Home / Financial Firm (Unknown - Insurer) / Determination 545018

Determination 545018

Claim delays and insurer's right to re-assess before cash settlement

FirmFinancial Firm (Unknown - Insurer)
Decided2019-02-07
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$63,962
SourceAFCA PDF

Summary

Complainant sought cash settlement of a home claim based on his builder's quote after a break-in. AFCA found the insurer entitled to further assessment, and accepted that claim management had been slow, noting the insurer's offer to waive the $500 excess.

The policy requires the insured to allow the insurer access to inspect damage, and that access is not limited to a single inspection.

Issues

Subjects and remedies

home or building damagetheft or burglaryno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination | Case number: 545018 Page 1 of 5 Determination Case number: 545018 7 February 2019 1 Determination overview 1.1 Complaint The complainant holds a home and contents insurance policy underwritten by the financial firm (the insurer) covering his home address. On 31 July 2018, the property was damaged during an attempted break in and a claim lodged under the policy. The insurer accepted the claim and arranged for an emergency make safe to be done to secure the premises. It also appointed builder “HR” to inspect the property and prepare a scope of works (SOW) for the repairs required. HR attended the property however confirmed the SOW exceeded its authority limit with the insurer. The insurer subsequently advised the complainant an internal assessor would be appointed to the claim to assess the loss, as well as a second builder. The complainant is dissatisfied with the time taken by the insurer to resolve his claim and is reluctant to allow further assessments. He seeks that it now resolves his claim by providing a cash settlement based on the quotation he sourced from his builder. 1.2 Issue and key findings Is the insurer entitled to further assessment of the property? The insurer is entitled to a further assessment of the property because:  the policy terms provide than an insured must allow the insurer access to inspect the damaged property;  this requirement is not limited to a sing le inspection; and  it requires an assessment in order to reasonably determine the extent of its liability. Determination | Case number: 545018 Page 2 of 5 1.3 Determination This determination is in favour of the insurer. The insurer is entitled to assess the damaged property prior to determining its liability for the claim under the policy terms. Determination | Case number: 545018 Page 3 of 5 2 Reasons for determination 2.1 Is the insurer entitled to additional assessment opportunities? Onus rests with the complainant to establish extent of loss There is no dispute between the parties the complainant suffered a loss from a risk insured against or the insurer accepted his claim. However, a dispute has arisen between the parties as to the extent of the insurer's liability and its management of the claim. Principally, the complainant maintains that he has co-operated with the insurer and allowed HR to assess the property. He also allowed a second assessment opportunity on 14 August 2018, however no one attended. That this has not yet been completed is due to the insurer, rather than any action on his part. He seeks his claim be settled without further recourse based on the quotation he has supplied from builder “OG”. No dispute the complainant did initially allow access There is no dispute that the complainant allowed access to HR for the purposes of assessing the damage. However, HR confirmed the cost of repairs (which it estimated at $15,000) exceeded its authority limits with the insurer, and another builder would have to be appointed to undertake the repairs. The insurer acknowledges that it advised the complainant it had arranged an assessor to attend the property on 14 August 2018, however that party did not arrive. The insurer also acknowledges a further assessment wi th its internal assessor “NW” arranged had to be rescheduled due to illness. Internal assessor “AP” was instead appointed to the claim and sought to arrange a suitable time with the complainant. Due to communication difficulties, this was not done. However, the complainant is dissatisfied with the delay and says he has attempted to contact both AP and the insurer via telephone and email, which have not been responded to. He seeks that his claim be resolved without further recourse by settling on the OG quotation. Policy terms are clear in stating insured must allow access to the property for assessment I am not persuaded by the complainant’s view. The policy terms are clear in this regard that the complainant must make his damaged property available for i nspection, in order that the insurer determines its liability for the claim. I do not consider the fact of the non-attendance on 14 August 2018 by an alternative contractor absolves the complainant from complying with his contractual obligations to allow access for an assessment. Further, I do not accept that the provision in the policy allowing access to the insurer to the property is, or should be, read as allowing Determination | Case number: 545018 Page 4 of 5 a single admittance only. Many claims are dynamic, and an insurer must be able to re-assess them over the course of the claim when additional information becomes available. Insurer’s offer to waive excess is reasonable recompense for the delay Whilst it is unfortunate that there have been some errors and delays throughout the management of this claim, the remedy is not automatic payment of it. This is particularly so where the quantum as estimated by the complainant ($50,962 plus $13,000 for damaged contents) is substantial, OG’s quotation is not itemised and the amount sought significantly ex ceeds HR’s initial assessment. The insurer is entitled to address this discrepancy. Whilst I accept more effective management of the claim by the insurer could have lessened the time taken to bring this matter to resolution, I note the insurer has offered to waive the policy excess of $500 in recompense of the delay. This is reasonable in the circumstances, particularly when considering that the fact the claim has stalled is, at this point in time, due to the complainant. Insofar as the complainant says the delay has caused additional damage to the property due to the make safe being insufficient, then the insurer is required to address this issue as part of its assessment. AFCA expects the parties to a dispute to work together to resolve any issues and minimise the time taken to finalise a claim. For the sake of consistency, the insurer should nominate a single point of contact for the complainant, to ensure a smooth and expedient progression of his claim. Determination | Case number: 545018 Page 5 of 5 3 Supporting information 3.1 The determination is made under FOS Terms of Reference The Australian Financial Complaints Authority ( AFCA) has commenced managing disputes previously lodged with F inancial O mbudsman S ervice (FOS) . This determination is made under FOS Terms of Reference but has adopted the following terminology for consistency with AFCA. In this determination the AFCA terms have the same meaning as the FOS terms defined in paragraph 20.1 and Schedule 1, 2 & 3 of the FOS Terms of Reference. FOS definitions AFCA term applicant complainant financial services provider financial firm dispute complaint claim claim 3.2 AFCA approach to this complaint A full exchange of the relevant information has taken place between the respective parties and each party has had the opportunity of addressing any issues raised. All of the provided material has been reviewed and considered. The parties have raised numerous issues in their submissions to AFCA. For the purposes of this determination, commentary is restricted to only those issues considered relevant to the outcome.