A borrower with two construction loans complained that the bank unreasonably delayed the final progress payment and lent irresponsibly, seeking $500,000. AFCA found in the bank's favour and ordered no compensation, although it found some administrative and payment errors by the bank.

The loans were affordable and suitable, and the progress payment delay was caused by the complainant not providing the invoices and information the bank reasonably requested, so no loss was caused by the bank.

Issues

Subjects and remedies

financial hardshipno remedy

Related

All Financial Firm (Unknown - Bank) determinations · Find similar determinations

Text of the determination

Determination | Case number: 549185 Page 1 of 9 Determination Case number: 549185 28 August 2019 1 Determination overview 1.1 Complaint In 2016, the complainant obtained two construction loans with the financial firm (bank) to assist in the construction of two investment properties (the properties). The complainant also borrowed further funds privately during the course of construction. The complainant says the bank unreasonably delayed the release of his final progress payment, resulting in him losing a potential buyer for the proper ties. The complainant also says the loans were approved irresponsibly and that he has not received the entirety of the agreed loan amount. 1.2 Issues and key findings Were the findings of the recommendation correct? Based on all the available information, the findings contained in the recommendation were correct and are adopted in this determination. Further submissions provided after the recommendation have been considered. Do the complainant’s submissions change the outcome of this complaint ? For the reasons set out in section 2 of this determination, the complainant has not established a basis for departing from the findings in the recommendation. 1.3 Determination This determination is in favour of the bank. The bank is not liable to pay compensation to the complainant. If the complainant is in financial difficulty, he should complete a statement of financial position for the bank and call the bank to discuss a repayment arrangement. The parties should work together to try to come to an arrangement. In doing so the bank should have regard to its obligations for dealing with customers in hardship contained in the National Credit Code and/or the Code of Banking Practice. If the parties are unable to reach an agreement and the complainant is in financial difficulty, the complainant can lodge a further dispute with AFCA about that issue. If Determination | Case number: 549185 Page 2 of 9 no arrangement is made, then the bank may be able to take enforcement action if the loan accounts remains in arrears. Determination | Case number: 549185 Page 3 of 9 2 Reasons for determination 2.1 Were the findings in the recommendation correct? The recommendation was correct I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous AFCA decisions. I have taken into account all the material submitted by the parties, both before and after the recommendation. Both parties have been provided with a reasonable opportunity to present their case and respond to information submitted by the other party. The parties were provided with a reasonable time frame to respond to the recommendation and make further submissions about any finding they disagreed with. Having reviewed the recommendation and information provided to AFCA, I consider that the issues raised in the complaint were addressed adequately and correctly in the recommendation. I therefore do not repeat the analysis in this determination. Instead, I attach a copy of the recommendation. The complainant raised further issues since rejecting the recommendation and I have addressed these in section 2.2 below. The issues raised have not changed the outcome of the complaint. 2.2 Do the further submissions change the outcome of the complaint? The recommendation was in th e bank’s favour The recommendation found the complainant was not entitled to any compensation because:  the loans were not unsuitable and the complainant could afford to repay them  the bank acted in line with good industry practice when it requested the additional information before releasing the final progress payment in October 2018  the delay in payment primarily came from the time it took the complainant to present the bank with the appropriate invoices and information  the bank is not responsible for the delay caused in the release of the final progress payment. The complainant rejected the recommendation The complainant responded to the recommendation by acknowledging that he could afford the loans when they were provided. However, he rejected the recommendation including on the basis that:  the main basis of his complaint is about the delay in releasing the last progress payment and overall mismanagement of his loans Determination | Case number: 549185 Page 4 of 9  on 16 August 2018, the bank transferred approximately $80,000 into his mortgage account. He transferred $7,000 of these funds into his personal account  later that day, the bank reversed the $80,000 transaction  on 16 August 2018, the bank contacted him saying his transaction account was in debit about $73,000 and it would not release any progress payments until this was rectified  he told the bank he was in a hardship arrangement from early 2018, but the bank denied knowledge of such an arrangement. As the bank had not contacted him for eight months to set up a payment arrangement, he assumed a hardship arrangement was in place  on 31 October 2018, the bank released a final progress payment of $55,717.65, instead of the agreed $83,000  when questioned, the bank said it mistakenly paid an additional $17,000 in the first progress payment and it deducted the $7,000 he took from the mistaken $80,000 transfer. Hence the last payment was $55,717.65  the bank paid the last progress payment directly into the builder‟s account, which was in arrears. Therefore, the funds were unable to be utilised. The complainant‟s submissions are considered below. The bank did not unreasonably delay releasing the final progress payment A central issue in this complaint is whether the bank unreasonably delayed releasing the final progress payment to the complainant or his builder. The complainant says this delay resulted in him losing potential sales for the investment properties. I note that unless and until the properties are sold he will not be in a position to establish a crystallized loss even if we found that the bank was responsible for the potential buyer changing his/her mind. I have reviewed the complaint information including the timeline in the recommendation. A number of events occurred after the complainant first requested the final progress payment on 16 August 2018 which contributed to delays. The main delays were in relation to:  obtaining a final valuation and ensuring there was nothing further to be done  receiving an appropriate invoice on the builder‟s letter head  resolving defects outlined in a final inspection report  obtaining council approval for the proposed subdivision. The bank required the above information to be satisfied that the build was complete and the complainant would obtain the occupancy certificate. I also note the building invoices the complainant provided were confusing and included costs for painting and landscaping. It also appears at one point the complainant informed the bank he was Determination | Case number: 549185 Page 5 of 9 going to use some of the money to pay a “3 rd tier lender” (outlined in more detail below). In all the circumstances, I agree with the outcome of the recommendation that the bank did not unreasonably delay releasing the final progress payment in the circumstances. Further, the bank acted reasonably in requiring the further information. Finally, there is no objective information to show that any delay caused the complainant to lose a potential buyer for the properties or that it represents a loss to him. The bank transferring money directly to the builder did not lead to loss As outlined in the progress claim certificate, there are two payee options available. One option is to credit the builder ‟ s account which is the usual practice for construction loans, the other is t o credit the customer‟s account. H owever, this second option is only available for „Owner Builder Loans‟ . The complainant ticked the Owner Builder option when he applied for the loans. Until the final progress payment was released on 31 October 2018, the bank transferred all progress payments to the complainant‟s personal account “as if” it was an owner builder loan. It is unclear why this occurred as it appears to have been an error by the bank. However, this is not relevant to the outcome of the complaint as the bank transferring to the complainant in the initial payments did not lead to a loss. On 22 October 2018, the complainant provided the bank with an invoice from the builder for $55,717.65. The amount was due by 26 October 2018. On 31 October 2018, the bank released the final progress payment of $55,717.65 to the builder dire ctly. The complainant says the builder‟s account was in debit of approximately $100,000 and therefore were unable to be utilised by the builder, resulting in construction delay. While I concede that the bank changed how it made progress payments, as these works were already completed and the invoice was paid by the bank two days before its due date, the state of the builder‟s account and what it did with the funds are irrelevant to the progress and completion of the properties. The builder still received the payment value. The funds were intended to pay the builder and the bank ‟ s actions resulted in the builder being paid. The bank was entitled to retrieve the mistakenly transferred $80,000 On 16 August 2018, the bank transferred approximately $80,000 to the complainant‟s transaction account in error. At that time, the complainant‟s personal account was in debit $72,100.87. Accordingly, this would have put the account in credit $7,899.13. The complainant immediately transferred $7,000 of these funds to his business account. Later this same day, the bank reversed the $80,000. This put the account in debit $79,100.87. Determination | Case number: 549185 Page 6 of 9 As the complainant was not entitled to these funds and the bank acted quickly to fix this issue by reversing the transaction, this error did not lead to any unusual amount or stress or inconvenience to the complainant. This error also did not lead to any financial loss and had no bearing on the bank ‟ s decision to release the final progress payment. The bank was not in a position to release the final payment until the appropriate invoices were presented in late October 2018. The transaction account was already in debit at that time. The account was in debit a further $7,000 after the bank reversed the $80,000 (as the complainant had taken those funds). The bank failed to monitor the progress payments it was making The complainant says the final progress payment was meant to be $80,000. He also says the bank failed to disburse the full amount of the funds available under the construction loan. I have reviewed the building contracts and the progress payments the bank has made. It is clear the bank failed to adequately monitor the progress payments the complainant was requesting against the building contracts he provided. I have outlined the payments required under the building contracts and the payments the bank made in section 3.2 below. None of the payments the bank made matched the amounts the complainant was required to pay under the contracts. It appears the bank made the payment based on an invoice from the builder and the complainant‟s signed progress claim certificates. However, given the bank was simply following the complainant‟s instructions when it made the payments, the complainant has not suffered any loss as a result. The bank is not required to make further payments to the complainant The building contracts show the complainant was required to pay $792,500.50 in total to build both properties. The construction loan was for $812,000 and the bank has released progress payments totalling $787,217.45 including the final invoice payment. The complainant wants the bank to release the “ remaining ” amount. The complainant has not provided sufficient information to establish what exactly happened during construction whereby he obtained other funding. The complainant appears to have obtained three additional loans totalling about $390,000 from two different lenders to complete the build at very high interest rates (33%, 48% and 12% per annum). I accept that the behaviour of the builder may have contributed to the actions taken by the complainant and increased his stress and inconvenience, but the bank is not responsible for the builder‟s conduct. Determination | Case number: 549185 Page 7 of 9 Despite this, the complainant now confirms that the properties are built. Accordingly, the bank is not required to make any further payments to him under section 2.3(d) of the terms and conditions which says: 2.3 If your home loan has building loan conditions the following applies to you. … (d) if the building work is completed for less than the anticipated total cost stated in the Details, we need not lend you that part of the home loan being the difference between the anticipated total cost and the actual cost There is no information to show there was a hardship arrangement The complainant says the bank refused to release his final progress in August 2018 payment due to his financial hardship arrangement that had been put in place to address his home loan as it was $80,000 in arrears. The bank denies knowledge and existence of such an arrangement and there is no documentary proof that any arrangement ever existed. The home loan repayments were being automatically debited to the complainant‟s transaction account ending #8624, a different account to his home loan. However, because the complainant had no money in this account from August 2017, the account was going further into debit while the home loan account was staying up to date. This is likely why the bank overlooked the status of the account and did not trigger its collection process. Regardless, there is no information to show the complainant informed the bank about his financial difficulty or the complainant was on a financial hardship arrangement with the bank. In any event, the bank confirms this was not a reason for the delay which is supported by the available information. Determination | Case number: 549185 Page 8 of 9 3 Supporting information 3.1 The determination is made under FOS Terms of Reference The Australian Financial Complaints Authority ( AFCA) has commenced managing disputes previously lodged with Financial Ombudsman Service (FOS). This determination is made under FOS Terms of Reference but has adopted the following terminology for consistency with AFCA. In this determination the AFCA terms have the same meaning as the FOS terms defined in paragraph 20.1 and Schedule 1, 2 & 3 of the FOS Terms of Reference. FOS definitions AFCA term A pplicant complainant financial services provider financial firm D ispute complaint C laim claim 3.2 Building contracts and progress payments made Progress payments schedules in building contracts Stage Lot 1 Lot 2 Deposit + floor slab $125 ,475.03 $112,275.18 Frame $83 , 650.05 $74,850.05 Lock up $83 , 650.05 $74,850.05 Fix out $52 , 281.28 $46,781.28 Finishing $ 52 , 281.28 $46,781.28 Completion $20 , 912.51 $18,712.51 Total $418,250.25 $374,250.25 Determination | Case number: 549185 Page 9 of 9 Progress payments the bank made Date Amount Paid to 1 August 2016 $97,500 .00 The complainant 2 March 2017 $158,500.10 The complainant 31 May 2017 $158,500.10 The complainant 31 May 2017 $158,500.10 The complainant 20 July 2017 $79,250.05 The complainant 11 August 2017 $79,250.05 The complainant 31 October 2018 $55,717.05 The builder Total $787,217.45 Recommendation | Case number: 549185 Page 1 of 10 Recommendation Case number: 549185 18 March 2019 4 Overview 4.1 Complaint The complainant obtained two loans with the financial firm (bank) to construct two investment properties (the properties). Due to the actions of the construction company he was originally working with, the loan didn‟t cover the entirety of construction. Th e complainant borrowed a further $80,000 privately to try and finish construction himself and eventually enlisted a new construction company. The complainant says:  after reviewing his finances, he believes the bank should never have approved him for the loans  the bank delayed in paying his final instalment for the construction of the properties  he had a buyer for both properties, but due to the delay in completion, the buyer is no longer interested  construction is now completed, but he has not been able to sell due to the decline in the housing market  he wants the bank to resolve this complaint by providing him with $500,000 compensation. 4.2 Issues and key findings Did the bank lend responsibly when it approved the loans? Based on the information which the complainant provided to the bank, and on which the bank was entitled to rely, the bank lent responsibly when it provided the loan because:  the loan was not unsuitable, and  the complainant could afford to repay it Did the bank unreasonably delay in releasing progress payments? The available information suggests the delay in payment primarily comes from the time it took the complainant to present the bank with the appropriate invoices. While I Recommendation | Case number: 549185 Page 2 of 10 accept the bank changing its standard of satisfaction for information may have inconvenienced the complainant, it is my view the bank acted in line with good industry practice when it requested the additional information. As such, the bank is not responsible for the delay caused in the release of the final progress payment. 4.3 Recommendation The recommendation is in favour of the bank. The bank is not liable to pay compensation to the complainant. If the complainant accepts this recommendation and if he experiences difficulty meeting his repayments on the loans, then the parties should work together to reach a repayment arrangement (see part 3.3 below). Recommendation | Case number: 549185 Page 3 of 10 5 Reasons for recommendation 5.1 Did the bank lend responsibly when it provided the loans? Financial firms have responsible lending obligations at law A financial firm has an obligation to exercise the care and skill of a diligent and prudent lender in its assessment of whether a loan is not unsuitable for the customer. The bank‟s obligations are set out in the National Consumer Credit Protection Act 2009 (NCCP), the Code of Banking Practice (Code) and as a matter of good industry practice. Relevant sections of the NCCP and the Code are set out in section 3.1 of this recommendation. In the process of assessing credit, the financial firm should: Meeting the responsible lending obligations generally requires taking three steps:  making reasonable inquiries about the consumer‟s financial situation, and their requirements and objectives  taking reasonable steps to verify the consumer‟s financial situation a nd  making a final assessment about whether the credit contract is „not unsuitable‟ for the consumer, such as ensuring they can comply with their repayment obligations. The loans were not unsuitable When a lender provides consumer credit, it must comply with the “responsible lending” provisions of the National Consumer Credit Protection Act 2009 (NCCP Act). The NCCP Act says a lender must not enter into a credit contract with a consumer, suggest a credit contract to a consumer or assist a consumer to apply for a credit contract if the credit contract is unsuitable for the consumer. The provision of credit will be unsuitable if:  the consumer could not comply with their financial obligations under the credit contract, or only with substantial hardship, or  the credit does not meet the customer‟s requirements and objectives. In my view, the loans were not unsuitable because:  the loan contracts met the complainant‟s requirements and objectives, which were to refinance an internal land loan and funds to construct two town houses for investment properties  this was a retail product for an internal refinance of a loan and a loan for construction purposes  the loans were affordable at the time they were approved Recommendation | Case number: 549185 Page 4 of 10 The bank made sufficient and reasonable enquiries to assess the loan applications As part of our investigation of this complaint, the views of the AFCA industry advisor (advisor) have been sought to:  review the bank‟s assessment, and  to independently calculate affordability based on the available information. The advisor has reviewed the available information at the time of the loan applications and says the bank enquired about the complainant‟s purpose for the funds and offered a suitable product. The bank understood the complainant‟s loan applica tions were to refinance an existing debt as well as his intention to construct the town houses on the land. The bank offered the complainant appropriate loans for the refinance and construction. The bank also enquired into the complainant‟s financial circ umstances to ascertain if the credit offered was affordable. The loans were affordable The complainant says upon reviewing his financial position, he should not have been provided the loans because:  he could not afford to repay it, and  the bank knew of his financial position The ability of the complainant to repay the loan is crucial to good lending practices. As such, AFCA‟s advisor independently assessed the complainant‟s financial position at the time of the loans being approved. The advisor calculated that the complainant had a monthly surplus of $1,013 and could service the loans (see section 3.2 below for a detailed calculation and explanation). On this basis, the loans were affordable and remain interest bearing. 5.2 Did the bank unreasonably delay in releasing progress payments? The complainant requested for release of final payment in August 2018 The complainant says the bank significantly delayed in releasing the final progress payment which has resulted in multiple lost opportunities to sell the properties. It remains unclear what date the invoices were provided to the bank at first instance, however it is undisputed he requested the release of final payment and provided invoices around 28 August 2018. Therefore, I accept this to be the time the complainant first made this request. Recommendation | Case number: 549185 Page 5 of 10 The bank was not satisfied with the invoices provided Contemporaneous documents show on the same day, the bank contacted the complainant requesting further information as it was not satisfied with the invoices he had provided, particularly because:  the invoices were formatted on a word documented with no header or footer, and  the invoices were seeking payment for stages that had already been completed and paid for. The complainant contacted the bank to query why he had to provide such documentation as he had not been obligated to do so before. The bank acknowledged that while it may not have required such information in the past, it required it to release the final progress payment. The complainant refused to provide the information requested by the bank, and as such, the final progress payment was not released. The complainant provided satisfactory information and final payment was released After two months of resistance, the complainant provided further documentation to the bank on 22 October 2018. The bank subsequently approved the progress claim on 23 October 2018 and paid the final drawdown of $55,717.65 to the builder‟s account (see section 3.1 for a full chronology). Given the complainant did not provide the bank with the information it requested for two months, and the bank approved the progress claim the next day once it did, it cannot be said the bank caused the delay. In fact, it is clear the delay stemmed from the complainant‟s refusal to provide the informati on the bank requested. While I accept the bank may have changed its standard of satisfaction by requesting more documentation than it had in the past (which might have inconvenienced the complainant), this does not amount to unreasonable delay. The bank‟s actions accord with good industry practice when it required further substantiating documents before releasing the final progress payment. Therefore, the claim becomes one about customer service issues. AFCA considers any customer service issues should be r aised with the bank itself, as customer service issues generally reflect the bank‟s own policies and procedures and issues such as staff training. As such, the bank cannot be held liable for the delay in releasing the final progress payment and the complai nant is not entitled to compensation. Recommendation | Case number: 549185 Page 6 of 10 6 Supporting information 6.1 Chronology of key events Date Action/event 10 May 2016  GR complete ap praisal valuing House 1 at $800 per week and Hous e 2 at $700 per week . 1 Jul y 2016  Home loans ending 8187 ($680,574.36) & 2471 ($806,074.69) are approved. 19 Nov ember 2016  Construction of the two properties commence. 26 Jan uary 2017  The complainant requests release of $158.500.10 instalment from the bank. 23 May 2017  The complainant requests release of $158,500.10 instalment from the bank. 7 Aug ust 2017  The complainant requests release of $80,341 instalment from the bank. Nov ember 2017  The complainant stops making payments on loan due to financial difficulty. 22 December 2017  The complainant gets $200,000 privat e loan from Mango Mortgages. 2 Mar ch 2018  The complainant gets $80,000 second private loan from Mango Mortgages. August 2018  The complainant calls the bank and asks for release of final payment of $80,341. 16 August 2018  The bank takes back $7,000 as it was transferred to Recommendation | Case number: 549185 Page 7 of 10 Date Action/event complainant in error. 28 August 2018  The complainant provided the bank with an invoic e for the final completion stage  The bank rejects the application for last payment based on no redraw being available/ not satisfied wit h invoice provided 7 September 2018  The complainant gives the bank invoice for landscaping, the bank refuses to release payment due this 10 September 2018  The complainant queries why he has to provide these invoices now as the bank has never needed them before  The bank tells him it may not have asked for them in the past but is asking for them now. 11 September 2018  The bank contacts the complainant and says the inspection was conducted on the property and there are a few things yet to be finalized. It also says it has concern with occupancy cert.  The complainant hangs up and says he will “take this furt her”. 10 October 2018  The complainant calls the bank and speaks to the manager. He says documents requested “have nothing to do with the bank” and threatens self - harm. The manager says he will call the police as this is the second time complainant has said this. 1 0 October 2018  The bank calls complainant again and reiterat es its concerns  The bank says it will not release any further funds until it is satisfied that the occupancy certificate can be issued and properties sold. The complainant says he will call FOS an d ASIC  The complainant says he has to pay $5000 for a subdivision and requests the bank pay for it. The bank denies the request and says he needs to pay this himself. 10 October 2018  The bank pays the subdivision fee of $6,292. Recommendation | Case number: 549185 Page 8 of 10 Date Action/event 15 October 2018  Complainant says he had/lost buyer for properties. 17 October 2018  The complainant sent construction invoices to the bank for release of final payment  A phone call also occurs in which the complainant says he plans to finish the house, put properties on the market next week, sell immediately and pay debt in full  The bank declines release of funds as he has an outstanding debt of $80,000. 18 October 2018  The complainant calls the bank and asks why $80, 000 was taken from his account. The bank says he was notified on 17 Aug 2018 that this was done to correct a mistaken transaction by the bank. 18 October 2018  The complainant calls the bank again and says he has been in hardship for 8 months. He says he doesn‟t have any correspondence from the bank reflecti ng this, neither does the bank. 19 October 2018  The complainant calls the bank and the bank requests a detailed invoice about what funds will be used for  The bank contacts complainant and says he‟s owing $7,000 as “he took it from the account when he shouldn‟t have. ” 23 October 2018  The complainant provides the bank with satisfactory invoices and documentation  The complainant‟s progress claim is approved by the bank.  The bank talks to complainant and advises she will be sending a PDF he needs to sign to release funds to the builder. 24 October 2018  The bank processes final payment of $55,717.65 to builder. 6.2 Serviceability assessment Details Amount Recommendation | Case number: 549185 Page 9 of 10 Details Amount Monthly income Com one PAYG Busine ss Income Rent Total monthly income $4,689 $6,762 $3,170 $14,621 less monthl y expenses New loan - $666,500 New Loan - $812,000 Existing Credit Card - $10,000 Living expense s less Total monthly expense s $4,650 $5,661 $380 $2,917 $13,608 Surplus/(deficiency) $1,013 Explanation of the figures adopted in the serviceability assessment  Income: Income adopted via individual tax returns for the complainants for 2014. We have adopted the bank figures which is lower compared to the tax returns once the tax is deducted. Income adopted net $56,268 per annum or $4,689 a month  Business: We have adopted the bank figures as its lower. They have not taken deprecation amount of $10,687. For consistency purposes we have used the lower amount. We are assuming that the depreciation is for private usage of a car and that there is no debt against it  Rental income: We have adopted 6% rental income for the two properties  New loan ($666,499): We have adopted the bank figure of $4,650 per month which is calculated at 7.25%. This is 2.50% added onto the interest rate of 4.75% as per good industry practice to test servicing.  New loan ($812,000): We have adopted the bank figure of $5,661 per month which is calculated at 7.25%. This is 2.55% added onto the interest rate if 4.70$ ad per good industry practice to test servicing  Credit card: repayments have been calculated at 3.8% as per bank policy  Living expenses: We have adopted the bank living expenses of $2,917 per month, which we assume includes the $500 a month board expense. The bank living expenses are higher than HEM for March Quarter 2016 published 15 May 2016 and as such are preferred. For the calculation of living expenses, no business income has been taken. Recommendation | Case number: 549185 Page 10 of 10 6.3 Repayment arrangement If the complainant is experiencing financial difficulty, the following should apply within 14 days of both parties accepting this recommendation:  the complainant should provide details to the bank of his current financial position, together with a reasonable repayment arrangement acceptable to the bank for the repayment of the debt  if the bank requires more information to make its assessment, it should write to the complainant identifying the information required. The complainant should, in turn, co-operate with the bank‟s reasonable requests for information  the bank must consider the complainant‟s proposal, but is not obliged to accept it if the bank does not consider it to be reasonable. If a reasonable repayment arrangement is not agreed between the parties within 14 days of the complainant‟s proposal, or if the complainant does not provide any such proposal, the bank is entitled to rely on the terms and conditions of the loan including taking recovery action, once our file is closed.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.