does not mean the
insurer should necessarily be held responsible for those.
As already considered above, I am not persuaded there was an unreasonable or
avoidable delay (for which the insurer should be held responsible) in handing over the
properties, as it was necessary to certify both properties were returned to normal
ecology before repairs could commence, and the insurer was reliant on M providing
that certification.
$500 in compensation warranted for service-related issues
The complainant says he has been inconvenienced due the poor service provided by
the insurer, including a lack of proactive contact once he lodged his complaint. The
insurer has not supplied a copy of its claim notes in response to this.
It does appear, though, that the complainant has had to follow up responses and
information from the insurer, during what has understandably been a difficult time for
him. It is also worth noting that on one occasion he was told he had reached the
maximum policy limit in respect of his temporary accommodation entitlement when
that was not correct. That will only have added to his stress.
I am satisfied the complainant has experienced an unusual degree of upset and
inconvenience because of aspects of the insurer’s handling of his claims. It is fair in
the circumstances that the insurer pays $500 as compensation for non-financial loss.
Determination | Case number: 637690 Page 7 of 8
3 Supporting information
3.1 AFCA approach to this dispute
This complaint has been determined based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous decisions of AFCA or its predecessor schemes (which are not binding).
A full exchange of the relevant information has taken place between the respective
parties. Each party has had the opportunity of addressing any issues raised.
All of the provided material has been reviewed and considered. The parties have
raised numerous issues in their submissions to AFCA. However, commentary in this
determination is restricted only to those issues considered relevant to the outcome.
3.2 Relevant policy wording for owner occupied property
21. Temporary accommodation
If your home is so damaged by an event for which we agree to pay a claim that it
cannot be lived in, we pay up to:
$20,000, or
20% of the sum insured for your home, or
20% of the sum insured for your contents
whichever is the highest, for the additional cost of:
reasonable temporary accommodation,
emergency removal and storage of your contents,
emergency accommodation of your pets
where the home is your principal place of residence.
3.3 Relevant policy wording for investment property
22. Loss of rent or temporary accommodation
We pay the following benefit if your home is so damaged by an insured event that
it cannot be lived in or let to tenants:
Determination | Case number: 637690 Page 8 of 8
If this Policy insures your home
We pay up to $20,000 or 20% of the sum insured for your home, whichever is the
higher, for:
(a) loss of rent or rentable value if the home is tenanted or is between tenants at
the time the loss or damage occurred,
(b) additional cost of: reasonable temporary accommodation, emergency storage
of your contents, emergency accommodation of your pets, where the home is
your principal place of residence.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.