Text of the determination
Determination | Case number: 545425 Page 1 of 12
Determination
Case number: 545425 27 June 2019
1 Determination overview
1.1 Complaint
The complainants hold a building and contents policy with the financial firm (insurer).
They lodged a claim for property damage following a storm in April 2015. The insurer
accepted the claim and authorised repairs to start after a 12-month drying out period.
The repairs were commenced in about October 2016, but the complainants say they
identified faults three weeks after completion. The insurer assessed the new damage
and says that was due to differential movement and is not related to the original claim
or the repairs. So it declined cover for the new damage.
The complainants also believe the piers under the house were damaged by the storm,
and should be covered, but the insurer maintains it is not liable for that .
1.2 Issues and key findings
Is the insurer responsible for the claimed damage?
The cause of the new damage is the quality and timing of repairs authorised by the
insurer, and not differential movement. The insurer is responsible for rectifying the
internal property damage from its builder’s repairs and the original storm event.
The available evidence also shows, on balance, the proximate cause of damage to at
least some of the piers/footings was the storm event. That means the insurer is
responsible for repairing/replacing the damaged piers to current building standards.
Are the complainants entitled to compensation?
The complainants are entitled to compensation for non-financial loss for the significant
upset and inconvenience caused by the way the insurer and its builder dealt with the
claim, and specifically the claim-related work.
Determination | Case number: 545425 Page 2 of 12
1.3 Determination
This determination is substantially in favour of the complainants.
The insurer is required to contribute 50% of the complainant’s quoted cost for
piers/footings. It is also required to appoint a new builder to conduct an assessment o f
the other necessary rectification works and provide a new detailed quote, actionable
by the complainants, and otherwise as set out in section 2.1 below. The insurer is
then required to cash settle the claim for the total of those two amounts.
The insurer is also required to pay $1,500 as compensation for non-financial loss.
Determination | Case number: 545425 Page 3 of 12
2 Reasons for determination
I have decided this case on its merits, having regard to the relevant law, good industry
practice, codes of practice and previous AFCA decisions. I have taken into account all
the material submitted by the parties, both before and after the recommendation. I am
satisfied that the documentation I have relied on has been provided to both parties.
2.1 Is the insurer responsible for the claimed damage?
Engineer MS recommended 12-month drying out period, and 2-step repairs
The complainants lodged a claim in April 2015 following storm damage to their
property. The insurer appointed an engineer (MS) to attend and assess the damage.
MS attended in July 2015 and stressed that a 12-month drying out period should be
allowed before any repairs were undertaken. MS said that more cracking should be
expected during that time. That effectively meant the repair work could not be scoped
until the buildings had been allowed to settle over the course of that period.
MS also very clearly stated that internal repairs should only take place after the
external repairs had been completed. In the repair schedule section of their report
relating to the main residence, MS identifies the consecutive steps to be taken,
starting with the following:
1. Check the internal levels of the floor…
2. Jack and pack piers which require adjustment to realign the doors and level any
floor areas…
3. …there may be an increase in the crack wi dth upon settlement of the piers
4. When satisfied the levels and stability is satisfactory proceed with the internal
repairs.
MS noted the main residence and granny flat were believed to have been built during
the same period, and stated the damage to the granny flat had included water
removing the foundation soil, and piers toppling or dropping. The insurer has paid for
repair/replacement of the piers under the granny flat.
Engineer FC found settlement, and says footings not to Australian Standards
After the 12-month drying out period, the insurer appointed a new engineer (FC). FC
attended the property on 27 April 2016 and noticed apparently recent cracks to the
ceilings and cornice and most walls, ranging from under 1mm to around 2mm,
running vertically and horizontally along the internal linings. As well, FC noted
irregularities in the flooring.
Determination | Case number: 545425 Page 4 of 12
FC also reported there was cracking to top soil in the subfloor, which it said indicated
highly reactive soil. However, they did not conduct any soil testing. FC observed the
piers and hardwood floor frame were generally in good condition, except one pier
which had visible cracking; but they also found severe erosion of soil around footings.
FC concluded the structural movement observed was typical of a structure where the
foundations had undergone differential settlement. FC said that was likely due to the
highly reactive clay ‘which caused extreme swelling/shrinking during…the storm
event’ .
FC observed (but did not substantiate) that the footings ‘ probably ’ did not meet
current Australian Standards in terms of foundation resistance. They did say,
however, if the footings were not upgraded, such damage would recur.
Internal repairs in the residence reported as faulty in January 2017
The insurer then appointed a builder (EP) to prepare the scope of works for the
residence and the granny flat. EP started the repairs in October 2016 and completed
them before Christmas. The complainants say the cracks and other faults started
appearing in the main residence (internal walls and floor tiles in bathroom and
laundry) three weeks after the works were completed; although there were no
problems with the granny flat.
FC returned on 27 September 2017 to assess the property. It reports the original
repairs are not the reason for the cracking. Instead, it says the damage is due to
‘probable ongoing movement’ of the foundation material due to the construction
method used for the building, specifically the footings.
Based on FC’s second assessment, the insurer concluded the new damage was
unrelated to the original claim and the repairs undertaken by EP. So a new claim was
lodged for investigation.
Experts not consistent in identifying cause of the damage
Independent builder (AG) was engaged by the insurer and attended the property on
15 January 2018. AG ’s professional opinion was that, given the extent of the pier
movement, the storm had ‘a major effect’ and not all the damage could be attributed
to ground movement. AG recommended the insurer appoint an engineer to review the
claim and damage.
In its third assessment on 3 April 2018, FC maintained the damage was due to
seasonal climatic changes on subfloor soils, and n ot the builder’s repair method.
Builder DW, engaged by the complainants, reported in November 2018 however that
the damage was due to a mixture of ground movement and poor workmanship. DW
said it appeared the piers and footings had been compromised by the storm. In a later
report, he confirmed ‘the original storm has pushed the brick piers out of plumb’ and
Determination | Case number: 545425 Page 5 of 12
also noted that ’in some areas packing installed for carrying out original repairs [is] not
touching the bearer’.
These observations are broadly consistent with those of builder, PC, who also
reported to the complainants in April 2019 on the damage. PC identified damage he
says has recurred to previously repaired areas/as a result of poorly executed repairs.
PC, like DW, also found ‘a number of isolated piers [under the house] that had been
previously packed ’ . He said ‘a number of these piers have rotated from plumb and
also settled, causing the packing to fall out and not supporting the timbers above’.
I appreciate the insurer prefers FC’s opinion , as it says FC is an engineer and holds a
higher qualification than AJ and DW (builders). So, b ased on FC’s reports, it declined
the claim for the new damage.
Need to establish proximate cause of damage, including to piers/footings
There is no dispute the complainants had a valid claim following the storm event in
2015. The repairs the insurer undertook were in response to that claim. The policy
provides that there is a lifetime guarantee on repairs authorised and conducted by the
insurer.
So if the new damage has arisen either from the original claim event, or is a result of
the quality of the insurer’s repairs in response to the original claim, then the insurer is
liable for it.
The insurer maintains that the new damage is the result of policy exclusions: gradual
deterioration; the home not being maintained in a watertight and structurally sound
condition; and settling and foundation movement.
No evidence has been presented that reasonably supports the first two suggested
exclusions; and while the reports have found settlement and foundation movement,
the question becomes whether or not it was the storm which was responsible for that
settlement/movement, or whether it would have happened in any case. In other
words, whether the storm was the proximate cause of damage to the piers and the
other new damage as well.
In their first report, FC had said the footings probably did not meet the current
Australian Standards in terms of foundation movement resistance. GC, a builder
engaged by the complainants in March 2019 to report and quote on the new damage,
also noted that may be the case. However, GC went on to point out that the footings
observed were commonplace at the time the house was built, and I have seen
nothing to show they would not have met the applicable standards at that time.
So even though FC recommended ‘a review of the structure for an upgrade of the
existing footings’ in order to avoid the same sort of damage occurring in the future,
any deficiency in the footings by reference to current building standards is not in itself
Determination | Case number: 545425 Page 6 of 12
a valid basis for declining the claim. Nor does it necessarily mean that the state of the
footings was the proximate cause of the damage.
I am also not persuaded, on the available evidence, that the nature of the soil itself
was the proximate cause of the settlement/movement damage; and I note no detailed
analysis or findings have been provided on that point. The available evidence does
not show that the state of the soil or the piers before the storm had caused issues
such as those which occurred after it.
The insurer’s file notes for the original claim, on 24 May 2016, report that EP attended
the property and ‘did some packing to the piers that had sunk’. The evidence
suggests that sinking had occurred since the storm. The complainants say cracking
did not appear in the granny flat after the repairs were completed late in 2016 (as it
did in the main residence). They believe this is because the builder replaced the
granny flat piers before commencing any internal works. The complainants say the
house never had any cracking prior to the storm, and they maintain the piers/footings
themselves were also damaged/compromised by the storm.
To support that submission, the complainants provided a report from an engineer
(PC) after they rejected the recommendation. PC reports the piers had settled and
rotated from the plumb causing the earlier packing to fall out.
Other c omments throughout the various reports (including FC’s) refer to the severity
and effect of the storm on the surrounding soil; not just from erosion, but also in terms
of causing swelling/shrinking. The fact that a 12-month drying out period was
recommended following the storm event and before any repairs were undertaken,
reasonably suggests that further movement and cracking, as a consequence of the
storm itself, was expected – and that proved to be the case.
So, I consider that the further movement of the piers/footings which occurred during
that 12-month settling period is, on balance, attributable to the storm, which is
therefore the proximate cause of that damage. Under the circumstances, I also
consider that any additional movement in the piers (and consequently in the building
itself) which may have occurred since the ‘repairs’ is also more likely than not the
result of the failure to properly address the damage caused by the storm in the first
place.
That means I am satisfied the insurer should be responsible for the
repair/replacement (as necessary) of those piers/footings which were damaged,
whether by actual cracking, or by displacement.
The complainants have provided a quote from GC (dated 8 March 2019) for the
supply and installation of 60 new piers. It is not clear on the evidence available just
how many of the original piers were damaged or compromised by the storm event.
However, it is clear that all the piers should be replaced to ensure appropriate
protection against future movement. Part of the responsibility for that falls to the
Determination | Case number: 545425 Page 7 of 12
complainants, since the insurer is not obliged to pay for undamaged parts of the
building.
In the absence of specific information about the number or proportion of the
piers/footings which were actually damaged from the storm event, I consider it fair in
the circumstances that the insurer contribute 50% of the complainants’ quoted cost for
replacement of the piers.
Repairs should not have proceeded as and when they did
On 29 September 2016 there is a note on the insurer’s file for the original claim which
refers to a scope of works that applies for structural work only (and not internal
repairs); a subsequent reference which clarifies that scope is for stage 1, with a
further scope for stage 2 (internal repairs) to follow; and then a specific note that after
stage 1 works are completed, there needs to be a 4 week settling period after which
stage 2 works can be scoped.
The complainant has consistently reported that they were told the work to the house
piers needed to happen before such a settling period, after which the internal repairs
could proceed.
The insurer has maintained – and EP subsequently said, in response to a specific
question about the need (or not) for any break period during the repairs – that no such
period was needed.
However, the first expert report obtained by the insurer (from MS) also very clearly
sets out a stepped approach which incorporated a delay between structural work and
internal work; and t he insurer’s file notes contain a specific reference to a two-stage
process.
I am satisfied the insurer knew, or should reasonably have known, that the internal
work should not have happened until the recommended work on the piers/footings
had been undertaken: and that was not just the interim measure by EP of packing the
piers to level the floors at that point in time, but also the complete re-assessment and
replacement of all piers (regardless of whether that was the insurer’s or the
complaina nts’ responsibility) to bring them into line with current building standards, in
order to minimise or avoid future problems.
Insurer is responsible for rectification works
Given the available evidence, I am satisfied, on balance, the new damage to the main
residence was the result of the nature, quality and timing of repairs the insurer
authorised and undertook in response to the accepted storm claim.
Specifically:
> the insurer proceeded with external, structural work to the piers/footings while
simultaneously conducting internal repairs (when the evidence indicates there
Determination | Case number: 545425 Page 8 of 12
should have been a time lag between those two stages to allow for further
settling, in addition to the initial delay to allow for the 12-month drying out period)
> the insurer authorised and undertook the repairs when its experts had previously
made it clear that substantial (and not just interim) work needed to be carried out
to the footings beforehand
> it is not clear on the evidence that the complainants were ever made aware of
the recommendation/need for preceding substantial work to the footings, or that
they knew the insurer believed they were responsible for that.
Even if the interim work to ‘jack and pack’ the piers had been appropriate and
sufficient, the evidence indicates that was not done properly in any case: GC
observed ‘incorrect positioning of packing, and lack of it. The plastic wedges used
were also substandard for what is required for this type of work’.
That means the insurer is responsible for all rectification work arising from its repairs
and the storm event.
Under the circumstances, claim should be cash settled
I acknowledge the complainants wanted the insurer to engage its builder to undertake
the repairs, however, under the circumstances I consider the appropriate approach is
for the insurer to cash settle the complainants. That is because the insurer is liable for
only some of the work to the piers, and it is appropriate that the complainants attend
to the pier replacement before the remaining internal repairs (for which the insurer is
responsible) are carried out.
In cash settling, the insurer must ensure the settlement amount is reasonable and
sufficient for the complainants to complete the necessary work themselves. That is,
the amount must be arri ved at having regard to all relevant factors, including the fact
that the risk is passing to the complainants, since they will lose the lifetime guarantee
on the work; it should also include an amount for contingencies, as well as covering
applicable additional benefits available under the policy (such as costs for
demolishing and removal of debris, rebuilding fees and fees incurred in meeting
building requirements).
Importantly, the quote on which the settlement is based must be actionable by the
complainants (and not just based, for example, on trade rates available only to the
insurer).
The insurer is required to appoint a new builder to assess the rectification work
needed, prepare the scope of works and provide a quote on which the cash
settlement is based.
Determination | Case number: 545425 Page 9 of 12
2.2 Are the complainants entitled to compensation?
Compensation payable in some circumstances
The FOS Terms of Reference allow for an award of compensation (capped at $3,000)
for non-financial loss. We may decide an insurer should compensate a complainant
for such loss only where there has been an unusual amount of physical
inconvenience, time taken to resolve a situation, or interference with the
complainant’s expectation of enjoyment or peace of mind.
The claim was first lodged in April 2015. A builder and an engineer assessed the
damage and advised in July 2015 that a 12 -month drying out period was needed
before repairs; make safe works were completed and then the actual repairs
commenced in October 2016. The repairs were reported as faulty approximately three
weeks after they were completed.
The complainants say the insurer’s claims management was unsatisfactory . They say
the scope of works was never provided to them, and the evidence does suggest they
were not fully or adequately kept informed of critical matters, which then caused
further problems. In addition, the insurer decided to simultaneously carry out the
internal repairs (and interim external work to the footings) knowing the condition of the
footings and the possible longer-term implications of that, and against the advice of its
experts.
The complainants were entitled to expect the insurer’s repair work, when it was done,
to have been completed professionally, thoroughly and well. They were also entitled
to have been kept informed of relevant and critical issues in a timely manner. I am not
satisfied that happened.
The nature and extent of the damage that has recurred since the original repairs is
such that the complainants have experienced considerable and protracted upset and
inconvenience, which could have been avoided. I accept this interfered with the
complainants’ reasonable expectation of enjoyment and peace of mind.
In the circumstances of this claim, I am satisfied it is fair the insurer pays the
complainants $1,500 as compensation for non-financial loss.
Determination | Case number: 545425 Page 10 of 12
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previously lodged with Financial Ombudsman Servi ce (FOS).
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
applicant complainant
financial services provider financial firm
dispute complaint
claim claim
3.2 Expert reports
Record Key points
Financial firm’s expert (MS)
Scope of works
21 July 2015
A subsoil drying out period of 12 months should be
allowed before any remedial works are undertaken
The subsoil should be examined to ensure thorough
dryness before external works commence.
Financial firm’s expert (FC)
Structural Engineer’s Report
31 October 2017
We also note that the granny flat that had the footings
upgraded as part of the recommended remedial work has
not had cracking to the internal finishes reappear.
Differential movement of the foundation material under
the main reside nce’s footings is the cause of the cracking.
This is due to the construction met hod employ ed and
without upgrading the residence footings to current
Australian Standards, the ongoing cracking will probably
continue over the life of the structure.
Financi al firm’s expert (FC)
Structural Engineer’s Report
4 April 2018
The original stumps to the main residence had not been
affected by the claimed event and all that was
Determination | Case number: 545425 Page 11 of 12
Record Key points
recommended by ourselves and MS Engineering was to
relevel the subfloor after a 12 - month drying out period to
allow for works.
The existing footings have been packed and re - levelled
without any upgrading of the existing foundations as per
the scope rec ommended by MS engineering.
Complainants’ Expert (DW)
Builder Asse ssment Report
12 November 2018
Based on our visual inspection and the information
available at the time of our assessment we believe the
cause of the damage is due to movement/poor
workmanship.
The majority of the walls in the house show signs of
cracking predominantly horizontal cracks where the
plasterboard is joined and there also evidence of vertical
cracking.
The cracking of the floor, wall tiles and lifting of the hob
has also been cause by movement.
The splashback tile cut around the tap and door latch in
the laundry is due to poor workmanship.
3.3 Key policy terms
Product Disclosure Statement
Pages Wording
58
If we agree to cover your claim under
Buildings Insurance, then we will:
> pay the cost to repair or rebuild the part of your home that was
damaged (whichever is lower)
How we settle your buildings claim
We will choose to settle your claim for loss
or damage to your home or 'other cover' in one of the following ways:
1. Arrange for repairers, builders or
suppliers to repair or rebuild your
home.
If you agree, we can arrange for our preferred repairers, suppliers or builders
to repair or rebuild your home.
2. Pay you the reasonable cost to
repair or rebuild your home.
We can choose to:
Determination | Case number: 545425 Page 12 of 12
Pages Wording
> pay you
> pay your nominated repairer, supplier or builder, or
> provide you with store credits from one of our nominat ed suppliers.
59
Lifetime guarantee
We provide a ‘lifetime guarantee’ when
your home is repaired or rebuilt by one
of our preferred repairers or builders.
This means:
> we guarantee the workmanship of
repairs that we authorised for the
lifetime of your home
> we will fix any defect caused by
poor workmanship.
61 Under Buildings Insurance
> we only repair the damaged parts of your home.