Home / Westpac / Determination 631607

Determination 631607

Storm damage scope disputed and further repairs refused

FirmWestpac
Decided2021-01-19
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$2,500
Non-financial loss—
Amount claimed$65,255
SourceAFCA PDF

Summary

The complainant disputed the insurer's storm damage cash settlement and sought $65,255.01 for further roof, internal and contents damage. AFCA found most of the claimed damage was not caused by the storm and ordered an additional $2,500 payment.

The proximate cause of the disputed damage was wear and tear, poor maintenance and defects, which are excluded, so the insurer is liable only for the storm-related works plus a modest top-up for cash settlement risk.

Issues

Subjects and remedies

home or building damagenatural disasterpay claim

Related

All Westpac determinations · Find similar determinations

Text of the determination

Determination Case number 631607 Financial firm Westpac General Insurance Limited Determination | Case number: 631607 Page 1 of 10 Case number: 631607 21 April 2020 1 Determination overview 1.1 Complaint The complainant holds a home and contents insurance policy with the financial firm (insurer). He lodged a claim with the insurer for damage sustained to his property following a storm in late December 2011. The insurer accepted the claim and agreed to cover certain areas of damage. The complainant is unhappy with the insurer’s scope of works and its assessment of the extent of the storm-related damage. He believes the insurer should repair the roof and other internal damage as well. He is seeking $65,255.01 for the outstanding damage. 1.2 Issues and key findings Is the insurer ’s cash settlement for the storm damage fair? The insu rer’s costed scope of works is a reasonable basis for cash settlement and, on reflects the extent of the storm-related damage. However, it is fair in the circumstances that the insurer pays the complainant an additional $2,500 to factor in the transfer of risk to the complainant, and any unforeseeable damage which might become apparent in the course of claim-related repairs; to acknowledge the considerable time taken for the cash settlement to be made, and to allow for the possibility of further minor contents damage (although the complainant has not clearly established insured storm damage to all contents claimed). The insurer is not liable for any further repairs. That is because the evidence shows the remaining damage claimed by the complainant is, on balance, the result of wear and tear and gradual deterioration, maintenance-related issues and some defective workmanship, all of which is excluded under the policy. 1.3 Determination This determination is substantially in favour of the insurer. The insurer is required to pay the complainant an additional $2,500. It is not required to take any further action. Determination | Case number: 631607 Page 2 of 10 2 Reasons for determination I have decided this case on the basis of what I consider fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous AFCA decisions. I have taken into account all the material submitted by the parties. I am satisfied that the documentation I have relied on has been provided to both parties. For the purposes of this determination, I will deal with only those points considered relevant. 2.1 Is the insurer’s cash settlement for the storm damage fair ? Policy covers storm damage, subject to exclusions The complainant is required to show, on the balance of probabilities, he has suffered a loss caused by a risk insured against under the policy. This is known as a prima facie claim. If the complainant is able to establish a prima facie claim, then the onus shifts to the insurer to show that, on the balance of probabilities, it can rely on an exclusion under the policy or that it is otherwise entitled to deny the claim. The complainant ’s policy provides cover for damage caused by the insured events listed in the policy (including storm), subject to certain conditions and exclusions. There is no dispute the complainant has established a valid claim under the policy for storm damage. The insurer has already cash settled the complainant for what it accepted as storm- related damage, in accordance with its builder’s scope of works. However, the parties disagree about the extent of the damage for which the storm itself was responsible, and the complainant believes the insurer should cover additional damage he has identified, including to the roof (for a full roof replacement), internal areas and some contents. Insurer’s liability for disputed damage depends on proximate cause In order to dete rmine the extent of the insurer’s liability for the disputed damage, it is necessary to identify the proximate cause of the damage. The proximate cause is the dominant, effective or operative cause of the damage. It is not required to be the sole cause, or the first or the last in time. The identification of the proximate cause is a question of fact that depends on the circumstances of each particular case. If the proximate cause of the damage is an insured event (in this case, storm), then the insurer is liable for that. However, if the proximate cause is a factor that is excluded under the policy, then the insurer is not liable. Determination | Case number: 631607 Page 3 of 10 Parties have disagreed over successive scopes of work of repairs The insurer engaged a loss adjuster (LAC) to assess the storm damage to the property. In his report of 6 February 2012, LAC says the property sustained hail damage to the cement tiling, air-conditioner, pergola and boundary fence , and also reported minor water ingress in the rear hallway, with staining evident around the ceiling. LAC organised for a quote from builder TC, which totalled $9,609. When the complainant disagreed with the proposed scope of works, the insurer arranged for a second builder (KS) to assess the damage and complete repairs. The complainant disagreed with KS’ proposed scope of works (29 March 2012) too, as he believed the whole roof needed to be repainted as a result of the hail event. He did not allow KS to undertake the work which the insurer had authorised. The insurer then engaged a roofing specialist (HQ) to provide a second opinion on the nature of the damage to the roof in June 2012. HQ concluded the roof damage was due to both hail and age but could not apportion that. The insurer then agreed to cover the cost of repainting the roof. However, it appears the complainant would still not allow the work to proceed, despite the insurer’s assessor expressing concern about the risk of further damage in the meantime; and the insurer says it was not until February 2013 that the complainant was contactable or responded to attempts at communication, so the matter could progress. Due to the complainant’s ongoing disagreement with the insurer’s scope s of works and his refusal to allow the insurer to undertake repairs, the i nsurer offered to cash settle the claim. On 22 October 2013, approximately 22 months after the storm event, the insurer offered the complainant $22,094 for the total cost of repairs. In response, in March 2014 the complainant himself compiled a costed scope of works totalling $63,060.48. The scope was not prepared or supported by a builder. Some of the damage included in that scope of works relates to the building, while some relates to contents. However, I not satisfied the complainant has established all the damage claimed should be covered under the policy, since there is no substantive supporting evidence. The insurer engaged a new loss adjuster (DL) to attend the property and resolve the scope of works issues. Following DL’s assessment in June 2014 (delayed because of the complainant being overseas for some time) , the insurer accepted some of the complainant’s scope of works. However, DL noted that some of the damage in the complainant’s scope had Determination | Case number: 631607 Page 4 of 10 arisen because of the delays in attending to repairs (which might have progressed had the complainant allowed that). DL recommended the appointment of an engineer to assess causation and the extent of the storm damage for the disputed items. Evidence does not establish storm was the proximate cause of the roof damage The insurer engaged an engineer (JM) to assess the extent of the hail damage to the property. JM noted that 2 mm of rain fell on the reported day of the storm and 28 mm fell on the next day. In his comprehensive and detailed report of December 2014, JM says the property had been poorly maintained, particularly the concrete tiled roof. JM assessed in detail the complainant’s own scope of works and considered causation in respect of each item. In addressing the roof tiles, JM says the y:  have reached their usable life expectancy  are severely lacking maintenance, such as the repointing of the hip and ridge  are chipped and broken to a great extent; this is due to the substantial foot traffic over the brittle tiles in the process of fitting the solar panels. JM says the maintenance neglect on the roof has been long-term; that neglect caused the tiles to become brittle as water penetrated the cement matrix of the tiles. JM concludes that with respect to the hail damage, over many years concrete tiles of this type generally perform much better in hail conditions. JM noted there was no evidence of any attempts to replace the previously damaged tiles. JM also says the following maintenance work should have taken place 10 years ago, which is well before the storm:  the damaged roof tiles should have been replaced  the entire tiled roof area should have been water pressured with chlorine additive to kill moss and recoat it. It is also significant to note the Laserlite sheeting was not damaged by hail. JM argues that if the hail damage was not significant enough to cause penetration in this sheeting, abrasion damage could not have been inflicted on the concrete tiles ; there is no evidence of any hail puncture marks or damage to these sheets as might be expected if the hail was intense. As well, over the 50 years of the life of the roof/building, JM suggests many hail storms would have occurred. He adds, had the tiles’ coating been maintained, the concrete tiles would have had additional protection against possible hail damage. Determination | Case number: 631607 Page 5 of 10 JM opines none of the tiles would have been broken by the hail, the pointing of the ridge and hip tiles would have been completely unaffected, and only minimal damage from hail, if any at all, would have occurred. JM notes the installation of solar panels on the roof would have involved a substantial amount of foot traffic on the brittle tiles, and that would have been responsible for many of the tiles being broken. In addressing the roof plumbing, JM says:  the roof plumbing has not been carried out by a roof plumber  there is inadequate plumbing to the south east corner of the garage  there is damaged spouting  excessive sealant is evident at the north west of the garage  an over flashing should have been fitted to prevent the moisture seeping through the deteriorated mortar in the brickwork  inadequate join of the flashing at the eastern end of the garage. JM identified a gutter opening in the spouting on the south side of the garage where an excessive amount of roof rainwater runoff is directed to the outlet. Consequently, the rainwater tank below would become overloaded on occasions of heavy rain. I am satisfied, on the available evidence, and particularly JM’s compelling report, that much of the damage claimed by the complainant was not the result of the storm (as the proximate cause), but instead was from wear and tear, gradual deterioration, and lack of maintenance. Faulty roof structure was not damaged by the storm The complainant says the hail has also caused damage and misalignment to the roof structure, as well as to the tiles/sheeting. JM says the misalignment on either side of a timber prop is caused by incorrect original construction of the roof framing; there is inadequate propping and support; the excessive sag in the rafter is caused by the excessive spanning. JM noted a fairly recent skylight has been installed by cutting through a structural support rafter and concludes the skylight installation has seriously weakened the roof structure in this location. JM says such a structure is non-compliant and would appear to have been built without a permit; had a permit been applied for, engineering computation, correct sizing and spacing of the roof structure elements would have been required. The complainant has not provided any ev idence to refute JM’s findings. I accept that defects have been identified in the roof structure, and these represent exclusions under the policy. Determination | Case number: 631607 Page 6 of 10 C omplainant’s engineer’s report does not advance his position The complainant tendered a report from engineer AZ who assessed the roof in August 2019. AZ notes the following damage:  hail impact damage to concrete roof tiles  chipped tiles from hail impact  possible repointing in part  polycarbonate roof damage. AZ had access to several photos of the roof apparently taken in December 2011 but notes that tiles and internal damage had been repaired by the time they inspected. AZ says hail impact to tiles had caused them to become more brittle and this was evident in the eight years since the storm. It appears AZ had also been informed by the complainant that grit and sand from tiles had since blocked water tanks on several occasions; AZ said that should be regularly be cleaned out. AZ says:  the tiles should have been repaired immediately after the storm eve nt  he was informed pointing to the tiles was damaged in the hailstorm , however photos cannot confirm this  current photos confirm the repointing is required and hail storm may have contributed to this  the polycarbonate roof sheeting appears also to have sustained damage from storm. However, AZ ’s report only addressed the roof and none of the other disputed areas ; nor did AZ specifically refute any of JM ’ s findings. AZ did not elaborate on the mechanism and nature of the hail impact (if any) in light of the roof’s already deteriorated condition, as observed and reported by JM. AZ’s report is not conclusive of the scope or nature of the damage that occurred in the storm event (about eight years before their inspection). I accept the roof has shown a number of defects and maintenance/age-related issues which I consider are not related to the storm-event, but which are likely to have made it susceptible to further damage, including from storms. I am not satisfied the evidence shows the proximate cause of the damage to the roof was the storm. Instead, I am satisfied the roof was already at the end of its serviceable life, and it was its age, long-term wear and tear, lack of appropriate maintenance and defects in design or workmanship which was responsible for its condition. The policy specifically excludes damage from those factors. That means I do not consider the insurer is liable for any further damage to the roof. Determination | Case number: 631607 Page 7 of 10 Water tank is faulty and regularly overflows In his report, JM says the water tank installed outside the garage at the north west corner of the house is faulty:  the filter on top of the tank limits the amount of water flowing into the tank  there is too much rainwater runoff from the roof having regard to the capacity of the tank, causing spills on occasions of heavy rain  there is no concrete sub-base to support the tank  the paving around the tank is incorrectly graded and sheds any spillage directly into the garage. JM concludes any rainwater penetration into the garage has been a direct result of the faulty tank installation, associated plumbing and the absence of appropriate drainage and poor grading of the paving. That means damage to the tank, or caused to contents, because of the defects in the tank’s installation are excluded. No storm--related damage to garage/house wall The complainant says due to the hail damage, underpinning is required for the south wall of the garage, which is a common wall with the house. I note the complainant has not tendered any expert evidence to elaborate on this claimed loss. Engineer JM assessed this wall and notes it is structurally sound and does not required underpinning. There are no cracks on the wall and there is no evidence of any footing movement. In the absence of any other information, I am not satisfied the wall has been damaged by storm. Engineer JM concludes claim largely untenable JM concludes the majority of the complainant’s clai m for storm damage is ‘untenable’ and unsubstantiated on the evidence. In his findings, JM says he gave the complainant the maximum benefit of the doubt, however the workmanship issues are fairly widespread. JM maintains there is no hail damage to the concrete tiles which has caused physical damage, although the hail may have contributed to a slight further breakdown of almost non-existent coating. JM concludes the roof seriously lacks maintenance in recent years, long before the subject storm, and the broken tiles needed replacement for many years. JM noted un- tradesman like repair attempts at localised repointing of hip and ridge cappings and says adequate complete repointing should always be carried out by a professional. In concluding on the condition of the roof tiles, JM says a stage has been reached where they need to be discarded for normal wear and tear and lack of the required Determination | Case number: 631607 Page 8 of 10 periodic maintenance, as distinct from hail damage. As well, the intense foot traffic associated with fitting of the solar panels has contributed to the number of damaged roof tiles. The policy allows for cash settlement The policy states the insurer may choose to settle a claim by paying:  the reasonable cost of repairs  the reasonable costs of replacement to new condition  a cash amount. The complainant is dissatisfied with the insurer’s decision to cash settle the claim in this case. However, given the breakdown in communication between parties, and in the interests of bringing this matter to a conclusion after many years, I consider it is fair and appropriate that the claim was cash settled. That is further justified in the circumstances since the complainant has apparently now proceeded with certain repairs. I am not persuaded, on the evidence, that the scope of works on which the insurer based its cash settlement was inadequate or incorrect in accounting for the claim- related damage. By March 2019, the insurer cash had settled the complainant $25,846.75 based on KS’s scope of works, and other items which were accepted by the various loss adjusters (including electrical works to the solar panels and plumbing fees). However, when an insurer undertakes the repairs itself, it guarantees the quality of materials and workmanship of the repairs; while with a cash settlement, all the risk associated with the necessary repairs (including the possibility of further unforeseen damage or additional work) is transferred from the insurer to the complainant. Fair to increase cash settlement by $2,500 I note the insurer had repeatedly revised its scope of works in response to the complainant’s concerns about the extent of the insured loss. The insurer expressed its willingness on numerous occasions to undertake the accepted repairs to the storm - related damage. I also note that the very considerable delays in this claim being finalised were largely due to the actions of the complainant. The complainant also says some of his contents were also damaged during the storm event. The complainant has not provided compelling evidence to substantiate his claim. The complainant has provided one photograph of his terracotta duck sculpture and a list of the claimed items. While I acknowledged the many photographs he provided relatively recently, they have not been fully explained and I am not satisfied they confirm the further damage as claimed. Determination | Case number: 631607 Page 9 of 10 In the circumstances, however, I consider it fair the insurer pays the complainant an additional $2,500 in settlement of the claim. This is to factor in any contingencies for the repair of the accepted storm-related works; to acknowledge possible minor contents damage, as well as the fact that it was not until some years after the storm event that the cash settlement was made. Determination | Case number: 631607 Page 10 of 10 3 Supporting information 3.1 Policy Wording We do not insure you for any loss or damage that is caused by or arises from: … • wear and tear, gradual deterioration, or fading … • failure to keep the property insured in good condition

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.