Home / Financial Firm (Unknown - Insurer) / Determination 601725
Determination 601725
Claim for additional increased costs of working (alternative rent) after fire, beyond policy cap
Summary
After a fire at his business premises, the complainant claimed further increased costs of working beyond the policy cap, totalling $131,387.78 including interest. AFCA found the insurer responsible for some delays and ordered a payment of $29,259.87 in full and final settlement, subject to a deed of release.
An insurer is liable for loss caused by its own unreasonable delays, but not for all extra costs, and fair compensation is limited to the delay-related period.
Issues
- Claim amount dispute primary · upheld
“It is fair that the insurer pays $29,259.87 for six months' additional rent over and above the ICOW cap; no further liability under the claim.”
- Delay secondary · upheld
“The insurer's administrator delayed obtaining permits and the project unnecessarily, causing additional rent costs.”
Subjects and remedies
business interruptionsmall businesspay compensation
Text of the determination
Determination | Case number: 601725 Page 1 of 6
Determination
Case number: 601725 26 July 2019
1 Determination overview
1.1 Complaint
The complainant lodged a claim on his business insurance policy held with the
financial firm (insurer), following a fire at his property on 11 February 2014.
The insurer accepted the claim and made a number of payments to the complainant
under various sections of the policy (including for property damage and reduction in
revenue). Re-building works were completed, and the complainant moved back into
the property in December 2017.
The complainant is seeking further „ increased costs of working ‟ (ICOW), which were
the costs of establishing and trading from alternative premises, including rental
payments. The complainant says the insurer delayed processing his claim and he
incurred extra expense as a result.
The insurer has already paid the complainant the cap for ICOW under the policy.
1.2 Issues and key findings
Is the insurer liable for any additional ICOW?
It is fair in the circumstances that the insurer pays the complainant $29,259.87
(including GST) for six months‟ additional rent, over and above the policy limit for
ICOW, in recognition of the delays for which it was reasonably responsible.
Apart from that payment, the insurer has no further liability under the claim.
It is appropriate and reasonable that the complainant enters a deed of release to this
effect with the insurer.
Determination | Case number: 601725 Page 2 of 6
1.3 Determination
This determination is substantially in favour of the complainant.
The insurer is required to pay the complainant $29,259.87. The complainant is
required to enter into a deed of release with the insurer accepting that amount in full
and final settlement of the claim.
The insurer is not required to take any further action.
Determination | Case number: 601725 Page 3 of 6
2 Reasons for determination
I have decided this case based on what I consider fair in the circumstances, having
regard to the relevant law, good industry practice, codes of practice and previous
AFCA decisions. I have taken into account all the material submitted by the parties,
both before and after the recommendation issued by AFCA on 13 May 2019.
I am satisfied that the case analyst‟s recommendation contains an accurate summary
of the complaint, the issued to be determined, any applicable paragraphs of the Rules
and any relevant law. I will not repeat all the evidence set out in the recommendation,
but have considered it in reaching my decision.
The case analyst recommended that it was fair that the insurer pay the complainant
$29,259.87 (including GST) for six months‟ additional re nt, in recognition of the delays
it caused. This was on the condition that the payment resolved the complainant‟s
entire claim, and that the complainant signed a deed of release with the insurer to
reflect that. The complainant did not accept the recommendation.
2.1 Is the insurer liable for any additional ICOW?
Insurer attempted to resolve the matter
There is no dispute that the property was seriously damaged by fire. The insurer
accepted the claim and cash settled for various losses covered under the policy,
including: building damage, contents and stock, personal effects, damaged carpet,
antiques/works of art and claim preparation costs. It also cash settled to the maximum
provided for under the policy for a reduction in revenue, and over the cap for
increased costs of working (ICOW).
The remaining issue is the complainant‟s concern that the insurer‟s delays in dealing
with the claim (particularly with regard to the demolition of the party wall) caused him
to incur additional ICOW, because he had to make extra rental payments during that
time.
The insurer has attempted to resolve the outstanding issues with the complainant on
numerous occasions. The emails submitted show that the complainant did not accept
several offers by the insurer to resolve the ICOW component of the claim. This has
contributed to the claim becoming unnecessarily protracted.
Insurer caused complainant to incur additional rent costs due to its delays
I am, however, also satisfied that the insurer was responsible for some of the delays
in processing the claim.
The party wall was not demolished until the local council made an order for that to
happen. I appreciate the insurer had previously relied on its expert report, which had
Determination | Case number: 601725 Page 4 of 6
advised that the wall could be reinstated (and so did not need to be demolished). I
consider it was not unreasonable for the insurer to rely on that expert report until it
was advised differently by council.
I also note that the complainant has acknowledged that the council had been involved
continually throughout the claim. The insurer should not be liable for delays caused by
council, as that is a separate entity, over which the insurer has no control.
However, the evidence also indicates that the insurer‟s administrator (R) delayed
obtaining permits (such as the permit for continual business operation) and delayed
the project unnecessarily by raising other issues.
The complainant noted that it took R eight months to obtain several quotes, and that
while R was on holiday, he did not hand over the work to others, which further
delayed the project and increased the complainant‟s rent charges while he was in an
alternative property.
The insurer had acknowledged its part in delays by offering the complainant six
months‟ additional rent payments, for the period of March 2015 to August 2015. The
insurer‟s claim notes show that there was not much activity on the claim during this
time. The evidence shows the complainant did not accept these offers.
Meanwhile, the complainant had attempted to mitigate his losses, by choosing
reasonable rental premises.
Insurer to pay for additional 6 months’ rent, in resolution of the whole claim
Following the recommendation, the complainant claimed additional rental expenses,
together with interest at 10%. The total now being claimed is $131,387.78.
The complainant is also concerned about signing a deed of release in return for
further payment from the insurer in resolution of the claim and complaint. He believes
that might mean he loses any other right he might have to claim against his
neighbour, whom he believes was responsible for the fire (as well as limiting his right
to pursue other issues that may arise with the insurer). He says he has sought advice
from a barrister on the deed of release.
The complainant, of course, has a right to consider and investigate his broader
options (and their legal consequences) and make his decision about the claim and
this determination on that basis. It is not our role to provide legal advice.
My role is to decide a fair outcome for this dispute about the handling of the insurance
claim as between the complainant and the insurer, based on the evidence available to
me.
This matter has been ongoing for five years now, and in fairness to both parties, there
needs to be certainty and finality to the claim. I consider this period of time should
Determination | Case number: 601725 Page 5 of 6
reasonably have been sufficient for all claim-related issues to be raised and dealt
with.
I have considered the complainant‟s claim for additional reimbursement, including the
submissions made since the recommendation was issued. I appreciate the
inconvenience, disruption and expense the complainant has experienced since his
property was damaged, but I am not satisfied the insurer can reasonably be held
responsible for all of that. It has already paid up to the policy limit for ICOW.
Given the additional delays however, it is fair in the circumstances that the insurer
compensates the complainant for some further expense, over and above the cap in
the policy. At the same time, I am not persuaded that the insurer should be
responsible for more than the six months‟ additional rent costs (for the period March
2015 to August 2015) already identified. This amounts to $29,259.87 ($26,599.88 +
GST).
I am not aware of any other specific unresolved concerns with the claim. So, in order
to bring this matter to a final resolution, it is reasonable and appropriate (and usual
practice) that the complainant enter a deed of release with the insurer accepting the
payment in full and final settlement of the claim.
Determination | Case number: 601725 Page 6 of 6
3 Supporting information
3.1 Policy documents
Record Key points
Product
Disclosure
Statement
25 May 2012
Pages 55, 58
Section 5 – Back in Busine ss
This section of the policy covers a reduction in your business revenue as a
result of damage t o property caused by any of ins ured events 1 to 12 listed in
this section. An insured event does not include the items, events or
circumstances set out beside the event in the “What we exclude” column.
You can claim for a reduction in your revenue , or the increased costs of
working, if the business is interrupted directly by loss or damage as
described under “What we cover” if:
“Back in Business” is shown under “What we cover” on the schedule;
the loss or damage occurs during the period of insuranc e;
the claim is not excluded under the “What we exclude” column of this
section; and
the loss or damage is not excluded by any of the General Exclusions listed
on pages 103 and 104.
Page 58 What we will pay for a reduction in revenue and increased costs of
working:
We will pay:
the amount by which as a cons equence of one or more of insured events 1
to 12 as described, the revenue earned during the indemnity period falls
short of the standard revenue where revenue, for the relevant periods, is
calculated p rimarily by reference to the amounts shown at G1 on your
Business Activity Statement for the relevant periods and by also
considering your other business records, such as cash books, bank
statements, stocktake lists, invoices issued and received, GST calcu lation
sheets and your Business Plan;
in respect of the increased costs incurred to avoid a reduction in revenue as
a consequence of one or more of insured events 1 to 12 and with our
consent, increas ed costs necessarily and reasonably incurred for the sole
purpose of avoiding or diminishing the shortage in standard revenue,
provided the costs are less than, or equal to, the amount we would have
paid for a reduction in standard revenue under (a) above; les s…