Determination 633282

Termite damage and incomplete 2010 storm repairs

FirmQBE
Decided2019-11-18
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$2,600
Non-financial loss$500
Amount claimed$3,600
SourceAFCA PDF

Summary

The complainant, an elderly woman, sought roof and ceiling repairs after a 2019 ceiling collapse caused by termites, and wall lining replacement from a 2010 storm claim. AFCA found the insurer not liable for the termite damage but ordered $2,600 for wall linings and $500 non-financial loss.

The insurer did not repair or replace the timber roof frame and had no notice of termite risk, but inadequate contractor repairs and an unreplaced water-damaged wall lining from the 2010 claim are the insurer's responsibility.

Issues

Subjects and remedies

elderly or capacityhome or building damagenatural disasterpay claimpay non financial loss

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 633282 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 633282 Page 1 of 5 Case number: 633282 11 November 2019 1 Determination overview 1.1 Complaint The complainant lodged a claim with the financial firm (insurer) for storm damage to her home in early 2010. The insurer accepted that claim and authorised repairs. In February 2019, the complainant’s lounge/rumpus room ceiling collapsed. She contacted the insurer who investigated and found the cause was termite infestation of the roof beams. The insurer says it did not authorise or undertake repairs to the timber roof beams when dealing with the 2010 claim, and so is not liable for the current damage. The complainant disagrees and wants the insurer to cover the roof and ceiling repairs. She also says the insurer never replaced the waterlogged insulation and laminated wall lining after the claim in 2010. 1.2 Issues and key findings Is insurer liable for 2019 damage and other 2010 claim-related repairs? It has not been shown, on the available evidence, that the insurer replaced or undertook any specific work to the timber roof frames following the 2010 claim. Nor does the evidence show there were signs of termites in the beams at that time, or that the insurer should otherwise have been aware of the problem or likelihood of it. That means the insurer is not liable for the termite infestation and resulting 2019 damage. The insurer ’s first contractor failed to replace waterlogged insulation after the 2010 claim, although that was later completed. However, recommended replacement of water damaged laminated wall lining was not undertaken. The insurer is liable for that. Is the complainant entitled to compensation? The insurer caused the complainant avoidable upset because of the way the original claim was handled, specifically because of the faulty/inadequate repairs of its first contractor; and because it has since been found some recommended repairs were still outstanding. Compensation for non-financial loss is warranted. 1.3 Determination This determination is partly in favour of the complainant. The insurer is required to pay $500 compensation, and $2,600 for laminated wall lining replacement as set out in section 2.1 below. It is not required to take any other action. Determination | Case number: 633282 Page 2 of 5 2 Reasons for determination I have decided this case on the basis of what I consider fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous AFCA decisions. I have taken into account all the material submitted by the parties, both before and after the preliminary assessment. I am satisfied that the documentation I have relied on has been provided to both parties. For the purposes of this determination, I will deal with only those points considered relevant. 2.1 Is insurer liable for 2019 damage and other 2010 claim-related repairs? No evidence that insurer repaired or replaced timber roof frame at any time After the complainant contacted the insurer in 2019, builder WB attended and identified the termite infestation as the reason the ceiling collapsed. Specifically, however, WB found the timber roof frame had been built of untreated timber, and because the affected room itself was not on a concrete slab, there had been no protection or barrier against termites. WB said that treated timber should have been used, and that it was bad building practice and poor workmanship not to have done so. The issue is whether the insurer is responsible for the use of untreated timber and the resulting damage. The insurer has provided copies of invoices from C, the first contractor engaged after the 2010 claim to fix the identified damage, and from B, who subsequently attended to rectify/finalise the inadequate repairs undertaken by C. Neither of those invoices shows any work was done to the timber roof frame itself (such as repair or replacement of the wooden frame). There is however reference to the timber frame in the September 2010 causation inspection report of the insurer’s building consultant, S. There S notes the skillion roof of the affected room was non-compliant, and amounted to defective building work, and that contributed to the periodic water penetration into the ceiling. On that basis, S said the ‘entire metal roof should be removed and replaced with new timber battens complying with the required minimum pitch recommendations’. S went on to comment that ‘could be combined with changing the roof sheet profile…to minimise change of batten size and alteration of the roof frame’. That work was not deemed to be the responsibility of the insurer under the policy then in place, but instead was reported as being the complainant ’s responsibility . I assume that is because, under the cover available for water damage, the policy provided that the insurer was not liable for fixing defects in design or construction. Determination | Case number: 633282 Page 3 of 5 The insurer’s claim file notes indicate this matter was raised with the complainant but she did not agree the roof needed to be re-pitched, since she had never had water ingress issues previously, and so that work to the timber battens to change the pitch was not undertaken; and the repairs for which the insurer accepted liability went ahead. Th ere was nothing in S’s report to suggest the existing timber frame itself was otherwise inadequate or inappropriate for the purpose; nor is there any reason to show the insurer or its contractors should have been on notice of the risk of termites in the context of the claim at the time. I am satisfied on the available evidence that the insurer did not repair or replace the existing timber roof frame, nor that it should otherwise be responsible for the use of untreated timber in the frame and the resulting termite damage discovered in 2019. It is also worth noting that the complainant’s ho me insurance, when the 2019 damage occurred, was no longer held with the insurer and so there is no specific policy under which the insurer might be liable for that new damage. Waterlogged insulation was eventually replaced by insurer The complainant has expressed concern that certain repairs recommended after the 2010 claim was first made were not completed. The invoice from C (referring to work authorised by the insurer on 28 May 2010) covers the removal and replacement of the ceiling and the ceiling insulation, and associated work. However, when S attended in September 2010 they noted C’s newly replaced plasterboard ceiling lining was sagging, and said that was due to the original saturated insulation batts not having been replaced ; and that in turn allowed more moisture penetration over the 5 months since the storm event. I am satisfied, on balance, the waterlogged insulation was subsequently removed and replaced by B, as referred to in their invoice of July 2011. Not shown that water damaged laminated wall linings were replaced by insurer The complainant also says the water damaged laminated wall linings were never replaced after the 2010 claim. S reported in September 2010 that the north-western elevation laminated wall linings should be disposed of and replaced, as they had been damaged by the ongoing moisture penetration, as well as from the original storm event. As well S observed water staining in areas ‘generally adjacent to the rear north - western wall elevation’, including ‘ adjacent top sections’; also attributed to the storm event. Determination | Case number: 633282 Page 4 of 5 I have seen nothing in any of the later reports, quotes or invoices to show that this work was ever done, or that there was a reason for it no longer being necessary. The insurer has not explained this apparent oversight, apart from maintaining that all repairs were completed, despite the lack of evidence to confirm that. The complainant says there are still holes in the wall where pictures used to hang, and other black marks. She has provided a quote for $3,600 for replacement of the damaged walls. The quote does not cover associated painting or electrical work. The insurer has not commented on the quote. In the circumstances, I consider it fair and appropriate that the insurer cover the cost of replacing the water damaged wall linings, as identified in S’s report , and broadly based on the complainant’s quote. Since the quote is not detailed or specific (for example, as to the materials to be used, the scope of what it refers to as ‘damaged’ and the extent to which that damage is actually claim-related), I consider it fair in the circumstances that the insurer pay the complainant $2,600 towards the replacement of the water-damaged walls. 2.2 Is the complainant entitled to compensation? Concern about adequacy and completeness of repairs The evidence indicates other incomplete or sub-standard work by C also needed to be rectified by B after the 2010 claim. For example, S found the existing timber frame cornice had not been reinstalled by C but had been left on an open patio exposed to the weather. S noticed other issues with the roof, including some roof sheets that were ‘slightly uplifted and/or not fitted tightly’. S ‘s opinion was that was ‘ approximately 50% due to the frequent foot traffic during the recent insurance related repair works [by C] ’. The insurer’s loss adjuster, C L, later reported that in a conversation, S changed their view, saying that ‘the foot traffic was minor and not contributing to the leak’. That is not substantiated by any written evidence, and is inconsistent with S’s written report and the subsequent report/quote of B (11 January 2011), which referred to damage to the roof from ‘a recent storm and repair work’, including ‘severe’ damage from ‘ heavy boot traffic ’ attributed to the previous contractors. In July 2011, B’s work to rectify/complete that of C did include a replacement of damaged roof sheeting, however I consider it concerning that there appear to have been attempts by the insurer to avoid or reduce its liability for that. In the meantime, the complainant had the worry and inconvenience of protracted repairs, having discovered the insurer’s first attempts had been inadequate and incomplete; compounded when it later became apparent, based on the available evidence, that the water-damaged laminated wall linings were never replaced at all. Determination | Case number: 633282 Page 5 of 5 I consider the complainant should have been able to rely on all the 2010 claim-related work being accepted and carried out promptly, professionally and in its entirety at the time. Complainant has also raised customer service concerns The complainant has also expressed concern about the standard of customer service she has received since reporting the 2019 damage. She has said the insurer has not met its promised time-frames for calling her back and making contact, and there have been delays in the matter progressing. Compensation for non-financial loss is warranted The complainant is elderly and lives alone with no family support. She has said her health has suffered because of the worry and stress of this matter, and I also understand her home is now uninsured as the termite damage has not been fixed. While I accept the insurer is not liable for the termite damage (and the complainant has said she will now pay for the timber roof frame), I also consider the complainant has experienced an unusual amount of upset and inconvenience because of the way the original claim was handled. This has been exacerbated more recently by her becoming aware of the extent of the problems with those initial repairs. The insurer is required to pay the complainant $500 compensation for non-financial loss.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.