Text of the determination
Determination | Case number: 550759 Page 1 of 14
Determination
Case number: 550759 30 April 2019
1 Determination overview
1.1 Complaint
The first complainant (complainant) is the director of the complainant company
(company). The company held an overdraft facility (overdraft) with the financial firm,
secured by three registered security interests, ending *740, *543 and *768 (charges).
The company sought funds from another lender for building works to establish a
dental clinic. The complainant says the financial firm delayed releasing the charges
which caused the company to suffer financial loss.
The financial firm accepts there was a delay in removing the charges. The complaint
is about how much compensation the complainants are entitled to.
A preliminary view partly in favour of the complainants was provided to the parties on
12 March 2019. The complainant rejected the preliminary view and provided further
submissions relating to the consequential losses incurred by the complainant due to
the bank’s delay .
1.2 Issues and key findings
Did the financial firm make any error or cause any delay?
The financial firm did unreasonably delay its release of the charges.
Did the further submissions change the outcome?
The further submissions led to reconsideration of the period of delay caused by the
financial firm, and the proximity and timing of the bank’s delay to claimed
consequential losses.
What compensation are the complainants entitled to?
The financial firm’s delay caused the company consequential loss, as the builder’s
deposit was not paid on time and building works were delayed. The established loss
is penalty interest of $708.82, additional costs incurred for extra works of $2,200, and
loss of part of the rent-free period, $4,219.17. Under FOS Terms of Reference,
consequential loss must be capped at $3,500 per claim. The complainant is entitled to
$2,000 in non-financial loss compensation for the stress and inconvenience the
f inancial firm’s delay would have caused her.
Determination | Case number: 550759 Page 2 of 14
1.3 Determination
This complaint is partly in favour of the complainants.
If the complainant accepts this determination within 30 days, the financial firm should
pay the following amounts to the complainant within 14 days of notice of acceptance.
The amounts should be paid into an account nominated by the complainant with her
acceptance of the determination.
$708.82 for consequential loss incurred from late payment of the deposit
$2,200 for consequential loss incurred for delayed extra works
$3,500 for consequential loss incurred from loss of rent-free period
$2,000, non-financial loss compensation for stress and inconvenience caused by
the delay.
A total amount of $8,408.82 is payable to the complainant.
Determination | Case number: 550759 Page 3 of 14
2 Reasons for determination
2.1 Did the financial firm make any error or cause any delay?
The complainant sought a release of the charges.
The complainant held an overdraft with the financial firm, secured by registered
interests (charges) over the company and the com plainant’s trust.
A detailed time-line of events is provided in Section 3.2 of the determination. The
complainant sought finance to build a dental clinic in a new shopping centre. The
information shows on 21 September 2018, the complainant obtained conditional
approval from a new lender for $350,000. The funds were to be approved once the
charges held by the financial firm, over the company and trust, were released.
On 21 September 2018, the complainant emailed the financial firm requesting it to
remove the charges. The financial firm told the complainant the securities could only
be discharged once the limit on her overdraft was reduced to nil. On 25 September
2018, the complainant repaid the overdraft, and again requested the financial firm to
remove the charges. The complainant then booked an appointment with the new
lender to sign the loan documents, for 2 October 2018.
On 9 October 2018, the financial firm emailed the complainant a discharge and
variation form, which the complainant signed and returned on the same day. On 30
October 2018, the financial firm released all three charges. On 2 November 2018, the
new lender approved the finance.
A financial firm is only liable to compensate a customer for an unreasonable
delay
A financial firm should action a customer’s request withi n a reasonable time frame.
Discharging security may be delayed for different reasons, and some of these may be
outside the control of the financial firm. For example, the financial firm may be waiting
for documents from a customer or a third party.
A financial firm will only be liable to compensate a customer if it has caused an
unreasonable delay. In other words, if the financial firm ’s error or omission has
caused the delay. If a financial firm has caused an unreasonable delay, then AFCA
will assess whether this delay has caused the complainant a loss.
The financial firm delayed the release of the charges
The complainant says the financial firm should have removed the charges as soon as
she paid the overdraft, being 25 September 2018. On this basis, she says the
financial firm’s delay was around seven weeks.
Determination | Case number: 550759 Page 4 of 14
The financial firm says it required a completed discharge and authority before it could
release the charges. While it acknowledges there was a delay, it says this delay only
occurred after the completed discharge form was received.
The complainant asked the financial firm to release the charges on 21 September
2018, and again on 25 September 2018 (once she had paid the overdraft). While the
financial firm says it required a completed discharge form to complete the discharge,
it did not provide the complainant with this form or advise her of the need to complete
one until 9 October 2018. As such, the complainant was unaware of this requirement,
and proceeded to organise a day to sign loan documents with the new lender.
Had the financial firm provided the discharge form to the complainant on either her
first or second request to release the securities, this would have allowed the
complainant time for her to return the discharge form and for the financial firm to
release the securities prior to her appointment to sign the loan documents with the
new lender.
On 9 October 2018, the financial firm received the completed discharge form.
However, it did not release the charges until 30 October 2018. Based on the available
information, there is no reason why the charges weren’t released upon receipt of the
completed discharge form.
Based on the above, the financial firm unreasonably delayed:
sending the discharge form to the complainant and;
releasing the charges once the completed discharge form was received.
The financial firm is not responsible for any delay prior to 2 October 2018
While I accept the financial firm did cause unreasonable delay, I do not accept the
financial firm is responsible for any delay prior to 2 October 2018.
This is because after paying the overdraft, the complainant booked an appointment to
sign the loan documents with the new lender for 2 October 2018. Therefore, the new
loan would not have been approved any earlier than 2 October 2018, regardless of
the financial firm’s error.
Based on the above, I consider the financial firm unreasonably delayed the release of
the charges for a period of 28 days (2 October 2018 to 30 October 2018).
Accordingly, the financial firm is required to pay compensation for any loss incurred
by the complainant for this delay.
Determination | Case number: 550759 Page 5 of 14
2.2 What compensation are the complainants entitled to?
AFCA’s approach to financial loss
As this complaint was lodged in October 2018, this determination is made under the
Financial Ombudsman Service’s (FOS’ ) Terms of Reference. Under FOS’ Terms of
Reference, AFCA can compensate a complainant for:
direct financial loss up to the amounts specified in FOS’ Terms of Reference, and
consequential loss up to $3,500.
Direct losses are losses caused directly by the financial firm’s conduct. Consequential
losses are considered ‘indirect’ as they are a step removed from the error .
For compensation to be paid for any loss (whether direct or consequential), the loss
must have been caused by the breach and not be too remote. It must also have been
reasonably foreseeable, or within the contemplation of the parties, at the time the
error occurred.
The initial payment of the deposit was late
The complainant says because her finance was delayed, she was unable to pay the
deposit to the builder, and the builder charged her an extra $25,000 for late payment
of the deposit. The complainant is wanting the financial firm to compensate her
$25,000. The available information shows:
the complainant signed a contract with the builder, dated 10 September 2018
the total contract value was payable in stages
under the terms of the contract, the builder was entitled to issue invoices for the
first two stages upon execution of the contract
on 10 September 2018, the builder issued an invoice for $7,700 (being for design
and preparation of plans) and an invoice for $61,600 (being the initial deposit), with
payment due in seven days
the complainant paid the builder: $7,700 across 11 and 12 September 2018, and
$61,600 on 2 November 2018. There have also been subsequent payments
made.
The builder charged the complainant $25,000 for late payment of the deposit
On 4 November 2018, the builder told the complainant due to late payment of the
deposit, he had been unable to pay deposits on special order materials and lock in
contractors. On 6 November 2018, the builder issued an invoice to the comp lainant
for $25,000 being for:
‘compensa tion for breaking contract start by 7 weeks due to delay in deposit
payment…including loss of income, considerable stress, anxiety, depression and
Determination | Case number: 550759 Page 6 of 14
financial hardship and embarrassment with subcontractors have to hold them off
due to delay.’
The building contract provides the terms for late payment
Section 13 of the building contract dated 10 September 2018, outlines the terms of
payment between the builder and the complainant. Under the terms:
the purchaser is required to pay no later than five days after receiving the relevant
tax invoice
non-payment by the purchaser entitles the contractor to cease work until payment
has been made
interest shall be payable at the rate of 15% per annum on late payments from the
due date for payment, until such payment is made.
Therefore, under the terms of the building contract, the builder was only entitled to
charge an interest penalty on late payments from the due date to when the invoice
was fully paid.
The builder is only entitled to charge 15% interest on late payment
The builder issued the deposit invoice for $61,600 on 10 September 2018, meaning
payment of the full amount became due on 17 September 2018 (five business days).
The complainant made full payment of the deposit amount on 2 November 2018.
Under the terms of the building contract, the builder was entitled to charge interest of
15% per annum on the deposit amount of $61,600. The deposit payment was late by
46 days. Interest of 15% calculated on $61,600 calculates to $9,240 per annum, or
$1,164.49 for a period of 46 days.
The builder is only entitled to charge the complainant extra interest on the deposit
amount for the period the deposit was late, in this case $1,189.80. The builder is not
entitled to charge the complainant $25,000. Accordingly, it is not reasonable for the
financial firm to compensate the complainant for the $25,000 charged by the builder.
The building contract gives the builder the entitlement to treat non-payment as
repudiation of the contract. There is no evidence to support the builder electing to do
so. Indeed, the builder proceeded to work under the existing contract.
The complainant says it was necessary to pay the builder to progress the building
works. The complainant may wish to recover these costs from the builder in a
different forum, as AFCA has no jurisdiction over the builder or the building contract.
Determination | Case number: 550759 Page 7 of 14
The financial firm is only required to compensate for loss caused by its error
The financial firm is only required to compensate for any loss indirectly or directly
caused by its error. The period of delay caused by the financial firm totalled 28 days
(2 October to 30 October 2018).
The financial firm is not responsible for any penalty the complainant incurred for late
payment prior to 2 October 2018 or for the period after the charges were removed to
when the deposit was fully paid from (30 October 2018 to 2 November 2018).
It is reasonable for the financial firm to compensate the complainant only for the delay
it caused. This delay was 28 days, and as per the terms in the building contract, the
interest penalty for this period totals $708.82.
The complainant seeks loss of business trade and opportunity
The complainant says the expected start date for trading (as agreed with the
shopping centre) was 6 December 2018 . The complainant says the financial firm’s
delay:
cost her business approximately six weeks trade
she lost a business opportunity to gain new clients (as she was unable to trade
over the Christmas period when many clinics were closed)
due to loss of income over this time, she flew to Darwin to locum for 5 weeks,
which caused her inconvenience.
In support of her claims, the complainant provided AFCA with a dental schedule of
fees, the emergency dental treatment roster for the holiday period and her business
projected cashflow.
The onus is on the complainant to quantify and prove her loss
AFCA can consider a claim for consequential loss, such as loss of business trade,
arising from unreasonable delay caused by a financial firm. The onus is on the
complainant to quantify and prove their loss. Any loss should be:
quantified at the amount which should be paid to put the complainant in the same
position had it not been for the error
foreseeable and
caused by the financial firm’s error.
The test of remoteness will determine whether a loss is compensable. The more
remote the loss, the less likely it is to be compensable.
Determination | Case number: 550759 Page 8 of 14
The complainant is not able to quantify her trading loss
The complainant bases her loss of trade and business opportunity on the expectation
that, were it not for the financial firm’s error, her clinic would have been open for trade
on 6 December 2018.
The complainant has provided her projected cashflow based on gradual patient take-
up of services with a clinic in a new location. The cashflow shows net deficits in the
first eight months, and projects no income in December 2018 and January 2019. The
complainant has also provided a 2018 industry survey of dentist incomes, and rates
for specific procedures applying to emergency work under the Dental Scheme
applying from 14 December 2018 – 13 January 2019 for dentists on the roster. The
complainant is seeking trading loss of $7,500 per week.
The complainant is establishing a new business and is not transferring clients from an
existing practice. Her business did not have an established history of earnings. The
complainant’s claim for loss of trade is speculative and cannot be quantified to put her
in the same position she would be had it not been for the financial firm’s er ror.
T he complainant’s claim for lost business opportunity is also based on her
expectation that she would sign up to the emergency dental treatment roster to obtain
new clients over the holiday period. The complainant says she did not sign up to the
roster due to concerns about not completing the build in time. Further, there is no
guarantee under this scheme of the number of patients, nor the specific procedures
required for each patient. The income foregone is hypothetical and speculative.
It is also noted that the complainant earned income providing locum dental services in
Darwin from 22 December 2018 to 25 January 2019.
Based on the above, the financial firm is not required to pay compensation for the
company’s loss of trade or busi ness opportunity as the claimed loss is hypothetical
and cannot be quantified or proven.
It is also relevant to note that the complainant advised on 28 February 2019 that she
was hoping the clinic fit-out works would be completed by end March. Therefore, it is
not possible to say with any certainty that the complainant would have been trading
on 6 December 2018, were it not for the financial firm’s error.
Specific extra building costs are payable by the financial firm.
The complainant says that building works were substantially delayed because the
financial firm’s delay caused a ‘flow on effect’ that resu lted in further delay and
subsequent costs she would not have incurred . Specifically, the complainant seeks to
be compensated for $3,080 ($2,800 plus GST) additional building costs (‘extra
works’ ), being for x-ray shielding and extra layers of gyprock for the wall to ensure
EPA compliance.
Determination | Case number: 550759 Page 9 of 14
On 18 October 2018, the landlord’s contractor asked the builder when the steel
shielding sheets were being installed, as the steel studs would be installed by the
second week of November (around when handover to the complainant was due).The
builder confirmed the sheets are installed directly on the studs and covered by
plasterboard, once in-wall plumbing and electrical work is completed.
The first deposit was paid to the builder on 2 November 2018. The building contract
enabled the builder to ‘cease work’ until the deposit was paid. The builder had
previously informed the complainant that in the absence of the deposit monies, he
was unable to order special items and schedule contractors to undertake works.
Generally, a financial firm is not liable to compensate the complainant for additional
costs arising from subsequent delays to building works where the loss is too remote
to the actions of the financial firm.
In my view, in this instance the builder was unable to meet the landlord’s timeframe
for the extra works due to the delay caused by the financial firm. As a consequence,
the landlord’s c ontractor completed the plasterwork without the steel sheets being
installed to effect handover of the premises to the complainant. The sheets
subsequently had to be installed over the existing plasterwork, and additional plaster
sheets installed.
In February 2019 the builder obtained a quote of $2,800 (plus GST) for these extra
works. However, the builder stated that he would have incurred costs of $800 to do
the original work as part of the building contract. Accordingly, the extra cost incurred
by the complainant for the extra works is $2,200 ($2,000 plus GST). In the
circumstances I think it is fair that the financial firm compensates the complainant this
amount.
The financial firm is required to pay compensation for the company’s loss of
part of the rent-free period
The complainant says the financial firm’ s delay caused her to lose part of her rent-free
period. The complainant is seeking $8,333.32 compensation, being rent from mid-
November 2018 to mid-January 2019.
Although the company is yet to sign the formal lease agreement, it has an agreement
to lease with the shopping centre (lessor). The complainant provided AFCA with its
letter of offer dated 19 July 2018 and the agreement to lease contract, dated 16
October 2018, between the company and the lessor.
The letter of offer shows the annual rent payable by the lessee is $50,000 per annum
(plus GST). The letter of offer also provides the lessee with an 8-week rent free period
(upon commencement of the lease) and an incentive of $37,500 to be taken as either
rent-free of fit-out contribution. The complainant says she elected to take the rent-free
period.
Determination | Case number: 550759 Page 10 of 14
It is established the financial firm’s delay i n releasing the charges caused a delay in
the payment of the builder ’ s deposit. On the information available, it is unclear
whether the builder stopped work due to late payment, however the email
correspondence shows the builder was unable to obtain materials or engage
subcontractors due to non-payment. This would have slowed the building works,
leaving the complainant unable to fully capitalise on the rent-free period. I accept the
company suffered loss of part of the rent-free period as an indirect consequence of
the financial firm’s delay. Accordingly, the financial firm should compensate the
company for this loss.
The building works were scheduled for completion by 6 December 2018, whereas in
late February 2019 the complainant advised she was hoping for works to be complete
by end of March 2019. The delay is close to four months. Email correspondence
between the builder, the complainant and the shopping centre show multiple factors
contributing to further delay, with the impact of the financial firm’s error becoming
increasingly remote.
The financial firm is only required to compensate the company for loss directly or
indirectly incurred by its error. The information shows payment of the deposit was
already late prior to the complainant requesting release of the securities. Further,
increasingly, multiple factors caused delay in the building works after the charges
were released.
The financial firm’s delay caused payment of the builder’s deposit to be delayed by 28
days. Under the terms of the lease, the rent payable for a 28-day period calculates to
$4,219.17. It is reasonable for the financial firm to compensate for this loss.
The consequential loss amount is limited to $3,500 under FOS’ Terms of
Reference
This complaint was lodged on 30 October 2018 under FOS’ Terms of Reference .
Under the Terms of Reference, the maximum amount of consequential financial loss
or damage FOS may award for disputes lodged at this time is $3,500 per claim. As
such, although the complainant may be entitled to $4,2019.17 (being 28 days rent),
under FOS Terms of Reference this amount must be capped at $3,500. Accordingly,
the financial firm is only required to compensate the complainant the maximum claim,
being $3,500.
The complainant is entitled to non-financial loss compensation
AFCA can require a financial firm to compensate a complainant for non-financial loss
caused by the firm’s cond uct in cases where there has been an unusual amount of
inconvenience or time taken to resolve a situation.
When a company lodges a complaint with AFCA, it is the legal entity that makes a
claim for financial loss. AFCA will generally only award compensation for non-
financial loss to individuals, not companies. An exception to this may be where a
Determination | Case number: 550759 Page 11 of 14
director is a sole proprietor of the company and there are no employees. I consider an
exception applies to this case, as the company is essentially the complainant working
in her own capacity.
When assessing whether to award compensation for non-financial loss, AFCA
expects complainants to bear the normal degree of inconvenience experienced when
a problem occurs and take reasonable steps to minimise the inconvenience suffered.
In some cases, it may be appropriate to consider whether the complainant, or other
factors unrelated to the financial firm’s conduct, contributed to the stress and
inconvenience suffered by the complainant.
In these circumstances, the complainant left her employment and undertook to build a
dental clinic within the time-frames set by the lessor. There were multiple variables
impacting these time-frames, and the complainant was under significant stress to
ensure everything fell into place. Although the financial firm’s delay was only one of
multiple factors that progressively contributed to the delay in the building works, it is
accepted this delay would have compounded the complainant’s stress level s. As
such, it is appropriate for the financial firm to pay the complainant $2,000 in non-
financial loss compensation.
Determination | Case number: 550759 Page 12 of 14
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previously lodged with F inancial O mbudsman S ervice (FOS) .
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
A pplicant C omplainant
financial services provider financial firm
D i spute C omplaint
C laim C laim
3.2 Time-line of events
Date, source What happened
June 2018, email
correspondence
Complainant commences discussions with builder regarding
dental clinic
19 July 2018, letter of offer Complainant signs letter of offer with shopping centre, is
provide with draft agreement for lease.
10 September 2018,
building contract
Complainant signs building contract
Builder issues first two invoices
11 September 2018,
account statement
Complaina nt pays first invoice
21 September 2018, email
correspondence
Complainant rec eives conditional approval for loan
$350,000
New lender advises needs to remove charges
Complainant emails financial firm requesting charges be
removed so finance can go through
Financial firm emails advising overdraft limit needs to be
reduced to nil
25 September 2018, email
correspondence, account
statements
Complainant pays overdraft facility, requests financial firm to
remove the charges as quickly as possible
Complainant b ooks to sign loan documents with new lender
2 October 2018
Determination | Case number: 550759 Page 13 of 14
Date, source What happened
28 September 2018,
contact notes
Financial firm sends internal email requesting to remove the
charges
2 October 2018, email
correspondence
Financial firm emails complainant to advise her request is
being process, uncertain of turnaround time
9 October 2018, email
correspondence
Financial firm send complainant discharge form to be
completed
Complainant completes and returns the form
10 October 2018, email
correspondence
Builder texts complainant saying needs money in bank by
tomorrow
12 October 2018, contact
notes
Completed discharge form received by financial firm
settlements team
16 October 2018,
agreement to lease
Complainant signs agreement to lease
18 October 2018, email
correspondence
New lender emails financial firm requesting charges be
released
24 October 2018, PPSR
release
Charge ending *768 released
25 October 2018, contact
notes
Complainant calls financial firm regarding the delay
30 Oc tober 2018, email
correspondence
New lender emails financial firm advising two charges still
need to be removed
Financial firm removes charges *543 and *740
Emails PPSR releas e confirmation and sends execut ed
deed of release by express post
2 November 2018, email
correspondence
Finance is approved by new lender and loan documents
signed
Complainant makes payment of $61,6 00 to builder
5 November 2018, email
correspondence Scheduled handover of premises.
6 November 2018, email
correspondence
Builder issues invoice to Complainant for $25,000 for
compens ation
Determination | Case number: 550759 Page 14 of 14
Date, source What happened
4 December 2019, email
correspondence Scheduled commencement of trading by dental clinic
28 February 2019, email
correspondence
Complainant ‘ hopes ’ fit out works will be complete by end
March 2019
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.