Home / Financial Firm (Unknown - Insurer) / Determination 618256
Determination 618256
Claim for scratched windows denied as damage not shown within insurance period
Summary
An owner builder claimed for over 20 scratched windows discovered in November 2017. AFCA found the insurance period ended 31 October 2017 and that the evidence did not show the damage occurred within it, so the denial stood.
The insuring clause requires the damage to occur during the Period of Insurance, and the complainant could not show that on the available information.
Issues
- Claim denial primary · not upheld“The insurer is entitled to deny the claim because the information does not show the windows were damaged before 31 October 2017.”
- Product terms interpretation secondary · not upheld“The period of insurance therefore ends at the end of the construction period, not on the date the occupancy permit was issued.”
Subjects and remedies
home or building damageno remedy
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Determination | Case number: 618256 Page 1 of 7
Determination
Case number: 618256 21 June 2019
1 Determination overview
1.1 Complaint
The complainant held a construction policy with the financial firm (the insurer) in
relation to a home he was building for his family (the home). He made a claim on the
policy as over 20 windows installed at the home were scratched.
The insurer denied the claim because it did not accept the information shows the
damage occurred during the period of insurance. Alternatively, the complainant did
not discover the damage within the period of insurance.
1.2 Issues and key findings
Can the insurer deny the claim?
The insurer is entitled to deny the claim because the information does not show the
windows were damaged before 31 October 2017.
1.3 Determination
This determination is in favour of the insurer.
The insurer is entitled to decline the claim.
Determination | Case number: 618256 Page 2 of 7
2 Reasons for determination
There has been a full exchange of the material between the parties and each party
has had the opportunity of addressing the issues that arise from the information
exchanged. This determination is based on what is fair in all the circumstances ha ving
regard to the relevant legal principles, terms of the policy, good industry practice
including codes of practice and prior determinations where applicable .
2.1 Can the insurer deny the claim?
The cause of damage is unclear
The complainant has provided the following background which the insurer does not
dispute:
the complainant commenced construction of his residential home in December
2015 as an owner builder
the property sits on about ten acres and isolated from surrounding properties
the windows were delivered around December 2016
prior to installation, the complainant inspected the windows and discovered one of
them had been damaged – this was replaced
the windows were installed between March and July 2017
from the date of delivery until installation, the windows were covered by plastic
sheets
the scaffolding was removed from the property around 22 July 2017
the property facades were completed on 28 October 2017
the damage was discovered on 14 November 2017
The policy contains the following insuring provision:
We agree, subject to the terms of this Policy and in consideration of the payment
of the Premium, to indemnify You with respect to the Insured Project to the extent
and in the manner stated below against Indemnifiable Events occurring during the
Period of Insurance
Indemnifiable Event is defined as:
A sudden, unforeseen and unintended physical loss of or damage to the insured
project resulting from any cause not excluded by this Policy, occurring at and
discovered at the Project Site during the Period of Insurance.
Period of insurance ended on 31 October 2017
An issue in dispute between the parties is when the ‘Period of Insurance’ ended.
Determination | Case number: 618256 Page 3 of 7
The policy defines the ‘Period of Insurance’ as the period from the commencement of
the ‘Construction Period’ to th e expiry of the defects liability period, if applicable. The
policy says the defects liability period commences at the end of the construction
period. There being no permitted defects liability period, the period of insurance
therefore ends at the end of the construction period.
According to the policy, the end of the construction period occurs at the earliest of
these three events:
the time a certificate of practical completion is issued
with respect to any portion of the contract works, the time that portion is taken over
or put into use (whichever is the earlier) by the purchaser or principal
the expiry date of the construction period as stated in the policy schedule.
The complainant says the period of insurance ended on 8 December 2017, being
when an occupancy permit was issued.
The policy schedule refers to an ‘Effective Date’. Under this, it says:
Endorsement to extend the expiry date from 2 August 2017 to 31 October 2017
and increase the Contract Value of $1,200,000.
The complainant argues this is an ambiguity given the policy schedule does not
define the construction period. Therefore, the end of the construction period is 8
December 2017, being when the occupancy period was issued.
I do not agree. The above wording refers to extending the ‘expiry date’ to 31 October
2017. The policy refers to the ‘expiry date’ by reference to the construction period or
defects liability period. As the latter is not applicable, it is reasonable to accept the
expiry date referred to in this schedule is by reference to the end of the construction
period.
In particular, if I accept the complainant’s construction, then this wording in the
schedule is meaningless. This would produce commercial nonsense or works
commercial inconvenience. Further, I do not accept such a construction produces a
commercial result.
In addition, the construction I have proposed ensures the provisions operate
congruently and to the contract as a whole. It is also consistent with the surrounding
circumstances known to both parties given the complainant had extended the policy
through his agent. If the expiry date had no effect, then the complainant had no
reason to extend this date.
Further, and in the alternative, I consider this construction to be fair in all the
circumstances for similar reasons.
Determination | Case number: 618256 Page 4 of 7
Information does not show windows were damaged before 31 October 2017
The complainant says the only reasonable explanation for the damage is the removal
of mortar from the windows by the bricklayers and renderers following completion of
the bricklaying and rendering and while the scaffolding was in place. This is
particularly so given some of the damaged windows were five metres from the
ground.
The complainant says no one noticed the damage until 14 November 2017, many
months after the damage was allegedly caused.
No independent evidence has been produced describing how such damage could
have been caused. The complainant says where direct proof is not available, it is
reasonable to infer the damage has happened in the manner alleged.
I am not persuaded that an inference is appropriate in these circumstances. No
analysis has been made as to how the scratches were produced and what would
have caused them. For instance, no evidence has been provided to show what tools
were being used by the bricklayers and renderers that could have resulted in the
damage identified.
I also note the complainant has not provided any correspondence to the bricklayers or
renderers putting his concerns to them and given them an opportunity to respond. To
infer such extensive damage was caused by their negligence without given them an
opportunity to respond to such an allegation is inappropriate. Particularly given it
would constitute such extensive poor workmanship.
No evidence has been provided of their experience either. Given the extensive
damage, it is difficult to accept they could have been negligent to such a degree
unless the workers were inexperienced.
It is also not clear how such extensive damage was missed between 22 July and 14
November 2017. This is almost a four-month period. Whilst I accept the damage may
not have been obvious, it does not appear to have been that difficult to identify when
any of the windows are looked at closely.
The information also does not rule out the possibility the items were maliciously
damaged after 31 October 2017. The site is in a private area. The complainant had
visited the site on 28 October 2017 and had not noticed any damage. It is possible a
perpetrator coming on site after this could have caused the damage.
Given all the available information, there is insufficient basis to infer or conclude how
or when the damage concluded. Therefore, I do not accept the complainant can show
there was an ‘Indemnifiable Event’.
Determination | Case number: 618256 Page 5 of 7
Section 54 of the Act does not help the complainant with this claim
The complainant submits section 54 of the Act applies to prevent the insurer from
relying upon any late discovery to refuse the claim.
This would arguably only assist if I was satisfied the complainant can show the
windows were damaged during the period of insurance. As I am not satisfied there is
sufficient basis to conclude this, section 54 does not assist.
Therefore, after careful consideration of all the available information and arguments, I
am satisfied the insurer is entitled to deny liability for the complainant’s claim.
Determination | Case number: 618256 Page 6 of 7
3 Supporting information
3.1 Key Policy Provisions
Definition Key points
WHEN YOU ARE INSURED In consideration of Premium paid to Us, We will indemnify You
with respect to Your pec uniary interest in an Insured Project and
the Named Insured in accordance with this Policy during the
Policy Period.
D34 “Period of Insurance”
means
The period from commencement of the Construction Period to
expiry of the Defects Liability Period, if applicable.
D22 “Indemnifiable Event”
means
A sudden, unforeseen and unint ended physical loss of or
damage to Insured Property, resulting from any cause not
excluded by this Policy, occurring at and discovered at the
Project Site during the Period of Insurance.
Any such loss of or damage to the Insured Projec t during any
one period of seventy - two (72) consec utive hours caused by
water, subsidenc e, landslip, cyclone, storm, tempest, earthquake
or bushfire will be deemed to be one single Indemnifiable Event.
The Named Insured may select the time from which any such
period will commence but no two such selected periods
will overlap.
D7 “Construction Period”
means
The period of time starting with the date of legal possession of
the Contract Site by the contractor or from the date of the start
of the Contract Works at the Contract Site but no earlier than the
date stated in the Policy Schedule and continuing to the earlier of
(unless amended by Endors ement ):
a) the time a certificate of practical completion is issued;
b) with respect to any portion of the Contr act Works, the time
that portion is taken over or put into use (whichever is the
earlier) by the purchaser or principal; and
c) the expiry date of the Construction Period as stated in the
Policy Schedule.
Where the construction cont ract specifies that the Contract
Works or any part thereof is required to undergo either testing
or commissioning then for the purposes of this Policy such
testing and commissioning will be deemed to occur during the
Construction Period
S1.1 INSURING CLAUSES We agree, subject to the terms of this Policy and in consideration
of the payment of the Premium, to indemnify You with respect to
the Insured Project to the extent and in the manner stated below
against Indemnifiable Events occurring during the Period of
Insuranc e
Determination | Case number: 618256 Page 7 of 7
Definition Key points
S1.1.1 Du ring the
Construction Period
We will indemnify You, subject to the Limit of Indemnity,
against an Indemnifiable Event to either the Contract Works
or Pre - Existing Property, occurring and discovered during the
Construction Period
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.