Home / Financial Firm (Unknown - Credit) / Determination 541928
Determination 541928
Bank allegedly misled complainants that it would fund house construction
Summary
Complainants bought land in a house-and-land package and borrowed to buy the land. After the bank declined construction funding, they complained it had misled them. AFCA found no misrepresentation and ordered no compensation.
Approving land-purchase loans was not a representation that the bank would also fund construction, which was always subject to a separate credit assessment.
Issues
- Misleading conduct primary · not upheld“The available information does not show the bank misrepresented that it would fund the build.”
- Claim denial secondary · not upheld“AFCA cannot review a bank's commercial credit assessment decision to decline to approve a loan.”
Subjects and remedies
no remedy
Related
All Financial Firm (Unknown - Credit) determinations · Find similar determinations
Text of the determination
Determination | Case number: 541928 Page 1 of 6
Determination
Case number: 541928 29 August 2019
1 Determination overview
1.1 Complaint
This dispute is about whether the bank led the complainants to believe it would
finance the building of the house in their house and land package. The bank financed
the purchase of the land only (loans).
The AFCA case manager issued a recommendation dated 26 February 2019
(attached) in the bank‟s favour. She found the bank did not mislead the complainants.
The complainants rejected the recommendation on the following grounds:
the bank misrepresented what occurred and AFCA made incorrect assumptions
they contracted for a house and land package; it follows the loans were meant to
fund the build as well as the land cost
the bank made progress payments for the build
they do not understand why funding for the loans had to be split.
1.2 Issues and key findings
Were the findings of the recommendation correct?
The findings in the recommendation were correct and are adopted in this
determination. I have considered submissions made since the recommendation.
Do the complainants’ submission s change the recommended outcome?
The complainants‟ submission s do not change the recommended outcome because:
The available information does not show the bank misrepresented that it would
fund the build. Rather, it shows the funding of the build was always subject to credit
assessment and did not pass credit assessment.
The reference in the recommendation to the house and land having been sold was
incorrect but did not impact the recommended outcome.
The bank did not release progress payments for the build.
Determination | Case number: 541928 Page 2 of 6
The loans were split because complainants M, MC and J could not afford to borrow
the full cost of the land. The funds were therefore split into a $450,000 loan for M,
MC and J, with the remainder lent to their parents (complainants R and M).
1.3 Determination
This determination is in the bank‟s favour. It does not have to pay compensation.
Determination | Case number: 541928 Page 3 of 6
2 Reasons for determination
2.1 Were the findings in the recommendation correct?
I have decided this case on its merits, having regard to the relevant law, good industry
practice, codes of practice and previous FOS and AFCA decisions. I have taken into
account material submitted by the parties, both before and after the recommendation.
I am satisfied the documents I have relied on have been provided to both parties.
The case manager‟s recommendation contains an accurate summary of the
complaint, the issues to be determined and relevant law.
2.2 Do the complainants’ submission s change the outcome?
The case manager assessed the information in line with AFCA’s approach
AFCA is not a court and we do not have the power to take or test evidence on oath.
The AFCA case manager assessed this complaint by considering all the available
documents, the recollections of the parties and all relevant circumstances. In line with
our approach, she gave more weight to contemporaneous documentary information
than retrospective recollections.
Where there was no relevant documentation the case manager decided what was
most likely to have occurred based on the information provided to us , after weighing
up the information. She followed AFCA‟s approach to misleading conduct claims by
asking the complainants and the lender about what the complainants were told ;
reviewing the bank‟s contemporaneous records; reviewing emails and letters between
both parties and third parties, amongst other documents. She properly considered all
the information provided.
I apologise for the comment in the recommendation that the land and build has been
sold when it has not. This error was unintentional and did not impact the
recommendations made.
The available information does not show the bank misled the complainants
I can understand why the complainants would think because they applied for a land
and home package with the builders, and the bank was aware of this, that when the
bank granted the loans to purchase the land, they would also later fund construction
on the land.
However, approving the loans for the land purchase was not a representation by the
bank that it would also later fund the build. I can understand why the complainants
would logically assume this, but the bank did not have to lend for the whole
Determination | Case number: 541928 Page 4 of 6
development. Unless the bank actually represented it would fund the build, it was not
obliged to do so.
The weight of the information shows the bank approved the loans to purchase the
land but never agreed to lend more. It does not support that the bank led the
complainants to believe it would lend them the money to fund the build.
The complainants do not dispute that the bank had not made them an unconditional
offer to fund the build. The available documents show that:
On 9 October 2016 some of the complainants entered into a contract to purchase
the land.
On 16 October 2016 the complainants paid a significant deposit for the land.
On 4 November 2016 the complainants first approached the bank for funding.
On 21 and 28 November 2016 the bank issued loan offers to the complainants.
On 21 November 2016 the bank emailed the complainants saying it had almost
finished the loan for the land purchase.
On 1 December 2016 the bank emailed the complainants to tell them it had
unconditionally approved funds to purchase the land.
On 2 and 11 December 2016 the complainants entered into loan contracts with the
bank. RC and M added $450,000 to their existing home loan and M, JA and MG
took a new loan for $450,000.
On 17 January 2017 the complainants entered into a contract with the builder.
On 23 January 2017 the complainants paid a deposit of $27,969 to the builder.
On 24 January 2017 the land purchase was settled for $890,000.
On 7 February 2017 one of the complainants asked the bank by email what would
happen if they did not continue any further with the loan process. The banker
confirmed that they meant with loans for construction and that there would be no
penalty for not pursuing these.
On 13 June 2017 the developer asked the complainants whether they had an
unconditional loan offer so they could start construction.
On 21 June 2017 the complainants and the developer emailed the bank requesting
approval for funds for construction. The bank confirmed that it needed further
information from the complainants. A conversation transcript shows the bank had a
discussion with the complainants on that date, in which their priority was to get “a
construction loan for a new owner occupied property”.
On 26 June 2017 the builder received the construction certificate and the
complainants say they paid him $8,570.
In July 2017 the bank declined to provide further funding to the complainants,
because it was not satisfied they could afford additional lending.
It is apparent from the above that:
Determination | Case number: 541928 Page 5 of 6
Some of the complainants had already entered into a contract to purchase the land
and paid a deposit for it before approaching the bank to borrow funds to complete
settlement. They therefore cannot have been relying on the bank funding the
construction when they purchased the land.
It was clear from the correspondence preceding the loans, that the loans were to
purchase the land – the emails do not mention anything about construction.
The amounts borrowed under the loans were sufficient to complete the purchase of
the land, but clearly not sufficient to fund construction on the land. The loans
amounted to $900,000 and to settle the land purchase cost $890,000. The
complainants were aware when the loans were granted, that they covered the land
purchase only, not construction.
When the loans were granted, the bank did not know how much the complainants
may later need for construction, as there was no building contract in place.
When the complainants entered into a contract with the builder and paid a deposit
to the builder, it was after the loans for the land purchase had been approved, but
before they had a conditional or unconditional loan offer for the construction phase.
The complainants were aware they had to go through a further loan process (i.e.
application and assessment) for the construction phase.
Whilst the complainants clearly assumed they would be able to borrow from the bank
for construction, there is nothing in the available information to show the bank
misrepresented to them they would be approved for this.
The information shows a loan for construction was always subject to a further
application and credit assessment at the time, and the complainants were aware of
this. The complainants accept that they knew funds for the construction were subject
to credit assessment but seem to have assumed they would be approved. There is no
information to show this assumption was induced by any misrepresentation by the
bank.
I understand the complainants‟ disappointment at being declined for a construction
loan, especially when they had already entered into a contract with the builder and
made payments to the builder. I also understand their frustration with having to seek
finance elsewhere and sell an overseas property to be approved for construction
funding. However, there is nothing in the available information to show the bank
misrepresented to them that it would fund the build – it was always subject to credit
assessment.
The bank declined to provide additional credit (fund the build) because it concluded
the complainants could not afford to repay additional funds. It was a matter for the
bank as to whether it would lend more. It did not have to offer additional credit.
Given the issues the complainants had with getting approval from other banks,
necessitating selling an overseas property to get approval, it seems there were
legitimate concerns about affordability.
Determination | Case number: 541928 Page 6 of 6
In any event, AFCA cannot review a bank‟s commercial credit assessment decision to
decline to approve a loan.
The bank did not make progress payments for the build
The complainants say the bank either agreed to fund the build or led them to believe it
would because it released progress payments funding the build.
The bank never approved a loan to fund construction. I accept that the complainants
made payments to the builder on the assumption the bank would approve further
funding for the build. However, there is nothing to show the bank made progress
payments to the builder. This is confirmed by:
Both loan contracts state:
This is a single drawdown loan. You can only draw it in one instalment.
That is, they were clearly not construction loans where progress payments would
be released to the builder from the approved loan funds as and when needed.
The loan account statements do not identify any progress payments to the builder.
The bank split the lending so the complainants could qualify for finance
The lending was split into two credit facilities of $450,000 for affordability reasons, not
to facilitate funding the build.
The documents show complainants M, MG and JA contracted to purchase the land on
9 October 2016, before they applied for the loans in early November 2016. They did
not have lending pre-approval but they did pay a deposit on the purchase contract.
The bank split the lending into two credit facilities because M, MG and J did not meet
its serviceability assessment, meaning they could not afford the necessary loan. As
the complainants:
did not want to lose the deposit paid for the land before they approached the bank
wanted to purchase the land so the children could get a foothold in the Sydney
property market
the bank split the lending into portions which the borrowers could afford to service.
That resulted in a loan of $450,000 to complainants M, MG and JA and an additional
$450,000 to complainants RC and M.
It was appropriate in the circumstances for the bank to structure the loans this way.
This suited the complainants, as they risked losing the deposit and the land they
wanted otherwise.
Recommendation | Case number: 541928 Page 1 of 6
Recommendation
Case number: 541928 26 February 2019
1 Overview
1.1 Complaint
In October 2016 the complaints contracted for a house and land package. In the
December, they took out two loans between them with the bank to fund the land
purchase (loans). The land and the loans are described in 3.1 below.
After lending the funds to buy the land, the bank declined to fund the whole build.
Ultimately, the complainants sold the land and the loan accounts were closed.
This dispute is about whether the bank led the complainants to believe it would fund
all the build and whether it should compensate them for losses they incurred as a
result of not receiving the building loan.
1.2 Issues and key findings
Did the bank mislead the complainants?
The bank never approved the complainants‟ application for building funds. The
information provided does not show the bank said it would finance the build or that it
acted in a way which reasonably led the complainants to believe it would do so. In
lending for only part of a larger project, the bank was not representing it would fund
the entire development.
Did the complainants incur losses because of the bank’s miscon duct?
As the bank did not lead the complainants to believe it would fund the build, it is not
responsible for any losses they incurred in reliance on it doing so. The bank did not
make an error.
Should the bank compensate the complainants?
The bank does not have to compensate the complainants as it did not mislead them.
Recommendation | Case number: 541928 Page 2 of 6
1.3 Recommendation
This recommendation is in favour of the bank.
The loans have been closed and I understand there is no outstanding debt. This
means no further action is required by either party.
Recommendation | Case number: 541928 Page 3 of 6
2 Reasons for recommendation
2.1 Did the bank mislead the complainants?
The loans were to fund the land purchase
The loan contracts specify the purpose of the loans as „purchase newly erected
dwelling‟ and „construction of dwelling‟ respectively. W hilst this suggests one of the
loans was to fund the build, these summaries do not accurately reflect the loan
purpose. There was no dwelling purchased, nor was the build approved. Specified
loan purposes are usually quite generalized and, in this case, were intended to
categorize the loans as home related credit.
The fact the loans were taken out to finance a home and land package does not
mean the loans were intended to finance both the land purchase and the build. The
documents provided shows the loans were taken out to fund the purchase of the land
alone; after the loans were provided, the complainants had to provide additional
information to support their application for building funds.
The complainants contracted to buy the land before meeting with the bank
The complainants entered into the house and land contract with the developer before
they discussed funding either the land purchase or the build costs with the bank. The
loans had not been approved and the complainants had not sought or obtained pre-
approval when they entered into the house and land contract.
It is clear the complainants did not buy the land in the belief the bank had approved
funding for either it or the build. The documents provided correlate with the
complainants‟ timeline of events and show:
they bought the land/signed the house and land contract on 9 October 2016
they first approached the bank for funding on 4 November 2016
the bank issued offers for the loans on 21 and 28 November 2016 and
they signed the loan contracts on 2 and 11 December 2016.
The information provided shows the bank did not induce the complainants to enter
into the contract. They asked the bank to finance their purchase after they committed
to buying the land. That being the case, the bank did not cause or contribute to any
of the losses they incurred as a result of entering into the contract.
The bank did not represent it would fund the build
The complainants say the bank led them to believe the loans were „open loans‟ and
that it would release payments when it was time for building.
Recommendation | Case number: 541928 Page 4 of 6
None of the documents provided show the bank told the complainants the loan would
allow for progress payments for the build or that it said it would fund the build. It
appears the complainants misunderstood what the ba nk said and/or the purpose for
which the loans were provided.
The weight of the information provided shows the bank did not lead the complainants
to believe it would lend them the money to fund the build, either before or after it
approved the loans. They knew the bank had yet to approve a building loan. I note:
The complainants do not claim the bank said it had approved or would approve
further funds to fund the build. They only say the lender said the loan was „open‟,
that progress payments for the buil d wouldn‟t be a problem and, later, that she
made a mistake in relation to the loans
The complainants knew the loans were to fund the cost of the land alone. On
21/11/16 the bank emailed them saying it had almost completed the loan for the
land purchase and did not mention build funds
On 1/12/16 the bank emailed the complainants that it had unconditionally approved
funds to purchase the land. It said it would use one of the complainant‟s incomes
when assessing the building loan application. This shows the building loan was yet
to be assessed let alone approved
The bank‟s application notes do not record any approval or pre -approval of a
building loan
The bank says it did not approve the building loan and never said it would
The bank says it told one of the complainants at the request for funding meeting on
4/11/16 that it could not guarantee the building funds given the final construction
amount had not been specified and the employment position of another of the
complainants and
The emails exchanged between the bank, the complainants and/or the developer
reinforce the fact the loans were to cover the cost of the land and that building
funds had not been approved. Some of these emails are identified in 3.1.
The bank did not have to fund the whole house and land development
The complainants say that, by approving the loans, the bank represented it would
fund the build as well as the land purchase because the land purchase was part of a
combined house and land package. They question why the bank would lend for only
part of the development as by lending some of the necessary funds, it implied it would
fund the whole project given it was a land and house development. The complainants
say the bank should not have provided the loans if it wasn‟t prepared to fund the
whole development as this was the logical expectation which induced them to
proceed with the house and land contract.
It is a matter for a lender as to what lending risk it will accept and how much it will
lend. It was open to the bank to finance only part of the development and the bank
did not have to assist the complainants to complete the build. The bank was not
Recommendation | Case number: 541928 Page 5 of 6
acting for the complainants and did not have to put their interests above its own, nor
act in their best interests.
The bank declined to provide additional credit (fund the build) because it concluded
the complainants could not afford to repay additional funds. It was a matter for the
bank as to whether it would lend more and it did not have to offer additional credit.
2.2 Did the complaina nts incur loss as a result of the bank’s conduct?
The bank did not cause the complainants loss
The bank did not induce the complainants to enter into the house and land contract
and it did not mislead them about funding the build. The bank did not cause or
contribute to any loss the complaints may have incurred as a result of entering into
the house and land contract and taking out the loans.
2.3 Should the bank compensate the complainants?
The bank does not have to pay compensation
As the bank did not make a compensable error, it does not have to pay
compensation.
One of the complaints is that the bank did not respond to the complainants in a
professional or timely manner and that its service has been poor. This organization
does not have the power to consider disputes about the general level of service the
bank provided and so I have not reviewed this aspect of the complaint in detail or
awarded related compensation.
Recommendation | Case number: 541928 Page 6 of 6
3 Supporting information
3.1 Key References
The following is key information which I have relied on in forming my preliminary view
of this complaint. It has been exchanged.
Record Key points
Emails between
complainants, developer
and/or the bank
On 21/11/16 the bank emailed the complainants saying it had just
about completed the loan for the land
On 11/7/ 17 the developer emailed the complainants and the bank
seeking progress with regards to the formal loan approval
On 21/6/ 17 the complainants emailed the bank seeking formal loan
approval
On 21/6/ 17 the developer emailed the bank asking for formal loan
approval update and the bank replied that it was chasing
information from the complainants
The loans
Investment Loan ending #1743 for $750,000
Home loan ending #0504 for $450,000
The property
Lot 3/121 T B Circuit, K.