Delay in valuation and settlement of commercial property loan
Summary
A company buying commercial property complained that the bank's valuation and document errors delayed settlement. AFCA found no unreasonable delay, although the bank made documentation errors that did not cause the delay, and ordered nothing.
Settlement was held up by the correct Transfer of Land document, not by the bank's errors, and customer service complaints are outside AFCA's jurisdiction.
Issues
- Delay primary · not upheld“The bank did not unreasonably delay obtaining the valuation, which was completed within the 10 working days it advised.”
- Administrative error secondary · upheld“I accept the bank made an error in not providing the guarantee document on 19 October 2018 and may have lost the statutory declaration.”
- Complaint handling failure secondary · not upheld“The bank responded to the complainant's complaint within the required time frame.”
Subjects and remedies
no remedy
Related
All Financial Firm (Unknown - Credit) determinations · Find similar determinations
Text of the determination
Determination | Case number: 548417 Page 1 of 6
Determination
Case number: 548417 25 March 2019
1 Determination overview
1.1 Complaint
The complainant company purchased a commercial property on 16 September 2018.
The company’s representative (complainant) says the financial firm (bank) caused the
company to make numerous changes to the sale contract to extend the time for
finance approval and settlement because the bank:
delayed obtaining the property valuation
did not provide all the documents for signing
lost one of the signed documents
did not provide satisfactory support.
Property settlement occurred on 1 November 2018. The complainant is seeking
compensation for the costs it incurred as a result of the delays.
1.2 Issues and key findings
Did the bank unreasonably delay obtaining the valuation?
The bank did not unreasonably delay obtaining the valuation. It completed the
valuation within the time frame of 10 working days it advised to the complainant.
Did the bank unreasonably delay the property settlement?
The bank did not unreasonably delay the property settlement. The bank made an
error in not sending one of the documents and may have los t another document.
However, this did not cause settlement to be delayed. Settlement occurred the day
after it received the correct Transfer of Land document.
Did the bank breach an obligation to the complainant in its complaint handling?
The bank responded to the complainant’s complaint within the required time frame.
The complainant was not happy with the bank’s response, but the bank is not
obligated to make an offer to resolve a complaint if it does not consider it has made
an error.
1.3 Determination
This determination is in favour of the bank.
Determination | Case number: 548417 Page 2 of 6
The bank is not required to take any further action.
Determination | Case number: 548417 Page 3 of 6
2 Reasons for determination
2.1 Did the bank unreasonably delay obtaining the valuation?
Bank ordered valuation
Once the bank had conditionally approved the loan on 4 October 2018, it ordered the
valuation. The valuation was scheduled for 10 October 2018. The bank notes show
the valuer had issues accessing the property so did not complete the valuation until
17 October 2018. The complainant disputes the bank’s valuer had difficul ty accessing
the property.
In any event, as discussed below, the valuation was completed within 10 business
days.
Valuation obtained within bank’s internal standard time
The bank has an internal service level requirement of 10 business days for the
valuation to be completed. The complainant executed and gave the valuation request
to the bank on 3 October 2018. The complainant says the bank advised that it
estimated the valuation would be completed within 10 business days.
The val uation was completed on 17 October 2018, which is within the bank’s service
level requirement and within the time it advised the complainant.
The complainant says 10 business days is not a reasonable time frame. However,
AFCA’s specialist banking adviser h as confirmed 10 business days is a reasonable
time frame for completion of a valuation.
Based on the above information, I am satisfied the bank did not unreasonably delay
obtaining the valuation.
2.2 Did the bank unreasonably delay the property settlement?
Bank sent documents to the complainant
The bank unconditionally approved the loan on 18 October 2018. It sent the loan and
security documents it required the company and its guarantors to complete the
following day. The complainant says the bank did not send a guarantee document for
one of the guarantors and lost a statutory declaration the complainant had returned.
The available information shows the bank sent the documents to the complainant on
19 October 2018 by post and email. It received the executed documents on 24
October 2018. The bank identified it had not received a guarantee document or
statutory declaration and advised the complainant’s broker. It also requested a copy
of the Transfer of Land from the complainant’s solicitor.
Determination | Case number: 548417 Page 4 of 6
The complainant’s broker provided soft copies of the guarantee and statutory
declaration to the bank on 25 October 2018 and originals of these documents on 26
October 2010.
I accept the bank made an error in not providing the guarantee document on 19
October 2018 and may have lost the statutory declaration. However, this did not
significantly delay the settlement because the bank was not able to settle until it had a
correct Transfer of Land document.
Settlement occurred once the bank received all necessary documents
The available information shows the bank requested the Transfer of Land (Transfer)
from the complainant’s solicitor on 24 October 2018. It received the Transfer that day
but it included incorrect information.
On 25 October 2018, the bank requested the complainant’s solicitor correct the
information. The bank received the Transfer on 26 October 2018, but it still included
incorrect information. The bank requested the complainant’s solicitor to include the
correct information.
The bank sent an email to the complainant’s solicitor on 30 October 2018 requesting
the Transfer with the correct information included. It sent an email to the
complainant’s broker on 31 October 2018 requesting the Transfer with the correct
information. The bank received the correct Transfer later that day and booked the
settlement for the next day. Settlement occurred on 1 November 2018.
I understand the complainant would have preferred the property settlement to have
occurred earlier. However, based on the available information I do not consider the
bank unreasonably delayed settlement. It could not settle until it had all the correct
documents including the Transfer of Land.
2.3 Did the bank breach an obligation to the complainant in its complaint
handling?
Bank responded to the complainant’s complaint
The complainant’s representative has requested compensation for non -financial loss
because the bank was not willing to resolve the complaint. He says the bank did not
contact it throughout the internal dispute resolution stage, did not offer to resolve the
dispute and did not address all the complainant’s concerns. He also says the ba nk
breached its obligations under ASIC Regulatory Guide 165 .
The complainant said in his complaint form that he did not lodge a complaint before
he lodged the company’s dispute with the Financial Ombudsman Service (FOS) on 15
October 2018. As part of the FOS process, the bank was required to provide a
response to the complainant by 29 November 2018. It did so.
Determination | Case number: 548417 Page 5 of 6
I understand the complainant is not satisfied that the bank did not resolve the dispute
to his satisfaction. He says the bank showed a clear unwillingness to commercially
resolve the dispute. However, the bank is not obliged to commercially resolve a
dispute or make an offer to resolve a dispute.
Determination | Case number: 548417 Page 6 of 6
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previously lodged with F inancial O mbudsman S ervice (FOS) .
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
applicant complainant
financial services provider financial firm
dispute complaint
claim claim
3.2 AFCA Approach
Customer service issues
The complainant says the support from bank staff was ‘horrendous’. It says no -one
took ownership of the matter when a staff member was away. AFCA is a dispute
resolution service. Our role is to consider specific types of disputes about financial
firms and we can award compensation for loss or damage caused by a financial firm’s
error. However, we do not have the power to consider disputes about the general
level of service provided by a financial firm.
Disputes relating to customer service are more appropriately dealt with by the
financial firm itself. This is because the level of customer service is influenced by the
financial firm ’s policy on issues such as staff levels and training.