Home / Westpac / Determination 625940

Determination 625940

Cash settlement of fire-damaged home and contents claim, asbestos handling and delay

FirmWestpac
Decided2020-01-30
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$553,921
Non-financial loss$5,000
Amount claimed$592,294
SourceAFCA PDF

Summary

A home and contents claim after a neighbouring fire was disputed over asbestos decontamination, scope of works and delay. AFCA ordered cash settlement of the building and contents, further temporary accommodation and $5,000 non-financial loss, and refused reimbursement of the representative's fees.

The insurer's proposed repair-based settlement was not shown to fulfil its policy obligations given inadequate asbestos handling and delay, so cash settlement at full sum insured was fair.

Issues

Subjects and remedies

home or building damagemental healthnatural disasterpay claimpay non financial loss

Related

All Westpac determinations · Find similar determinations

Text of the determination

Determination Case number 625940 Financial firm Westpac General Insurance Limited Determination | Case number: 625940 Page 1 of 16 Case number: 625940 21 January 2020 1 Determination overview 1.1 Complaint The complainant lodged a claim under her home and contents insurance policy with the financial firm (insurer) after her ho use was damaged by a fire in her neighbour ’s property in November 2018. The insurer accepted the claim for loss and damage to both the building and contents. It arranged for removal of contents, obtained scopes of works and assessments of the complainant’s home for asbestos contamination. The complainant does not agree with the proposed scope of works or response to the asbestos issue. She wants the property to be deemed a total loss. She also says not all contents have been accounted for. As well, the complainant is unhappy with the way the claim has been handled. She is seeking compensation for delays and the adverse effects of the insurer’s actions on her emotional and psychological well-being; and reimbursement of professional fees incurred in the course of the claim. 1.2 Issues and key findings How should the building damage be settled? It is fair, in the particular circumstances, that the claim for property damage be cash settled on the basis of a total loss, for the full building ‘sum insured’ of $392,815. As explained in detail in section 2, that is because of the significant delay, and on-going concerns about the insurer’s management of the claim and the adequacy of the insurer’s proposed scope of works in fully satisfying its obligations under the policy. In addition, t he ‘building additional benefit’ for ‘demolition and removal of debris’ should also be paid, up to the policy limit of 10% of the building sum insured, based on a quote or invoice for the work to be obtained and provided by the complainant. How should the contents be settled? The evidence shows the initial contents inventory taken by the insurer was incomplete. The complainant has identified damaged or missing contents valued at $199,479. It is fair in the circumstances that she be paid the full contents ‘sum insured’ of $134,174 for damaged and missing contents; together with $13,417 representing the applicable additional policy benefit (‘sum insured safety net’). That totals $147,591. Determination | Case number: 625940 Page 2 of 16 Is the complainant entitled to additional temporary accommodation? The complainant is entitled under the policy to $39, 281.50 (10% of the building sum insured) for emergency/temporary accommodation. The insurer has already paid $25,766.26 over and above that. However, given the delays in finalising the claim so far, and the remaining uncertain timeframe before the home can be habitable, it is fair that the complainant be paid a total of $78,563 (twice the policy allowance), less the amounts ($39,281.50 plus $25,766.26) already paid, which is $13,515.24. Is the complainant entitled to further compensation? The complainant is entitled to the maximum $5,000 compensation for non-financial loss for the significant distress and inconvenience, delays and uncertainty she has suffered as a result of the insurer’s handling of the claim. The complainant is not entitled to reimbursement of professional fees incurred for the claims management specialist she engaged. 1.3 Determination This determination is in favour of the complainant. The insurer is required to:  cash settle the building damage by paying $392,815  cash settle the cost of the ‘building additional benefit’ for demolition and removal of debris up to the policy limit, based on a quote/invoice to be obtained by the complainant  cash settle the contents loss and damage by paying a total of $147,591  pay the complainant $5,000 compensation for non-financial loss. Statutory interest does not apply to these payments. The insurer is not required to take any other action. Determination | Case number: 625940 Page 3 of 16 2 Reasons for determination There has been a full exchange of all information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. This determination has been made by a panel consisting of an ombudsman, an individual with extensive insurance experience and another individual with extensive consumer experience. The decision follows consideration of all the material exchanged. It is based on what is fair in all the circumstances having regard to relevant legal principles, the terms of the policy, good industry practice including codes of practice, and previous decisions where applicable. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues considered directly relevant to the outcome. 2.1 How should the building damage be settled? Policy sets out how building claims may be settled The complainant holds a home and contents insurance policy (Quality Care level) with a buildings sum insured of $392,815 and general contents sum of $134,174. Loss or damage caused by ‘fire’ is covered under the policy. The terms of the policy are set out in the product disclosure statement (PDS). The PDS allows the insurer to decide how to settle a claim for property damage, either by paying:  the reasonable cost of repair  the reasonable costs of replacement to new condition with property of the same size and specification or with items as near to original as is currently possible, or  a cash amount being ‘ the amount it would reasonably cost to repair or replace the property ’ . The PDS also states when the insured property is damaged or destroyed to such an extent it cannot be rebuilt or repaired and/or the total sum insured under the policy has been exhausted, it will then be declared a total loss. However, in applying the policy provisions and exercising any discretion under the policy, the insurer is expected to act reasonably and fairly, having regard to the particular circumstances. Determination | Case number: 625940 Page 4 of 16 Insurer’s p roposed settlement based on scope and quotations obtained The insurer’s builder, P, inspected in December 2018 and provided an initial report and broad scope of works/quote (for $75,777.55) for asbestos removal and decontamination (noting the property was highly contaminated and not suitable for occupancy), general removal of damaged property, and inventory of contents. That scope of works did not cover the actual repair of the damage it identified to the home (including to plumbing, fencing, roofing, guttering and other external fixtures, and the internal and external asbestos contamination) but was for remediation which needed to be carried out first. It was noted that full repair of the complainant’s property could not be carried out until the neighbour’s property had been fully decontaminated, given the high level of asbestos. P anticipated long-term alternative accommodation would be needed for the complainant and her family. In February 2019, P provided a scope for the damage repairs, together with another for the proposed cash settlement of 50% of the shared boundary fencing and for landscaping, although it was noted tha t landscaping is not covered under the complainant’s policy. That totalled almost $94,000. The insurer subsequently appointed a loss adjuster S to take over both the contents and building repair elements of the claim, as the complainant had been unhappy with P’s involvement (a concern which proved to be justified, as set out below). In February 2019, S engaged building consultants SBC to provide a scope of works for the actual repairs. They reported that P’s make safe works to the property had been poor, allowing plastic to be ripped off the eaves in high winds exposing the roof, and a broken window being shattered. SBC also expressed concern this had allowed asbestos fibres to enter the ceiling cavity. Further make safe was undertaken, and asbestos testing carried out. The insurer obtained a repair quote dated 16 April 2019 from builder BC for $204,939.24 (valid for 30 days); and one from builder N dated 10 April 2019 for $241,855.19, based on SBC’s 15 March 2019 scope of works, and predicated on the requirement that an asbestos clearance certificate would be obtained before their work commenced. These quotes were reviewed and compared by S in a document described as ‘total loss detailed cost estimate @ March 2018 [sic] rates’ dated 24 April 2019 . (It would appear that was meant to be identified as being at ‘March 2019’ rates.) S arrived at a ‘trade’ estimate of $209,727, by reference to SBC’s scopes of works. It was noted that some pre-existing and unrelated water damage was not covered in the scope or quotes. Determination | Case number: 625940 Page 5 of 16 The insurer has proposed settling the claim by attending to the decontamination of the asbestos and repairing the complainant’s home based on SBC’s scope of works , using builder BC. Complainant does not accept scope of works is complete or sufficient However, the complainant rejects SBC’s scope of works on which the repair quote was based. In particular, she says the scope does not fully address the extent of asbestos contamination to the building ; and that if that was thoroughly and appropriately dealt with the building would effectively be a total loss . She wants the claim to be cash settled by payment of the full building sum insured ($392,815), together with allowances for additional benefits to which she is entitled under the policy. The complainant has not provided any specific expert reports to show the insurer’s broad scope of works would not be effective to repair the property to the appropriate standard required under the policy. However, there is remaining uncertainty about the adequacy of the proposed asbestos decontamination (as well as the steps already taken), and the implications of that on the scope of work that would ultimately be needed. Concerns about asbestos contamination/proposed remediation are justified The panel understands that i nitial asbestos testing by the insurer’s hygienists (P r) showed no asbestos present, but that the testing was only in three areas, and not in the ceiling or wall spaces. In March 2019, the insurer engaged environmental services expert/hygienist T, whose assessment identified ‘ asbestos impact ’ in all internal areas of the house, including remaining contents; the internal ceiling cavity and roof cladding; certain external areas including the front lawn. The recommended scope of works included removal of all roof cladding, environmental cleaning of ceiling cavity followed by encapsulation with an emulsion spray-cleaning of non-porous areas (for later re-inspection). Test results attached to T’s report showed the ceiling cavity revealed no asb estos, but wall cavities were not tested. This is in contrast to a test conducted by hygienist ZA in January 2019, which had identified asbestos in the ceiling cavity (but was apparently only conducted after the complainant requested it). The insurer ac cepted T’s report . After the complainant’s representative became involved and raised a number of specific queries, the insurer contacted builder BC asking them to arrange for their asbestos company FG to respond to those queries and advise whether the additional requested work would need to be undertaken. On the same day (30 May 2019), hygienist T sent an email to FG/BC which was forwarded to the insurer. In their Determination | Case number: 625940 Page 6 of 16 email, T said ‘it would be better to err on the side of caution and conduct a full decontami nation of the wall cavities as best practice’. T went on the say: As a precautionary measure the roof structure was included for removal in the latest scope of works report. To eliminate any doubt regarding asbestos contamination of the ceiling cavity timber trusses I am happy to include these as part of the asbestos removal along with the roof structure. On 12 June 2019, S urgently instructed BC to ‘undertake additional asbestos testing of the wall cavities and other areas to determine the current extent of asbestos contamination, if any’. Those instructions do not reflect T’s recommendation for a full decontamination. The complainant declined access to her property for that testing when she was told it was to be to limited areas only (that is, only the walls down the left side, closest to the fire, and only if asbestos was found would further testing be done to all remai ning walls). She believes a full strip-out of the internal walls is necessary, as indicated to her by the asbestos experts. In rejecting the scope of works and the proposed asbestos work, the complainant points out:  while removing contaminated soil, the contractor P left the windows and doors of the home open, allowing contaminated dust to enter  this was further exacerbated by removal of sofit linings while the contaminated soil was being removed, allowing contaminated dust into the roof space (as confirmed by the insurer’s hygienist) and wall cavities  asbestos decontamination work should include storm water and sewer lines which were open to the atmosphere  the wood wall frames are classified as ‘ porous ’ raw wood and cannot be cleaned (of soot, smoke or asbestos), which means the wood wall frames must be removed and disposed of  the impact on electrical wiring and attached appliances has not been considered by the insurer  smoke-logging in wall cavities has not been addressed  the method of encapsulation proposed by the insurer (spraying the structure with PVA to ‘ glue ’ the asbestos fibres to the structure and keeping it on-site) fails to comply with the terms and conditions of the policy, which states debris is to be removed from the site. The complainant also says the encapsulation method is a short-term solution and burdens her with the risk of further asbestos exposure over time. Determination | Case number: 625940 Page 7 of 16 The insurer has not responded to the complainant’s specific concerns regarding encapsulation, smoke logging, or removal of all contaminated debris, despite it having asked BC to address those points. The complainant submits that it is highly unlikely the property could be properly decontaminated without effectively destroying the whole structure, although no specific quotes, scopes of works or reports have been provided in support of that conclusion. Cash settlement for building ‘sum insured’ is fair in the circumstances The panel accepts the complainant’s concerns are valid, and does not consider the insurer has adequately addressed them, or otherwise justified its proposed resolution of the claim and complaint. The panel notes:  asbestos testing to date, and proposals for further investigation and remediation, are inadequate to deal with a serious invasive contaminant and associated health risk which was introduced to the property: ‘encapsulation’ has not been shown to fulfil the insurer’s obligations under the policy to deal with the damage  the work initially undertaken by P, with regard to the asbestos issue and more generally, was inadequate and exacerbated the damage. It is worth noting that the insurer (in an email of 31 May 2019) notified S that the complainant’s neighbour had issued a letter of demand on the basis that P had been responsible for re- contaminating their property. That is in addition to the effects of P’s actions on the complainant’s property.  the resulting delays by the insurer/its agents in progressing the claim, in circumstances where a family was left without their home  repair quotes received by the insurer are now almost twelve months old, are highly unlikely to reflect the cost to the complainant to undertake repairs herself in the event of a cash settlement (then or now), and are based on an insufficient scope of works in any case  the insurer’s failure to provide, to either the complainant or AFCA, the 30 May 2019 email from hygienist T, with its recommendations for a much more robust handling of the asbestos issue. It was only after a number of specific requests that it was received.  the complainant’s understandable loss of confidence in the insurer’s handling of her claim. Having considered all the available evidence, the panel considers it fair in the circumstances that the property damage component of the claim be cash settled. It also considers the settlement should be for the full ‘sum insured’ under the policy. Determination | Case number: 625940 Page 8 of 16 Building additional benefits apply The policy also provides certain ‘building additional benefits’ which are payable over and above the building ‘sum insured’. That includes ‘emergency accommodation’, which is considered separately in section 2.3 below. It also includes cover for ‘demolition and removal of debris’ up to a limit of 10% of the sum insured, and requires the insurer to pay ‘the costs of any necessary demolition of [the] home or parts of it, and the removal of resulting debris from the site…’ . At this stage it is not clear what those costs would be. However, the panel is satisfied the insurer is liable for that. The complainant will need to obtain a quotation or invoice for that work from an appropriately qualified contractor, and provide that to the insurer. The insurer is required to pay the quoted/invoiced amount (up to the policy limit) in addition to the full building sum insured. 2.2 How should the contents be settled? Insurer requested a list of missing contents In the initial property inspection in December 2018, P noted the recommendation that most, if not all, the contents needed to be removed and disposed of as they had been subject to asbestos contamination. The insurer’s loss adjuster S said it obtained a copy of the contents inventory prepared by builder P. The complainant had advised the insurer that some of the contents from the house were missing from that list, alleging these had been stolen by P during the initial remediation stage of the claim . S confirmed that in their opinion, P’s inventory was ‘ in sufficient’, and that given the size of the house, the number of people living there and the quality of the items left behind, the full contents sum insured might be exhausted – subject to the complainant providing her own completed contents list, which she was asked to do. S also noted that based on its own assessment, including of the items left on-site, it appeared to them that the majority of the items were unable to be restored to pre - damage condition. In a response dated 28 May 2019, the complainant advised she had not supplied her final contents list to the insurer yet because she was waiting for confirmation as to whether she was required to lodge a theft claim for the missing items, as had been suggested. The complainant says the insurer has not confirmed that. Determination | Case number: 625940 Page 9 of 16 The complainant’s claimed contents were left in the care and control of the insurer and its representatives at the time (P). They undertook to provide a full inventory, but the evidence indicates they did not do so. The panel is satisfied, on balance, that some contents items went missing during that time, whether by misadventure, lack of care or otherwise. The insurer is responsible for that. Given the circumstances surrounding the inventory-taking, removal and assessment of contents items, in the course of which a large number have been unaccounted for, the panel does not consider it fair that the complainant should have to lodge a separate claim for theft for those items (and presumably pay an extra excess for that, as well as having to establish there was, in fact, a ‘theft’) . In November 2019, the complainant did provide comprehensive details of her contents. That consists of a list/values of the contents as initially photographed and recorded by the insurer’s representative ($165,079), together with a list of contents which she says were in the house at the time and not recorded, but which she believes were taken by the insurer’s representatives ($34,400). The total value of the contents identified by the complainant is $199,479. The complainant is also claiming the additional policy benefit (‘sum insured safety net’) which provides up to a further 10% of the $134,174 contents sum insured (which is $13,417). That applies if the cost to repair or replace the contents is more than the sum insured – which, on balance, is the case here. The panel has no reason to dispute the comprehensive and detailed information provided by the complainant, whether in regard to the identity, quantity or value of the listed items. It is now over a year since the fire occurred and the contents were exposed to smoke and asbestos. It is not clear which of those contents now identified in full by the complainant have already been disposed of, which simply went missing during the claim handling or are otherwise unaccounted for, and which have been retained and are likely to be capable of safe and sufficient repair. In the circumstances, the panel considers it fair that the insurer pay the complainant the full contents sum insured, together with a further 10% on that amount, in line with the additional policy benefit. That totals $147,591. 2.3 Is the complainant entitled to additional temporary accommodation? Policy limits ‘emergency accommodation ’ cover The additional policy benefit for emergency/temporary accommodation provides cover for the cost of ‘similar alternative accommodation’ while the home is unliveable, for up to 12 months from the event causing the damage, or the policy limit of $39,281.50 (10% of the sum insured), whichever is less. Determination | Case number: 625940 Page 10 of 16 However, there were service issues identified in relation to the work of builder P who was first engaged to deal with the repairs. That necessitated further work being done and caused avoidable and unanticipated delays, for which the complainant was not responsible. It was in recognition of those service issues that the insurer decided to accept temporary accommodation costs over and above the policy limit. That is fair and appropriate. The insurer arranged for temporary accommodation to be paid up to 6 September 2019. The insurer submits it has now paid $25,766.26 over and above the policy limit on an ex gratia basis, and has not agreed to pay any more. Complainant had certain entitlements for temporary accommodation Even without those initial delays, the complainant ’s requirements for (and entitlement to) ‘similar alternative accommodation ’ – allowing dogs; four bedrooms; a pool – made it difficult to find a suitable property. That was also exacerbated by the uncertainty about when the claim would be finalised and the house liveable again. As a result, the complainant has been required to move on a semi-regular basis, through no fault of her own; and has had to take much of the initiative in sourcing the accommodation. This lack of clarity, stability and continuity has been particularly disruptive for the complainant and her three young children. Delays have meant repair work could not commence when it first might have After the initial delays, in May 2019 the insurer provided approval for its appointed builder to commence repairs on the property, but the complainant advised she would not authorise repairs since she did not agree with the scope of works, and had serious concerns about the asbestos issue. She also engaged her representative at around that time. The insurer then revisited aspects of its investigation and assessment of the damage, including to do with the sufficiency of asbestos testing and recommended decontamination work. As already explained, the evidence indicates those further reviews were justified. However, they would not have been necessary if the matter had progressed as it should have from the beginning. So, as well as the delays which have occurred to date (meaning it is already over a year that the complainant has been without her home), there will now inevitably be a considerable amount of further time taken before the house can be fully rebuilt. It will remain unliveable in the meantime. In the particular circumstances, the panel considers it fair that the complainant receive a further $13,515.24 for temporary accommodation. That is twice the policy Determination | Case number: 625940 Page 11 of 16 entitlement for temporary accommodation ($78,563.00), less the amount of $65,047.76 ($39,281.50 plus $25,766.26) already paid. 2.4 Is the complainant entitled to further compensation? AFCA may award compensation for non-financial loss Under the AFCA Rules, we may award compensation (capped at $5,000) for non- financial loss where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. We adopt a conservative approach to the award of compensation for non-financial loss, and expect complainants to be moderately robust and bear the usual stress and inconvenience associated with an insurance claim. However, we do consider the complainant’s particular circumstances and how the actions of the insurer have impacted them. In this case, the evidence shows the complainant has experienced a significant and unusual degree of upset and inconvenience because of the actions of the insurer and its representatives and agents. The complainant is the single parent of three young children, for whom she has been trying to maintain stability in uncertain and protracted circumstances . She has provided a report from her treating psychologist which attests to the significant decline in her mental health which has resulted from, not just the loss of her home (for which the insurer is, of course, not responsible), but the time and complications involved in making that right again. Her home and possessions were fundamentally damaged, and proposals to remedy that included an inadequate approach to dealing with the serious issue of asbestos contamination. The way that was handled by the insurer only added to her concern and lack of confidence in how and when the claim would be resolved and her family returned to their home. The complainant was entitled to expect and receive a professional and respectful handling of the matter, confident that her interests as a policyholder with a valid claim were being conscientiously addressed. It is apparent that is not how she feels about the experience – starting with P’s failure to properly and safely deal with the initial remediation and handling of her contents ; and continuing with the insurer’s apparent reticence about providing her (and AFCA) with a copy of the hygienist’s email which clearly recommended a more robust approach be taken in dealing with the asbestos issue than the insurer was inclined to adopt. The panel is satisfied it is fair in the circumstances that the complainant receive $5,000 compensation for non-financial loss. Determination | Case number: 625940 Page 12 of 16 The panel understands the insurer has previously agreed to make an ex gratia payment to the complainant of $3,000 in recognition of the issues with its service. To be clear, the award of compensation in this Determination is in addition to any such previous offers or payments by the insurer. Insurer is not required to contribute to cost of representation In the course of the claim, the complainant appointed a claims specialist as her representative. She is seeking the costs of engaging that representative to assist her, although the amount has not been identified. Under our Rules, we may require an insurer to reimburse a complainant for professional costs incurred regarding their claim. We will not require an insurer to contribute more than $5,000 to these costs, unless exceptional circumstances apply. However, we provide a service which is free to complainants. It is not usually necessary for them to be represented. We decide whether the insurer should contribute to these kinds of claimed costs by considering what is fair in the circumstances, taking into account the complexity of the complaint and whether the complainant genuinely required expert assistance. In this case, the panel appreciates it would have been a significant extra burden for the complainant to have had to continue managing the claim and complaint herself, particularly as time went on. However, the issues are not in themselves complex, despite the complications that have arisen. Nor is the panel satisfied the input of the representative specifically altered the course of the matter, or the outcome. The panel does not consider it appropriate or necessary in the circumstances for the insurer to meet those costs. Interest on cash settlement not required The panel has considered whether statutory interest should be added to the cash settlement the insurer is now required to make, but has decided that interest need not apply. That is because the panel is satisfied the required total cash settlement represents the outcome, in the particular circumstances, which fairly accounts for the complainant’s loss and the insurer’s liability. Determination | Case number: 625940 Page 13 of 16 3 Supporting information 3.1 Relevant policy wording X Building or home does not mean: - page 14 Greenery and outdoor decorations • lawn, landscaping, plants, shrubs, trees or potted plants – unless covered by Premier Care Additional benefits (refer to page 31), X Contents doe s not mean: - page 15 Greenery and animals • lawn, landscaping, plants, shrubs, trees, Building additional benefits Emergency accommodation – page 29 If your home is unliveable, we will cover the cost of similar alternative accommodation for you and any other ins ureds. This expense will only be paid if you actually incur costs for emergency accommodation, and only while your home remains unliveable. Quality Care – Up to 10% of the sum insured or the cost of accommodation for up to 12 months from the date of the event, whichever is less. Benefits paid in addition to your contents sum insured Sum insured safety net – page 33 If the cost to repair or replac e your contents is more than your sum insured, we will cover the extra cost to: • repair damage to your contents, and/or • replace your contents. Quality Care - Up to 10% of the sum insured How we settle your claim – pages 50-51 Repairing or replacing When we agree to pay a claim for loss or damage: We may choose to pay:  the reasonable cost of repair, or  the reasonable costs of replacement to new condition with property of the same size and specification or with items as near to original as is currently possible, or Determination | Case number: 625940 Page 14 of 16  a cash amount. If we agree to pay cash, we’ll pay the a mount it would reasonably cost or repair or replace the property. Where a building is not being replaced, the amount we’ll pa y will be less a reasonable deduction for depreciation due to wea r and tea r and age of the property. … If repair or replacement is not commenced within 6 mont hs from the dat e of the event, any increases in costs due to the delay must be paid by you unless we agree in writing to a longer term. Glossary of defined term s -pages 55-57 Total loss – page 57 When the property insured is damaged or destroyed to such an extent it cannot be rebuilt or repaired and/or the total sum insured under the policy has been exhausted. 3.2 Expert Reports Record Key points I nsurer ’s builder ( P ) Report 21 December 2018  neighbour property had caught on fire resulting in the insured’s property being damaged due to radiating heat.  the insured was evacuated by council due to the neighbouring property being full of asbestos and the insured property is contaminated.  found da mages to the left - hand side of the property which has been caused due to the radiating heat, where building fixtures have melted, windows have cracked  decromasitic roof tiles have sagged due to the heat.  the property is heavily contaminated by asbestos d u e to the neighbouring property.  insured advised that during the claimed event their windows were open and now they have concerns that asbestos conta mination has occurred internally.  unable to dec ontaminate the property until the neighbouring property ha s been fully decontaminated due to its high level of asbestos contamination.  fire damage to HWS, plumbing, fencing, roof, guttering and external building fixtures.  asbestos contamination externally and internally.  fire has caused the resultant damage.  property is highly contaminated and not fit for occupancy.  Need for large amount if not all internal contents to be removed and disposed of as they have been subjected to asbestos contamination. A detailed invent ory will be taken of the items disposed of I nsurer ’s loss adjuster ( S ) Report 4 March 2019  due to the high winds the plastic was ripped off the eaves leaving the roof exposed and the broken window that was taped up by P shattered Determination | Case number: 625940 Page 15 of 16 Record Key points  the building cons ultant was required to board the window up to ensur e no further damage was sustained to the building.  concerned that the poor make safe works to the eaves has possibly allowed asbestos fibres to enter the ceiling cavity. I nsurer ’s loss adjuster ( S ) Asbestos Report 15 March 2019  fire destroyed the asbestos roofed building  asbestos fibres resultant of the fire has been located throughout the internal and external areas of the insured property  asbestos suspected in eaves linings and roof gable lining  the damages occurring during the make safe works we re entirely avoidable and in the most part is due to poor building/demolition practices and the omission of attention to detail. I nsurer ’s expert ( T ) Email 30 May 2019  in relation to the concerns regarding the wall cavities, as it has been many months since the initial swabs were taken it is prudent to conduct a visual inspection of the cavities and take swabs at various locations to confirm or deny the presence of asbes tos.  once the visual inspection is completed, we can make a more informed decision  it would be better to err on the side of caution and conduct a full decontamination of the wall cavities as best practice.  as a precautionary measure the roof structure wa s included for removal in the latest scope of works  to eliminate any doubt regarding asbestos contamination of the ceiling cavity timber trusses, include these part of the asbestos removal along with the roof structure. I nsurer ’s loss adjuster ( S ) Repo rt 27 June 2019  spoke to the insured to seek approval to access the property to carry out testing of the walls  insured stated that unless all walls were tested throughout the entire property she would not give permission to access the property  advis ed tha t the walls down the left side, closest to the fire were to be tested and if asbestos was found further testing of all remaining walls would be undertaken  the insured stated the as bestos company suggested all walls be stripped  no document ation received b y our office stating that all walls required stripping  asked the insured for her approval to proceed with the asbestos testing to which her ans wer was not unless all walls were stripped and tested  contacted the builder and confirmed there was no suggestion that all walls required stripping  he believes that initially only the walls down the left - hand side should be undertaken and if asbestos was found within the wall cavity only then should all wall s be tested  if asbestos was not found he sees no reas on for all walls to be tested throughout the property. Determination | Case number: 625940 Page 16 of 16

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.