Home / QBE / Determination 620065
Determination 620065
Additional loss of rent claimed after cash settlement, due to delayed implementation of prior determination
Summary
After a fire at an investment property and a cash settlement, the owner sought 18 more weeks of loss of rent, arguing the insurer delayed the scope of works. AFCA found the insurer caused a ten-week delay and ordered $5,500 plus interest, rejecting the balance.
The insurer's inadequate first scope of works caused part of the delay, and loss of rent for that period falls outside the prior determination's limit.
Issues
- Claim amount dispute primary · upheld“The insurer should pay an additional ten weeks loss of rent because the information shows it delayed implementing the determination by this period.”
- Delay secondary · upheld“To this extent, I accept the insurer has delayed the implementation of the determination.”
Subjects and remedies
home or building damagepay claimpay interest
Related
Text of the determination
Determination
Case number 620065
Financial firm QBE Insurance (Australia) Limited
Determination | Case number: 620065 Page 1 of 4
Case number: 620065 24 October 2019
1 Determination overview
1.1 Complaint
The complainant lodged a complaint against the financial firm (insurer) with the
Financial Ombudsman Service (FOS) following a fire at his investment property.
FOS issued a determination substantially in favour of the insurer. Following this, the
insurer paid $444,644.12 net of excess. This included the cost to repair the home as
well as rent for the time it would take to repair the damages.
When settling the claim, both parties agreed to leave the case for additional loss of
rent open for AFCA to review.
The complainant is seeking an additional 18 weeks of loss of rent. Part of the reason
is that he says the insurer delayed the claim after the FOS determination.
The insurer disagrees and says the complainant is not entitled to any further loss of
rent payments and the complainant never showed evidence the home would be re-
tenanted.
1.2 Issues and key findings
Is the insurer required to pay additional loss of rent?
The insurer should pay an additional ten weeks loss of rent because the information
shows it delayed implementing the determination by this period.
1.3 Determination
This determination is partially in favour of the complainant.
The insurer should pay $5,500 for loss of rent as well as interest pursuant to section
57 of the Insurance Contracts Act 1984. Interest is payable from 23 March 2017 until
the date of settlement.
Determination | Case number: 620065 Page 2 of 4
2 Reasons for determination
2.1 Is the insurer required to pay additional loss of rent?
Previous determination
The panel in the previous Determination (case 415726) said that:
In the event that the parties agree to cash settle the claim, the FSP will be
required to pay the applicant loss of rent benefits for the actual period it takes to
complete the repairs
The complainant’s representative says this period should include the time taken to
initially assess the matter, a reasonable period for the complainant to raise any
concern as well as the time taken to reinstate the buildings.
I do not agree. If this was the panel’s intention, then it would have expressed the
period to include the time taken to calculate the cash settlement. Alternatively, the
decision could have simply said the insurer is to pay for lost rent until repairs are
completed. It does neither.
Given this, I accept the determination was intended to:
limit the loss of rent benefit to the actual period it takes to complete the repairs, and
exclude the period it would take to assess the cost to do so.
I do accept though that if the complainant can show the insurer unreasonably delayed
implementing the determination, then any losses that flows from this would not be
covered by the previous determination. This is because:
it is effectively a new issue, and
it is unlikely the panel wou ld not have intended to limit the complainant’s losses in
such circumstances.
Complainant says insurer caused delays
There are no standard timeframes set down for the processing of claims or
implementing a determination. In general terms, AFCA will look at whether:
the insurer acted fairly and promptly
there has been an unreasonable delay
there were factors which were outside the insurer’s control or otherwise
unavoidable
whether the complainant’s actions caused or contributed to the delay.
Further, the insurer is entitled to make reasonable enquiries and conduct reasonable
investigations to clarify its liability.
Determination | Case number: 620065 Page 3 of 4
The complainant says the insurer took 10 months after the FOS determination to
agree to a scope of works and this contributed to further losses. The insurer
disagrees.
Insurer contributed to the delay
The available information shows the insurer’s first scope of works did not consider all
relevant factors. This is supported by the fact the complainant engaged an engineer
who provided a report highlighting several issues. This resulted in the scope of works
being revised two more times, the third time for minor changes.
To this extent, I accept the insurer has delayed the implementation of the
determination. I consider this timeframe would have added about two and a half
months to the process. This is based on the following:
there was correspondence between the complainant’s representatives and the
insurer on 22 September 2016 that discussed the appointment of an engineer to
review the first scope of works
the complainant’s engineer provided a report on 24 October 2016 that addressed
several gaps in the first scope of works
the insurer provided a revised second scope of works on 8 December 2016
I do not accept the balance of the timeframe was due to th e insurer’s conduct for the
following reasons.
Part of the delay was due to the complainant disputing the first scope of works as he
was reagitating issues dealt with the previous determination. This cannot be attributed
to the insurer’s conduct.
The other parts were associated with the following:
time spent compiling the first scope of works
sourcing quotations from builders for the agreed scope of works
agreeing and finalising on a cash settlement figure
These factors would fall within the reasonable period it would take to assess the cost
of repairs.
Insurer’s arguments do not assist it
The insurer has submitted several arguments to dispute any additional loss of rent.
This includes:
the complainant has not shown any objective evidence to show the property would
have been leased out
the complainant has received a total amount of about $1,135,000 for the property
given he was cash settled for almost $450,000 and sold the property for $690,000
Determination | Case number: 620065 Page 4 of 4
I do not accept these arguments for the following reasons.
The panel in the previous determination concluded it is:
… fair in the circumstances that the FSP pay the applicant loss of rent benefits for
the period required to complete the necessary repairs. The applicant has clearly
lost the ability to generate income from the property during this time
It would be inappropriate to conclude differently now. I also agree the panel’s decision
is fair. Whilst the claim remained unsettled, the complainant has plainly lost the ability
to generate any income on an investment property that has a mortgage. Whilst I note
he has listed the property shortly after the settlement, the reasons he says he did so
was due to:
the delay in settlement, and
having to manage the mortgage with no income.
Regarding the amount gained from the sale of the property, this is not a relevant
consideration. The policy insures the building and pays the complainant for the costs
to repair or rebuild claim related damage. In doing so, the policy does not allow the
insurer to consider the value of the land in assessing this cost.
Insurer is to pay $5,500 in full and final settlement
After careful consideration of all the available information, it is fair the insurer pays an
additional ten weeks rent. This is based on the delay resulting from gaps in the first
scope of works.
Therefore, the insurer is to pay an additional $5,500 as well as interest in full and final
settlement of this claim.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.