Home / Financial Firm (Unknown - Insurer) / Determination 540431
Determination 540431
Burglary claim management, repair delay and repair quality
Summary
After a burglary, the complainant complained about repair delays, the scope of works and the insurer's claim management, and sought non-financial loss compensation. AFCA found the insurer managed the claim reasonably and awarded nothing.
Non-financial loss is awarded only for unusual inconvenience, and the delay and make-safe measures were not unreasonable on the evidence.
Issues
- Poor claim handling primary · not upheld“The insurer's management of the claim was reasonable overall and no compensation is warranted.”
- Delay secondary · not upheld“The delay in commencing repairs resulted from the complainant's delay in returning a signed scope of works and was minor.”
Subjects and remedies
theft or burglaryno remedy
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Determination | Case number: 540431 Page 1 of 5
Determination
Case number: 540431 27 February 2019
1 Determination overview
1.1 Complaint
The complainant holds a building and contents insurance policy with the financial firm
(the insurer). The insurer accepted the complainant’s claim f or contents theft and
building damage which occurred during the burglary.
The complainant is dissatisfied with how long it took the insurer to repair his back
door, side gate, flyscreen, and the quality of the repairs.
The rectification of property damage has been settled. The complainant remains
dissatisfied with the way the insurer managed his claim and seeks compensation for
non-financial loss.
1.2 Issue and key finding
Has the insurer managed the claim reasonably?
AFCA cannot award compensation for non-financial loss in a complaint arising from a
claim on a general insurance policy that excludes such liability. It can, however,
compensate a complainant for non-financial l oss arising from the financial firm’s poor
management of the claim. In this complaint I am satisfied the insurer managed the
claim reasonably overall, so no compensation is warranted.
1.3 Determination
This determination is in favour of the insurer.
The insurer is not required to take any further action.
Determination | Case number: 540431 Page 2 of 5
2 Reasons for determination
2.1 Has the insurer managed the claim reasonably?
The Terms of Reference allow for compensation in limited circumstances
The FOS Terms of Reference allow AFCA to compensate a complainant for non-
financial loss. Compensation for non-financial loss is limited and capped at $3,000.
AFCA may decide a financial firm should compensate a complainant for such a loss
only where there has been an unusual amount of physical inconvenience, time taken
to resolve a situation , or interference with the complainant’ s expectation of enjoyment
or peace of mind.
AFCA takes a conservative approach to compensation and expects a complainant to
bear the usual degree of stress and inconvenience when managing an insurance
claim. The simple passage of time is not a trigger for compensation.
Insurer’s management of claim reasonable overall
The complainant says the make safe repairs made the back door secure but
inoperable for an unreasonable period of time. The polic y covers the reasonable cost
of emergency repairs needed to prevent further loss or damage and make buildings
safe and secure when a claim is accepted under the buildings policy.
The insurer’s builder bolted the rear access shut as a precautionary safety measure.
In circumstances where a burglary had just occurred, these make-safe measures to
prevent further loss and make the area secure are reasonable. The complainant still
had alternative access to his house, and while this may have result in some
inconvenience, it is not to such an extent that compensation is warranted.
The complainant says that the insurer took 11 weeks to begin any repair works, did
not order the replacement doors promptly, and failed to perform repairs on the first
two occasions. Whil e the insurer agreed to order the door on 29 August 2018 without
a scope of works, the repairer did not order the materials until after the scope of
works was signed by the complainant on 10 September 2018. This delay is minor in
the context of the claim as a whole and does not warrant compensation.
Whilst I appreciate the complainant was dissatisfied with the service he received, the
available information does not suggest there were any undue delays on the part of the
insurer. The insurer’s management of the claim was reasonable overall, and I have
set out the key steps it has taken to manage the claim in section 3.2 below.
The circumstances suggest that the insurer acted in good faith to effect repairs as
quickly as possible. The insurer accepted the claim and arranged for make safe
repairs on the day that the claim was made. The delay in commencing repairs
appears to result from the complainant’s delay in returning a signed scope of works.
Determination | Case number: 540431 Page 3 of 5
The complainant says the scope of works was initially inaccurate, vague and
unsuitable. No information has been presented to suggest there was any substantive
obstacle in the scope of works which was initially drawn up and that which was
ultimately agreed.
I am not satisfied the reasons given by the complainant justified him seeking to cancel
the policy, refusing to the pay the excess to the contractor, refusing to agree to the
scope of works, and delaying signing the scope of works. Based on the information
provided, I am satisfied in the circumstances the insurer and its agents worked with
the complainant to progress the claim. .
The complainant says the insurer and its agents corresponded and called him at the
same time about the same issues . I consider that this supports the insurer’s position
that it made efforts to contact the complainant to work around his availability and meet
his needs. I do not consider such conduct to be harassment.
On the available information, I consider the insurer’s management and progre ssion of
the claim reasonable.
Complainant not entitled to compensation
Accordingly, taking into consideration AFCA’s conservative approach to
compensation and the degree and extent of inconvenience incurred, I consider the
insurer’s conduct of the claim was appropriate overall. Therefore, any award of
compensation in these particular circumstances is not appropriate.
Determination | Case number: 540431 Page 4 of 5
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previously lodged with Financial Ombudsman Service (FOS).
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
applicant complainant
financial services provider financial firm
dispute complaint
claim claim
This complaint 540431 has been determined based on what is fair in all the
circumstances, having regard to the relevant law, good industry practice, codes of
practice and previous FOS decisions (which are not binding).
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other. All material provided has been reviewed and considered.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues which are
considered directly relevant to the outcome only. Complaint 610945 about rectification
works required to fix the side gate and flywire has been resolved between the parties.
3.2 Summary of key events
Date Action
4 August 2018 The complainant lodged the claim with the insurer .
The insurer approved e mergency repairs .
7 August 2018 The insurer’s assessor attended the complainant’s house and drafted
provisional scope of works which was provided to repairer ANT. The
insurer emailed the complainant to advise of the authority and payment
of the excess to repairer ANT . The complainant was unhappy with this
process and indicated he did not wish to pay excess to repair er ANT.
Determination | Case number: 540431 Page 5 of 5
Date Action
8 August 2018 The insurer’s assessor email ed the complainant to reinspect in order to
address his concerns, which was declined.
The complainant requested to withdraw his claim and cancel his policy.
As a consequence, authority to repairer ANT was cancelled.
10 August 2018 The complainant decided to continue with the claim, and paid excess to
insurer direct. A new authority was sent to repairer ANT.
15 August 2018 The insurer’s a ssessor telephone d the complainant to discuss his claim
and conc erns, but he terminated the phone call.
17 August 2018 The insurer’s Team Manager cont act ed the complainant to discuss his
claim, with a follow up on 21 of August 2018.
17 August 2018 The complainant lodged FOS dispute 540431 about claims management
and delay.
21 August 2018 The complainant authorised repairer ANT to carry out the repairs, but did
not want the assessor to attend.
23 August 2018 Repairer ANT arranged to meet with the complainant at his home to
finalised the scope of works , and provide an approximate timeframe .
29 August 2018 The insurer provided the scope of works to the compla inant to sign but
sought to order the material (doors) wit hout the signed scope to avoid
further delays.
10 September 2018 The complainant provide s signed scope of works by email .
11 September 2018 Doors ordered .
27 September 2018 The complainant told the insurer that he wa s available from 9 October
2018 onwards .
9 October 2018 Work commenced .
15 October 2018 Complainant rais es complaint of tears in screen door and timber chips
on floor. Repairer ANT attended and rectified the timber ch ips and
replaced the flyscreen.
20 December 2018 The complainant lodged AFCA dispute 610945 about workmanship .
Repairer ANT leaves messag es for complainant to contact them about
the rectification work.