Home / Financial Firm (Unknown - Insurer) / Determination 547498

Determination 547498

Temporary accommodation rate, contents storage limit and repair delays after storm damage

FirmFinancial Firm (Unknown - Insurer)
Decided2019-06-12
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$1,000
Amount claimed$42,000
SourceAFCA PDF

Summary

After storm damage, the complainant disputed the temporary accommodation rate, contents storage payments and repair delays. AFCA found the $750 weekly rate and the policy-limit storage payment fair, but ordered $1,000 compensation for an unusual delay before repairs began.

Temporary accommodation is payable at a rate equal to a similar-standard residence within the policy limit, and an unusual delay in starting repairs caused physical inconvenience warranting non-financial loss compensation.

Issues

Subjects and remedies

home or building damagenatural disasterpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination | Case number: 547498 Page 1 of 11 Determination Case number: 547498 10 May 2019 1 Determination overview 1.1 Complaint On 23 July 2018, the complainant lodged a claim under his policy with the financial firm (insurer) after his home sustained storm damage. The insurer accepted the claim. After negotiation, the parties agreed the insurer’s builder would undertake repairs. The complainant authorised the insurer’s bui lder to proceed with repairs on 1 November 2018. The disputed items relate to the complainant’s claim for temporary accommodation and contents storage. The complainant also complains about the repair delays. The case manager provided the parties with a recommendation on the issues in dispute. The recommendation was in favour of the insurer. As the recommendation was not accepted by the complainant, the complaint has been referred to me for determination. 1.2 Issues and key findings Is the insurer’s offer for temporary accommodation fair? The available material establishes the offer of $750 per week for temporary accommodation is fair because accommodation of a similar standard to the complainant’s property can be leased for a lesser weekly sum. The insurer is to pay to the complainant $750 per week for temporary accommodation (up to the policy limit) for the time it takes to repair the building to a liveable condition. Is the insurer’s required to pay anything further for storage of contents? The insurer is not required to pay anything further for storage of contents because the insurer has paid the policy limit of $10,000 which is 10% of the contents sum insured. Is the complainant entitled to compensation? While acknowledging the Christmas period and delays in obtaining Council building permits, there has been an unusual amount of time between when the insurer agreed to repair the property and commencing repairs. As this delay has caused an unusual amount of physical inconvenience which would interfere with complainant’s Determination | Case number: 547498 Page 2 of 11 expectation of enjoyment or peace of mind, the complainant is entitled to compensation. 1.3 Determination This determination is substantially in favour of the insurer. Should the complainant accept this determination, then within seven days of acceptance, the insurer is to pay to the complainant $1,000 compensation. Otherwise, the insurer is not required to take any further action. Determination | Case number: 547498 Page 3 of 11 2 Reasons for determination I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have considered all the material submitted by the parties, both before and after the recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues considered directly relevant to the outcome only. Submissions and material provided after recommendation After the recommendation was rejected, both parties made further submissions and provided further material. Where relevant, these submissions and material will be referred to in this determination. 2.1 Is the insurer’s offer for temporary accommodation fair? Policy covers temporary accommodation subject to policy limits The complainant must establish on the balance of probabilities he has suffered a loss caused by an event to which the policy responds. This is known as a prima facie claim. The insurer’s policy covers temporary accommodation if an insured event damages the building. It is not in dispute the storm event damaged the building to the extent the complainant could not live there. The insurer has agreed to pay for temporary accommodation costs for the time it will take to repair the building to a liveable condition. The complaint relates to the amount the insurer has agreed to pay. After engineer’s work, building was safe to live in until repairs made The claim was made on 23 July 2018. On 24 July 2018 the insurer arranged emergency accommodation for the complainant and his wife at a local motel. Thereafter, emergency accommodation was arranged at a local serviced two- bedroom apartment until 22 August 2018. Because of the structural integrity of the building following the incident, the local council issued an emergency order which required the complainant to arrange a structural engineer to attend to have safety works completed. The complainant engaged a structural engineer. The available material shows the complainant made all necessary arrangements with the engineer which included the make safe and that he was reimbursed by the insurer in the sum of $16,478.55. Determination | Case number: 547498 Page 4 of 11 The complainant indicated on the number of occasions he was concerned the property was not safe to live in because of the local council’s emergency order. The order says the structural engineer is to carry out an inspection once the safety works were completed and advise the council that the building will be suitable to occupy for the next 60 days and/or until rectification buildi ng works have been carried out and completed in accordance with the building permit. I have reviewed the engineer’s report. The engineer said it was possible to have temporary props to support the roof trusses until repairs were made. In the circumstances, on the available material, I am satisfied the building was safe to live in until repairs were made. Complaint relates to the amount paid for temporary accommodation The complainant resumed living in the property until the parties agreed the claim would not be settled by way of a cash settlement, but the insurer would undertake repairs. This agreement was reached on 1 November 2018. Thereafter, after Council permits were obtained, the repairs commenced and were to be completed on 2 April 2019. The insurer paid to the complainant $750 per week for temporary accommodation from 1 November 2018 and will continue to make the payment for the time it will take to repair the building to a liveable condition. The available material shows $750 per week has been paid up to and including 4 April 2019. The complaint relates to the amount paid. Initially the insurer offered to pay $450 per week which it said represented the average rental cost in the area for a home like the complainant’s home. The complainant seeks $508 per night. He says as it is difficult to obtain a short-term lease in his area, he should be paid for the serviced apartment/motel rate. He also says his claim is justified because of his personal circumstances, his lifestyle activities, his wife was pregnant, his family does not live close by and the amount offered will not allow him to rent a home like his own home. He also contends he is entitled to 10% of the sum insured which is $42,000. The most insurer is required to pay is $42,000 The insurer’s policy terms are set out in supporting section 3 of this determination. The policy provides it will pay for reasonable temporary accommodation costs for the time it takes to repair the building to a liveable condition. The most the insurer will pay is up to 4 weeks in short-term accommodation and up to another 48 weeks in residential accommodation of a similar standard to the complainant’s home. Determination | Case number: 547498 Page 5 of 11 The complainant did not opt to take complete replacement cover. Therefore, the most the insurer will pay for any one event is 10% of the building sum insured. The certificate of insurance shows the building sum insured is $420,000. Therefore, the most the insurer is required to pay for temporary accommodation because of the storm event is $42,000. Insurer not obliged to anything further for short-term accommodation The insurer paid for short-term accommodation until 2 August 2018. It had arranged to pay short- term accommodation until 22 August 2018. However, the complainant’s wife was unwell and did not want to stay in the short-term accommodation any longer. As set out above, I am satisfied the available information indicates the house was safe t o live in once the complainant’s engineer’s make safe work was completed until repairs commenced. The insurer is not obliged to pay temporary accommodation costs if the complainant does not need to pay for temporary accommodation costs. I am satisfied the insurer is not obliged to pay anything further for short-term accommodation. $750 per week for temporary accommodation is fair Once repairs commenced, the photographs show the property was not in a liveable condition. The available information establishes the insurer has paid $750 per week from 1 November 2018 until 4 April 2019 while repairs were undertaken. The insurer is only required to pay for residential accommodation of a similar standard to the complainant’s home. From the available info rmation, I am satisfied a home of a similar standard to the complainant’s home could be rented for $400 -450 per week. While I acknowledge it may be difficult to obtain a short-term lease in the complainant’s area, I do not accept the insurer is required t o pay the serviced apartment/motel rate. As homes like the complainant’s home can be rented for around $450 per week, I am satisfied the offer to pay $750 per week for temporary accommodation is fair in the circumstances. The insurer is not obliged to pay anything further than $750 per week for the time it will take to repair the building to a liveable condition up to the policy limit of $42,000. Determination | Case number: 547498 Page 6 of 11 2.2 Is the insurer’s required to pay anything further for storage of contents? Policy limit is $10,000 The available material establishes the insurer has made three separate payments to the complainant totalling $10,000 for packing costs, removalist’s costs and contents storage costs. The complainant says he is paying $1,800 monthly to store contents. He was prepared to compromise this claim and requested payment of $900 per month for storage costs. The relevant policy terms are set out in supporting section 3 of this determination. The insurer agrees undamaged contents cannot be kept at the insured address. The policy says the insurer will pay the reasonable costs to store the undamaged contents until the contents can be kept at the insured address. However, the policy also says the most the insurer will pay for the storage of undamaged contents is 10% of the contents sum insured. The certificate of insurance shows the contents sum insured is $100,000. 10% of $100,000 is $10,000. It is not known where the complainant is storing his undamaged contents. The complainant has provided no documentation to substantiate his claim he is paying $1,800 per month for storage fees. The only material provided was an undated letter indicating the complainant was paying $300 cash per month for storage. In any event, as the insurer has paid to the complainant the maximum policy allowance of $10,000, I am satisfied it is not obliged to pay anything further to the complainant for storage of undamaged contents. 2.3 Is the complainant entitled to compensation? Compensation paid in some circumstances The complainant made several complaints about the insurer’s claims handling including the failure to provide certain information, failure to respond in a timely fashion and delays. The insurer says it has properly managed the claim and provided options to the complainant which exceed its liability under the policy. The Rules allow the payment of compensation (capped at $3,000) for non-financial loss. We may decide an insurer should compensate a complainant for such loss only where there has been an unusual amount of physical inconvenience, time taken to resolve a situation, or interference with the complainant’s expectation of enjoyment or peace of mind. Determination | Case number: 547498 Page 7 of 11 After the recommendation, the complainant advised the fortnightly payment for temporary accommodation was not paid over the Christmas period. The complainant said he originally asked for a lump sum. However, this is not feasible in circumstances where the total amount payable is not certain. The insurer apologised the temporary accommodation payment was not issued while the claims manager was away over the Christmas period. The missed payment and a further payment were issued upon notification and received in the normal time frame. The complainant also complains he did not receive a second builder’s quotation. However, as the insurer is completing repairs this is no longer relevant. The claim was made on 23 July 2018. After the local council mandated certain arrangements, the complainant engaged his own engineer to attend to the council requirements. The insurer’s agent completed the remaining make safe arrangements and the property was structurally sound and able to be lived in by 1 August 2018. By mid-August 2018, a scope of works was prepared. By the end of August 2018, the insurer had received quotations to repair the storm damage. The insurer made an offer to cash settle the claim in early October 2018. However, the parties were unable to agree on the extent of the scope of works or the repair costs. In early November 2018 the parties agreed the insurer would carry out repairs rather than cash settle the claim. The builder had to obtain a building permit from the local council. The repairs were to start late February 2019 and finish on 22 March 2019. After the recommendation, the revised program from the builder indicated the work was to start on 4 March 2019 and be completed on 2 April 2019. The insurer also provided claim file notes after the recommendation. The notes indicate an issue with the box gutter which required further assessment. Fair in the circumstances the insurer pays the complainant $1,000 We take a conservative approach to compensation for non-financial loss. The storm damage to this home was significant. This kind of damage and the ensuing insurance claim are often stressful. I acknowledge the claim has caused the complainant upset and inconvenience particularly in circumstances where the complainant’s wife was pregnant. Generally, I consider the insurer has acted reasonably in its claims management. Determination | Case number: 547498 Page 8 of 11 While I acknowledge the Christmas period and delays in obtaining Council building permits, I consider there has been an unusual amount of time between when the insurer agreed to repair the property and commencing repairs. I consider this delay has caused an unusual amount of physical inconvenience which would interfere with com plainant’s expectation of enjoyment or peace of mind. For this reason, I am satisfied it is fair the insurer pays the complainant $1,000 compensation. Determination | Case number: 547498 Page 9 of 11 3 Supporting information 3.1 The determination is made under FOS Terms of Reference The Australian Financial Complaints Authority ( AFCA) has commenced managing disputes previously lodged with F inancial O mbudsman S ervice (FOS) . This determination is made under FOS Terms of Reference but has adopted the following terminology for consistency with AFCA. In this determination the AFCA terms have the same meaning as the FOS terms defined in paragraph 20.1 and Schedule 1, 2 & 3 of the FOS Terms of Reference. FOS definitions AFCA term applicant complainant financial services provider financial firm di spute complaint claim claim Terms of Reference Rules 3.2 Relevant policy extracts The relevant policy extracts are referred to in correspondence between the parties and in the insurer’s notice of response dated 30 October 2018. Both the policy document and the rotice have been exchanged with the complainant. Home building product di sclosure statement Temporary accommodation We cover When an ins ured event damages the building to the extent you cannot live there, and we agree, we will pay for your reas onable temporary accommodation costs for the time it will take to repair or rebuild the building to a liveable condition. The most we will pay is: • up to 4 weeks in short term accommodation agreed to by us (e.g. standard rates for a hot el, motel or serviced apartment), then if necessary; • up to another 48 weeks in residential accommodation of a similar standard to the building. We will also pay the reasonable and necessary costs for: • redirection of mail from the insured address for up to 52 weeks; • utility connection costs at the temporary accommodation residence; • assistance with bond payment if required, however any amount we pay in bond is recoverable from you by us. We may deduct this amount from any amount payable to you. Limit Determination | Case number: 547498 Page 10 of 11 The most we will pay for any one event is 10% of the building sum insured, unle ss your certificate of insurance shows that you have Complet e Replacement Cover® option (see page 31), in which case we pay the reasonable and necessary costs. We do not cover • temporary accommodation costs: –– if damage to the contents is the reason why you cannot live there; –– if you do not intend to repair or rebuild the building; –– if before the loss or damage occurred, you had planned to demolish the building; –– if you do not need to pay for temporary accommodation; –– if the building was not your principal place of residence at the time of the loss or damage; –– if you had not intended to be living at the building during the repair period (had the building not been damaged); –– beyond the period it should reasonably take to replace or repair the building so you can live there again. • any costs related to any business activity operated at the building. Home contents product di sclosure statement Storage of undamaged contents We cover If you make a claim for loss or damage to your contents due to an insured event and we agree that the undamaged contents cannot be kept at the insured address, we will also pay the reasonable costs to store the undamaged contents until your contents can be kept at the insured address. The most we will pay for the storage of undamaged contents is 10% of the contents sum insured. Note: We will pay for any loss or damage to the undamaged contents caused by an insured event while they are at the place of storage but only up to the contents sum insured shown on your certificate of insurance (less any amount paid for loss or damage to your c ontents as part of the original claim). This cover stops when your policy is cancelled or lapses or we stop paying for storage, whichever happens first. All the conditions, limits and exclusions of this policy apply to this cover. We do not cover • stora ge costs following loss or damage or loss or damage in storage caused by flood if you do not have cover for insured event ‘Flood’; • storage costs once we decide your contents can be returned to the insured address; • storage costs outside of Australia; • loss or damage that is excluded by this policy; • if your temporary accommodation is the plac e of storage. 3.3 Other relevant material considered and relied on  p arties’ submissions, emails , invoices, and photographs and all attachments to all submissions both before and after the recommendation  certificate of insurance  insurer’s claim file notes  material from local council  material from complain ant’s engineer Determination | Case number: 547498 Page 11 of 11  mater ial from the insurer’s builder  correspondence between the parties.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.