Home / Financial Firm (Unknown - Insurer) / Determination 620186

Determination 620186

Refusal to cover mould remediation under lifetime guarantee and claims processing inconvenience

FirmFinancial Firm (Unknown - Insurer)
Decided2019-09-16
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$1,500
Non-financial loss$2,000
Amount claimed—
SourceAFCA PDF

Summary

The complainants said mould from a 2016 water leak was not remediated, and the insurer denied the mould remediation claim. AFCA found the 2016 remediation was incomplete, ordered reimbursement of $1,500 for remediation by another contractor with interest, and awarded $2,000 for non-financial loss.

The policy's lifetime guarantee covers remediation works that were not adequately completed, and expert evidence showed the 2016 remediation did not address the hallway and subfloor.

Issues

Subjects and remedies

health or medicalhome or building damagepay claimpay interestpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination | Case number: 620186 Page 1 of 9 Determination Case number: 620186 12 September 2019 1 Determination overview 1.1 Complaint The complainants hold a building and contents insurance policy with the financial firm (the insurer). On 26 August 2016, the complainants lodged a claim for water related damage. The insurer accepted the claim. The complainants say water damage remains unrepaired as there is mould at the property. The insurer says mould is unrelated to the 2016 water leak event and is not covered by the policy. 1.2 Issues and key findings Is the insurer entitled to deny cover for mould development? The insurer is not entitled to deny cover for mould remediation. This is because, on balance, I am satisfied the 2016 remediation process was incomplete. Are the complainants entitled to additional payments? The insurer is required to make a payment of non-financial loss in the sum of $2,000 as a compensation for the high level of inconvenience they suffered during the processing of their claim. 1.3 Determination This determination is in favour of the complainants. The insurer is required to set tle the complainants’ claim by way of issuing the following payments:  $1,500, being the fee the complainants paid to (E) for mould remediation  Interest on the sum of $1,500, in accordance with the Insurance Contracts Act ( 1984) from the date the complainants paid E’s account, until the date of settlement. The complainants are to provide the insurer with details of when payment was made. Determination | Case number: 620186 Page 2 of 9  $2,000 for non-financial loss. Determination | Case number: 620186 Page 3 of 9 2 Reasons for determination 2.1 Is the insurer entitled to deny cover for mould development? The repairs authorised by the insurer are covered by a lifetime guarantee The insured property is a single level house, raised on a timber foundation and estimated to be approximately 35 years old. On 26 August 2016, the complainants lodged a claim for damaged beams under their insured property. Damage was found to be caused by a leaking hot water system unit in the eastern corner of the subfloor area located directly underneath a bedroom (referred to as bedroom two/one within expert reports). The expert’s findings established the hot water unit was spraying water up onto the timber flooring for approximately four to six weeks, resulting in elevated moisture levels and mould growth in the subfloor area. The insurer accepted the complainants’ claim and authorised the required repairs. Following further assessments, it was found the water escape event also caused structural movement as it soaked the highly reactive soil beneath the subfloor area. Over time, the complainants were cash settled for this aspect of their claim with the final payment made in May 2018. The complainants say that mould growth was not remediated successfully in 2016 and has overtime extended to the internal areas of the home. It is not in dispute the insurer authorised a restorer (O) to remediate the mould and to dry out the subfloor area. However, the insurer challenges that those remediation works were unsuccessful. In addition, the insurer says mould currently present at the property is not related to the 2016 event. Under the policy, the complainants are entitled to a lifetime guarantee on the remediation works if they can establish the works were not adequately completed. On balance, the hot water unit leak allowed development of mould Following a review of the exchanged material, on balance, I am satisfied the mould remediation works were not completed adequately. This is because:  the initial 2016 mould assessment showed high levels of mould in the hallway, south-eastern bedroom and the subfloor area of the insured property  the initial report issued by O in 2016 shows the carpet area was affected by the water escape event  the 2016 mould remediation works did not include remediation process of the hallway area Determination | Case number: 620186 Page 4 of 9  following the completion of O’s remediation in 2016, no tests were conducted to ensure mould is no longer present at the property  there is no evidence of a secondary leak at the insured property while Himalayan salt lamps do not contain water. Over the period between November 2016 and February 2018, the complainants have consistently argued that there was mould at their property. However, mould assessment was not conducted until February 2018 when (P) recorded excessive levels of airborne mould in the hallway and the bedroom adjacent to bedroom one/two areas (south-eastern bedroom). The assessment also recorded excessive levels of surface mould in the subfloor area near the hot water unit. P’s subsequent assessments showed mould dissipated in th e subfloor area, with the exception of the hallway and the south-eastern bedroom. Based on this last finding, P concluded mould was unlikely caused by the 2016 water escape event on the basis that the areas showing mould contamination are located away from the location of the previous leak. I find P’s conclusion disregards consideration of its previous findings discussed above. A detailed review of O’s 2016 report contains a photograph which shows the hallway carpet was affected by the moisture ingress from the water escape event. However, details on the remediation process conducted by O do not contain any indication the hallway carpet was remediated. Summary of O’s report and the remediation process is contained under section 3 of this determination. Other expert findings show that the water escape event caused the soil beneath the subfloor area to absorb water. O’s reports do not contain any indication whether, post remediation process, the soil was adequately dried, or whether the leak allowed moisture into the air of other areas of the insured property. The expert assessments did not locate any source of a secondary leak at the property. I do not accept the salt lamp (located in the hallway above the affected carpet area) is capable of causing excessive levels of airborne mould and moisture ingress. This is because Himalayan salt lamps are hygroscopic, meaning they absorb moisture from the air. When switched off, in highly humid areas, the water that is collected on the surface of the lamp will condense and drip or leak down. Finally, b y the insurer’s ow n description, salt lamps do not contain water. The insurer is required to cover the cost of mould remediation The complainants say they appointed (E) to remediate mould at their property. In support, the complainants provided an email showing a quoted fee of $1,500 for ‘mould micro misting’. In addition, the complainants have also provided a ‘schedule of loss’ that contains items which the complai nants say were affected by mould. The complainants say Determination | Case number: 620186 Page 5 of 9 those items were not restorable and they had to dispose of them. The complainants were unable to provide sufficient evidence to show proof of ownership, valuation or proof of disposal for the items listed on the schedule of loss. Without such evidence, the insurer is not required to make payment for the claimed items. In light of the above, the insurer is required to reimburse the complainants for the remediation cost of $1,500 completed by E. 2.2 Are the complainants entitled to additional payments? AFCA has jurisdiction to award compensation Where an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the complainant’s expectation of enjoyment or pe ace of mind has occurred, under AFCA’s Rules, AFCA may decide that an insurer compensate the complainant for non-financial loss. The maximum remedy is $5,000. The complainant is dissatisfied with the time taken by the insurer to carry out mould assessment and its final decision to deny their claim for mould remediation. The complainants suffered a high level of inconvenience The following is a relevant timeframe of events with respect to mould formation at the insured property:  the insurer’s internal f ile notes show on 28 November 2016, the complainants reported a mouldy smell in the bedroom to the insurer  the insurer’s engineering report issued by (EMC) in January 2017 contains information that suggests mould has been recurring and the complainants have been repainting the affected areas  in January 2018, the complainants placed the insurer on notice that mould remains present at the property and is causing them and their young family respiratory related health issues  on 27 February 2018, an assessor (P) appointed by the insurer carried out mould investigation  in March 2018, P issued a report showing elevated levels of mould growth in the bedrooms, the hallway and the subfloor areas  on 23 March 2018, P carried out another investigation (report issued on 11 April 2018) showing elevated mould levels  on 18 April 2018, the insurer advised the complainants the property is mould contaminated and is unsafe to occupy  the complainants were required re-located on four occasions during temporary allocation arrangements. Determination | Case number: 620186 Page 6 of 9 In addition to the above, the complainants provided a letter issued by Dr KR which states the complainants were suffering from respiratory tract infections in the period between June 2017 and April 2018. The letter suggests this was a result of mould at the property. The insurer is to issue a payment of $2,000 as an award of compensation In light of the above, I am satisfied the complainants have suffered a high level of inconvenience during the processing of their claim and subsequent mould assessment process. Accordingly, the insurer is required to compensate the complainants for non-financial loss in the sum of $2,000. Determination | Case number: 620186 Page 7 of 9 3 Supporting information 3.1 Relevant expert report findings and comments on mould growth Record Details Insurer’s loss adjuster ( CL ) Escape of liquid claim – 1 st report 01 09 2016  Hot water system unit located beneath the house and directly below bed room two area is spraying up on the timber flooring  damage observed to: > elevated moisture levels (location not listed) > mould growth to the underside timber flooring located in the subfloor area > cupping across timber flooring of bedroom number two > it is possible the carpet f loor area covering the inside o f bedroom two wil l not restore to pre - loss condition. The insurer’ s restorer (O) Fixed rate restoration service report 22 09 2016  Caus e: > a slow leak has affected the timber floor, causing mould to form  damage: > water and mould to the carpet on rubber underlay in bedroom on e (3.94 x 2.73m) > water and mould to the exposed beams and underside of the floorboards under the house area (10 x 5.1m) > affected hallway carpet (photo with description)  action taken: > an air filtration device installed to prevent mould spores and cross contamination of the property > removed and dispos ed of carpet, underlay and smoot h edge in in the area of bedroom one > applied an antimicrobial solution to the timber floor in bedroom one > cleaned and decontaminated the underside timber frames and floorboards throughout the subfloor area > applied an antimicrobial solution through a misting device to the underside of the timber frames and the floorboards in the subfloor area  action required: > appoint a plumber to replace the hot water system unit. Insurer’s re s torer (O) O Final report 10 11 2016  Damage: > dark stains visible on the timber where a previous leak occurred  cause: > discoloration from the copper pipe that sits very close to the frame work  action taken > moisture testing on the affected area and a comparison reading from another beam – both returned a reading of 15% > cleaned the discoloration from the timber framework and sanitised with anti - microbial solution. Insurer’s engineer (MBC) Engineering report – water damage  During the assess ment the complainants advised that: > Following leak detection mould started forming in bedroom one > Since the insurer’s remediation process, mould had recurred three time and the owners have repainted the affected areas with mould inhibitor Determination | Case number: 620186 Page 8 of 9 Record Details 03 01 2017 paint  engineerin g findings: > clear signs the soil beneath the house around the hot wat er unit was extremely saturated in water > walls around the affected areas in the internal of the house have been repainted > bowing of the floor and cracked int ernal wall limning in bedroom one. Insurer’s loss adjuster CL Escape of liquid claim – progress report 2 – recommending a payment 06 02 2017  Recommended cash settlement to the complainants: > building: $2,345.48 > contents: $4,019.40. Insurer’s a sse ssor (P) Mould contamination investigation 03 2018 Investigation carried out on 27 02 2018  Visual observations showed: > yellow staining (suspected to be mould) on the doors of all three bedrooms > carpet in the hallway was rippling (possibly due to moisture) > paint discoloration on the ceiling of the South Eastern bedroom > rotting timber and suspected black mould observed to the studs of the underside flooring underneath the hous e adjac ent the hot water unit > peeling/flaking paint to the ceiling of the south eastern bedroom  high levels of airborne mould recorded in the following areas: > hallway 9,500 > south - eastern bedroom 29, 000 > master bedroom 16,000  high levels of surface mould recorded in the following areas: > yellow stain on the master bedroom > underside of the timber floorboards above the hot water system unit  source of mould > unable to definitely determine. Insurer’s a sse ssor (P) Follow up mould testing 11 04 2018 Investigation carried out on 23 03 2018  Visual observations showed: > no mould to the areas where vis ual signs of mould were observed during the initial assessment. however, some localised suspect visible staining was observed to the master bedroom door > under surfac e of hallway linen cupboard particle board shelf > under - surface of the lounge room timber cabinet/dresser > mould obs erved below the area where hallway carpet was placed  the remediation contractor (details unknown) reported to O: > hallway carpet wet in the area were a salt lamp was located and was reported leaking following usage  high levels of airborne mould recorded in the following areas: > ceiling void 36,000 (not sampled in the previous report) > airborne mould was not tested in the hallway area > the airborne mould in the master and south - eastern bedrooms significantly dissipated  high levels of surface mould recorded in t he following areas: Determination | Case number: 620186 Page 9 of 9 Record Details > hallway, timber floor under carpet, beneath the dresser/salt lamp (previously not tested) > lounge room timber dresser (previously not tested) > areas where surface mould was previously recorded were not tested .  source of mould > unable to d efinitely determine. Insurer’s a sse ssor (P) Mould int rusive investigation 08 05 2018  Hallway area (when tested) showed elevated moisture levels > the bedroom above the hot water unit did not show elevated levels of moisture  high levels of surface mould recorded in the following areas: > south - east corner bedroom (internal wall lining north and west elevations > hallway levels dissipated since last testing > the subfloor area was not tested  source of mould > unable to det ermine the cause, however unlikely cause d by the previous hot wat er system leak as the areas showing mould contamination are located away from where the previous leak was.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.