Outstanding and defective fire repairs, contents remainder, balcony, fences and storage costs after earlier determination
Text of the determination
Determination | Case number: 607263 Page 1 of 12
Determination
Case number: 607263 6 September 2019
1 Determination overview
1.1 Complaint
The complainant previously lodged a complaint (496359) against the financial firm
(insurer) for fire damage to her property. FOS (AFCA’s predecessor scheme) issued a
determination on 11 September 2018, partially in the complainant’s favour.
The complainant now seeks the following additional considerations:
Further non-financial compensation for service issues and delays
Reimbursement for all expenses including professional costs, report fees and loss
of rental income
Settlement for the remainder of the contents sum insured
The insurer to provide authorisation for the complainant’s builder to complete all
outstanding works and rectification of previous poor repairs
Completion of works to the balcony
Storage costs.
1.2 Issues and key findings
Is the complainant entitled to compensation for service issues and delays?
The previous determination addressed the issue of compensation and the
complainant was awarded $1,500 for non-financial loss. I do not consider the insurer
liable for the payment of further compensation.
Is the complainant entitled to reimbursement of professional costs, report fees
and loss of rental income?
The previous determination addressed professional costs, report fees and loss of
rental income, concluding the complainant was not entitled to reimbursement of these
amounts. As such, these items fall outside the scope of this review.
Is the insurer required to settle the remainder of the contents sum insured?
The insurer is to settle the complainant $17,000, which is the remainder of the
contents sum insured, in order to bring finality to this aspect o f the complaint.
Determination | Case number: 607263 Page 2 of 12
Is the insurer required to authorise the complainant’s builder to complete
outstanding and defective repairs?
The insurer is required to either complete the outstanding works with its authorised
repairer or provide a cash settlement with an increase of 17.5%, to account for
contingencies and risk transference.
Is the insurer required to repair the balcony?
The insurer is not required to repair the balcony.
Is the insurer required to pay for fences?
The insurer is not required to pay for fences.
Is the insurer required to pay further storage costs?
The insurer is required to cover an additional 5 weeks of storage costs.
1.3 Determination
This determination is partially in favour of the complainant.
The insurer is required to:
pay the complainant the balance of the contents sum insured, $17,000
complete outstanding and defective works including the bathroom and floor
scraping or staple removal, or at the insurer’s discretion make an equivalent cash
settlement payment plus an additional 17.5%
> the complainant is to allow access to the property by the insurer’s authorised
representatives in order for them to prepare a scope of works and quotation
pay the complainant a further 5 weeks for contents storage costs.
The insurer is not required to:
pay additional amounts for non-financial loss
reimburse the complainant for professional costs or report fees
pay for loss of rental income
repair the balcony
authorise the complainant’s nominated builder to complet e the outstanding works
pay any additional amount for contents removal
pay for fences.
Determination | Case number: 607263 Page 3 of 12
2 Reasons for determination
Determination 496359 issued on 11 September 2018 dealt with non-financial loss,
professional costs, loss of rental income and legal fees. As such, this determination
deals only with issues arising from the date of the previous determination.
2.1 Is the complainant entitled to compensation for service issues and
delays?
Insurer seeks further compensation for delays
The complainant seeks compensation for service related issues.
The complainant was awarded $1,500 for non-financial loss in the determination
issued 11 September 2018, because the insurer did not allow the complainant to use
her own builder and substantively underestimated the cost of repairing the property.
The complainant says the insurer has continued to delay the completion of repairs
which prevented her from moving back in to the property.
Complainant identified outstanding issues
The complainant provided a report from her expert G which outlines the defective or
incomplete repairs.
The insurer agrees with the list of defects, with the exception of the balcony which the
insurer says was not damaged in the fire event. On 28 September 2018, the insurer
formally stated it would rectify all outstanding issues and I am satisfied it has made
attempts to contact the complainant for this purpose. The insurer says the
complainant did not agree to its requests to reattend the property.
Multiple attempts to arrange a site meeting with the complainant’s experts
The insurer says it has made a number of offers to meet with the complainant’s expert
to discuss the outstanding items and appropriate repair methods. The complainant
has declined these requests.
During the course of the complaint, the authority also sought to arrange a time for the
parties to meet on site for the purpose of obtaining final agreement on the outstanding
work. These attempts were also unsuccessful.
Insurer not liable for further compensation
I have carefully reviewed the exchanged material and a timeline of events since the
previous determination. Based on my review, I do not accept the insurer has caused
undue delays that would warrant compensation above what has already been paid.
Consequently, the insurer is not required to pay further compensation.
Determination | Case number: 607263 Page 4 of 12
2.2 Is the insurer required to settle the remainder of the contents sum
insured?
Insurer partially paid the contents sum insured
The certificate of insurance lists the contents sum insured at $147,000 for the 2016/17
policy period.
The insurer has provided documentation showing the following contents payments
made to the complainant:
07/07/2017 $50,000
31/07/2017 $80,000
The balance of the sum insured is $17,000.
Complainant says contents are missing or damaged
The complainant requested her contents be delivered to her place of residence on 15
April 2019 as she did not intend on moving back to the original property.
After several attempts to follow the matter up, the contents were delivered on 27 May
2019, 6 weeks after the request was made.
The insurer had previously agreed to reassemble cabinetry, desks and shelving as
the removal trades originally dismantled these items. However, the insurer was
unable to do so as it could not locate the screws, nuts and bolts rendering these items
unusable.
The complainant also says many items are missing from the storage units. Whether
these items have been taken, moved by the complainant or disposed of as non-
restorable is unclear, as is the value of these items. It should be noted the
complainant has not provided a list of missing items.
The insurer says the complainant had access to the storage units and speculates
items may have been removed by her. This speculation cannot be substantiated.
On review of the inventories completed by the insurer, I note the original inventory
includes 1,034 line-items with multiples of many of these. Of this, a significant portion
of the contents was deemed non-restorable, although the insurer has not provided a
breakdown of the amounts paid to the complainant for contents.
In the absence of a list of missing items and or damaged items from the complainant,
I am unable to establish the extent of the com plainant’s loss. However, the inventories
indicate significantly fewer items were delivered to the complainant than were
originally placed in storage.
Determination | Case number: 607263 Page 5 of 12
In the absence of quantifiable information, I consider it fair in all the circumstances for
the insurer to settle the complainant $17,000, which is the remainder of the contents
sum insured, in order to bring finality to this aspect of the complaint.
In addition, the insurer paid the cost of shifting the contents from storage to the
complainant’s current residence. I am satisfied that it was fair that the insurer paid this
amount and the insurer is not required to pay any additional amounts for any contents
removal.
2.3 Carpet replacement cash settled by the insurer
The payment made on 7 July 2017 includes $16,390 for new carpet but does not
allow for scraping of the floor or staple removal, which the insurer’s quote says is
required for the installation of new carpet.
The complainant has said the exposed staples and lack of carpet makes the property
uninhabitable and for this reason among others, she has not moved back in to the
property to date.
I am satisfied that once that scraping of the floor or staple re moval has been
completed, the home is habitable.
The insurer is to, at its discretion, complete the floor scraping or staple removal, or
obtain a quote to do so, add 17.5% and settle the complainant for this amount.
2.4 Is the insurer required to authorise the complainant’s builder to
complete outstanding and defective repairs?
Parties agree on the outstanding issues
G’s reports include a detailed list of outstanding building items.
With the exception of the balcony, the parties agree the following items are
outstanding:
1. Front double door handles (inside and outside of doors)
2. Kitchen exhaust canopy to be ducted to outside as per BCA standards
3. Bathr oom door downstairs to have outward facing hinges as per B CA s tandards
4. B a throoms privacy lock/h andles
5. Upstairs bathroom repairs not complete
6. R eplacement of all l ight f ittings
7. Painting to steel lintels on dining room windows, sliding doors and western side
eaves
Determination | Case number: 607263 Page 6 of 12
8. Ensuite d ouble h eated t owe l rack, toilet paper holder, soap and t o othbrush
holders in master b edroom ensuite
9. F ly screens to master and last b edroom windows.
10. Ducted h eated h ose & attachments
11. Wron g d ucted heated vent in m eals area
12. Cast iron f ret work
13. Shelving and chrome hanging rods to bedrooms, walk in robes, family room and
store room.
The complainant adds damaged fencing, carpet replacement and balcony repairs.
The insurer agrees the majority of the above items remain outstanding and has
offered on several occasions to reattend with the complainant’s builder to discuss a
final scope.
The insurer submits the following exceptions:
The carpet was cash settled to the complainant in July 2017, and therefore it is not
liable for this repair. This item was dealt with in section 2.3.
All required works were completed to the upstairs bathroom and the insurer
dismisses contrary reports from the complainant’s builders.
The balcony was not damaged in the claimed event and has likely failed due to
constant exposure to the elements. This item is dealt with in section 2.5.
The fencing was not damaged in the claimed event. This item is dealt with in 2.6.
Complainant says the bathroom needs to be stripped and fixtures replaced
In his report dated 5 August 2019, G says the main bathroom has the following
outstanding issues:
Signs of smoke damage including jet covers - stains.
Toilet and cistern in the main bathroom upstairs have signs of smoke damage –
stains.
Tiling grouts in main bathroom wall and floor upstairs shows signs of smoke
damage-Stains.
Exhaust fan and light fitting shows signs of smoke damage and discolouration.
Cupboards doors, vanity soap holder and vanity bench top shows signs of smoke
damage- stains and discolouration.
In response, the insurer says the report is a copy of an earlier draft with annotations
and that it has sought to reattend the property on multiple occasions to assess the
Determination | Case number: 607263 Page 7 of 12
items. As previously stated, the complainant has refused the insurer’s attempts to
attend the property with her builder for the purpose of agreeing on a final scope.
Similarly, the complainant says she does not want the insurer to complete the
outstanding work, preferring instead to have her own builder do so.
In the absence of a reattendance, the insurer was unable to give further consideration
to the issue. The insurer also says its builder B informs it the light fittings, cistern,
toilet seat, exhaust, and stop in the main bathroom upstairs have been replaced and
acknowledges this contradicts the complainant’s statements.
On careful examination of the photos provided by the parties, it does appear soot
staining is present and from a close-up photo of the sealant at the base of the toilet, I
am not satisfied this item has been replaced. I am unable to comment on the
remainder of the bathroom from the photographs.
The complainant also provides a copy of the Gyprock installation guidelines which
says Gyprock plasterboard affected by smoke or fire damage is recommended to be
replaced.
The complainant says this is evidence the insurer should have completely stripped
the bathroom. I note this a generic comment in a commercial guidelines manual and
no t specific to the complainant’s circumstances. As such, I do not consider it proof
that the plasterboard has not been reinstated to its pre-event condition.
The complainant is to give all the insurer’s representatives access to the property to
assess what items need to be either replaced (if that has not already occurred) or
cleaned, as is required.
The items that either require replacement or cleaning are to be included within the
scope of works and quotation, in accordance with this determination.
Insurer not required to authorise the complainant’s builder
On the basis of the exchanged material, I accept that there are outstanding works to
be done. The remainder of the concerns agreed upon by the parties also need to be
addressed.
While the complainant is entitled to have the outstanding works and rectification
repairs completed by a licenced builder, I do not accept the insurer is required to
authorise her builder to do so and in so doing, guarantee an unaffiliated builder’s
work. Furthermore, the policy allows the insurer to nominate the repairer or provide a
cash settlement for the works.
The insurer is required, at its discretion, to either complete the outstanding works or
provide a cash settlement on receipt of an updated costing from the complainant’s
builder including the bathroom issues identified by G. A provision for a final clean of
Determination | Case number: 607263 Page 8 of 12
the property should also be included given the passage of time and additional work
required.
The cash settlement should exclude the carpet, which has already been settled, as
well as the balcony and fence repairs which I do not consider the insurer liable for
(see item 2.5 and 2.6).
Any cash settlement should be increased by a margin of 17.5%, to account for
contingencies and risk transference.
The complainant is to allow access to the property by the appropriate representatives,
in order that they may prepare a scope of works and quotation in compliance with this
determination.
The parties are to cooperate to bring effect to the terms of this determination.
2.5 Is the insurer required to repair the balcony?
Complaina nt’s expert speculates balcony was damaged during the event
The complainant’s expert J says in its August 2018 report:
The front balcony has suffered water damage that may be attributed to the
suppression methods employed to extinguish the fire.
G’s repor t dated 27 January 2019 says:
It is evident that entry and front balcony suffered water damage attributed to the
suppression methods employed to extinguish the fire
It is assumed this area was hit with high pressure water flow during extinguishing
fire resulting in such damage
On 27 May 2019, the complainant’s expert F completed a comprehensive report on
the balcony damage which states:
It was noted majority of the balcony flooring has been moist and decayed
It was advised from the CFA report that the fire hose was applied to defuse the
fire during the event.
It was advised to this office the owner of the property had not noticed any
damage/ decay to the balcony framing/ flooring/ cracking to any part of the front
balcony.
Determination | Case number: 607263 Page 9 of 12
It was assumed, during the firefighting porch and balcony was used to access the
dwelling. It was assumed that the high-pressure water hose was used during
firefighting causing porch ceiling board damage, moisture penetrating through
underside of the porch ceiling to the balcony framing, balcony tile lifting, and
cracking may have occurred. Also, the separation gap between the tiles at the
face of the balcony was seen. Refer Appendix B for photographs. Suppression
method was employed to extinguish the fire and balcony was exposed to extreme
wet condition. And due to the cracks and separation, water must have passed
inside the balcony and the balcony joist, framing and flooring must have absorbed
the water. It is our opinion that due to the plastic membrane over particle board
water vapour was trapped in and the balcony was exposed to unnaturally high
moisture for long period deteriorating and decaying the balcony framing and
flooring materials.
To conclude, it is our opinion that the deterioration of the balcony joist, framing,
flooring and tiling is mostly due to the exposure of the balcony members to
extreme water pressure during firefighting and unnaturally high moisture content
trapped for long period.
We note from the email sent by [insurer] dated 18th Feb 2019, that the balcony
was exposed to the weather elements since the time of construction. However,
we were informed and noticed that all the balcony members have been covered
using ceiling board underneath the framing and tiles/ water proofing membrane/
floorboard over the framing. The report further mentioned that there was the
ground movement causing the piers to move slightly and breaking/ dislodging the
tiles around the pier. However, it is our opinion that if there were any ground
movements, dislodging/ cracks on tiles to other locations would also have existed.
Furthermore, due to the ground movements cracks on ceiling and walls to other
locations would also have occurred. In absence of the other movement related
distresses, we are of the opinion the cracks onto the tiles around the pier is
unlikely due to the foundation movement.
Insurer says the balcony was not damaged during or after the fire event
In her reports, the insurer’s loss adjuster V says:
41 st report:
Upper level balcony is in poor condition, with loose tiles, missing grout, moss
growing between the tiles and water ingress is occurring which has damaged the
front verandah ceiling below. The balcony could also be in a dangerous condition.
44 th report:
A site meeting between the complainant’s builder H, the council representative G,
Insurer’s works supervisor B and V took place on 25th September 2018…
Determination | Case number: 607263 Page 10 of 12
… G explained to H the complainant was asking for repair works be undertaken
on the upper including the upper level balcony and strip out of the main bathroom,
as well as additional works which were not related to the fire incident.
H agreed the balcony state of disrepair is unrelated to the effects of the fire. He
was also aware of the Insured wanted the main bathroom stripped out whereas
he had previously agreed, this did not have to be undertaken due to the effects of
the fire.
In an email to the complainant’s solicitor, V also noted there was no evidence of entry
over the balcony, and the fire was seated i n the ground floor living room away from
that area.
A further report from building consultant GF says:
I attended site on 07/11/2018 and met with the council representative to discuss
repairs and inspect the balcony area…
…It is my opinion this damage has been occurring for over 36 months and is due
to a combination of a breakdown in the bedding mortar and tile grout and general
ground movement causing the piers to move slightly and tiles to dislodge…
… Had damage occurred to this balcony due to firefighting using the balcony to
access the dwelling cracking would have occurred to the tiles in the centre of the
balcony from foot traffic, there is no damage in the centre of the balcony.
Had large amounts of water been concentrated to the balcony area there would
be damage to the dwelling flooring substrate in this area, none is evident. This
balcony has been exposed to the weather elements since the time of
construction.
It is my professional opinion the balcony damage is not consistent with damage
from Firefighting activities such as foot traffic or high-pressure hose.
In its most recent submission the insurer also provides a fire authority attendance
report which says:
Incident type: Fire damaging structure and contents
Action taken: Ventilate, extinguish, salvage and overhaul
Comments: Upon arrival noticed smoke issuing from garage roof and spots of
fire inside window of living room. All windows and doors were locked, and forcible
entry made through front door. Fire was found inside living room, dining room and
laundry with heavy smoke damage throughout.
Determination | Case number: 607263 Page 11 of 12
Area of origin: Dining area, lunchroom, cafeteria
Level of fire origin: Level 01 or Ground level
Insurer not liable for balcony repairs
I carefully considered the exchanged materials.
Terminology such as ‘ may be attributed to suppression methods ’ and ‘ it is assumed
the area was hit by high pressure water ’ suggests the complainant’s experts are
operating on an assumption the fire authority used high pressure hoses on the
balcony. F’s conclusions also appear t o be based on this assumption.
However, the insurer’s view is the damage to the balcony is due to long term wear
and exposure to the elements, possibly exacerbated by ground movement.
The fire authority’s report says entry was gained through the front door and not over
the balcony as the fire was seated in the loungeroom away from that area. No
mention is made of water being used on the balcony.
When considering the entry point and the location of the fire, I accept that on balance
it is unlikely the balcony issues were caused by fire suppression methods employed
by the fire authority. Consequently, the insurer is not liable for balcony repairs.
2.6 Is the insurer required to pay for costs in respect of fences?
Having reviewed all of the exchanged material, I am not satisfied that the complainant
has established that the fences were damaged in the fire event.
The insurer is entitled to deny this aspect of the complainant’s claim.
2.7 Is the insurer required to pay further storage costs?
Policy covers storage costs
The policy covers the reasonable costs to remove and store contents for up to 12
months when the property suffers loss or damage as a result of an insurable event.
The insurer has paid the full policy entitlement for this additional benefit and says it is
not required to provide further settlement.
Property is liveable
I considered whether the complainant could reasonably have been expected to return
to the property in order to assess potential further entitlements to storage.
Determination | Case number: 607263 Page 12 of 12
Generally, an insurer considers a property to be liveable if it has running water, a
functional kitchen and bathroom, working electricity, and is water tight and structurally
sound. To this I would add that there should be no danger to the inhabitants.
I accept the property would meet the liveability criteria with the exception of the last
point. The smoke damaged carpet was removed by the insurer leaving staples
exposed. Given the complainant’s personal circumstances I accept this would
constitute an unsafe environment.
However, the insurer paid the complainant for carpet replacement in July 2017 and
therefore holds no further liability for this item. To date, the work has not been done.
Whilst I accept that the insurer should pay to have the cost of floor scraping or staple
removal, I do not accept that this means it should pay for further storage costs.
The complainant has said the council only recently removed the building notice, and
she could not move back in to the property before this. However, I note no work has
been done at the property since before the previous determination was issued. This
means the notice could have been cancelled much sooner if not for the ongoing
complaint.
I also consider it reasonable for the insurer not to have sought the cancellation of the
notice prior to the completion of repairs. As such, I consider the property to have been
brought as close to a liveable state as possible by the insurer prior to the previous
determination.
Insurer delayed return of contents
On 15 April 2019, the complainant requested the return of her contents from storage.
The insurer liaised with the service and several emails were exchanged before the
contents were delivered on 27 May 2019, 6 weeks after the initial request. This
process should have taken 1 week to arrange.
Although the complainant’s entitlement for storage has been exhausted, further
storage costs have been incurred which were outside her control.
As such, I consider it fair in the circumstances for the insurer to settle an additional 5
weeks for storage costs.