Determination 544035
Loss of rent stopped before repairs complete; insulation not included in scope of works
Summary
A landlord complained the insurer stopped paying loss of rent before repairs were finished and refused to install ceiling insulation. AFCA ordered rent to 1 June 2018 and $1,000 for non-financial loss, but found no obligation to install insulation or pay rent after that date.
The insurer's agreement to pay rent until repairs were completed applies, but rent is not owed for the period lost to the complainant's insulation dispute, and non-financial loss is awarded for unreasonable claim handling.
Issues
- Claim denial primary · upheld
“The insurer should pay for loss of rent until 1 June 2018; it is not liable to install insulation in areas that had none before.”
- Poor claim handling secondary · upheld
“The information shows the insurer's handling of the claim was inadequate; $1,000 awarded for non-financial loss.”
Subjects and remedies
home or building damagepay claimpay non financial loss
Text of the determination
Determination | Case number: 544035 Page 1 of 8
Determination
Case number: 544035 12 March 2019
1 Determination overview
1.1 Complaint
The complainant lodged a claim for damage to her investment property which was
accepted by the financial firm (the insurer). During the course of the claim, the insurer
agreed to pay for loss of rent up until repairs have been completed.
The complainant says the insurer stopped paying rent from 30 April 2018 despite
there being a number of outstanding items. This includes the installation of insulation
between the levels of the home.
The insurer says repairs are completed apart from minor rectification iss ues. Given
this, and the fact the insured property can be lived in, the insurer is not prepared to
pay any additional loss of rent. The insurer also says that insulation is not required to
be installed as this was not there previously.
1.2 Issues and key findings
Is the insurer liable to install insulation?
The insurer is not liable to install insulation in areas that had none prior to the claim.
Is the insurer required to pay for more loss of rent?
The insurer should pay for loss of rent until 1 June 2018 because the available
information does not show the repairs were delayed by the complainant’s
unreasonable action prior to this.
The insurer is not liable to pay for loss of rent after this as the information shows it
was due to the complainant seeking for the insulation to be installed.
Should the insurer pay non-financial loss?
The insurer should pay $1,000 for non-financial loss because of its unreasonable
handling of the claim.
Determination | Case number: 544035 Page 2 of 8
1.3 Determination
This determination is partially in favour of the complainant.
The insurer should pay for loss of rent until 1 June 2018 as well as $1,000 in non-
financial loss.
Determination | Case number: 544035 Page 3 of 8
2 Reasons for determination
This complaint has been the subject of an AFCA recommendation issued on 30
November 2018.
It was the case analyst’s recommendation that the insurer is not liable to replace the
insulation or pay any further rent. The case analyst did award $1,000 in non-financial
loss.
The complainant rejected the recommendation. The complainant says the insurer
agreed to pay for rent until repairs were completed, which was not done. The
complainant also says that the insulation was to be installed as part of the agreed
scope of works and this should be followed through. The complainant did not provide
any submission about the amount awarded for non-financial loss.
The insurer did not respond to either the recommendation or the complainant’s
submission after the recommendation.
This determination follows consideration of all of the information exchanged and is
based on what is fair in the circumstances, having regard to the relevant legal
principles, good industry practice, industry codes and, where applicable, prior
determinations.
2.1 Is the insurer liable to install insulation?
Insurer is not required to install insulation
The agreed scope of works inclu ded the installation of ‘new batt insulation’ to the
kitchen/dining area and two bedrooms. For the kitchen/dining area, the scope of
works said:
- Remove wet insulation to be disposed of
- Install new batt insulation to match existing
There is no dispute there was no insulation in the ceiling. Therefore, it is clear that at
least this part of this scope of works cannot be affected as there is no insulation to be
disposed of or matched.
Regardless, whilst the parties agreed to a scope of works, I do not consider it is fair
that it be followed strictly. It is plain the scope of works are to reflect the extent of the
insurer’s liability to repair the claim related damage. It should not be followed if doing
so means either party is adversely affected.
Whilst the complainant advocates otherwise given the current circumstances, the
following example illustrates the above point where the situation was reversed:
during the repair, other damage was identified that was not included
Determination | Case number: 544035 Page 4 of 8
it is clear the insurer would have been liable to repair this damage under the policy
it would cost a significant amount to repair
these works were not included in the agreed scope of works
It is plain from the above example that the insurer must include the new works
irrespective of the fact they were not in the agreed scope of works.
Therefore, I consider it is fair that such an approach be applied here. There was no
insulation in the ceilings. The policy does not require the insurer to install insulation in
such circumstances.
As such, the insurer is not liable to install new insulation in the ceiling.
2.2 Is the insurer required to pay for more loss of rent?
Repairs have yet to be completed
Following a dispute between the parties, an agreement was reached where the
insurer said:
[Insurer] has agreed to cover you for loss of rent up until repairs have been
completed
The insurer’s assessor (PC) provided a report dated 25 May 2018 that identified the
following outstanding items:
upstairs bathroom not being cleaned
a hole in the ceiling
cracking at joins of new plasterwork
upstairs bedroom cornice appears to be missing a coat of paint
Therefore, as at this date, it is clear the insurer had not completed the repairs.
Most of the insurer’s arguments do not assist it
The insurer has covered rent until 30 April 2018. The insurer is not prepared to cover
any additional rent for a number of reasons. This includes the following:
the insurer paid for 10 months’ rent outside the policy limit
repairs to the property have been completed
the property is not unliveable as a result of the rectification works
the complainant has not provided evidence to show they are not receiving rent
the insurer is not obligated to pay for loss of rent beyond the period it should
reasonably take to complete the repairs
further delays occurred due to the complainant seeking options regarding the
insurer’s refusal to install insulation
Determination | Case number: 544035 Page 5 of 8
Most of these submissions are not persuasive. The insurer agreed to pay for loss of
rent until repairs were completed. This was not qualified by being subject to the policy
terms. Therefore, references to the policy provisions or limit are not relevant.
The insurer agrees there are rectification issues. If this is the case, then it is plain the
repairs are not completed.
The insurer’s offer was to pay for loss of rent. If the complainant received rent during
any of the relevant times, then this must be deducted.
I do accept there is merit to the insurer’s arguments about the delays due to the
insulation. This will be expanded on later.
Nothing to show complainant delayed the repairs prior to 25 May 2018
The complainant says that the insurer agreed to pay for rent until repairs are
completed and should be held to this. However, I do not accept the insurer’s offer
should be applied so strictly.
For instance, the insurer should not be liable to pay rent if the inability to complete
repairs are due to any unreasonable action taken by the complainant. For example, if
the complainant had simply decided to refuse access to the insurer’s contractors for
three months for no reason.
In such circumstances, it would be harsh and unfair for the insurer to pay rent during
this period of time. Further, I do not accept a reasonable person in the position of the
parties would expect the agreement to be applied in such a manner.
At the time PC inspected the property, it is clear there were outstanding rectification
issues. The insurer indicated that during this time, the complainant had authorised
private works which had delayed the process.
However, the insurer’s contrac tor (P) provided an email dated 26 April 2018 that
noted the following about this period of time:
repairs were estimated to be completed on 29 March 2018 – this extended to
Easter Monday (2 April 2018) due to the complainant’s contractors being on site
a variation having to be approved for the lighting
on 23 April 2018, P having to attend next week as the insured was having floors
sanded
I am not satisfied this shows the complainant unreasonably interfered with the
insurer’s ability to effect repairs. There fore, I do not accept this was a basis for the
insurer to have stopped paying rent before PC inspected the property.
Determination | Case number: 544035 Page 6 of 8
Insurer not liable to pay for lost rent due to the dispute about insulation
Following 25 May 2018, I accept the insurer is not liable to pay rent beyond the
reasonable period of time it should have taken to address the rectification issues.
This is because at that point:
the complainant had sought for the insulation to be installed
PC noted that rectification could not be completed until this issue was resolved
given part of the works involved the ceiling
the complainant’s position about the insulation was not substantiated.
Further, I do not accept the complainant’s position on the insulation was reasonable.
She was made aware during PC’s in spection that there was no insulation in the
ceilings previously. There was no basis under the policy for the insurer to install this. It
was relatively apparent that its inclusion in the scope of works was due to a
presumption that it was there previously, not as an improvement the insurer agreed to
undertake.
Therefore, the insurer is not liable to pay for any loss of rent that flowed from the
complainant’s position to dispute the insulation.
Insurer is to pay for loss of rent until 1 June 2018
The insurer says it would only have taken one day to complete the rectification.
However, I consider it fair for there to be an allowance of seven days. This is to
account for contractors to facilitate a time to be available and having access to the
property.
This means the insurer should pay for loss of rent until 1 June 2018. In doing so, the
complainant should provide confirmation that there was no tenant paying rent
between 1 May and 1 June 2018.
I do not accept the insurer is liable for loss of rent after this. This is because I accept
that loss was due to the complainant seeking the insulation to be installed.
2.3 Should the insurer pay non-financial loss?
Insurer is to pay $1,000 in non-financial loss
Compensation for non-financial loss may be awarded in limited circumstances. That
includes for situations where there has been an unusual degree or extent of physical
inconvenience, time taken to resolve the situation or interference with the
complainant’s expectation of enjoyment or peace of mind.
Compensation is awarded conservatively.
Determination | Case number: 544035 Page 7 of 8
The information shows the insurer’s handling of the claim was inadequate. The scope
of works is not extensive. The claim was lodged on 29 June 2016 and almost two
years later, the repairs had yet to be completed. This is despite the fact the repairs
were meant to be given priority after January 2018, but this did not appear to occur.
Therefore, I accept the complainant suffered an unusual degree of inconvenience and
interference by this. I also accept this would have been mitigated to a degree by the
insurer agreeing to pay rent for most of this period.
Given all this, I accept that an award of $1,000 for non-financial loss is fair in all the
circumstances.
Determination | Case number: 544035 Page 8 of 8
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previously lodged with F inancial O mbudsman S ervice (FOS) .
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
a pplicant complainant
financial services provider financial firm
Dispute complaint
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.