Home / Westpac / Determination 610315
Determination 610315
claim_denial
Summary
A landlord denied a claim for cracking damage to an investment property, which the insurer attributed to soil settlement and pile installation. AFCA found the escape of water from a neighbouring stormwater pipe was the proximate cause, ordered the claim settled with interest, and confirmed $2,500 non-financial loss compensation.
The insurer did not establish the exclusions it relied on, and the expert evidence shows the leak from a fixed pipe was the proximate cause under the escape of liquid cover.
Issues
- Claim denial primary · upheld“The insurer cannot deny the claim because the expert evidence, on balance, indicates the damage was likely caused by the leak.”
- Poor claim handling secondary · upheld“The insurer confirms the claim was not handled in a timely manner and offers non-financial compensation in the amount of $2,500.”
Subjects and remedies
home or building damagepay claimpay interestpay non financial loss
Related
Text of the determination
Determination
Case number 610315
Financial firm Westpac General Insurance Limited
Determination | Case number: 610315 Page 1 of 9
Case number: 610315 21 October 2019
1 Determination overview
1.1 Complaint
On 14 August 2017, the complainant lodged a claim with the financial firm (insurer)
under his landlord insurance policy. He claimed for cracking damage to the northwest
corner of his investment property, which he says was caused by a leak from a
neighbouring underground stormwater pipe.
The insurer denied the claim on the basis the damage was caused by the incorrect
installation of the screw piles, which support the concrete slab of the house , and soil
settlement.
The complainant disputes this and raises an issue with delays during the insurer’s
claims handling.
1.2 Issues and key findings
Can the insurer deny the claim?
The insurer cannot deny the claim because the expert evidence, on balance,
indicates the damage was likely caused by the leak.
Is the complainant entitled to compensation for non-financial loss?
The complainant is entitled to compensation for non-financial loss. The insurer has
offered $2,500, which is fair in all the circumstances.
1.3 Determination
This determination is in favour of the complainant.
The insurer is required to settle the complainant for his claim.
If the insurer cash settles the claim, it is to pay interest on the claim amount in
accordance with section 57 of the Insurance Contracts Act 1984 from 22
November 2017 to the date of settlement of the claim.
The insurer is to pay the complainant $2,500 compensation for non-financial loss, if
it has not already done so.
Determination | Case number: 610315 Page 2 of 9
2 Reasons for determination
2.1 Can the insurer deny the claim?
Parties agree there is a leak from a stormwater pipe
It is not disputed by the parties that:
there is an underground stormwater pipe installed in the lot north of the property
this pipe is about 1.2m in diameter and described by one of the engineers as a
major stormwater pipe
there is a split in this pipe near the north western corner of the insured house with
a substantial 0.7m deep void in the soil near the crack
the building level survey shows general settlement of the home building, but more
severely near the northwest corner of the house.
The complainant has cover for listed insured events. He is required to show, on the
balance of probabilities, he suffered a loss caused by an insured event. This is known
as prima facie claim.
One of the listed insured events is “escape of liquid”, which covers “loss or damage
caused by accidental escape of liquid from any fixed pipe …”.
Expert evidence is not conclusive as to other potential causes of damage
Both parties have provided extensive expert evidence to support their positions. Their
findings are summarised in section 3.2 below.
Having carefully reviewed the information, I am not persuaded by the insurer’s
position for the following reasons:
No investigation was carried out to confirm the depth to which the screw piles have
been attached to the foundation soils.
The conclusions of the insurer’s experts on causation assume that the depth of the
screw piles necessarily follows the building design (depth of 5m) and thus would be
attached to the natural clay soil.
Depending on the depth of where the screw piles are attached, two of the
engineers say the settlement may have been caused by the leak.
While the possibility of piles founded on different soil or inadequate founding
material of the screw pile could be accepted, they do not account for the fact the
more severe settlement is limited to the northwest corner of the building. This also
happens to be proximate to the leak of the major stormwater pipe.
There is insufficient information to confirm that there are different soil compositions
within the site or that only the north-western corner screw piles have been founded
in inadequate material or to an inadequate depth.
Determination | Case number: 610315 Page 3 of 9
On balance, I am not satisfied there is sufficient information from the engineers to
show why the proposed alternative causes of damage may have influenced only one
corner of the property and no other areas.
I accept reactive clay soils would heave when moisture content increases and the
moisture levels of the deep layers of clay soil (around 8m deep) have not been
affected by the leak.
However, there is also a layer of backfill which could collapse in conditions of high
moisture. This means, depending on the depth of the screw piles and where they are
attached, the leak could be the cause of the north-west settlement. Particularly given
its proximity to the area of greatest settlement of the home.
Insurer has not established exclusions
Based on the available information, I am persuaded the proximate cause of damage,
that is, the effective or operative cause, was the leak from the neighbouring
underground stormwater pipe.
This is supported by several engineers, the leak being proximate to the area of
movement and the main movement of the house being isolated to this area.
In its submissions to AFCA, the insurer has also argued the application of an
exclusion for “events or circumstances that are covered by a warranty, guarantee or
service contract”. That is, that the builder sho uld be responsible for the damage.
Given there is no clear evidence to show the cause of damage was either the
inadequate foundation material or the depth to which the screw pile is attached, I am
not satisfied the insurer has established this other exclusion.
2.2 Is the complainant entitled to compensation for non-financial loss?
Insurer’s compensation offer is fair in all circumstances
Under its Rules, AFCA may award compensation (capped at $5,000) for non-financial
loss where a complainant has suffered an unusual degree or extent of physical
inconvenience, time taken to resolve the situation or interference with his or her
expectation of enjoyment or peace of mind.
In its email dated 26 February 2019, the insurer confirms the claim was not handled in
a timely manner and offers non-financial compensation in the amount of $2,500. This
offer was further discussed during the conciliation conference. In an email on 6 June
2019, the insurer confirms the offer of compensation is still current.
Having reviewed the claim notes, I agree with the parties that the matter could have
been handled in a timelier manner. I am satisfied the insurer’s compensation offer is
fair in all the circumstances.
Determination | Case number: 610315 Page 4 of 9
3 Supporting information
3.1 AFCA approach
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other.
This complaint has been determined based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous decisions (which are not binding).
During this complaint, the complainant has been represented. For the purpose of this
determination, submissions made by the representative are treated as if they had
been made by the complainant himself.
3.2 Key points on relevant expert material
Record Key points
Insurer’s builder
( PI )
Report
15 August 2017
Upon a recent inspection, the complainant found cracking to the front
section of the house, which appears to be sinking.
A major stormwater pipe running towards the house appears to be leaking in
several locations due to large gaps between the individual pipes.
There was cracking to the front bedroom, laundry and dining room area, to
plasterboard walls , ceiling linings and external brickwork.
Given the age of the house (about two years old) and the cracking
experienced, PI believes some earth movement has caused the cracking.
This may be due to the leaking of the major stormwater running pass the
proper ty, causing ground movement or the design of the footings.
Complainant’s
engineer (JR )
Report
21 August 2017
Movement is limited to the north - western corner of the building.
Subsidence was apparent around the affected area of the house.
A large stormwat er pipe is directly adjacent this area. There is a
displacement at a pipe joint adjacent to this corner of the house.
The piles near the damaged pipe have settled despite the relatively light
loading, compared to their design capacity.
The ingress of water a djacent the base of the piles has softened the ground
supporting the piles.
Structural movement has occurred and while not proven, it is highly likely
connected with the damage to the adjacent pipe and resultant washout and
inundation of the local soil.
There is no immediate cause for concerns in terms of major structural
damage and safety.
Insurer’s engineer
(IE )
Report
11 September 2017
The floor is a concrete slab wit h perimeter footing beam, supported on
screw piles.
The complainant found a stormwate r pipe extends along the hous e’s
northern side. A split in the pipe was discovered near the north - western
Determination | Case number: 610315 Page 5 of 9
Record Key points
corner.
There are several cracks throughout the north - western side of the house.
The ground around this corner slopes away from the house.
The buildin g’s north - western corner has settled downwards. The settlement
extends across the front and north sides.
The soil near the site is a moderately reactive clay soil. However, the soil in
the upper portion of the site likely contains sandy backfill. This soil can
undergo a “grains collapse” due to inundation. The resultant collapse can
lead to a rapid settlement of the soil surface.
If the screws have been driven into the ground to a minimum of 5m, they
would be founded in reactive clay soil beneath the house. Therefore, the
settlement has been caused by shrinkage of reactive clay soil due to
reducing soil moisture content due to seasonal and environment al factors.
The house may have been built while there were high moisture levels in the
soil under the northwe st corner, which has then gradually dried out and
settled since the house’s construction. However, the stormwater pipe has
likely been leaking before the construction and has continued to leak.
Rainfall data does not show any high rainfall events during th e time of
construction. Therefore, this stormwat er leak has not contributed to reactive
clay soil settlement.
If the screw piles are founded within the trench backfill around the pipe,
inundation from the leaking stormwater pipe may have caused the backfil l to
collapse, resulting in settlement. This would also cause the soil within the
pipe area leak to settle.
It would be expected the settlement to be localised near the leak and cause
only the northwest corner of the house to settle.
However, as evident on the level survey, the entire front elevation has
settled, indicating the screw piles beneath the garage have also been
affected to some degree. This is more consistent with clay shrinkage.
The house’s north - western corner and surrounding soil has settled. This
may be caused by reactive clay shrinkage due to soil drying or sandy backfill
collapse due to an inundation. The actual soil conditions can be determined
by carrying out site sampling and soil identification.
Insurer’s engineer
(IE )
Report
14 November 2017
Two soil samples were taken at different locations to depths of 3.3m and 6m
around the north western corner.
Fill exists to a depth of at least 3.6m below ground level. Natural soil exists
from a depth of around 4.2m at borehole 2.
There were several cracks and gaps between pipe sections throughout the
pipe’s length. A 0.7m deep void exists in the soil at the crack near the
house’s northwest corner. The soil appeared damp within the void.
The pipe is near the house’s corner screw pile. Any moisture leaking from
the crack in the pipe may be influencing the soil around the pile.
However, the 5m deep pile is most likely founded in clay soil rather than the
backfill of the pipe trenc h and the fill at the site. Therefore, the moisture from
the le aking stormwater pipe has not caused the fill to subside under the
weight of the house and/or caus ed the fill to erode.
The clay soil that the piles are reportedly founded in has a relatively low
reactivity (surfac e movement of around 2mm).
Determination | Case number: 610315 Page 6 of 9
Record Key points
The level surve y indicates the house has settled by around 54mm at the
north western corner. Therefore, the movement in the house has not been
cause by clay soil shrinkage.
It is possible moisture from the leaking pipe could have softened the clay
soil horizon or the low er sand soil horizon, resulting in the soil failing under
the load of the structure, which would result in the house settling.
However, moisture entering the soil would only occur when the pipe is
flowing (only during rain events). There would not be signi ficant amounts of
water discharging into the soil at the crack location.
Any moisture would remain within the excavated pipe area (the trench
backfill) and then dry out or flow along this backfill area.
This moisture in the backfill may be absorbed into th e drier natural soil over
several rainfall events. However, this is highly unlikely to influence beyond
the location of the second pile (around 4m away). The area of influence this
crack would have is isolated to the north western corner.
However, there is a relatively uniform settlement across the front and
northern side. There is no sudden change in curvature near the leak. This is
inconsistent with a leak induced movement.
Based on the evidence and assuming the piles are a minimum of 5m into
the soil, th is movement has not been caus ed by the stormwater pipe leak.
A possible cause of damage may be a varied soil profile beneath the house.
The north - western corner may have a softer soil profile than the rear area
and sout hern side that has allowed the nort h western corner to gradually
subside over time under the weight of the structure.
This varied soil profile could be explained by the natural water cours e that
appears to extend through the area. The water course would have a
different soil profile along its banks compared to the higher land area. This
soil subsidence is unrelated to the leaking stormwater pipe.
The soil samples confirmed the northwest corner is built over about 3.6m of
fill underlain by natural clay and sand soil horizons. The pipe is around 1. 6m
away from the northwest corner and about 4.5m below ground level, which
would be above the design embedment depth of the piles.
The pile footings have most likely been installed into inadequate soil for the
construction. Piles may not have been screw ed into the natural soil, or there
may be a variation in the soil profile beneath the north western corner that is
insufficient to support the house.
As a result, the foundation soil beneath the piles has gradually subsided
under the load of the dwelling, causing the damage to the house.
The evidence indicates the stormwater pipe has not caused the house to
settle and crack.
Complainant’s
plumber ( JA )
Report
19 November 2018
JA found numerous breaks in the pipe. The most severe being near the front
corner of the property. JA observed an attempt had been made to join a pipe
coming from the Golf Club sump into the stormwater pipe.
This work was not carried out by a licensed plumber and as a result has
caused a prolific amount of water to escape and undermine the property.
The person attempting to install a junction box (which is not to code) is
responsible for the damage caused to the site.
Determination | Case number: 610315 Page 7 of 9
Record Key points
Insurer’s engineer
(IE )
Report
5 March 2019
The pipe and carpark that covered the pipe were built around 1979 - 1989.
The carpark replaced an original creek and natural waterc ourse.
The pipe has been buried for many years before the house was built in
2015. It has most likely been leaking into the soil for most of this time during
rain periods.
There are two different source s of moisture entering the drain pipe, the
sump and runoff from the catchment area at the northeast end of the pipe.
The pile footings have most likely been installed into soil inadequate to
support the house construction. The piles may not have been screw ed into
the natural soil, or there may be a variation in the soil profile beneath the
house’s north - western corner that is insufficient to support the house.
As a result, the foundation soil beneath the file has gradually subsided under
the load of the dwe lling, causing the damage to the house.
Complainant’s
engineer (ML )
Report
7 June 2019
The dwelling appeared in sound structural condition. No major structural
issues were evident.
There is cracking of the internal plasterboard lining around the [northwest
area]. External walls are in good condition, with minimal signs of cracking.
The existing footing system consists of 120mm thick reinforced concret e
slab, supported by screw piles.
The original design drawings says the piles are to be founded at a depth of
5m with a nominal safe working load of 8tn. No as - built record of the screw
piles was available. The founding dept hs of the piles are unknown.
Cracking in the walls and ceiling only occurred in the [northwest corner] of
the house.
A certain deg ree of settlement of the house footing is expected. The slab
has settled unevenly. The northwest corner has undergone a significant
amount of settlement compared to other areas. This has caused tensile
stress in walls and ceiling.
Soil movements are common in the region due to high soil reactivity, with
seasonal moisture variations. The introduction of additional water to the soils
would generally affect the performance of house footings and foundations.
It is difficult to estimate how much water entered th e underlying soil layers
via the cracks and gaps found on the pipe work. Given the proximity of the
pipe, water likely entered the surrounding soils, including the soil layer
where the screw piles are founded.
When soils are saturated, they would generally lose their bearing capacity
and lead to settlement of the screw piles and footings above.
The settlement of footings could be caused by the settlement of the screw
piles, if the founding soil layer has inadequate bearing capacity. Differential
settlement of the piles would occur if the piles are founded on different soil
strata.
As the cracking was not worsening, the soils and footing system might have
been stable, and any further settlement might not be significant.
It is reasonable to conclude that the c racking issue was the result of
excessive settlement of the screw piles and the concrete slab. There are two
probable causes: the leaking water from the adjacent pipe and soil layers
with insufficient bearing capacities.
It is difficult to conclude a singl e cause of settlement without further
Determination | Case number: 610315 Page 8 of 9
Record Key points
investigation.
Insurer’s engineer
(LE )
Report
15 July 2019
The tenant says damage existed when the tenant moved into the property
(three years earlier). The owner says the property was leased in June 2016
and damage to the property was noticed in early 2017.
The break in the stormwater line was repaired in late 2018 or early 2019.
Repair dates are unconfirmed.
Site borehole testing shows fill material overlaying clay soils. Investigations
confirm highly reactive soils .
Three [more] boreholes were dug. The second borehole was dug at the
northwest corner to a depth of about 8m. Analysis confirms fill material up to
3.6m deep and overlaying moist stiff clay between 3.6m and 8m.
There is a general elevation in soil moistur e content in the upper 1.5m, with
soil moisture content reducing below this depth.
The third borehole was dug north from the property, to a depth of about 8m.
There is fill material to a depth of 3.3m, overlaying medium dense moist
sand at a depth of 3.3 - 4 .3m and overlaying moist stiff clay at a depth of
4.3m up until borehole termination (8m).
There was no anomalous increase in the soil moisture content at the second
borehole, near the leak and footing settlement compared to the third
borehole, remote from the location of the reported leak.
The screw piles should be founded into the natural clay stratum. However,
this has not been confirmed.
Soil tests confirm the fill layer to a depth of 3.3 - 3.6m is soft and an
inadequate foundation.
Building survey result s confirm no pattern of expected footing heave
localised and isolated to the northwest corner near the water leak,
consistent with localised increase in the moisture content of the reactive clay
foundation.
Preliminary soil testing and bearing capacity tes ts in the area of settlement
indicate the natural clay foundation soil remains stiff and has not lost bearing
capacity due to saturation.
If the screw piles have been founded int o the natural clay stratum, an
escape of water from the reported leak has not caused a reduction in the
foundation bearing pressure to cause the detected footing settlement of the
building.
Further, the estimated volume of water escaping is expected to runoff with
the fall of stormwater trench over the impermeable clay layer and is not
expected to result in widespread saturation affecting the foundation soils.
The duration and volume of water discharged from the reported leak has
been insufficient to adversely affect the virt ually impermeable foundation
soils into which the structura l footings have been founded.
The escape of water for the leak is not the cause of building movement or
damages.
Two large trees were observed, one to the northeast and one to northwest
corners of the property, within close proximity.
The founding depth of the screw piles is expected to be adequate to
alleviate the effects of tree root influenc e. The building survey results show
no anomalous pattern of settlement toward the northeast corner in the
Determination | Case number: 610315 Page 9 of 9
Record Key points
direction of the large tree.
There is a fall toward the nort hwest corner consistent with footing
settlement. This has occurred due to either a reduction in the moisture
content causing clay shrink age and/ or inadequate founding depth and
material of the screw piles causing consolidation under building loads.
The dam age began occurring less than one year after construction of the
building. The damage has progressively worsened within a short time and
has since stabilised, with no ex acerbation of the building cracking.
The localised nature of the settlement is inconsis tent with a reduction in
moisture content of the reactive clay foundation and this is not expected to
be the primary cause.
Footing investigations were unable to confirm the founding depth of the
screw piles. Inadequate founding depth and material of the s crew piles will
result in consolidation under load, causing footing settlement.
The pattern of building settlement relatively quickly after construction and
subsequent stabilisation of the building is consistent with consolidation of
the screw pile due to inadequate founding material.
The damage has been due to footing settlement toward the northwest
corner, caused by inadequate founding material of the screw pile, which in
turn caused consolidation and settlement under load.
Building survey results and soi l investigations indicate an escape of water
from the stormwater leak to the northwest corner of the building is not the
cause of the detected building movement or damage.