Determination 624036

Title insurance claims for unauthorised works and stormwater pipes

FirmFinancial Firm (Unknown - Insurer)
Decided2019-09-25
ProductGeneral Insurance · Other general
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant's title insurance claim for rectifying unauthorised council works was denied. AFCA found the policy responded and ordered the insurer to pay the rectification costs less a $10,000 credit, but rejected the stormwater pipe claim and compensation for non-financial loss.

A council's requirement to obtain retrospective approval and the impact on marketability fall within the Risks affecting use of the Land cover, interpreted practically.

Issues

Subjects and remedies

pay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination | Case number: 624036 Page 1 of 9 Determination Case number: 624036 10 September 2019 1 Determination overview 1.1 Complaint The complainant purchased a property in May 2018. She also acquired a title insurance (residential purchaser) policy with the financial firm (insurer) at the same time. A previous owner had converted the garage into a family / dining room. However, the local council had not authorised these works. There was also an issue with the carport not complying with the local council’s approval. The complainant wants to rectify the matter and lodged a claim against her policy (first claim). The insurer says the claim does not fall within the policy cover. It also says a policy exclusion may also apply. After moving into the property, the complainant learnt the neighbours’ stormwater pipes run underneath her front yard. She wants the pipes removed from her property. She claimed against her policy for the cost of relocating the pipes (second claim). The insurer says the claim does not fall within the policy cover. The complainant also says the claims process has caused her undue stress. She says she was misled with respect to the extent of cover the policy provides. 1.2 Issues and key findings Does the policy respond to the first claim? The policy responds to the first claim and the insurer is required to cover the relevant costs associated with the rectification work, less the amount credited in the purchase. Does the policy respond to the second claim? The complainant has not established she has a valid claim for which the policy responds. Determination | Case number: 624036 Page 2 of 9 Was the complainant misled about policy cover? Although it is unclear whether the insurer provided the complainant with a copy of the policy prior to policy inception, she has not suffered a loss. Is the complainant entitled to compensation? The complainant has not established an entitlement to compensation for non-financial loss. 1.3 Determination This determination is partially in favour of the complainant. The insurer is required to cover the relevant costs associated with the necessary rectification works in relation to the first claim, as outlined under section 2.1 of this determination. However, the complainant is unsuccessful with respect to the balance of her complaint. Determination | Case number: 624036 Page 3 of 9 2 Reasons for determination 2.1 Does the policy respond to the first claim? Complainant to establish valid claim The complainant bears the onus of establishing a valid claim for which the policy responds. She says the local council had not authorised the renovations to the home she and her husband purchased in May 2018. She further says the council does not want her and her family using the renovated area until an engineer checks it and she obtains a development approval. The complainant also says builder’s advice indicates the carport has not been built to the council’s approval. The complainant lodged a claim against her policy with the insurer. The policy provides cover in relation to those risks affecting the use of the property. One such policy provision is where a local authority prevents an insured from using their property as a residence. The provision also covers the situation where an insured is forced to rectify or remove all or part of the existing structures because these do not comply with the development approval. The claim relates to modifications to the home, occurring prior to the complainant purchasin g the home, that did not conform to the council’s development approval. The council notified the complainant about the use of the affected areas . Insurer says policy does not respond The insurer ’s denial letter (dated 7 February 2019) says the policy does not respond because the council is not able to undertake enforcement action against the complainant for the unauthorised works. The insurer also says the council is only recommending the complainant should not use the affected areas. Council’s correspondence to complainant The insurer refers to the council’s email to the complainant (dated 24 January 2019), which indicated there was no approval for a conversion of the garage and/or carport to a dwelling addition. The council further indicated: … if you wish to continue using this space as a habitable space (Dwelling Addition) you require to obtain a Retrospective Development Approval from council … In the meantime it would also be recommended to cease using this space as a habitable space (living space) until an engineer has carried out an inspection and you have obtained Development Approval. (sic) Determination | Case number: 624036 Page 4 of 9 The council’s follow - up correspondence (dated 23 May 2019) indicated the council’s building surveyor and consultant structural engineer inspected the c omplainant’s property on 10 April 2019. The visit revealed there had been additional building work undertaken without council approval. Policy provides cover in certain circumstances The insurer says the council is not preventing the complainant from using the extension as a living space. Instead, the council is recommending she does not use it. The insurer further says the complainant is still able to live on her property. The council acknowledged (letter dated 23 May 2019) it was not able to issue an enforcement notice with respect to the work undertaken without its approval. This was because the relevant time limits within which it could issue an enforcement order had long since expired. The complainant is still facing the prospect of modifications the council had not authorised. The council is aware of the situation and is strongly suggesting the complaint undertake the action outlined in its email to the complainant (dated 24 January 2019). The council stated in that email the complainant is required to obtain a retrospective development approval from it, should she wish to continue using that area as a habitable space. The policy provides cover in situations where a council prevents a person from using their property or where it forces a person to rectify or remove all or part of the existing structure. The policy also covers a situation where the property is unmarketable. The policy defines that term as: …another person has the right and refuses to complete a contract for the purchase of your interest in the Land, has the right and does not comply with their obligations under a lease, or will not grant you a mortgage. While the council is recommending the complainant rectify the unauthorised works, it is also saying the complainant is required to obtain a retrospective development approval. The use of the term ‘required’ takes the matter beyond it being simply a matter for the complainant as to whether she complies. This issue is also likely to impact on the complainant should she decide to sell her home, without rectifying the unauthorised works. The policy provides cover in situations where marketability of the property is an issue. The panel is satisfied that the council is exerting itself on the complainant to fulfil her obligations to bring the unauthorised works up to standard. While the council cannot issue an enforcement order, it nevertheless is exerting pressure on the complainant to Determination | Case number: 624036 Page 5 of 9 comply with its recommendation. In addition, there is a likely impact on the marketability of the property with unauthorised works, which the local council is fully aware of. The policy provision needs to be interpreted in a practical sense. As such, the cover provided under the policy does extend to the complainant’s claim. Insurer referred to policy exclusion The insurer also refers to an exclusion under the policy, saying it would apply. The policy excludes coverage for risks that an insured creates, assumes or agrees to at any time. The insurer refers to the pre-purchase report (dated 8 May 2018), the complainant obtained. The insurer says the complainant was aware the roof would have required replacement / rectification work, although it acknowledges she would not have known the dwelling additions had not been authorised. The insurer contends the complainant assumed the risks and therefore the exclusion applies. The pre-purchase report indicated some repair work was necessary in relation to the roof area over the verandah and rear extension. However, the report did not deal with the issue of the unauthorised work, whereby a previous owner converted the garage into a family/dining room. This means the complainant could not be regarded as having assumed the risks prior to settlement of the property purchase. The vendor allowed a credit of $10,000 in the purchase agreement to cover the identified repair work that was needed. As such, the exclusion does not apply to the claim. Insurer to cover the claim The insurer is required to pay the cost of rectifying the unauthorised works, less the $10,000 credited against the purchase price. The relevant areas of concern are the lounge and dining rooms, in addition to the carport. The insurer is required to obtain a structural engineer’s report within 14 days of the complainant accepting this determination (with a copy to be provided to the complainant). Once obtained, the insurer is to obtain quotes from three builders who would be prepared to carry out the necessary work for the price quoted. The insurer will then cash settle the complainant, less $10,000. 2.2 Does the policy respond to the second claim? Complainant has not established a valid claim The complainant lodged another claim against the policy in relation to her neighbours’ stormwater pipes running under her soil in the front yard. The insurer says the policy Determination | Case number: 624036 Page 6 of 9 does not respond because the neighbour is not pursuing a right in relation to the complainant’s property concerning the stormwater pipes. The complainant needs to establish the policy responds to her claim. There are various categories of cover under the polic y, including ‘risk affecting your ownership of the land’. The complainant wants to remove the pipes from her property because she wants to pave that area. The policy will respond where another party claims to have an easement, access order, an access right, or a right of way that affects the title of the property. The exception to this is where that interest is recorded on the title. In this case, the neighbours are not exerting a right in relation to the complainant’s property. The policy does not respond to situations where an insured is seeking a redirection of stormwater pipes. As such, the insurer is entitled to deny this claim. 2.3 Was the complainant misled about policy cover? Complainant says she was not aware of the extent of cover The complainant, who paid a premium of $402.93 for the policy, says she was not aware of the limitations in the cover when she acquired it. She says she only received a promotional sheet outlining the title insurance policy cover prior to signing the property purchase agreement and acquiring the policy. She further says (submission on 3 June 2019) the information omits the council’s time limits for issuing enforcements. She contends the cover is only worthwhile in situations where structural developments are less than 12 months old. Insurer says it provided a copy of policy The insurer says it made a copy of the insurance policy available to the complainant’s conveyancer by an online ordering platform that conveyancers use. The insurer has provided a screen shot in support. However, the information lacks real detail as to how the system works and why the insurer should feel confident the conveyancer received the information. No loss to complainant Nevertheless, the policy does respond to the complainant’s first claim. Since this is the situation, the insurer is not required to refund the premium the complainant paid for the insurance. Determination | Case number: 624036 Page 7 of 9 2.4 Is the complainant entitled to compensation? Complainant says claims process has adversely impacted on her The complainant says in her submission (1 July 2019) she was recently admitted to hospital on 26 June 2019. She further says the hospital suggested her condition was due to psychological stress. The complainant contends the claims process is the reason for her condition. Our approach to non-financial loss We take a conservative approach to awarding compensation for non-financial loss. Compensation is only provided where a complainant has suffered from an unusual amount of physical inconvenience or stress. Compensation can also be awarded where the financial firm’s conduct has meant the time taken to resolve the situation has been unusually excessive. However, we expect complainants to bear the normal degree of inconvenience experienced when a problem occurs and to take reasonable steps to manage the situation. Complainant has not established entitlement The length of time taken in relation to this claims process was not long. The insurer provided its decision reasonably quickly in response to the lodging of the claims. In addition, the complainant has provided no medical reports in support of her contention the claims process adversely impacted on her health. As such, the complainant is not entitled to an award for compensation for non- financial loss. Determination | Case number: 624036 Page 8 of 9 3 Supporting information 3.1 Our approach to this complaint We have considered it appropriate to expedite this complaint in accordance with the Operational Guidelines to the AFCA Rules, due to the nature of the complaint. Accordingly, this complaint has not been the subject of a preliminary assessment and has proceeded directly to determination. The determination is made by a panel consisting of the ombudsman together with a consumer representative who has extensive experience in consumer claims and an industry representative who has extensive experience in the insurance industry. This complaint has been determined based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous decisions (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All the material provided by the parties has been reviewed and considered. 3.2 Relevant policy wording 2. COVERED RISKS 2.1 Risks occurring before the Policy Date and during the Registration Period We will provide you with Cover against all of the following Covered Risks, if the circumstances creating or giving rise to these risks existed or occurred before the Policy Date. … Risks affecting your ownership of the Land … h) someone else claims to have an easement, an access order, an access right, or a right of way that affects the Title to the Land, other than those registered or otherwise recorded on Title on the Policy Date; … l) any other title defect or lien or encumbrance that affects Title to your Land which is not registered or otherwise recorded on Title on the Policy Date. … Risks affecting your use of the Land … n) your Land is Unmarketable, or you are prevented by a Local Authority from using the Land as a residence, or you are forced by a Local Authority to rectify or remove all or part of the existing structure(s) on the Land (other than boundary walls or boundary fences) because: i. the present use contravenes existing planning or zoning Laws; Determination | Case number: 624036 Page 9 of 9 ii. of any outstanding order, notice of violation or deficiency notice, provided the outstanding order, notice of violation or deficiency notice relates to a Covered Risk under the Policy and you did not agree to be responsible for them; iii. any portion of the existing structure(s) does not comply with or was built or modified without obtaining building or development approvals from the relevant Local Authority, provided building or development approvals would have been required by the relevant Local Authority at the time of construction of the structure; … 3. EXCLUSIONS – RISKS WE DO NOT COVER The following risks or circumstances relating to the Land are specifically excluded from Cover. We do not provide any Cover for any loss or damage of the type(s) listed below. We will not pay any loss for these matters. Also, we are not obliged to pay costs, legal fees or expenses for these matters. 3.1 Risks: …; b) that you create, allow, assume or agree to at any time; … 3.3 Workmanship, Infestation and Dilapidation a) any claims, loss or damage relating to the condition and repair of any structures erected on the Land, or the infestation or dilapidation of those structure(s); b) any claims, loss or damage relating to structures which have not been built in accordance with applicable building codes and standards. Subject to clause 3.1 of this Policy, this exclusion does not apply if notice of the non-compliance appears in Public Records as at the Policy Date or if the existence of the non-compliance would have been disclosed by a Local Authority Search of your Land as at the Policy Date and does not limit the Cover described in sub-clause 2.1 (n) (iii); c) any claims, loss or damage relating to matters disclosed in a building inspection report or home inspection report obtained by the Insured prior to the Policy Date.