Home / Strata Community Insurance Agencies Pty Ltd / Determination 630135

Determination 630135

Insurer partly declined water ingress claim for sewing room ceiling as gradual damage

FirmStrata Community Insurance Agencies Pty Ltd
Decided2019-12-12
ProductGeneral Insurance · Strata
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A strata body claimed for water ingress damage, and the insurer accepted the event but declined the sewing room ceiling damage as gradual deterioration. AFCA found the ceiling damage predated the event and was excluded, and ordered no action.

Damage caused by gradual operating causes such as wear, tear and failure to maintain is excluded, and the evidence showed the ceiling damage existed since 2016.

Issues

Subjects and remedies

no remedy

Related

All Strata Community Insurance Agencies Pty Ltd determinations · Find similar determinations

Text of the determination

Determination Case number 630135 Financial firm Strata Community Insurance Agencies Pty Ltd Determination | Case number: 630135 Page 2 of 7 Case number: 630135 12 December 2019 1 Determination overview 1.1 Complaint The complainant holds a commercial strata insurance policy (the policy) underwritten by the financial firm (insurer) covering the insured building. In January 2019, the complainant lodged a claim seeking cover for water damage to the ins ured property, said to have been the result of a water ingress event. The insurer accepted the claim however has declined to cover damage to the ceiling in the downstairs sewing room on the grounds this damage was not the result of the event giving rise to the claim. Rather, on the balance of probabilities, this damage had been occurring gradually over an extended period of time. 1.1 Issues and key findings What does the policy cover? The policy covers accidental loss or damage to the insured property subject to the limitations and exclusions specified in the product disclosure statement (PDS). Is the insurer entitled to limit its liability under the claim? The insurer has been successful in establishing, on the balance of probabilities, the damage to the ceiling in the downstairs sewing room at the insured property is not the result of the event giving rise to the claim. Rather, on balance, this portion of the claimed damage is clearly excluded from cover under the policy. Accordingly, the insurer is entitled to partially decline the claim in line with the policy provisions specified in the PDS. 1.2 Determination This determination is in favour of the insurer. The insurer is entitled to decline cover for the damage to the ceiling in the sewing room given the available information and policy exclusions. Determination | Case number: 630135 Page 3 of 7 2 Reasons for determination This complaint has been the subject of the preliminary view provided to the parties on 15 August 2019, by AFCA. I acknowledge the preliminary view is in favour of the complainant. Having considered the available evidence, including additional information received after the preliminary assessment was provided, I am not of the same view and this determination is in favour of the insurer. The reasons for this are detailed below. 2.1 What does the policy cover? The policy is an accidental damage policy of insurance The policy provides cover for loss or damage to the insured property (building and common area contents) which occurs during the period of insurance, including additional covers as provided in the policy documentation. Cover under the policy is subject to the policy limitations and exclusions also specified in the PDS. The complainant lodged a claim seeking cover for water ingress damage to one of three offices located upstairs as well as the downstairs sewing room ceiling. The insurer has accepted to cover the damage to the office however it has declined cover for the ceiling damage in the sewing room. The insurer is of the position the damage to the sewing room ceiling is not the result of the water ingress event giving rise to the claim. Rather, that this damage has been present for several years and has continued to deteriorate over time due to wear, tear and gradual deterioration. It is established law that in order to seek cover under the policy the onus first rests with the claimant to establish, on the balance of probabilities, the loss claimed is covered by the terms of the policy. Only once this has been established, will the onus shift to the insurer to establish, on balance, that it is not responsible to cover the claimant for the loss in line with a provision or exclusion present in the terms of the policy. 2.2 Is the insurer entitled to l imit its liability under the complainant’s claim ? The onus rests with the insurer to establish it can decline cover for the ceiling The available information establishes the insured building has suffered damage because of a water ingress event relating to the evaporative air-conditioning unit located on the roof of the insured building. I accept this was an unintended and unexpected event, therefore, a valid claim has been established under the policy. Determination | Case number: 630135 Page 4 of 7 The insurer has sought to limit its liability under the claim to what it would cost to repair the water ingress damage in the upstairs office only. The insurer says the damage to the sewing room ceiling is not the result of the water ingress event resulting in the claim. Accordingly, the onus rests with the insurer to establish, on balance, the damage to the ceiling in the sewing room is excluded from cover. The parties to this complainant have sourced and rely on reports from various consultants who have assessed the insured property over the years. These reports have made this information available for AFCA’s consideration. I have considered these reports and the relevant information from these reports has been summarised in section 3 of this determination. The damage to the sewing room ceiling existed prior to the water ingress event I have carefully considered the information provided by the parties in support of their respective positions relating to the damage to the ceiling in the sewing room at the insured property. I am of the opinion this information shows, on balance, the insured building has been experiencing water ingress issues since at least 2015. With respect to the damaged ceiling in question, I am satisfied it has been shown, on balance, this damage was not the result of the more recent evaporative air-conditioning and box gutter water ingress event. The available information includes a dilapidation report completed by consultants’ ‘S’ in March 2016. This report includes very helpful photographic evidence that shows cracking to the cornice/ceiling around the downpipe as well as sagging air- conditioning vents. A quote for repairs completed by consultant’s ‘M’ in April 2017 sourced by the complainant, again identifies the dame damage noted in the S report a year prior as well as identifies 3sqm of sagging ceiling which it recommends required replacement. It is clear the damage to the sewing room ceiling had increased from what was noted in the dilapidation report some 12 months prior. Despite requests by the insurer, the complainant has not made available any evidence which establishes the repairs recommended and quoted by M in 2017, were completed to the sewing room ceiling . Further, I accept the damage noted in 2016 and later in 2017, is in the exact same location as the damage subject of the claim giving rise to this complaint before AFCA. Without evidence to the contrary, I accept the available information establishes on balance that the damage noted in 2016, has gradually continued to deteriorate and increase to the point where in 2019, the sagging increased to 75% of the ceiling. This Determination | Case number: 630135 Page 5 of 7 being due to the complainant’s failure to address the concerns identified in 2016 and 2017. Given this, I do not accept the complainant has been able to show, on balance, the damage to the sewing room ceiling subject of the claim is the result of the water ingress event which caused damage to the office. Rather, the damage to the sewing room ceiling has been present since as early as March 2016 and has continued to gradually increase due to wear, tear and a failure to maintain, which are circumstances clearly excluded from cover under the policy. I acknowledge the complainant’s reference to the fact the insurer’s appointed assessor, after the initial assessment, accepted there was damage to the sewing room ceiling consistent with the claimed water ingress event. However, this was based on what he was informed of at the time and not having had the opportunity to review the dilapidation report, M’s quote and other relevant information. Accordingly, I determine the insurer is entitled to decline cover for the damage to the sewing room ceiling under the claim in line with the policy exclusions specified in the policy. 3 Supporting information 3.1 Relevant policy wording Section 1- Insured Property We will not pay: (i) if gradually operating causes (such as but not limited to Wear, Tear, gradual corrosion, gradual deterioration, wet or dry rot, rust, vermin or insects) primarily contribute towards the Loss or Damage 3.2 Consultants’ evidence provided by th e parties Record Key points S Dilapidation Report 18 March 2016  the purpose of this report was to show the present condition of the property (insured building)  the survey giving rise to the report was completed on 14 March 2016 (the sewing room subject of this complaint bet ween the parties is referred to as the storage area in this report)  photographic evidence in this report shows damage in the form of a crack to the ceiling cornice around the downpipe and sagging air - conditioning ducts in the storage r oom. Determination | Case number: 630135 Page 6 of 7 Record Key points M’s Quote for repairs 16 March 2017  source and supply two side by side plastic air - conditioner vents, located next to the internal downpipe in stock room (s ewing room)  disconnect light, remove 3msq section of sagging gyprock ceiling in the stock room, scrape back existing glue and remove fixings. Inspect adjoining sheets to see if further sections of ceiling requires repair… W Air - conditioning and refrigeration report 15 January 2019  found water had leaked into the building from evaporative air - c onditioning due to the drains being blocked from leaves and dirt As Roofing quote  damage to upper room ceiling, extensive area of water damage due to water ingress from evaporative air - conditioning unit located above  lower floor ceiling damage, wat er ingress damage has caused water staining and sagging of the ceiling TS First Report 2 February 2019  attended insured property on 29 January 2019  two evaporative air - conditioning compressor units are installed on the roof of the insured property  TS was informed on 14 January 2019, the complainant discovered the plasterboard ceiling in the sewing room had been damaged by water as the cornice next to the main roof downpipe had cracked and the ceiling panels had dropped  an inspection by consultants ‘W” appo inted by the complainant had found the box gutter rainwater sump was blocked with debris preventing water from evaporative air - conditioning compressors draining into the downpipe  the following day the complainant also discovered wat er damage to the ceiling of the middle office of three located on the upper level of the insured property  TS concluded, based on the site visit and information from the complainant, the damage sighted was consistent with water overflowing a box gutter and drainage pipes from the air - conditioning compressor units TS Second report 19 February 2019  recently reviewed dilapidation report from 2016  the inspection of the ins ured property on 14 March 2016 show the damage to the sewing room ceiling cornice at the edge of the downpipe (ex act same position as it is now)  TS formed the view the damage existed before the claimed date of loss subject of the claim  Point 2  Point 3 Email from consultant JG 18 October 2019  JG was the consultant that attended the insured property on behalf of the TS to undertake the assessment in January 2019  JG only became aware after having submitted his first report that the informed provided to him by the complainant was inaccurate  he reviewed the dilapidation report completed in 2016 which Determination | Case number: 630135 Page 7 of 7 Record Key points showed damage to the same area as claimed under the current claim  JGT noted the quot e sourced by the complainant from M dated 16 March 2017  this quote also notes the presence of the same damage in the sewing room as well as removal and replacement of 3msq of sagging ceiling  given this additional information, JG from the opinion the complainant’s failure to rectify the fault with the ceiling despite being informed of it in 2016 and 2017, has led to further deterioration and more noticeable sag  when ceiling fixings start to fai l, this places/passes additional load bearing on the adjoining fixings – these adjoining fixings then begin to fail under the inc reased load until a section of the ceiling collapses.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.