Home / QBE / Determination 620418
Determination 620418
Storm damage cash settlement amounts disputed for two rural properties
Summary
Storm damage claims on two rural properties were accepted for cash settlement but the amounts were disputed. AFCA ordered further payments for the shed and M Way property with interest, $250 for claims-process inconvenience, and rejected the premium complaint.
Cash settlement should reflect the reasonable scope of works plus a 10% allowance for unquantified repair risk, and non-financial loss is awarded only in limited circumstances.
Issues
- Claim amount dispute primary · upheld“The insurer's settlement omitted several items in P's scope of works. The insurer provided no explanation as to why these should be omitted.”
- Delay secondary · upheld“The insurer is to pay the complainant this amount as compensation for the inconvenience caused during the claims process.”
- Policy cancellation or underwriting secondary · not upheld“the information does not show there was non-disclosure, misrepresentation or incorrect application of the premium.”
- Poor communication secondary · not upheld“The panel does not accept S misrepresented matters.”
Subjects and remedies
home or building damagenatural disasterpay claimpay interestpay non financial loss
Related
Text of the determination
Determination
Case number 620418
Financial firm QBE Insurance (Australia) Limited
Determination | Case number: 620418 Page 1 of 6
Case number: 620418 4 March 2020
1 Determination overview
1.1 Complaint
The complainant owns two rural properties, which he insured with the financial firm
(insurer). Both properties suffered storm damage on 11 October 2018 for which he
lodged claims.
The insurer assessed the damaged properties and accepted the claims. The insurer
has proposed to cash settle the claims. The complainant has agreed with cash
settling the claims but disputed the amounts offered for a shed and building.
The complainant also says the time taken to process his claims was unnecessarily
long and unfair. He says the loss adjuster misled him. The complainant wants
compensation for lost earnings due to the claims handling.
The complainant also raised a concern about the 2019-20 premium increase for one
of his properties.
1.2 Issues and key findings
Is the complainant entitled to additional payment for property damage?
The complainant is entitled to additional payments as set out in section 2.1.
Is the complainant entitled to compensation for non-financial loss?
The complainant is entitled to compensation of $250 for the inconvenience suffered
during the claims process.
Is the complainant entitled to relief from premium increase?
The complainant is not entitled to any relief.
1.3 Determination
This determination is partially in favour of the complainant.
The insurer should pay the additional amounts set out in section 2.1.
The insurer should pay the complainant $250 compensation fo r non-financial loss.
Determination | Case number: 620418 Page 2 of 6
2 Reasons for determination
2.1 Is the complainant entitled to additional payment for property damage?
Complainant’s two properties
The insurer accepted there was a strong storm on 11 October 2018 which caused
damage to the complainant’ s two rural properties. This complaint is about the extent
of the storm related damage to those properties.
The first property at F Road contains a house and a shed which is used for residential
purposes. Both the house and shed were damaged by the storm. The parties have
agreed on a cash settlement for the house but dispute the amount payable for the
shed.
The second property is at M Way. The parties also dispute the amount to be paid for
this property.
Builders’ quotes for M Way property
The insurer obtained a quote from DJL (dated 29 January 2019) for $51,922.20. The
insurer said it provided DJL with the relevant photographs of the damage as well as
S’s scope of works. The insurer says DJL’s quote covered all the necessary works
and was competitive when compared to other local builders.
The insurer says DJL is available to undertake the work. However, since the
complainant indicated he wanted his own builder to complete the repairs, the insurer
said it would cash settle him.
The insurer p aid the complainant $51,672.20. This amount was based on DJL’s quote
($51,922.20) less the policy excess of $250.
The insurer paid an additional $930, which arose from a further property inspection by
S, along with a roofer, TN, on 30 May 2019.
The complainant obtained a quote from his preferred builder, HBC (4 February 2019),
for $57,200.00. The complainant says he should receive payment of this sum plus an
additional allowance of 10 to 15 percent on top of that.
M Way claim should be settled in this way
The panel considers it is reasonable for the insurer to base its cash settlement on
DJL's quote.
DJL has provided an actionable quote (i.e. it is available to the complainant). The
panel does not accept that because S enquired with the complainant about whether
he would like a cash settlement, the insurer was obliged to accept a quote from a
builder of the complainant’s choice.
Determination | Case number: 620418 Page 3 of 6
However, the panel does consider it is fair that an additional allowance of 10% should
be included in DJL’s quote. The works are extensive and it is not clear, to what extent,
DJL’s quote would prove to be the final repair cost. At least in one aspect, there is a
possibility of further works in the scope of works as set out here:
Certification (report on battens) tie down as recommended by certifier
Given this, and considering the risk of the works are transferring to the complainant,
the panel considers a 10% allowance on DJL’s quote is fair in all the circumstances.
The insurer should also pay interest on the additional sum payable pursuant to
section 57 of the Insurance Contracts Act 1984 (the Act). Interest is payable from 25
March 2019, being the date the insurer sought to cash settle the repairs, until
payment is made.
Settlement for shed should be based on P’s revised scope o f works
The insurer based its settlement of $52,417.51 on builder P’s revised scope of works
regarding the shed.
However, the insurer’s settlement omitted several items in P’s scope of works. For
example, it did not include these works:
Item 20 - Supply and install edge protection ($2,000)
Item 26 - Stripping and replacing 1 square metre of tilings ($295.42)
The insurer provided no explanation as to why these should be omitted.
The insurer also omitted item 15 which was to ‘strip and replace steel frame t o shade
cloth’. This presumably relates to the policy exclusion for storm damage to shade
cloths and shade structures. This was referred to in the loss adjuster’s first report
dated 29 October 2018.
The complainant has not submitted that this part of the s hed was not a shade
structure. Given this, the panel accepts this can be excluded.
The insurer provided an allowance of $2,000 for the electrician. However, in P’s
revised scope of works, there were four items (14, 19, 21 and 24) that involved an
electrician. These totalled $2,306.58.
The panel does not accept it is fair for the insurer to reduce this allowance without any
confirmation from P that this would be appropriate.
There was a reduction of an allowance for a water tank from $15,000 to $5,000. The
complainant appeared to agree with this based on his email to the insurer dated 4
February 2019.
The insurer has not included P’s builder’s margin. This appeared to be 18.19%.
Determination | Case number: 620418 Page 4 of 6
Therefore, when the panel accounts for all these discrepancies, this totals
$65,027.56.
Insurer should pay $71,530.31 plus interest
P’s scope of works included an acknowledgment that:
Due to unforeseen circumstance additional damage may be exposed during the
repair process. If this occurs additional costs will be incurred.
This envisages the real possibility that further works will be required. The panel also
notes P’s scope of works is not an actionable quote. Given this, and the fact the risks
of the works are passing to the complainant, an allowance of 10% is fair in all the
circumstances.
This means the insurer should pay $71,530.31 for cash settling the damage to the
shed.
The insurer should also pay interest on any additional amount owing for the shed
pursuant to section 57 of the Insurance Contracts Act 1984 (the Act). Interest is
payable from 1 February 2019, being the date the insurer sought to cash settle the
repairs, until payment is made.
2.2 Is the complainant entitled to compensation for non-financial loss?
Compensation awarded in limited circumstances
The complainant raised issues about the length of time taken with respect to the
claims process. He also said the claims process was unfair. He said a specific person
from S had misled him. The complainant is also claiming $3,575 for the 65 hours he
said were spent away from his job as a real estate agent. He said that time was taken
up attending to the loss adjuster, the insurer, the trades people and so forth. He also
spent time dealing with correspondence.
AFCA may award compensation for non-financial loss up to a maximum of $5,000.
AFCA takes a conservative approach to awarding this type of compensation. It is only
awarded where the complainant has suffered from an unusual amount of physical
inconvenience or stress or the financial firm’s conduct has meant the time taken to
resolve the situation has been unusually excessive.
AFCA does not award non-financial loss compensation because the complainant has
suffered some inconvenience and anxiety. AFCA expects complainants to bear the
normal degree of inconvenience experienced when a problem occurs and to take
reasonable steps to manage the situation.
Determination | Case number: 620418 Page 5 of 6
Complainant entitled to some compensation
The insurer made an offer of $250 to the complainant in its final decision letter (dated
1 February 2019) to resolve this matter. The ins urer recognised there had been some
inconvenience to the complainant because of the claims process.
The claims process was more prolonged because the storm had caused extensive
damage within that region. There would have been a high demand for trades people
to inspect, quote and carry out repairs within the area. The storm occurred
approximately two months before the traditional Christmas and New Year break.
The complainant’s claim involved two properties. There were issues about the extent
of damage due to the storm and what was pre-existing. The complainant challenged
the scope of works and this meant the insurer needed to verify these matters.
The complainant said he spent 65 hours dealing with his claims. However, he has
provided no details on the time he said he spent dealing with these claims. AFCA
expects claimants to do whatever is necessary (within reason) to ensure the claim
progresses efficiently. Compensation will only be considered in exceptional
circumstances.
The panel does not accept S misrepresented matters. Whilst S sought the
complainant’s input as to whether he wanted to be cash settled, this did not infer the
insurer would pay a quote from a builder of his choice.
The amount of $250 is reasonable in these circumstances. As such, the insure r is to
pay the complainant this amount as compensation for the inconvenience caused
during the claims process.
2.3 Is the complainant entitled to relief from premium increase?
Complainant says there was an unreasonable increase
The complainant complained about the premium increase which occurred for the
2019 / 2020 insurance period for his F Road property. The complainant says there
was an increase of 86 per cent from the previous insurance period. The complainant
does not accept the insurer’s brief explanatio n about the increase.
AFCA’s Rules ordinarily require complaints about the premium level to be excluded.
However, there are exceptions. These include situations where the complaint
concerns non-disclosure, misrepresentation or incorrect application of the premium.
The other exception is where the financial firm has breached any legal obligation or
duty.
Determination | Case number: 620418 Page 6 of 6
Complainant not entitled to any relief
The insurer explained the increase was mainly due to the following factors:
an adjustment of the no claim bonus
a greater understanding of the risk.
The complainant said the house was fully renovated and the shed is not insured in the
new policy. However, according to the renewal notice provided by the insurer, there is
no exclusion for the shed.
The insurer has rais ed legitimate concerns about the shed’s compliance with council’s
standards. Given this, the panel accepts the specific factors the insurer has relied
upon in increasing the premium are consistent with the available facts.
Therefore, the information does not show there was non-disclosure,
misrepresentation or incorrect application of the premium. Further, the information
does not show the insurer breached any legal obligation or duty.
In addition, the panel notes the policy has since lapsed.
Given this, the complainant is not entitled to any relief for his complaint about the
premium level increase for the 2019 / 2020 insurance period.