Home / Credit Union Australia Ltd / Determination 629145
Determination 629145
Settlement delay causing penalty interest and mishandled FHOG processing
Summary
The complainant claimed penalty interest and a vendor default fee after settlement of his home loan was delayed, and said the lender mishandled his First Home Owners Grant. AFCA found the lender did not cause the settlement delay but awarded $250 for the FHOG processing failure.
The delay was caused by the complainant's construction and contract issues and his late notice of a realistic settlement date, while the lender's FHOG handling was unreasonable and caused short-term inconvenience.
Issues
- Delay primary · not upheld
“I am not satisfied the financial firm caused a delay in the settlement of the property.”
- Administrative error secondary · upheld
“The financial firm did not act reasonably in relation to the FHOG ... there was an issue with the processing of the FHOG application.”
Subjects and remedies
broker or intermediarypay non financial loss
Text of the determination
Determination
Case number 629145
Financial firm Credit Union Australia Ltd
Determination | Case number: 629145 Page 2 of 7
Case number: 629145 11 October 2019
1 Determination overview
1.1 Complaint
In February 2018, the complainant purchased an off the plan property (the property).
The complainant engaged a broker (the broker) to obtain finance for the property
purchase. The broker acted as the complainant’s agent and approached lenders on
his behalf. The complainant decided to obtain a loan from the financial firm.
The complainant says the financial firm delayed the settlement of the property. Due to
the delay he incurred financial loss included penalty interest charges of $2,748.18 and
a default notice of $660 from the vendor.
The complainant also says the financial firm contributed to a delay in processing the
First Home Owners Grant (FHOG) application and he was required to use $10,000 of
his own funds at settlement. The complainant’s claim is against the financial firm only .
1.2 Issues and key findings
Did the financial firm cause a delay in the settlement of the property?
On the available information, I am not satisfied the financial firm caused a delay in the
settlement of the property. There was initial delay due to issues with the purchase of
the property unrelated to the conduct of the financial firm. The financial firm has acted
reasonably and in accordance with good industry practice to complete the loan
approval process for settlement which occurred on 15 February 2019.
Did the financial firm cause a delay in processing the FHOG?
I am not satisfied the financial firm acted reasonably with the FHOG application and
this caused the complainant to use his own funds at settlement. He was
inconvenienced due to the financial firm’s conduct.
1.3 Determination
This determination is substantially in favour of the financial firm.
If the complainant accepts this determination, the financial firm should pay the
complainant $250 for his non-financial loss to an account nominated by him.
Determination | Case number: 629145 Page 3 of 7
2 Reasons for determination
2.1 Did the financial firm cause a delay in the settlement of the property?
The complainant made the loan applications with the assistance of the broker
I have prepared a timeline of relevant events which is included at section 3.2 of this
determination. I have reviewed the financial firm’ s internal system emails and the
application notes to determine the timeline. The complainant made three loan
applications to the financial firm before the settlement of the property. The loan
applications were made with the assistance of the broker.
The role of the broker is to act as an intermediary between the complainant and the
financial firm and to assist with the loan application. Ultimately, the loan is provided by
the financial firm. The credit risk decision and final decision rests with the financial
firm. In this case, the broker was responsible for providing the complainant’s
application and financial information to the financial firm in anticipation of the loan
assessment, approval and settlement.
The construction of the property was delayed
The first loan application (1008187) was submitted in February 2018. The
complainant then informed the financial firm there were issues with the purchase
contract. The complainant says he was offered a new land lot by the developer and
another contract of sale was executed. Therefore, the construction for the property
was delayed.
The financial firm provided pre-approval for the loan for a period of 90 days. The
financial firm also agreed to waive the application fee of $600 for the complainant.
The pre-approval expired on 24 June 2018 and the complainant agrees he was on
notice about this. There was no delay by the financial firm in this period.
The second loan application was submitted in October 2018
The complainant submitted the second loan application (1032066) to the financial firm
on 17 October 2018 seeking full approval for the loan. The financial firm conditionally
approved loan 1032066 on 26 October 2018. The broker was informed that the
approval was subject to some conditions being met; including requesting further
details about the shortfall funds for settlement, a credit enquiry and clarification of the
complainant’s name on the contract of sale which had previously been cancelled.
The broker says he provided the FHOG application and the new purchase contract,
following the conditional approval. He says further that he had clarified the other
outstanding issues previously with the financial firm. There is also nothing to show the
financial firm was instructed of the settlement date, and it appeared to be unknown at
that time. However, the complainant had 90 days from the conditional approval to
provide the information and inform the financial firm of the settlement date.
Determination | Case number: 629145 Page 4 of 7
The third application was submitted in January 2019
The financial firm sent an email to the broker on 10 January 2019, stating application
1032066 was cancelled. The financial firm says this was sent to the broker as a
warning to let the complainant know the application was due to expire shortly. On my
calculations, the application should have expired on 24 January 2019. In any event, it
is not clear when the financial firm became aware of a possible settlement date of 30
January 2019. However, regardless of the settlement date the financial firm required a
third application to be submitted.
The third application was submitted on 27 January 2019, with details of a settlement
booked for 6 February 2019. The complainant and his broker requested an extension
of time for the settlement to proceed.
The financial firm did not delay the settlement
I have reviewed all the material submitted by the parties and have considered what is
fair and reasonable in all the circumstances of this complaint. This was a complex
situation as there had been delays with the construction of the property which were
unrelated to the financial firm’s conduct.
However, the question for me to consider was whether there was any error or conduct
by the financial firm which caused the settlement to be delayed. The third application
was assessed and approved for document preparation on 7 February 2019.
Settlement then took place on 15 February 2019 , despite the broker’s claim it
occurred on 18 February 2019. I have concluded that it occurred on this day as
settlement funds were debited from the complainant’s account that day. The
complainant was required to pay penalty interest from 30 January 2019 to 18
February 2019 to the vendor. He says this should be paid by the financial firm.
On the available information, I am not satisfied the complainant let the financial firm
know in a timely manner that settlement was booked for 30 January 2019. This was
not a realistic settlement date, bearing in mind the third application was onl y
submitted on 27 January 2019. An extension of time was sought by the broker to 6
February 2019, but this was not sufficient time for the financial firm to complete all the
necessary process steps.
I consider the financial firm took reasonable steps to assess the loan application,
approve the loan and attend to all the administrative details to proceed to settlement
on 15 February 2019. All the information shows there was no undue delay by the
financial firm in this period. Accordingly, the financial firm is not liable for any penalty
interest the complainant has incurred.
Determination | Case number: 629145 Page 5 of 7
2.2 Did the financial firm cause a delay in processing the FHOG?
The financial firm did not act reasonably in relation to the FHOG
As the complainant was a first home owner, he made application to the State
Government for the FHOG. This is a separate process which the financial firm assists
the complainant to complete. There was some confusion about the process for the
FHOG but ultimately the financial firm was responsible for ensuring the process was
completed prior to settlement of the property.
I appreciate the whole process was a daunting one for the complainant, but he
engaged the broker to guide him through it. However, there was an issue with the
processing of the FHOG application and the complainant was required to use his own
funds to complete the settlement.
The financial firm has not provided an explanation as to why this issue arose and has
not acted reasonably towards the complainant, as he had to ensure he had additional
funds to complete the settlement at short notice. However, the complainant received
the funds on 20 February 2019, so he was only inconvenienced for a short period.
The financial firm should pay the complainant $250 for non-financial loss for this
inconvenience.
Determination | Case number: 629145 Page 6 of 7
3 Supporting information
3.1 This determination is made under AFCA Rules
This complaint has been determined based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous decisions of AFCA or its predecessor schemes (which are not binding).
A full exchange of the relevant information has taken place between the respective
parties. Each party has had the opportunity of addressing any issues raised.
All the provided material has been reviewed and considered. The parties have raised
numerous issues in their submissions to AFCA. However, commentary in this
determination is restricted only to those submissions considered relevant to the
outcome.
3.2 Timeline of relevant events
Date Action
12 February 2018 Com purchased the property
22 February 2018 Application 1008187 submitted to FF
26 February 2018 FF commences application and orders valuation
2 March 2018 Com advises property not ready as construction delay ed
9 March 2018 FF pre - approves the loan $600 application fee waived
26 March 2018 Purchase contract cancelled
24 June 2018 FF says pre - approval for 1008187 expired
17 Oct ober 2018 Application 1032066 submitted to FF
18 Oct ober 2018 Broker requests another application fee waiver
26 Oct ober 2018 FF conditionally approves the loan, broker was asked by the FF to provide
further information for the application, an email sent to the broker requ esting
information
The broker says he provided a response over the phone immediately
30 October 2019 FF requests furt her clarification from the complainant about the cancelled
contract of sale and the complainant’s full name
Broker confirms no settlement date booked
10 January 2019 Broker receives email saying application 103 2066 was cancelled
21 January 2019 Broker sends email to FF asking if the previous application can be copied
Determination | Case number: 629145 Page 7 of 7
Date Action
FF responds the application has expired (only lasts 90 days) so it will have
to be resubmitted
Broker says settlement was due next month
25 January 2019 FF receives Transfer of Land for settlement
27 January 2019 Broker lodges application again, informs FF settlement is booked for 6
February 2019
29 January 2019 FF acknowledges receipt of third application
30 January 2019 FF says loan appl ication is with assessor, FF again asking about credit
enquiry on complainant’s credit file
30 January 2019 Broker responds to FF stating as per the last application nothing eventuated
from the credit enquiry as no credit card issued
Everything remains unchanged from second application and settlement is
due next week, broker says complainant has already extended the
application twice due to building delays
31 January 2019 FF says complainant’s middle name is missing from contract of sale and
transfer of land, will need amended copies
4 February 2019 FF says loan is conditionally approved
7 February 2019 FF preparing documents for settlement
15 February 2019 Settlement takes place
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.