Text of the determination
Determination | Case number: 546937 Page 1 of 10
Determination
Case number: 546937 15 August 2019
1 Determination overview
1.1 Complaint
The complainants obtained a loan from the financial firm (lender) to purchase a
property (home loan) and a construction loan for $895,000 (construction loan) to
construct two duplexes on the property.
The complainants say the lender delayed five months in assessing the construction
loan application.
The AFCA case manager gave the parties a recommendation on the issues in dispute
on 28 March 2019. The recommendation was in the complainants’ favour. The
complainants rejected the recommendation for the reasons detailed at section 2.1
below. A copy of the recommendation is attached to this determination.
1.2 Issues and key findings
Were the findings of the recommendation correct?
The findings in the recommendation were correct and are adopted in this
determination, save for the amount of compensation awarded .
Did the lender unreasonably delay approval of the construction loan?
The construction loan was approved in accordance with good industry practice for the
reasons detailed in section 2.2 below. Nevertheless, the lender made several errors
during the loan application process which caused the complainants non-financial loss.
Do the complainants’ further submissions change the outcome?
The complainants provided further submissions which I have considered. They do not
change the outcome for the reasons set out in section 2.3 below, except I have
increased the compensation awarded for stress and inconvenience .
1.3 Determination
This determination is in the complainants’ favour. I agree with the case manager’s
reasons for the recommendation. However, I consider $10,000 to be adequate and
Determination | Case number: 546937 Page 2 of 10
appropriate compensation for the considerable stress and inconvenience the lender’s
many errors caused the complainants ($5,000 each).
Within 14 days of the complainants’ acceptance of this determina tion, the lender
should apply $10,0 00 compensation for the complainants’ non -financial loss to pay
down the complainants’ highest interest -bearing loan.
Determination | Case number: 546937 Page 3 of 10
2 Reasons for determination
2.1 Were the findings in the recommendation correct?
I have decided this case on its merits, having regard to the relevant law, good industry
practice, codes of practice and previous AFCA decisions. I have taken into account
material submitted by the parties, both before and after the recommendation. I am
satisfied that the documents I have relied on have been provided to both parties.
I am satisfied that the case manager’s recommendation contains an accurate
summary of the complaint, the issues to be determined, any applicable paragraphs of
the Rules and any relevant law.
The complainants rejected the recommendation
The complainants rejected the recommendation because they say the lender misled
them to believe the construction loan would be approved faster than it was. They say
they incurred a financial loss in reliance on the lender’s misrepresentation , by not
taking up other options available to them.
The complainants also say that after the recommendation was issued, the lender:
introduced a new condition requiring the property be subdivided before it wi ll
release the final progress payment to the builder (new condition)
fixed the home loan for a further two years without authority.
2.2 Did the lender unreasonably delay approval of the construction loan?
The complainants say the lender delayed the construction loan approval
The complainants say the lender delayed the construction loan approval by five
months, from February 2018 (when they first applied) to July 2018 (when the lender
approved the construction loan).
This is because they say the lender:
did not ask them to provide all the documents it required to assess the application
at once
made several errors during the loan application process (as detailed in the
recommendation).
As a result, the complainants say they incurred the following loss:
interest on the home loan from February to July 2018 while the property sat vacant
awaiting the lender’s construction loan ap proval (home loan interest)
a 6% price increase on building materials from 1 April 2018 (price increase).
Determination | Case number: 546937 Page 4 of 10
The complainants want $30,000 compensation for their financial and non-financial
loss.
The lender should keep the customer informed of its requirements
There is no general obligation on a financial firm to ask for all the documents it
requires to assess a loan application by a certain time. In accordance with good
industry practice, a diligent and prudent banker would inform its customer of the
financial firm’s application process at the ir initial interview. Once the loan purpose is
understood, the banker would then explain what documents would be required from
the customer.
During the assessment process, a diligent and prudent banker should keep the
customer informed of any changes or further requirements and follow up with t he
customer and decision maker. Any proposed variations to the building will generally
require the financial firm’s approval. Depending on the variation and costs, the
financial firm may require:
another affordability assessment
another valuation of the security property
the cost to be met from the customer’s own fun ds
changes to the loan agreement (such as interest rate or repayments)
other information or requirements at its discretion.
Therefore, the fact that the lender made changes and required further information
from the complainants does not mean the lender unreasonably delayed in the loan
approval process.
The lender has a two-stage assessment process which is not unreasonable
The lender says it has a two-stage process for assessing residential construction
loans. It requires affordability documentation first and once it is satisfied the applicant
can afford the loan, it then requires building specifications and tenders.
The requirement of a two-stage assessment is not unreasonable, because:
The first stage is to assess affordability and establish the maximum the customer
can afford to borrow. At this stage, the financial firm requests financial information
from the customer regarding income, expenses, assets and liabilities. On
completion of the first stage, the lender knows the maximum loan amount it will
lend, subject to the outcomes of the second stage.
The second stage is to determine the construction costs and security value. The
value of the security on completion of construction will formalise the maximum
amount the bank will lend. At this stage the lender requests documents confirming
approval of the build and firm costs.
Determination | Case number: 546937 Page 5 of 10
Therefore, the fact that the lender did not ask for building specifications and tenders
when the complainant first applied for the construction loan in February 2018 is not
unreasonable.
It cannot be determined if the lender’s errors caused a delay in loan approval
The lender made some errors in the handling of the assessment which were detailed
in the recommendation. However, these errors contributed to the complainants’ stress
and inconvenience rather than a delay in loan approval.
While the construction loan could have potentially been approved about two weeks
earlier, the timeframe for loan approval is dependent on the circumstances. In this
case, the circumstances surrounding the loan approval are not straight forward.
This is because the loan approval process was complicated by the way the
complainants provided the costings to the lender. Rather than providing just a building
contract on 3 April 2018, the complainants provided several different tenders and
quotations which would normally form part of the building contract. Further, one of the
quotations was not prepared until 3 April 2018, and the architectural plans were
prepared on 27 March 2018. The complainants then made changes to the
construction costs on 3 May 2018 when they submitted additional quotations for the
easement works, engineered flooring and storm water plumbing.
For these reasons, I cannot be satisfied with any certainty as to exactly when the
construction loan could have been approved, or by how many days the lender’s errors
may have delayed approval.
In any event:
the lender did not delay the loan approval process by the five months claimed by
the complainants. If anything, any delay would have been closer to a couple of
weeks at most (if that)
the complainants’ loss has not crystalised because the duplexes have not yet been
sold.
The lender’s errors caused considerable stress and inconvenience
As detailed above, I am not satisfied the lender’s errors caused a delay in the loan
approval. Rather, the lender’s errors contributed to the complainants’ stress and
inconvenience during the loan approval process.
The errors included:
incorrectly telling the complainants their proposed schedule of payments (payment
schedule) was fine when it did not comply with the lender’s policy. Given the
lender’s two tier assessment process and everything else that was still being
finalised at the time (see above), this did not significantly delay the loan approval
Determination | Case number: 546937 Page 6 of 10
process. It would have taken the same amount of time to amend the payment
schedule in any event. Rather, this caused the complainants stress and
inconvenience when they were notified seven weeks later that the payment
schedule needed to be amended
issuing the unconditional loan offer with a typographical error which took the lender
a week to amend. While this could have been amended in one business day rather
than four business days, this is not a material delay, but did exacerbate the
complainants’ stress and inconvenience
not clearly communicating its requirements of the draw down. When the lender
realised the progress payments were outside its guidelines it required the
complainants to make a nominal payment of $261.50 using their own funds. The
lender should have considered going outside its guidelines because of the small
amount involved, and because the error occurred due to the bank's failure to check
the payment schedule. This did not cause a delay in the loan approval, but rather
contributed to the complainants’ stress and inconvenience.
The recommendation did not adequately compensate for non-financial loss
The complainants say the $6,000 non-financial loss compensation awarded in the
recommendation does not adequately compensate for their time spent and stress
incurred in resolving the complaint.
As detailed in the recommendation AFCA does not award compensation for a
complainant’s time spent resolving a complaint or rectifying a financial firm’s error.
However, given the number of errors the lender made, and the cumulative effect of
the errors on the complainants’ peace of mind , I consider a higher award of
compensation for non-financial loss is appropriate. I consider $10,000 ($5,000 each)
adequately compensates the complainants for the stress and inconvenience they bot h
incurred because of the lender’s actions in:
incorrectly telling them on four occasions that their loan approval would be
received within 24 hours or a week ($500 per occasion = $2,000 each)
issuing the unconditional loan offer for the wrong amount, causing the
complainants to reschedule a solicitor’s appointment and wait four business days
for it to be amended ($500 each)
taking seven weeks to notify the complainants’ the proposed payment sche dule
had to be amended ($2,000 each)
not clearly communicating its requirements for the draw down and requiring the
complainants to make a payment of $261.50 to the builder from their own funds
($500 each).
Determination | Case number: 546937 Page 7 of 10
2.3 Do the complainants’ further submissions change the outcome?
The complainants say they were misled about the loan approval timeframe
Broadly, to succeed in a claim for misleading or deceptive conduct relating to a
financial product or service, the complainant must be able to show that:
the financial firm made a statement or engaged in conduct that was false or
misleading (misrepresentation);
the complainant relied on the misrepresentation to their detriment; and
the complainant suffered a loss as a result of the misrepresentation.
In rejecting the recommendation, the complainants say the lender misled them about
the time it would take for the construction loan to be approved (misrepresentation). In
reli ance on the lender’s misrepresentation, they waited for the lender’s construction
loan approval rather than taking one of the following options available to them:
sell the property in about March 2018 with the Development Application (DA) plans
(option 1); or
approach another financial firm to obtain the construction loan (option 2).
In not taking up option 1 or option 2, the complainants say they incurred the home
loan interest and price increase, which they would not have incurred otherwise.
For these reasons, the complainants want compensation for the home loan interest
and price increase.
The lender misrepresented when it would provide loan approval
As detailed in the recommendation, the lender incorrectly represented on 9 March, 26
March, 10 May, and 14 May 2018 that the construction loan would be approved within
a week or 24 hours (misrepresentations).
The lender provided conditional approval on 23 April 2018 and unconditional approval
(for the correct amount of $895,000) on 17 May 2018.
Therefore, I am satisfied the lender misrepresented when it would provide
construction loan approval to the complainants on four occasions.
On balance, the complainants did not rely on the misrepresentations
The complainants say:
they relied on the misrepresentations to await the lender’s appr oval of the
construction loan
but for their reliance on the lender’s misrepresentations , they would have taken
either option 1 or option 2.
Determination | Case number: 546937 Page 8 of 10
On balance, I am not satisfied the complainants relied on the lender’s
misrepresentations to await loan approval from the lender. This is because option one
was not their preferred option and they were taking active steps to pursue option 2
during the construction loan approval process despite the lender’s
misrepresentations. This is based on the following:
The complainants provided a letter from a real estate agent in which he says the
complainants enquired about selling the property with DA plans in March 2018.
The agent says the complainants declined an offe r to purchase the property at the
time, because they said their intention was to build on the property and they were
waiting to see if they could obtain finance. This shows the complainants preferred
option was to obtain a construction loan and build on the property. Option 1 was
the complainants’ backup option in the event they were declined finance.
Ultimately, the lender approved the construction loan, so the complainants did not
proceed with option 1.
The complainants emailed the lender on 9 April 2018 stating they would proceed
with option 2 if the lender did not give them an outcome by close of business.
Specifically, they stated they would withdraw their application because they
obtained pre-approval with another broker. This shows the complainants were
approaching other financial firms to pursue o ption 2 despite the lender’s
misrepresentations as at 9 April 2018.
After 9 April 2018, there is no record of any communication from the lender until 23
April 2018 when it provided conditional approval. Given the complainants had
already obtained pre-approval with another financial firm, I am not satisfied the
lender’s silence misled the complainants into waiting for the lender’s loan app roval.
The complainants could have proceeded with option 2 after the lender failed to
respond to their email of 9 April 2018, but they did not.
For these reasons, I am satisfied that the complainants did not rely on the lender’s
misrepresentations because option one was not their preferred option in any event
and they were taking active steps to pursue option 2 at the time the
misrepresentations were made.
The complainants have not shown the new condition caused them loss
The complainants say the lender has introduced a new condition to the construction
loan, requiring them to provide a subdivision certificate before it will release the final
progress payment to the builder.
However, the council plans state the council will not issue a subdivision certificate
without receiving the final occupation certificate from the builder. In turn, the builder
will not issue the final occupation certificate before he receives the final payment from
the lender.
Determination | Case number: 546937 Page 9 of 10
As a result, the complainants say they had to borrow funds at a higher interest rate to
make the final payment to the builder. However, the complainants have declined to
provide documentation to substantiate the loss they incurred (such as a loan
contract), because they say the effort involved in doing so outweighs the loss
incurred. For this reason, the complainants have elected not to pursue any loss
stemming from this claim.
Without substantiating their claim for loss, I cannot award the complainants any
compensation even if I were satisfied that the lender introduced a new condition
contrary to the terms of the construction loan.
The lender did not fix the home loan for two years
In rejecting the recommendation, the complainants say the lender fixed the home loan
for two years without their authority in February 2019. The complainants provided a
letter from the lender dated 20 February 2019 (February letter) to this effect.
The complainants also provided a letter from the lender dated 4 April 2019, in which
the lender explains that the February letter was system generated in error and can be
disregarded. The lender confirmed the home loan was originally on a 24 month fixed
term from 12 June 2018 to 11 June 2020.
I am satisfied the lender simply issued the February letter in error and did not fix the
home loan without the complainants’ authority. The complainants are not entitled to
compensation for this.
Determination | Case number: 546937 Page 10 of 10
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previously lodged with Financial Ombudsman Service (FOS).
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
applicant complainant
financial services provider financial firm
dispute complaint
Recommendation | Case number: 546937 Page 1 of 10
Recommendation
Case number: 546937 26 March 2019
4 Overview
4.1 Complaint
The complainants obtained with the financial firm (lender) a loan to purchase a
property (home loan) and a construction loan for $895,000 (construction loan) to
construct two duplexes on the property.
The complainants say the lender delayed five months in assessing the construction
loan application, because:
the lender did not ask them to provide all the documentation it needed to assess
the application at once,
the lender was understaffed, and
the lender’s credit officers made a number of errors.
4.2 Issues and key findings
Did the lender unreasonably delay approval of the construction loan?
A financial firm is not obliged to approve a loan or request information within a certain
timeframe. The lender provided conditional and unconditional approval within 15 days
of receiving all the information it required. This was in accordance with the general
industry expectation. Nevertheless, the lender was understaffed and made a number
of errors during the loan approval process. It also failed to appropriately communicate
how long the loan approval process would take.
What is an appropriate outcome to this complaint?
The complainants incurred stress and i nconvenience due to the lender’s errors and its
failure to appropriately communicate how long the approval process would take.
Therefore, the lender should compensate the complainants $3,000 each for their
stress and inconvenience. The complainants have not established their claim for
financial loss, because they were always liable to pay interest on the home loan
irrespective of the lender’s actions regarding the construction loan. Going forward, the
lender is not obliged to release any progress payments which do not comply with
section 6 of the terms and conditions applicable to the construction loan.
Recommendation | Case number: 546937 Page 2 of 10
4.3 Recommendation
This recommendation is in favour of the complainants. If all parties accept this
recommendation, then within a further 14 days, the lender should compensate the
complainants for their stress and inconvenience by paying $6,000 into an account
nominated by the complainants with their acceptance of the recommendation.
Recommendation | Case number: 546937 Page 3 of 10
5 Reasons for recommendation
5.1 Did the lender unreasonably delay approval of the construction loan?
The complainants say the lender delayed approving the construction loan
The complainants say the lender delayed in assessing the construction loan
application which set construction of the duplexes back by five months. Specifically,
the complainants say:
They were ready to proceed in February 2018 and were relying on the lender to tell
them what documents it needed to assess the application.
The lender would only tell them what documents it needed one by one, instead of
asking for it all at once.
The credit team was understaffed which caused delays in its assessment of the
documents. The staff also did not check documents properly so they would ask
them to re-submit documents with amendments at a later stage.
The lender gave unconditional approval for the wrong amount (being $845,000
instead of $895,000) due to a typographical error by its credit assessor.
The lender took out its fees from the construction loan, which meant the
complainants had to make further payments to the builder using their own money.
Generally, a lender is not obliged to offer credit within a certain timeframe
As a general rule, the relationship of lender and customer is one of contract. The
decision to make a loan offer is a commercial one solely at the financial firm ’s
discretion, and subject to its credit risk assessment criteria.
Applying for a loan does not create an obligation on a financial firm to approve the
loan or meet a specific time frame within which to make the loan funds available.
There is also no general obligation on a lender to request the information it requires to
assess an application within a certain timeframe. The time the lender takes to request
documents relates to its levels of customer service, which AFCA does not have the
power to consider (detailed in section 3.1 below).
Generally, it is expected a lender will assess a loan application within 10 to 15
business days from when it receives all the information it requires to complete its
assessment. This is provided there are no intervening factors.
The lender assessed the loan application within the expected timeframe
The parties provided the email correspondence between themselves from 12
December 2017 to 28 June 2018, which detail the timeline of the loan application
process.
Recommendation | Case number: 546937 Page 4 of 10
The emails show the lender provided conditional and unconditional approval within
the general industry expected timeframe. This is because the lender provided:
conditional approval on 23 April 2018. This was 14 business days after the
complainants provided the remaining i nformation the lender required (being
building specifications and tenders) on 3 April 2018. The conditional approval
stated any variation to the documents would require the lender’s approval
unconditional approval (for $895,000) on 17 May 2018. This was 10 business days
after the complainants made changes to the construction costs (by submitting
additional quotations for the easement works, engineered flooring, and storm water
plumbing) on 3 May 2018.
The complainants say they made changes to the constructions costs because the
lender initially told them it would only approve a certain amount. When it later
increased the amount it would approve, the complainants say they ‘added some
additional costs’. Irrespective of why, the lender is not responsible for t he
complainants’ decision to amend the construction costs. The time taken to amend the
construction loan approval was reasonable in these circumstances.
Nevertheless, the lender failed in its communication with the complainants
Notwithstanding the above, a financial firm should appropriately communicate with its
customers to ensure they do not hold unrealistic expectations as to how soon the
application may be assessed.
The emails show the lender appropriately told the complainants on 9 March 2018 that
its credit team was behind in its workload when the complainants asked for an
update. The fact that the lender was understaffed appears to have impacted on the
processing of the loan application.
However, the lender subsequently failed to manage the complainants ’ expectations
about the time it would take to assess the application (detailed in section 3.2 below). It
incorrectly told the complainants on four occasions (between March to May 2018) that
loan approval would be provided within 24 hours or a week, when this was not the
case. This encouraged the complainants to wait for the lender’s assessment, and
exacerbated their stress and inconvenience in the process.
The lender also made errors during the loan application process
In addition to failing to communicate how long it would take to assess the application,
the lender also made a number of errors during the loan approval process. These
errors further exacerbated the complainants’ stress and inconvenience, and are
detailed in section 3.1 below.
In summary, the lender:
Recommendation | Case number: 546937 Page 5 of 10
incorrectly told the complainants their proposed schedule of payments (payment
schedule) was fine, even though it did not comply with the lender’s policy,
took seven weeks to notify the complainants that the payment schedule did not
comply with its policy,
issued an unconditional loan offer for the wrong amount, which it took a week to
amend, and
made an error in the valuation which resulted in a shortfall that the complainants
had to cover using their own funds.
5.2 What is an appropriate outcome to this complaint?
The lender should compensate the complainants $6,000 for non-financial loss
I am satisfied that the lender’s errors caused the complainants an undue amount of
stress and inconvenience for which they should be compensated.
Having regard to our approach to non-financial loss and compensation caps (as
detailed in section 3.3 below), the lender should compensate the complainants $3,000
each in non-financial loss. This is because the complainants incurred stress and
inconvenience:
that was exacerbated on each occasion they were told loan approval would be
received within 24 hours and it did not eventuate
in having to wait a further week for the unconditional loan offer to be amended
when it was issued for the wrong amount. The complainants’ stress and
inconvenience was further exacerbated because they had to change a solicitor’s
appoin tment they had booked for 16 May 2018 at the lender’s instruction
in contacting the builder to obtain his consent to change the payment schedule,
because the lender failed to tell them their proposed payment schedule did not
comply with its policy
in having to pay the builder $261.50 from their own funds because of the valuation
error and resulting shortfall.
For these reasons, I am satisfied the complainants incurred undue stress and
inconvenience as a result of the lender’s errors, for which they should be
compensated $6,000.
The complainants have not established their claim for financial loss
The complainants say their financial loss is the five months of interest they paid on
the home loan while the property sat vacant awaiting construction to commence.
For the complainants’ financial loss claim to be successful, they must establish that
but for the lender’s errors on the construction loan, they would not have been liable
for the interest on the home loan. Even if the lender had processed the construction
Recommendation | Case number: 546937 Page 6 of 10
loan application without any errors, the complainants were always liable for the
interest on the home loan. For this reason, they cannot claim the interest on the home
loan as their financial loss for the errors relating to the construction loan.
The complainants also provided emails between themselves and the builder dated 29
March 2018, in which the builder says there will be a 6% rise in brick prices effective 1
April 2018. The builder gave the complainants until 3 April 2018 to place the order so
it holds the quantity and selection for the complainants ’ construction job. The
complainants have not provided any subsequent emails or invoices from the builder
showing exactly how much (if at all) they were charged extra. Therefore, even if the
lender was required to approve the construction loan within a certain timeframe
(which it was not), the complainants have not established how much extra they were
charged.
AFCA asked the complainants on 30 January 2019 to provide their supporting
documents for any financial loss they wished to claim. The complainants have not
provided documentation to show what other financial loss (if any) they incurred as a
result of the lender’s error with respect to the construction loan.
Progress payments must be released in line with the terms and conditions
The complainants have also raised concerns that the lender has placed the
construction loan ‘on hold’, but have not detailed why. The lender says the
complainants requested a variation in the construction contract and the release of
additional funds.
Section 6 of the terms and conditions applicable to the construction loan details how
the lender will lend funds for the construction loan (that is, how it will release progress
payments).
The lender says:
Any variation in the co nstruction contract is subject to the lender’s approval. It must
be satisfied that any variations will not diminish the overall value of the security.
This will require an inspection of the property to verify the effect of the changes on
the security value. In order to reimburse the complainants about $46,192 (for
existing payments they have made), it requires an additional inspection to
ascertain the effect of the changes compared to the initial specifications. The
lender is entitled to take this position in accordance with sections 6.7 and 6.19 of
the terms and conditions applicable to the construction loan.
It will not release funds to a borrower which have been designated for the payment
of invoices to a builder. It can consider a request to pay a particular invoice upon
presentment to the lender, together with a Progress Payment Request form. The
lender is entitled to take this position in accordance with sections 6.4 and 6.10 of
the terms and conditions applicable to the construction loan.
Recommendation | Case number: 546937 Page 7 of 10
The lender is not obliged to release any progress payments which do not comply with
the requirements under section 6 of the terms and conditions applicable to the
construction loan.
Recommendation | Case number: 546937 Page 8 of 10
6 Supporting information
6.1 AFCA cannot consider complaints about customer service
AFCA does not have the power to consider complaints about the general level of
service provided by a financial firm. This is because complaints relating to customer
service are more appropriately dealt with by the financial firm itself, as the level of
customer se rvice is influenced by the financial firm’s policy on a number of issues
such as staff levels and training.
For this reason, AFCA cannot consider the time the lender took to:
ask the complainants to provide certain documents, or
allocate a credit assessor to review the application.
This is because delays of this nature relate to the lender’s levels of customer service,
and do not breach any specific obligation owed to the complainants.
6.2 Details of the email correspondence from December 2017 to June 2018
Details of the lender’s failure to manage the complainants’ expectations
On 9 March 2018, the lender incorrectly said the loan application ‘should be
approved sometime next week’, in response to the complainant s asking about the
likelihood of approval. However, the subsequent week the lender asked for more
documentation to support the application.
On 26 March 2018, the lender incorrectly told the complainants it should have a
lending decision within 24 hours, in response to the complainants ’ request for a
progress update. However, at this stage it did not yet have the building
specifications or the tenders it required to complete its assessment.
On 10 May 2018, the lender incorrectly told the complainants it should have the
loan application formally approved by close of business. It then sent a follow up
email saying it cannot reach the senior assessor, but the loan application will
‘definitely’ be formally approved by tomorrow (11 May 2018). While it issued
unconditional approval on 11 May 2018, it was for the wrong amount due to a
typographical error.
On 14 May 2018, the lender incorrectly told the complainants that approval of the
full $895,000 was coming through that day. The loan approval did not come
through and the complainants had to reschedule the solicitor’s appointment they
had booked for 16 May 2018 (at the lender’s instruction on 10 May 2018).
Recommendation | Case number: 546937 Page 9 of 10
Details of the lender’s errors during the loan application process
On 2 May 2018, the complainants submitted their proposed schedule of payment.
The lender incorrectly told them it was ‘fine’ even though it did not comply with the
lender’s policy (unbeknownst to the complainants). The lender then took seven
weeks (being 20 June 2018) to tell the complainants that the schedule of payment
did not comply, and that it must be amended.
On 11 May 2018, the lender issued unconditional approval for the wrong amount,
being $845,000 (error). On balance, this amount appears to have been a
typographical error on the loan offer because:
> the lender’s ser vicing calculator completed on 11 May 2018 shows it calculated
serviceability based on a total loan amount of $895,000, and
> the credit notes show the credit assessor emailed the loan manager the next
day (12 May) saying page 8 on the new contract still shows $850,000 and it
should be amended to $895,000.
On 20 June 2018, the lender asked the complainants to make a further payment of
$261.50 to the builder because there was a shortfall between the valuation and the
amount the lender is lending (shortfall error). The lender states the valuer is
responsible for the shortfall error in its email of 27 June 2018. As the lender
procured the valuation for its own benefit, it is generally accepted that the valuer is
acting as an agent for the lender. Therefore, the lender is responsible for the
valuer’s shortfall error.
6.3 Our approach to compensation for non-financial loss
In circumstances where a financial firm has made an error, we can award non-
financial loss to compensate a complainant for any undue stress and inconvenience
caused by the financial firm’s error.
The Australian Financial Complaints Authority ( AFCA) has commenced managing
complaints previously lodged with F inancial O mbudsman S ervice (FOS) . Therefore,
t his recommendation i s made under FOS Terms of Reference (TOR). The maximum
non - financial loss we can award for any one claim under the TOR is $3,000.
We will only award compensation for non-financial loss if there has been an unusual
degree or extent of inconvenience. We will not award compensation for loss that a
complainant may incur as a result of pursuing a complaint or rectifying a financial
firm’s error.
When assessing whether the circumstances are of an unusual nature we will review:
the degree or extent of physical inconvenience suffered
the general time taken to resolve the complaint
Recommendation | Case number: 546937 Page 10 of 10
the extent to which the financial firm’s actions interfered with the complainant’s
expectation of enjoyment or peace of mind.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.