1.1 Complaint
The complainant had a Classic cover policy with the financial firm (insurer) for her
home and contents. She also took out the optional cover for accidental damage.
On 19 December 2018, the complainant’s living/kitchen room ceiling collapsed while
she was overseas, and her friend was house sitting at the time.
The insurer has accepted the damage to the contents items, as well as storage,
removal costs and temporary accommodation once the relevant documentation had
been provided.
However, the insurer has denied liability for damage to the home building due to the
ceiling collapse. This is because it says the ceiling collapsed due to wear and tear
and gradual deterioration. This is excluded under the policy.
The complainant wants the insurer to accept the damage to the home as a result of
the ceiling collapse.
1.2 Issues and key findings
Has the complainant established a valid claim?
The policy provides cover for accidental loss and damage (i.e. that which occurred
without intent). The complainant did not intend for her living/kitchen room ceiling to
collapse. She has therefore established a valid claim under the policy.
Can the insurer deny the claim for the ceiling collapse?
Based on the evidence presented, the proximate cause of the damage to the home
building was defects or faulty workmanship. The evidence does not show wear and
tear or gradual deterioration was the proximate cause.
The insurer has not relied on the defects exclusion to deny the claim. However, even
if this had been raised, it would not have been successful. This is because the
information does not show the complainant knew of this defect or should have
reasonably known about it.
Therefore, the insurer must accept the claim for the damage caused by the collapse
of the ceiling in the living/kitchen area, including the reinstatement of this ceiling. It is
not liable to provide cover for the replacement of the ceiling in the remainder of the
house, as this was not damaged in the loss event.
Determination | Case number: 620766 Page 2 of 9
Is the insurer liable to pay any further compensation for non-financial loss?
The panel acknowledges the complainant’s claim experience. However, the most
AFCA can award in compensation for non-financial loss is $5,000. The insurer
confirmed it had paid the complainant $10,000 in compensation for non-financial loss
on 14 March 2019.
In these circumstances, the insurer is not liable to pay any further amount towards
non-financial loss.
1.3 Determination
This determination is substantially in favour of the complainant.
The insurer must accept the damage that was caused by the ceiling collapse in the
living/kitchen open plan area.
The insurer is not liable to pay for the costs to replace the ceilings in the remainder of
the home, as these were not damaged in the loss event, but rather are preventative
works.
The insurer has paid the complainant $10,000 for non-financial loss. It is not liable to
pay any further compensation for non-financial loss.
Determination | Case number: 620766 Page 3 of 9
2 Reasons for determination
2.1 Has the complainant established a valid claim?
Complainant has established a valid claim under the policy
The complainant is required to demonstrate that, on the balance of probabilities, she
suffered a loss caused by a risk insured against under the policy. This is known as
establishing a valid claim.
The policy wording, together with the certificate of insurance, outline the conditions
under which cover is provided and the exclusions that apply to that cover.
The complainant lodged a claim for damage caused by the collapse of the ceiling in
her open plan living/kitchen area, during a period while the complainant was away
overseas and her friend was house sitting.
The complainant’s policy provides cover for accidental loss or damage .
Accidental damage is defined broadly in the Product Disclosure Statement (PDS), to
means loss or damage that occurs without intent.
It is clear the complainant did not intend for the damage to occur. The complainant
has therefore established a valid claim under the terms of the policy.
2.2 Can the insurer deny the claim for the ceiling collapse?
Insurer accepted contents and additional benefits claims
The insurer accepted the complainant’s claim for damage to insured contents
following the collapse of the ceiling. Several payments have been made to the
complainant for contents items, and there do not appear to be any further contents
items in dispute.
The insurer also recently accepted the complainant’s claims for storage, removal
costs and temporary accommodation, once the relevant documentation had been
provided. The complainant has not advised that anything remains in dispute regarding
these items.
Insurer says ceiling collapse was from wear and tear or gradual deterioration
The insurer says the ceiling collapse was caused by wear and tear, or gradual
deterioration. These are excluded under the policy. The insurer relies on several
expert reports in support of its position.
HR’s initial assessor’s report
The initial assessor’s report advised that damage to the ceiling had occurred as a
result of gradual deterioration, which was caused by glue failure.
Determination | Case number: 620766 Page 4 of 9
The assessor inspected the back side of the plaster for water staining and wet
insulation, as well as inspecting the exposed roof trusses and back side of the roof
tiles. He found no indication of water entry and says there was no storm or high winds
on the date of loss.
JC carpenter’s report
JC made safe the garage ceiling, and reinstated the ceiling in the kitchen, dining and
living room.
He noted the truss bottom chords bowed up and down, with a variance of up to
20mm.
JC believed the weight of the roof tile was causing the truss web to deflect down and
the truss bottom chord to bow up. He thought this structural element had reduced the
amount of fixings in the plasterboard ceiling and forced the glue to let go.
JH engineering report
JH concluded the failure of the ceiling attachment had occurred due to poor
installation practices. This, over time, has led to a progressive failure of the
attachment of the ceili ng to the timber chords of the trusses.
JH found that the evidence indicated that there was a significant lack of fixings and
adhesive used in the installation of the ceilings. JH concluded this was the cause of
damage.
JH noted there was no evidence of wind damage. For example, he found no evidence
of a structural failure within the roof trusses, which can occur during an extreme wind
event.
JH also found the deflection of the roof trusses observed were within construction
tolerances. Whilst this may have increased the stress across a glue joint, it would
result in minimal impact on the bonding of the glue joint.
MC engineer’s report
MC attended in March 2019. MC noted that the roof sheeting in the open plan
living/kitchen area where the collapse occurred had been replaced.
MC also found that the ceiling was not installed in strict accordance with the
manufacturer’s recommendations at the time of construction. MC found that over
time, the glue/nailing that was installed had failed, until the roof weight exceeded that
of the fastener capacity.
MC also noted that the remainder of the house was showing signs of ceiling failure
and spontaneous collapse in these rooms could be expected without the addition of
the make safe works.
Determination | Case number: 620766 Page 5 of 9
Proximate cause of damage was building defects/faulty workmanship
On the balance of probabilities, the panel considers the proximate (dominant, efficient
or operative) cause of the collapse of the ceiling was the building defects and faulty
workmanship.
JH’s opinion is persuasive. JH identified a significant lack of fixings and glue. This
meant the plasterboard was not installed in accordance with manufacturer’s
guidelines. MC and HR agreed with this. Whilst JC identified a deflection in the roof
trusses, JH’s reasoning as to why this was not the cause is persuasive.
For instance, the deflection was within tolerances and would not have caused the
fixings to fail. JH’s reasoning is also consistent with the following:
there was no evidence of water entry in the ceiling when inspected
contemporaneously by HR
a lack of structural issues that is consistent with wind damage.
The panel does not accept the proximate cause is wear and tear or gradual
deterioration. This is because whilst the damage was progressive in nature, the
evidence shows the proximate cause was the poor installation. Namely, the
inadequate fixings and glue.
Therefore, the panel does not accept the information shows the claim falls within the
policy exclusion for wear and tear or gradual deterioration.
Insurer has not relied on defect exclusion to deny liability
The panel notes the insurer has not relied on the general exclusion for defects. This
can include a defect, structural fault or design fault. There is no exclusion for faulty
workmanship.
Even if the inadequate fixings and glue is a structural fault or defect, the exclusion
only applies if the complainant knew about it or reasonably should have known. There
is no evidence of this. The defects were in the ceiling cavity and not observable.
Therefore, this exclusion would not apply.
Insurer must accept claim for damage to lounge/kitchen open area
The insurer is liable to accept the damage caused by the ceiling collapse.
I note that this is limited to the area that collapsed during the incident. The insurer is
not liable for the works to replace the remainder of the ceilings in the home, as these
were not damaged as a result of the accidental ceiling collapse.
Further, the information provided shows the defects in the living room ceiling are likely
applicable to the rest of the ceilings. The panel notes that the complainant is on notice
regarding the defects in any remaining ceilings at the property.
Determination | Case number: 620766 Page 6 of 9
2.3 Should the insurer pay non-financial loss?
Insurer not liable for further compensation for non-financial loss
AFCA can award compensation for non-financial loss, if there has been an unusual
degree or extent of inconvenience and delay. The maximum amount we can award
for non-financial loss is $5,000 for each claim of loss.
The panel acknowledges the numerous service issues experienced by the
complainant during the processing of the complaint. However, the panel also notes
the insurer said it paid the complainant $10,000 in compensation for non-financial loss
on 14 March 2019.
Given that this is double the maximum that AFCA can award, the panel does not
consider that the insurer is required to pay any further compensation for non-financial
loss in this matter.
Determination | Case number: 620766 Page 7 of 9
3 Supporting information
3.1 Key references
Policy documents
Record Key points
Product Di sclosure
Statement (PDS)
26 November 2012
Page 79
Words with special meanings
Accidental loss or damage
means loss or damage that occurs without intent.
Pa ge 58 General exclusions (page 58)
You are not covered under any section of this policy for damage, loss, cost
or legal liability that is caused by, arises from or involves:
…
Page 59 Defect, structural fault or design fault
a defect, structural fault or design fault that you knew about (or should
reasonably have known about) and did not fix before the loss or damage
occurred (e. g. if there are signs that a defect previously caused damage, we
will not pay a later claim for further damage from this defect).
Page 62 Wear, tear and gradual deterioration
wear, tear, rust, fading, rising damp, mould, mildew, corrosion, rot, action of
light, atmospheric or climatic conditions or gradual det erioration such as but
not limited to:
– tiles and their adhesive or grouting breaking down;
– weathering of roof tiles or roof ridge capping;
– g radual weathering and breakdown of bricks, mortar or concrete.
Expert reports
Report Key points
HR initial asse ssor’ s
report
Damage to the ceiling has occurred as a result of gradual deterioration
caused by glue failure.
Determination | Case number: 620766 Page 8 of 9
Report Key points
(undated; attended 20
December 2018 to
inspect + provided
initial m ake safe)
(for FF)
Inspected the back side of the plaster for water staining and for wet
insulation, also the exposed roof trusses and back side of roof tiles.
Found no indication of water entry, nor was there a storm or high winds
on the date of loss.
JC (carpentry)
report
(also undated;
inspected 31
December 2018)
(for Comp)
Was instructed to install timber battens to ceiling in garage, that
appeared ready to fail at any moment
Reinstated ceiling in kitchen, dinin g and living room, as heat through
roof was so intense the area was unliveable
T rus s bottom chords bowed up and down with variance of up to 20mm
W eight of the roof was causing truss web to deflect down on gang plate
join and the truss bottom chord between gang plate webs to bow up
Thought this structural element had reduced the amount of fixings in the
plasterboard ceiling and forced glue to let go
Installed vertical timber struts to rectify problem and reduce likelihood of
ceiling collapsing again; also in stalled framing timber. Licensed
plasterer assisted him in installing new plasterboard sheeting, in
accordance with manufacturer’s specifications.
JH engineering
report
29 January 2019
(for FF)
Failure of ceiling attachment has occurred due to poor installation
practices, which over time has led to a progressive failure of the
attachment of the ceiling to the timber chords of the trusses
Evidence indicat es significant lack of fixings + significant lack of
adhesive used in the installation of the ceil ings
Creasing of the ceiling also evidenced incorrect plastering
Note d water damage can cause delamination, however was not the
primary cause here.
Installation manual says correct spacing of plasterboard adhesive is
230mm max from nail fixing (NB this in stallation manual for plasterboard
from Boral is dated October 2016. Comps have not provided any
evidence to dispute that it is the relevant manual)
Found that:
> Spacing of screws was approx. 1000mm
> Glue spacing was greater than 1000mm
Henc e even if these were interspersed evenly, they would be 500mm
apart, which is over the 230mm max for spacing of the adhesive from
the nail fixings
T he amount of adhesive use, nor position of adhesive used correct
G lue was ‘sparingly’ applied
(Did not elaborate on how the position of the adhesive was incorrect.)
Noted incorrect plastering techniques, and queried expertise of
installers
No evidence of a strong wind event that would be sufficient to buffet and
distort the roof truss framing of the dwelling.
NB – FF claim not es not ed wind speeds of 81km/hr a couple of weeks
prior
No evidence of a structural failure within the roof trusses.
inspection of the roof cavity found no evidence to structural damage to
Determination | Case number: 620766 Page 9 of 9
Report Key points
the connections of the trusses which commonly occur during an
extr eme wind event
The roof trusses included observed deflections that were within
construction toleranc es.
Said that the main contributor to break down of glue fixings is long term
thermal movement, variation in timber moisture content and differential
foundat ion movement.
Timbers expand and contract. Once one section of glue fails, then the
additional load is carried by the next section of glue. Glue carrying more
load and process continued until load can no longer be supported and
ceiling fails. This is calle d progressive failure. Manufacturer accounts for
this in setting higher no. of glue fixing points than is structurally required
to support plasterboard.
MC engineering
report
22 March 2019
(for FF)
Roof sheeting in the lounge/ dining/kitchen area where the collapse
occurred has been replaced.
Insured advised by the initial building inspector that the ceiling
experienced spontaneous collapse. It was also observed that the
insulation was dry.
Make safe works were undertaken in December [2018], by way of fixing
timber battens to ceiling trusses in the main bedroom and formal
lounge/dining.
The ceiling and insulation in the lounge/kitchen/dining was replaced.
MB (builder) attended on this same day and provided additional make
safe to the lounge room at the rear of the house, and the garage.
Ceiling was not installed in strict accordance with manufacturer’s
recommendation at time of construction.
Over time, glue/ nailing has failed, until the roof weight exceeded that of
the fastener capacity.
Remainder of ho use showing signs of ceiling failure and spontaneous
collapse in these rooms can be expected without the addition of mak e
safe works.
Ceiling and insulation dry at time of collapse, and no water leak found
during site inspection.
Referred to study conducte d by WA government whic h found similar
issues in homes of similar ages.