Home / Financial Firm (Unknown - Insurer) / Determination 541508

Determination 541508

Cash settlement of water damage claim and temporary accommodation

FirmFinancial Firm (Unknown - Insurer)
Decided2019-01-18
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$500
Non-financial loss$500
Amount claimed—
SourceAFCA PDF

Summary

The complainant disputed the insurer's cash settlement of kitchen water damage and sought temporary accommodation, compensation and a premium refund. AFCA found the settlement offer reasonable and temporary accommodation not payable, but ordered the insurer to refund the $500 excess and pay $500 for how it managed the claim.

The policy lets the insurer choose the settlement method and limits repairs to damaged areas, and non-financial loss compensation requires an unusual degree of inconvenience or delay.

Issues

Subjects and remedies

home or building damagepay claimpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination | Case number: 541508 Page 1 of 8 Determination Case number: 541508 18 January 2019 1 Determination overview 1.1 Complaint The complainant holds a home building and contents policy underwritten by the financial firm (the insurer) covering her home address. On 27 April 2018, a claim was lodged under the policy for water damage to the kitchen due to a leaking dishwasher tap. The insurer accepted the claim and arranged for builder “P” to provide a scope of work (SOW) and quote for the necessary repairs. The complainant was dissatisfied with the SOW prepared by P, stating the replacement flooring quoted was inferior to the existing and that the SOW did not include all damaged areas. The insurer subsequently offered the complainant a cash settlement, based on P’s quote, although it did offer to consider any quotations she may obtain. After negotiations between the parties, the insurer agreed to re-quote the repairs, appointing builder “C” to prepare a SOW and quotation. The insurer offered the complainant the choice of having C undertake the works or having a cash settlement based on C’s quotation, plus an allowance for contingencie s. The complainant was amenable to this settlement proposal, however still had reservations on C’s quote. She also wants a temporary accommodation allowance whilst works are undertaken and compensation and/or a premium refund for the manner in which the insurer managed the claim. 1.2 Issues and key findings Does the insurer’s offer of settlement fulfil its obligations under the policy terms? The insurer ’s offer of settlement fulfils its obligations under the policy terms because:  the complainant has not show n C’s quotation or SOW are inadequate;  the policy terms allow the insurer the right to determine the method of settlement utilised in the claim; Determination | Case number: 541508 Page 2 of 8  the complainant is not entitled to an allowance for temporary accommodation as the property remains habitable; and  there is insufficient evidence the property is suffering from mould growth. The insurer has offered the complainant the choice of it undertaking repairs or providing a cash settlement based on C’s quotation, with an uplift of 25% for any contingencies. This is reasonable in the circumstances. Is the complainant entitled to compensation for the manner in which the insurer managed the claim? The complainant is entitled to a further amount of $500 compensation for the manner in which the insurer managed the claim, in addition to the insurer’s offer to refund the policy excess, making a total of $1,000 payable to the complainant. Is the insurer entitled to retain the premium paid? The insurer is entitled to retain the premium paid as it has provided the benefit of cover to the complainant and has been on risk since policy inception 1.3 Determination This determination is substantially in favour of the insurer. The insurer’s offer of settlement is reasonable and adequately discharges its l iability under the policy terms. Within 14 days of the date of this determination, the complainant is to advise the insurer of her preferred method of settlement, so this can be arranged. The insurer is also required to refund the policy excess of $500 and pay a further $500 compensation for the manner in which it managed the claim. Determination | Case number: 541508 Page 3 of 8 2 Reasons for determination 2.1 Has the insurer fulfilled its obligations under the policy terms? Onus rests with complainant to establish further entitlement There is no dispute the complainant suffered a loss from a risk insured against or the insurer accepted the claim and arranged to settle its liability for the damage by way of a cash payment. However, a dispute has arisen between the parties over the insurer’s settlement proposals. Principally, the complainant maintains the insurer’s offer is inadequate as is does not include an allowance for temporary accommodation nor any guarantees that the new building materials will match existing or damage occasioned during the repairs will be remedied. As the party seeking additional benefits, the onus rests with the complainant to establish she is entitled to them. Matters which were previously disputed between the parties but since resolved will not form part of this determination, although may be referenced where necessary. Insurer not obliged to provide an exact match The complainant raises issue with the kicker panels of the kitchen cabinetry and is concerned the replacement panels may not match the original. She seeks that there is no mismatch. The complainant does not dispute receiving the policy documents including the product disclosure statement (PDS), therefore I accept she did so. Accordingly, the insurer is entitled to rely on the policy terms within when assessing any claim made against the policy. The policy specifically turns its mind to the issue of undamaged materials and achieving a match with the existing , with the following provision: If we decide to repair your building(s), we will:  Only repair the part or parts that actually sustained damage, including damaged portions of fixed coverings to walls, floors and ceilings in the rooms, halls or passages where the damage occurred, to a condition as close as possible to when new, but not better  Try to match any material used to repair your buildings with the original materials or nearest equivalent available to the original materials Determination | Case number: 541508 Page 4 of 8 Accordingly, the policy quite specifically limits its liability for the damaged area(s) only. That is, the actual part of the kicker panels that sustained water damage (or any other areas of the home). Where the complainant is dissatisfied with the match to be achieved, she has the option of paying privately to replace undamaged areas to match. However, the insurer is not obliged to repair or replace undamaged parts of the home to create a uniform appearance. Policy entitles insurer to determine method of settlement The complainant has latterly requested the insurer undertake repairs rather than cash settle the claim, so as to transfer the risk to it should any issues arise during the course of repairs. She maintains she did not ask for a cash settlement and the insurer only did so after she raised concerns about P’s SOW. The PDS clearly states that the insurer retains the right to determine which method of settlement to utilise when settling a claim. Therefore, its decision to cash settle the claim is in accordance with the policy terms. Where an insurer has discretion as to how to settle a claim, AFCA expects an insurer to exercise this reasonably, as cash settlement may affect an entitlement to other benefits under the policy terms such as a repair guarantee. However, there is no evidence to suggest the insurer has not done so in this instance. It is clear the parties were at an impasse over the proposed settlement. The insurer considered the best method of settlement was a cash settlement rather than repairs, as this allows the complainant the flexibility to replace undamaged materials if she wishes. In such circumstances, the insurer's decision to cash settle was reasonable. Insurer has now offered complainant options for settlement However, the insurer has now confirmed it is prepared to offer the complainant the option of choosing her preferred settlement. It will either authorise C to undertake repairs on its behalf (based on the SOW provided by C) or provide a cash settlement based on C’s quote. The insurer has also offered an uplift of 25% on C’s quote to allow for any contingencies which may arise during the repairs in the event the complainant chooses the cash settlement option. This is reasonable in the circumstances. Were the complainant to allow C to proceed with repairs, she would be afforded greater protection under the policy terms, as the policy provides a lifetime repair guarantee on any repairs authorised by the insurer. The insurer also quite rightly points out that the SOW is dynamic and if any additional works are discovered during the course of repairs, then the SOW will be varied as necessary. This would include in the event mould was discovered as a result of the claimed event. However, at this point, this is only speculatory on the part of the complainant Determination | Case number: 541508 Page 5 of 8 and I am not prepared to make an allowance on this point based on the information provided. In the event the repairs were not satisfactory, then the complainant would retain her rights against the insurer. However, she does not have the same protection if she chooses to accept the cash settlement, although she will have the benefit of the 25% contingency allowance. This is to offset the risk the complainant is assuming in managing the repairs herself, as well as the forfeiture of the lifetime repair guarantee. Complainant’s quotation The complainant has latterly provided a quotation for comparative purposes from her builder “HB” in the amount of $28,380. She says the amount quoted by HB shows the SOW and quoted amount by C is inadequate. However, I do not agree. Provision of a more expensive quotation does not, of itself, show that eith er C’s quotation is inadequate to repair the damaged areas , that C cannot do the work for the quoted amount or that the SOW is inadequate. It generally reflects different pricing quoted by trade professionals, where the SOW is the same. HB’s quotation inc ludes further works to the kitchen than allowed for by C’s SOW. In particular, it is quoted to remove the kitchen cupboards along the wall as the plaster is moisture damaged. However, the dishwasher leak was on the island bench and it is unclear how that would damage plaster on the other wall. As stated above, in the event further damage is discovered during C’s repair, then the SOW will be updated. At this stage, there is insufficient evidence before me to suggest HB’s SOW and/or quotation should be preferred. In the event the complainant chooses to be cash settled, I am not persuaded she has adequately demonstrated either C’s quotation or SOW is inadequate. On this basis, I accept the insurer is entitled to rely on C’s material to base its settlement on. Complainant not entitled to an allowance for temporary accommodation The complainant also seeks an allowance for temporary accommodation whilst repairs are undertaken so as to minimise the inconvenience to her and her family. The insurer agrees the repairs will be inconvenient however the property will remain habitable throughout as it will remain connected to utilities. The policy does contain a provision for cover of temporary accommodation where an insured event renders the property uninhabitable. The policy does not specifically define the term uninhabitable. In the absence of a specific policy definition, AFCA has generally held the term to be usually limited to consideration of factors such as being secure to the elements, with utilities such as electricity, gas and water still available at the premises, and the absence of contaminants or other safety hazards. Determination | Case number: 541508 Page 6 of 8 Whilst it is accepted the replacement of the flooring and cabinetry will be inconvenient, no evidence has been presented to show the proper ty would be rendered uninhabitable with reference to the above listed factors. On this basis, the insurer was entitled to decline this aspect of the complainant’s claim. 2.2 Is the complainant entitled to compensation for the manner in which the insurer managed the claim? The Terms of Reference allow for compensation in limited circumstances The FOS Terms of Reference (the Terms) enable AFCA to compensate a complainant for non-financial loss (capped at $3,000). Compensation for non-financial loss is limited. AFCA may decide a financial firm should compensate a complainant for such a loss only where there has been an unusual amount of:  physical inconvenience; or  time taken to resolve a situation; or  interference with the complainant’ s expectation of enjoyment or peace of mind. AFCA takes a conservative approach to compensation and expects a complainant to bear the usual degree of stress and inconvenience when managing an insurance claim. The simple passage of time is not a trigger for compensation, nor is the mere fact that the parties were in disagreement over the SOW or other factors. Insurer did not manage all aspects of claim reasonably I agree the insurer did not appropriately address the complainant’s concerns about the quality of flooring quoted by P. Rather than make enquiries of P about the quality of flooring quoted and whether it was possible to only replace this in the kitchen, meals and entry way, the insurer sought to cash settle the claim. Whilst I have no issue with the insurer cash settling where reasonable, such an action is not a substitute for properly addressing issues raised by an insured, especially where it is later demonstrated the cash settlement was inadequate. C’s later quotation shows P’s SOW was flawed and that the flooring repla cement must extend to the other rooms due to the way the flooring was laid originally. The insurer also accepts P did not quote on like for like flooring. I consider had the insurer reacted appropriately to the complainant’s concerns when raised, these is sues could have been clarified much sooner in the claims process. Whilst the timeframe taken during the negotiations and preparing quotations and SOWs etc before the matter was brought to AFCA is not unreasonable, I do find this could have been lessened by more effective management of the claim, as set out above. However, I also note that at times, the complainant has been the source of some of the delays experienced in bringing this matter to resolution. Determination | Case number: 541508 Page 7 of 8 The insurer has previously offered to refund the policy excess of $500 in order to resolve the dispute. Whilst the complainant raises issue that she accepted this offer, yet the insurer has not refunded the excess, I note the offer was conditional upon the dispute being resolved. As it was not, the insurer was not required to refund the excess. However, the insurer has confirmed it is still willing to extend this offer to the complainant. Whilst this is reasonable on the part of the insurer, I consider an award of compensation is appropriate in the circumstances. Accordingly, taking into consideration AFCA’s conservative approach to compensation and the degree and extent of inconvenience experienced, I consider a further $500 in compensation is appropriate, making $1,000 in total payable to the complainant by the insurer. Insurer entitled to retain premium as it was on risk In the alternative, the complainant seeks a refund of the premium paid or a freeze on premium amount (either wholly or partially) in recompense due to the service she received throughout the claim. However, the premium is paid for the benefit of insurance cover. Payment of the premium is not tied to an intangible such as the level of service received. In all instances, the insurer was on risk for the complainant’s property. The insurer did and does continue to provide the benefit of cover subject to the policy terms and conditions. In fact, by lodging this claim, the complainant has obtained a benefit under the policy terms. Therefore, the insurer is entitled to retain the premium paid as it is providing the benefit of cover. In the circumstances, there is no basis for the complainant to be entitled to any premium refund. Determination | Case number: 541508 Page 8 of 8 3 Supporting information 3.1 The determination is made under FOS Terms of Reference The Australian Financial Complaints Authority ( AFCA) has commenced managing disputes previously lodged with F inancial O mbudsman S ervice (FOS) . This determination is made under FOS Terms of Reference but has adopted the following terminology for consistency with AFCA. In this determination the AFCA terms have the same meaning as the FOS terms defined in paragraph 20.1 and Schedule 1, 2 & 3 of the FOS Terms of Reference. FOS definitions AFCA term applicant complainant financial services provider financial firm dispute complaint claim claim 3.2 AFCA approach to this complaint A full exchange of the relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any issues raised. All of the provided material has been reviewed and considered. The parties have raised numerous issues in their submissions to AFCA. However, commentary in this determination is restricted only to those issues considered relevant to the outcome.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.